YEAR
No SUBJECT / ACTIVITY
NOV'11 DEC'11 JAN'12 FEB'12 MAR'12 APR'12 MAY'12 JUN'12 Remarks / Responsibility
1.2 Management HSE Site Visit 15 Nov '11 07, 21 Dec '11 07, 21 Jan '12 07, 21 Feb '12 07, 21 Mar '12 07, 21 Apr '12 07, 21 May '12 07, 21 Jun '12
1.3 Positive HSE attitude via rewards 05 Dec '11 06 Jan '12 06 Feb '12 08 Mar '12 6 Apr '12 7 May '12 8 Jun '12
Monthly Safety Award / Best Employee Of
(Monthly Safety Award) The Month / HSE Spot Award
3.2 HSE Meetings with workforce 28 Nov "11 28 Dec "11 28 Jan '12 28 Feb '12 28 Mar '12 28 Apr '12 28 May '12 28 Jun '12
6.2 HSE Performance (Manhours, KPI,Waste, 16 Feb ' 12 16 May "12 Review meeting for HSE Statistics
etc) and trends
7 AUDITING & REVIEW
7.1 Internal Audit on HSE-MS 18-20 Apr '12
7.4 Site Visit 15 Nov '11 07, 21 Dec '11 07, 21 Jan '12 07, 21 Feb '12 07, 21 Mar '12 07, 21 Apr '12 07, 21 May '12 07, 21 Jun '12
B12: absanji:
set visit for monitor observation and improvement
B14: absanji:
incentives, rewards, given out at set interval
B18: absanji:
any set periodical meeting for promoting and monitoring the understanding of HSE Policy
B20: absanji:
any set periodical meeting to review the policy
B24: absanji:
any set periodical meeting to review the organization structure and to be in line with item No.8
B26: absanji:
any set periodical meeting for promoting and monitoring the understanding of HSE Culture that is in additional to item 1.1
B28: absanji:
any set periodical meeting to review for improvement and updating
B30: absanji:
any set periodical meeting for conducting new and refresh HSE induction or as a mean of monitoring
B32: absanji:
any set periodical meeting to review and improve and to be in line with item No. 8
B36: absanji:
any set periodical meeting to review the insurance and welfare is covered and to be in line with item No. 8
B38: absanji:
any set periodical meeting to review and improve this document and to be in line with item No 8
B40: absanji:
any set periodical meeting to review and make improvement to document and monitoring of waste generated
B44: absanji:
Any set periodical meeting to vreview and monitoring of PAKAT feedback and set award in line with item 1.3
B48: absanji:
any set periodical visit to monitor this issue comply to the documentation and procedures, this visit act as a monitoring and compliances inline with item 5.2
B50: absanji:
any set periodical visit to monitor this issue comply to the documentation and procedures, this visit act as a monitoring and compliances inline with item 5.1
B52: absanji:
any set periodical exercises to meet the HSE-targets act as monitoring and compliances.
B56: absanji:
any set periodical meeting as required for monitor and improvement on the set target and review for future target.
B58: absanji:
any set periodical meeting as required for monitor and improvement on the set target and review for future target.
B62: absanji:
any set periodical meeting for monitor and improvement
B66: absanji:
any set periodical meeting for monitor and improvement
B68: absanji:
any set periodical meeting for monitor and improvement
B72: absanji:
any set periodical meeting for monitor and improvement
K14: absanji
Receipt or copy of award / incentives
K18: absanji:
Minutes of Meeting : HSE Management review meeting