Activity Duratio N Predecessor

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

ACTIVITY DURATIO PREDECESSOR

N
1-2 MOBILIZATION 2 0
1-3 CLEARING OF SITE 3 1-2
1-5 SECURE BUILDING PERMIT 21 0
2-7 PURCHASE DELIVERY OF INITIAL MATERIALS 6 1-2
3-4 TEMPORARY CONSTRUCTION OFFICE 3 1-3
3-5 TEMPORARY ENCLOSURE (FENCING) 4 1-3
4-6 TEMPORARY TOILET 4 3-4
5-8 TEMPORARY WATER LINE 2 1-5 , 3-5
6-11 INSTALL SCAFFOLDING FROM GROUND FLOOR TO SECOND FLOOR 20 4-6
7-8 TEMPORARY LIGHTING 2 2-7
7-10 PURCHASE AND DELIVERY OF STEELBARS AND LUMBERS 14 2-7
8-9 START LAYOUT 2 5-8
9-10 SHORING 3 8-9
9-11 EXCAVATION OF FOOTINGS 25 8-9
10-12 FABRICATION OF FOOTING AND RC WAL REBARS 12 7-10
11-13 FOOTING T-BEAM FORMS 3 6-11 ,9-11
11-16 INSTALL SECOND FLOOR FORM JOISTS AND BOTTOM BEAM FORMS 11 6-11 , 9-11
12-13 INSTALL RC WALL AND FOOTING REBARS 7 10-12
13-15 INSTALL FIRST FLOOR COLUMN AND FOOTING T-BEAMS REBARS 5 11-13 , 12-13
14-15 SOIL POISONING 2 12-14
14-18 INSTALL SECOND FLOOR BEAM AND GIRDER REBARS 8 12-14
15-16 POURING OF FOOTINGS AND T-BEAM RC WALL 4 13-15 , 14-15
16-17 INSTALL GRD. FLOOR COULMN FORMWORKS 5 11-16 , 15-16
16-18 INSTALL SECOND FLOOR SLAB PLYWOODFORMS 6 11-16 , 15-16
17-20 POURING OF GROUND FLOOR COLUMNS 2 16-17
12-21 FIRST FLOOR VAULT REBARS AND FORMS 5 16-17
18-19 ENCLOSE BEAM SID EFORMS 2 14-18 , 16-18
18-22 INSTALLSECOND FLOOR SLAB REINFORCING BARS 5 14-18 , 16-18
19-24 ROUGHING-IN PLUMBING SECOND FLOOR 6 18-19
20-22 REMOVAL OF COLUMN FORMS 1 17-20
20-23 REBARS OF CISTERN 2 17-20
21-22 POURING OF FIRST FLOOR VAULT 2 17-21
21-29 FABRICATION OF STEEL WINDOWS 14 17-21
22-24 ROUGHING-IN ELECTRICAL SEOND FLOOR 6 18-22 , 20-22
23-25 CISTERN FORMWORK 2 20-23 , 21-23
24-26 POURING OF SECOND FLOOR SLABS AND BEAMS 4 19-24 , 22-24
25-26 POURING OF CISTERN 1 23-25
25-28 TERMITE AND POISONING 2 23-25
26-27 CONTINUE SCAFFOLDINGS SECOND FLOOR 7 24-26 , 25-26
27-31 FABRICATION OF STEEL ROOF TRUSS 12 26-27
28-29 INSTALL OF GLASS BLOCKS 5 25-28
29-32 PLACING OF GRAVEL FILL AND TAMPING 5 21-29 , 28-29
30-31 INSTALL STAIR FORMS 5 26-30
31-34 INSTALL STAIR REBARS 3 27-31
32-33 PLACING OF GRAVEL FULL AND TAMPING 3 32-33
34-37 REMOVAL OF SECOND FLOOR COLUMN FORMS 6 31-34
35-36 INSTALL OF GLASS BLOCKS 5 33-35
35-39 SECOND FLOOR FORMWORKS AND POURING OF CONCRETE 3 33-35
36-38 INSTALLALUMINUM AND STEEL FRAMES 4 35-36
37-40 INSTALL ROOF BEAM REBARS 6 34-37
38-40 REMOVAL OF SECOND FLOOR SLAB AND POURING CONCRETE 3 36-38
39-41 SECOND FLOOR SLAB AND BEAMFORMS 3 38-41 , 39-41
40-42 FORMWOKRS AND STEELWORKS GROUND FLOOR STAIRS 6 37-40
41-43 FABRCATION OF GROUND FLOOR, CABINETS, AND COUNTERS, 9 38-41 , 39-41
CLOSETS
41-44 START GROUD CEILING JOIST 8 38-41 , 39-41
42-43 POURING OF GROUND FLOOR STAIRS 2 40-42
43-49 FGRINDING AND POLISHING OF MARBLE FLOOR AND COUNTERS 3 41-43 , 42-43

44-46 INSTALL ALUM. T-RUNNERS, CEILINGS, ACOUSTICS, BOARDS, 6 41-44


GROUND FLOOR
45-47 CONCRETE GUTTER REBARS 2 40-45
46-48 PEBBLE WASHOUT PERIMETER WALL FINISH 6 44-46
47-49 ROOF BEAM AND GUTTER FORMS AND POURING 2 45-47
48-50 WAINSCOATING AND TILES OF FIRST AND SECOND FLOOR 5 46-48
49-51 WATERPROOFING OF CONCRETE GUTTER AND TOILET FLOOR 5 43-49 , 47-49
50-52 INSTALL LONG SPAN COLORED 6 48-50 , 49-50
51-52 WAINSCOATING TOILET TILE 2 49-51
51-54 ELECTRIC WIRING 4 49-51

52-53 SECOND FLOOR CEILING JOISTS AND T-RUNNERS 5 50-52 , 51-52


53-55 START PAINTING SECOND FLOOR 19 52-52
53-56 INSTALL CEILING 5 52-53
54-55 ELECTRIC PANEL BOARD CIRCUIT BREAKER 7 51-54
55-57 ELECTRICAL LIGHTING FIXTURES 7 53-55 , 54-55
56-58 INSTALL STAIR RAILING 5 53-56
57-59 CLEARING UP 55-57 , 57-58
57-58 INSTALL ALL FINISHING HARDWARE 3 56-58