WRP 42, Period. 01-07 July 2019

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 281

PT.

GRID SOLUTIONS INDONESIA

WEEKLY PROGRESS REPORT


(WEEK. 42)

PT.PLN ( PERSERO) UNIT INDUK PEMBANGUNAN


INTERKONEKSI SUMATERA JAWA

PEMBANGUNAN GI 150kV TELUK NAGA II

Contract No. : 151.PJ/DAN.02.02/UIP ISJ/2017


Date: November 01,2017

REPORTING PERIOD :
( 01 July - 07 July 2019)
PEKERJAAN PEMBANGUNAN GI 150kV TELUK NAGA II

TABLE OF CONTENTS

I EXCECUTIVE SUMMARY

II PHYSICAL WEEKLY PROGRESS OVERALL

III WEEKLY PROGRESS ELECTROMECANICAL WORK

IV WEEKLY PROGRESS CIVIL WORK

V ENCLOSURE

1. SITE WEATHER REPORT (SWR)

2. Breakdown

3. Daily Activity

4. SITE PICTURES
WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

EXCECUTIVE SUMMARY

I PROJECT DESCRIPTION

Project Name : PEMBANGUNAN GI 150kV TELUK NAGA II

Contract No. : 151.PJ/DAN.02.02/UIP ISJ/2017


Date : November 01,2017
Amandement : -

Contractor : PT. GRID SOLUTIONS INDONESIA

Completion date : September 19, 2019

Scope of Work : Full Turnkey Project (All aspects starting from desig
fabrication, civil, testing up to commissioning) for S
Digital Air Insulated Switchgear that consist of 2x15
Bay to PLTU Lontar, 2x150 kV Line Bay to Teluk N
2x150 kV Transformer Bay, 1x150 kV Coupler Bay.

II PHYSICAL MONTHLY PROGRESS OVERALL

- Overall progress : 12.467%


- Elektromekanik Progress : 4.830%
EXECUTIVE SUMMARY PROGRESS, Page 3 of 281
WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

EXCECUTIVE SUMMARY
- Civil Progress : 7.637%

III ENGINEERING PROGRESS:

Progress Status
No Description Unit Rem
Prev. Week This Week

IV CONSTRUCTION :

Progress
No Description Unit Rem
Contract Actual

Cast-In Lean concrete K.125 - Cable Trench


1 Crossing Road

V MEETING

No Activity Place

VI WORK PLAN NEXT WEEK

Progress
No Description Unit Rem
Schedule Actual
EXECUTIVE SUMMARY PROGRESS, Page 4 of 281
WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

EXCECUTIVE SUMMARY
1 Control Building Foundation

Piling Work of Apparatus and 20kV Building


2
Foundation

3 Switchyard Access Road

EXECUTIVE SUMMARY PROGRESS, Page 5 of 281


PROGRESS REPORT
Period. 01 July - 07 July 2019)

UTIVE SUMMARY

ull Turnkey Project (All aspects starting from design,


abrication, civil, testing up to commissioning) for Semi
Digital Air Insulated Switchgear that consist of 2x150 kV Line
Bay to PLTU Lontar, 2x150 kV Line Bay to Teluk Naga,
x150 kV Transformer Bay, 1x150 kV Coupler Bay.

EXECUTIVE SUMMARY PROGRESS, Page 6 of 281


PROGRESS REPORT
Period. 01 July - 07 July 2019)

UTIVE SUMMARY

Remarks

Remarks

Remarks

Remarks

EXECUTIVE SUMMARY PROGRESS, Page 7 of 281


PROGRESS REPORT
Period. 01 July - 07 July 2019)

UTIVE SUMMARY

EXECUTIVE SUMMARY PROGRESS, Page 8 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

GRAND SUMMARY OVER ALL

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR ISIAN 5 : REKAPITULASI HARGA

PROGRESS
WEIGHT LAST THIS UP TO THIS
NO. DESCRIPTION
WEEK WEEK WEEK REMAKS
(%) (%) (%) (%)
(1) (2) (4) (5) (6) (5+6=7)

1 TOTAL PRICE FOR ELEKTROMEKANIK WORK GI 150 KV 69.832 4.830 0.000 4.830

2 TOTAL PRICE FOR CIVIL WORK GI 150 KV 30.168 7.637 0.000 7.637

SUB TOTAL 100.00 12.467 0.000 12.467

GRAND SUMMARY OVER ALL PROGRESS, Page 9 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

SUMMARY ELEKTROMEKANIK WORK


PEKERJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

PROGRESS

WEIGHT UP TO
NO. DESCRIPTION LAST WEEK THIS WEEK
THIS WEEK REMAKS

(%) (%) (%) (%)


(1) (2) (4) (5) (6) (5+6=7)

150 KV SWITCHYARD STEEL STRUCTURES, BUSBAR, OVERHEAD


1 12.622 0.322 0.000 0.322
GROUND WIRE (SHIELD WIRE)

2 150 KV LINE BAY TO PLTU LONTAR : 2 BAYS 10.842 2.289 0.000 2.289

3 150 KV LINE BAY TO TELUK NAGA : 2 BAYS 11.350 1.855 0.000 1.855

4 150 kV BUS COUPLER BAY : 1 BAY 8.481 0.888 0.000 0.888

5 150 kV TRANSFORMER BAY : 2 BAY(S) 10.978 1.562 0.000 1.562

6 150/20 KV POWER TRANSFORMERS AND AUXILIARIES 13.388 0.000 0.000 0.000

7 20 kV SWITCHGEARS AND POWER CABLES 12.611 0.000 0.000 0.000

8 ENERGY METERS FOR ALL TRANSFORMER FEEDER BAYS 0.704 0.000 0.000 0.000

9 SUBSTATION AUTOMATION HARDWARE 5.157 0.000 0.000 0.000

10 20 KV SUBSTATION AUTOMATION HARDWARE - - - -

11 SUBSTATION AUTOMATION SOFTWARE - - - -

12 INVERTER FOR SUBSTATION AUTOMATION 0.095 0.000 0.000 0.000

13 TELECOMMUNICATION EQUIPMENT 2.993 0.000 0.000 0.000

14 RADIO TRANCEIVER (Low Band Frekuensi), Tower, dan Aksesoris 0.512 0.000 0.000 0.000

15 150 kV SUBSTATION AUXILIARIES EQUIPMENT 5.416 0.000 0.000 0.000

16 MISCELLANEOUS 2.312 0.000 0.000 0.000

17 Training FOR ALL SCOPE OF PROJECT 0.975 0.000 0.000 0.000

18 TEST AND COMISSIONING FOR ALL SCOPE OF PROJECT 1.565 0.000 0.000 0.000

As Built Drawing FOR ALL SCOPE OF PROJECT in hard and soft copy (3
19 0.000 - - -
sets hardcopy and 2 sets softcopy)

Total for ELEKTROMEKANIK Work GI 150 kV 100.00 6.916 0.000 6.916

SUMMARY ELEKTROMEKANIK WORK PROGRESS, Page 10 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5

1 150 KV SWITCHYARD STEEL STRUCTURES, BUSBAR, OVERHEAD GROUND WIRE (SHIELD WIRE)

Galvanized steel structure to complete the specified scope of work for switchyard with 7 Bay Double
1.1 Busbar Type U of :
2x 150 kV Line Bays to PLTU Lontar
2x 150 kV Line Bays to Teluk Naga
2x 150 kV Transformer Bay
1x 150 kV Coupler Bay
Consist of :
- Post steel Structure Type TW-1, high 14,0 m' + steel Structure for earth wires high 4 m' Sets 24.00 2.549
- Post steel Structure Type TW-2, high 10,0 m' Sets 0.00
- Post steel Structure Type TW-3, high 14,0 m' (earthing tower) Sets 1.00 0.106
- Beam steel Structure for Busbar dan Crossbar, 12 m' Sets 20.00 1.476
- Beam steel Structure for Busbar dan Crossbar, 14 m' Sets 12.00 0.886
Sub total items 1.1

ELEKTROMEKANIK PROGRESS, Page 11 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
1.2 Overhead Ground Wire (Shield Wire) and Accessories
Consist of :
- Over Head Ground Wire ( with used GSW 55 mm2), Install from Post steel Structure Type1 (18m) to Post steel
Structure Type1 (parallel with Busbar and Parallel with Crossbar) lot 1.00 0.029

- Tension string set for GSW 55 mm2 (Complete jumper/ joint GSW 55 mm2 to structure and to GSW 55 mm2
other's) Sets 80.00 0.030

Sub total items 1.2

Substation and Building Earthing System (Mesh/ Grid System and Rod Electrode) and Complete with all
1.3 Connector Type
lot 1.00 2.950

- Copper strip or flexible conductors of the cross section specified, installed so as to form a grid system laid
directly in the ground enclosing the complete substation together with all electrodes for surge arester/LA, CVT
and Transformator equipment direct earthing (Rod Electroda).

ELEKTROMEKANIK PROGRESS, Page 12 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Copper strip of flexible conductors to connect metalclad parts of all equipment and structures to main Earth
System.Copper strip of flexible conductors to connect metalclad parts of all equipment and structures to main
Earth System (minimum CU 150 mm2).
- Copper strip of flexible conductors installed around the Building, metalclad parts of all equipment in the Building
and structures to connect to main Earth System (minimum CU 150 mm2).
- Copper strip or flexible conductors to bond all overhead line towers direct to the substation Earth System.

Sub total items 1.3

1.4 150 kV Double Busbar Type U (Conductor 2 x TAL 850 mm2/phase)


- Conductor 2 x TAL 850 mm2/phase for Double Busbar Type U lot 1.00 0.231
- Dropper to CVT Bus from Busbar I & II (3 phase) with Conductor 2 x TAL 850 mm2 (Complete with Connector
for Jumper ) lot 1.00 0.025

- Double Tension Insulator String for Busbar 2 x TAL 850 mm2/phase, with 2 x 12 Insulator/ set, 120 kN,
31mm/kV. (Complete with Connector for Jumper Busbar) Sets 54.00 0.746

ELEKTROMEKANIK PROGRESS, Page 13 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Single Suspension String Insulator Set 2 x TAL 850 mm2/phase for Jumpers of Busbar (Complete with
Sets 24.00 0.302
Connector Jumper)
- Spacer 20 cm for conductor busbar Sets 45.00 0.121
(Option 1)
- 150 kV Electronic capacitor voltage transformer (ECVT) for metering and protection (equal to class 0.2 and 3P), units 6.00
complete with clamps, supporting structure.

(Option 2)
150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3,
units 6.00 0.382
Burden 15 VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000
pF, complete with clamps, supporting structure.
- Miscellaneous equipment, LV power cable and accessories and necessary equipment (cable ladder, jumper,
clamp, cable lug, terminal, … etc)set of clamps, connectors and accessories for complete installation scope of lot 1.00 0.495
work.

Sub total items 1.4

ELEKTROMEKANIK PROGRESS, Page 14 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5

TOTAL PRICE ITEMS 1.1 - 1.4

2 150 KV LINE BAY TO PLTU LONTAR : 2 BAYS

2.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. lot 1.00 0.462
2.2 Conductor 2 x TAL 850 mm2/phase jumper for Inter HV Equipment (from CB to LA) and dropper from Transmission
line lot 1.00

2.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/phase Sets 12.00 0.166
2.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to DS Sets 6.00 0.076
2.5 Spacer 20 cm for conductor Sets 12.00 0.032
2.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm/kV, without
earthing switch, complete with clamps and supporting steel structure (DS Busbar). Sets 4.00 0.555

2.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
Sets 4.00 0.055
2.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV,
complete with clamps and supporting structure. Sets 2.00 1.069

ELEKTROMEKANIK PROGRESS, Page 15 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
2.9 (Option 1)
Electronic Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 2)
Optical Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 3)
Current Transformer 150 kV, 40 kA for Line Bay, 3 core, Creepage distance 31 mm/kV, complete with clamps and
supporting steel structure.
Core-1 : Class PX, 2000-4000/1 A units 6.00 0.645
Core-2 : Class 5P20, 2000-4000/1 A
Core-3 : Class 0,5, 2000-4000/1 A

2.10 Disconnecting switch 150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, with
earthing switch, complete with clamps and supporting steel structure (DSE). sets 2.00 0.360

ELEKTROMEKANIK PROGRESS, Page 16 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
2.11 (Option 1)
Electronic Capacitor Voltage Transformer (ECVT) 150 kV/√3 for metering and protection (equal to class 0.2 and units 6.00
3P), Creepage distance 31 mm/kV, complete with clamps, supporting steel structure.
(Option 2)
150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 15
VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, complete units 6.00 0.382
with clamps, supporting structure.

2.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure,and all
necessary equipment. units 6.00 0.266

2.13 Set of clamps, connectors and accessories for complete all installation lot 1.00 0.145
2.14 Protection and Control Cubicle for Line bay Comprising : sets 2.00 2.514
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) - Distance Relay, include DEF, Autorecloser, Synchrocheck, etc.
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- Optical distribution frame
ELEKTROMEKANIK PROGRESS, Page 17 of 281
GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Panel
Including but not limited to:
- miscellaneous equipment, optical cables and cord, control control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay
- all necessary work (dismantling, installation, integration, adaptation) to the existing system (SAS, Busbar
Protection, etc) in GI Lontar and adaptation in control center to complete the scope of works.

2.15 Marshaling kiosk for 150 kV Line Bay Comprising : set 2.00 2.437
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel and cooling system
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

ELEKTROMEKANIK PROGRESS, Page 18 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
Note: price of all Merging Unit and Switchgear Control Unit needed on 150 KV LINE BAY TO PLTU LONTAR is
include in item 2.15
2.16 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1.00 0.104
2.17 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works lot 1.00 0.989

TOTAL PRICE ITEMS 2

3 150 KV LINE BAY TO TELUK NAGA : 2 BAYS

3.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. lot 1.00 0.462
3.2 Conductor 2 x TAL 850 mm2/phase jumper for Inter HV Equipment (from CB to LA) and dropper from Transmission
line lot 1.00

3.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/phase Sets 12.00 0.166
3.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to DS
Sets 6.00 0.076
3.5 Spacer 20 cm for conductor Sets 12.00 0.032

ELEKTROMEKANIK PROGRESS, Page 19 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
3.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm/kV, without
earthing switch, complete with clamps and supporting steel structure (DS Busbar). Sets 4.00 0.555

3.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
Sets 4.00 0.055
3.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV,
complete with clamps and supporting structure. Sets 2.00 1.069

3.9 (Option 1)
Electronic Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 2)
Optical Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX) units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.

ELEKTROMEKANIK PROGRESS, Page 20 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
(Option 3)
Current Transformer 150 kV, 40 kA for Line Bay, 3 core, Creepage distance 31 mm/kV, complete with clamps and
supporting steel structure.
Core-1 : Class PX, 2000-4000/1 A units 6.00 0.645
Core-2 : Class 5P20, 2000-4000/1 A
Core-3 : Class 0,5, 2000-4000/1 A

3.10 Disconnecting switch 150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, with
earthing switch, complete with clamps and supporting steel structure (DSE). sets 2.00 0.360

3.11 (Option 1)
Electronic Capacitor Voltage Transformer (ECVT) 150 kV/√3 for metering and protection (equal to class 0.2 and
units 6.00
3P), Creepage distance 31 mm/kV, complete with clamps, supporting steel structure.

(Option 2)
150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 15
VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, complete units 6.00 0.382
with clamps, supporting structure.

ELEKTROMEKANIK PROGRESS, Page 21 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
3.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure,and all
necessary equipment. units 6.00 0.266

3.13 Set of clamps, connectors and accessories for complete all installation lot 1.00 0.145
3.14 Protection and Control Cubicle for Line bay Comprising : sets 2.00 2.204
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) - Current differential, syncrocheck, etc
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, rack cabinet, optical cables and cord, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

3.15 IED Main Line Protection - Current differential, syncrocheck, etc, for installed in GI Teluk Naga sets 2.00 0.801

ELEKTROMEKANIK PROGRESS, Page 22 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
Including but not limited to:
- miscellaneous equipment, optical cables and cord, control control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay
- all additional hardware and software needed to connect to the existing system (SAS, Busbar Protection, etc) on GI
150 kV Teluk Naga and to operated properly with MPU IED on GI 150 kV Teluk Naga 2
- all necessary work (dismantling, installation, integration, adaptation) to the existing system (SAS, Busbar
Protection, etc) in GI Teluk Naga and adaptation in control center to complete the scope of works.

3.16 Marshaling kiosk for 150 kV Line Bay Comprising : set 2.00 2.437
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

ELEKTROMEKANIK PROGRESS, Page 23 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
Note: price of all Merging Unit and Switchgear Control Unit needed on 150 KV LINE BAY TO TELUK NAGA is
include in item 3.16
3.17 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1.00 0.104
3.18 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works lot 1.00 0.989

TOTAL PRICE ITEMS 3

4 150 kV BUS COUPLER BAY : 1 BAY


4.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar. lot 1.00 0.231
4.2 Conductor 2 x TAL 850 mm2/phase for Inter HV Equipment lot 1.00
4.3 Double Tension Insulator String Set for Crossbar 2 x TAL 850 mm2/phase
Sets 18.00 0.249
4.4 Single Suspension Insulator String Set for Crossbar 2 x TAL 850 mm2/phase
Sets 9.00 0.113
4.5 Spacer 20 cm for conductor Sets 18.00 0.048

ELEKTROMEKANIK PROGRESS, Page 24 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
4.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 4000 Amp, 40 kA, Creepage distance 31 mm/kV,
Sets 2.00 0.284
without earthing switch, complete with clamps and supporting steel structure (DS Busbar).
4.7 Circuit Breaker 3 phase 150 kV, three pole for Couple bay, SF6, cap. 4000 Amp, 40 kA, Creepage distance 31
Set 1.00 0.417
mm/kV, complete with clamps and supporting structure.
4.8 (Option 1)
Electronic Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 2)
Optical Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX) units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.

(Option 3)
Current Transformer 150 kV, 50 kA for bus coupler bay, 2 core, Creepage distance 31 mm/kV, complete with
clamps and supporting steel structure. units 6.00 0.456
Core-1 : Class 5P20, 2000-4000/1
Core-2 : Class PX, 2000-4000/1

4.9 Set of clamps, connectors and accessories for all installation (including Inter HV equipment) lot 1.00 0.073

ELEKTROMEKANIK PROGRESS, Page 25 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
4.10 Protection and Control Cubicle for Line bay Comprising : sets 2.00 3.430
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) for 10 bays - Busbar Protection, DFR, etc
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, rack cabinet, optical cables and cord, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

4.11 Marshaling kiosk for 150 kV Coupler Bay Comprising : set 1.00 2.194
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
ELEKTROMEKANIK PROGRESS, Page 26 of 281
GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

Note: price of all Merging Unit and Switchgear Control Unit needed on 150 kV BUS COUPLER BAY and CVT Bus is
include in item 4.11
4.12 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1.00 0.052
4.13 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works. lot 1.00 0.495

TOTAL PRICE ITEMS 4


5 150 kV TRANSFORMER BAY : 2 BAY(S)
5.1 Crossbar Conductor 1 x TAL 850 mm2/phase + Dropper's Busbar to DS and Crossbar Conductor to DS & CB. lot 1.00 0.102
5.2 Conductor 1 x TAL 850 mm2/phase for Inter HV Equipment (from CB to Bushing Trafo) lot 1.00
5.3 Single Tension Insulator String Set for installation the Crossbar, Conductor 1 x TAL 850 mm2/phase sets 12.00 0.143
5.4 Single Suspension Insulator String Set with Conductor 1 x TAL 850 mm2/phase to DS & CB sets 6.00 0.076
5.5 Spacer 20 cm for conductor Sets 0.00
ELEKTROMEKANIK PROGRESS, Page 27 of 281
GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
5.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 1250 Amp, 40 kA, Creepage distance 31 mm/kV,
without earthing switch, complete with clamps and supporting steel structure (DS Busbar). sets 4.00 0.397

5.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
sets 4.00 0.055
5.8 Circuit Breaker 3 phase 150 kV, three pole for trafo bay, SF6, cap. 1250 Amp, 40 kA, Creepage distance 25
mm/kV, complete with clamps and supporting structure. sets 2.00 0.794

5.9 (Option 1)
Electronic Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.

(Option 2)
Optical Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX) units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.

ELEKTROMEKANIK PROGRESS, Page 28 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
(Option 3)
Current transformer 150 kV, 40 kA for transformer bay, 4 core, Creepage distance 31 mm/kV complete with clamps
and supporting steel structure.
Core-1 : Class PX, 150-300/1 A
Core-2 : Class 5P20, 150-300/1 A units 6.00 0.836
Core-3 : Class PX, 2000-4000/1 A
Core-4 : Class 0.5, 150-300/1 A

5.10 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure, and
units 6.00 0.266
all necessary equipment.
5.11 Set of clamps, connectors and accessories for installation lot 1.00 0.145
5.12 Protection and Control Cubicle for 150/20 kV Transformer Bay Comprising : sets 2.00 3.186
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main Transformer Protection - MPU (Trafo Differential, REF HV/LV side, DFR, etc.).
- IED Back Up Protection - BPU 1 for HV Side (Over Current, Earth Fault, Circuit Breaker Failure, DFR,
Instrument, etc.).
- IED Back Up Protection - BPU 2 for LV Side ( Over Current, Earth Fault, Stand by Earth Fault, etc).
ELEKTROMEKANIK PROGRESS, Page 29 of 281
GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- IED Bay Control - BCU
- IED AVR
- Optical distribution frame
- Panel
Including, miscellaneous equipment, test block, test plug, rack cabinet, optical cables and cord, clamps,
connectors, connection to individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to
complete the scope of works.
5.13 Marshaling kiosk for 150 kV Transformer Bay Comprising : set 2.00 3.412
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

ELEKTROMEKANIK PROGRESS, Page 30 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
Note: price of all Merging Unit and Switchgear Control Unit needed on 150 kV side of TRANSFORMER BAY is
include in item 5.13
5.14 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1.00 0.104
5.15 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works. lot 1.00 0.989

TOTAL PRICE ITEMS 5

6 150/20 KV POWER TRANSFORMERS AND AUXILIARIES


6.1 150/20 kV, 60 MVA 3-Phase power transformer complete with automatic voltage regulator relay, necessary
units 0.00
accessories and supporting structure for mounting 150 kV and 20 kV NCT.
6.2 Single phase neutral CT for 20 kV side Class x, 2000-4000/5 A complete with clamps for restricted earth fault
protection suitable for mounting outdoor on transformer tank or can be put inside the 20 kV neutral earthing resistor units 2.00
cubicle.

ELEKTROMEKANIK PROGRESS, Page 31 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
6.3 Single phase neutral CT for 20 kV side Class 10P20, 1000/5A complete with clamps for neutral earth fault
protection suitable for mounting outdoor on transformer tank or can be put inside the 20 kV neutral earthing resistor units 2.00
cubicle.
6.4 Single phase neutral CT for 150 kV side Class x 150-300/1A complete with clamps for restricted earth fault
units 2.00 0.092
protection suitable for mounting outdoor on transformer tank.
6.5 20 kV stainless steel neutral earthing resistor rated 12 Ohm, 10 seconds. sets 2.00 0.848
6.6 Transformer online monitoring system comprising : sets 2.00 5.671
- Tan Delta and capacitance for HV and LV Bushing and Winding
- Dissolve Gas Analysis For Transformer Oil
- Moisture/Water Content in Transformer Oil
- Partial discharge monitoring
- Oil Level Monitoring
- Oil Temperature & Winding Temperature
- OLTC monitoring
- IED Device, Including Panel
- Diagnostic Software
- Support Material
ELEKTROMEKANIK PROGRESS, Page 32 of 281
GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Industrial Class Server, Rack Mounted
- Workstatuin & VDU
Miscellaneous equipment and material required for completion the scope of work.
6.7 Transformer Blast and Fire Prevention equipment, complete with accessories sets 2.00 5.554

TOTAL PRICE ITEM 6

7 20 kV SWITCHGEARS AND POWER CABLES


7.1 3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between 150/20 kV power transformer
and 20 kV incoming cubicle, including cable support, 20 kV post insulators, metal bars, cable terminations and
accessories, cable rack etc.. to complete scope of work. (Cable length approximately 2 x 3 x 4 x 1 x 100 m' ) m 2400.00 0.800

7.2 3 phase, 1 x single core of 95 SQMM copper 20 kV XLPE power cable/phase between 20 kV auxiliary transformer
cubicle and the auxiliary transformer, including cable support, cable termination and accessories, cable rack, etc..
to complete scope of work sets 2.00 0.099

ELEKTROMEKANIK PROGRESS, Page 33 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
7.3 Power cable 20 kV XLPE Alluminium single core 1 x 630 sqmm (for Neutral Cable), between 150/20 kV Power
transfomer and NGR sets 2.00 0.023

7.4 20 kV Indoor Metalclad Switchgear Single-Busbar Scheme Comprising :


- Incoming Cubicle. set 2.00 1.191
- CB 25 kA, 24 kV/2000 A
- IED (Protection and control) Include in Bay Level Trafo
- KWh Meter (Include in Bay Level Trafo)
- IED Power Meter
- Incoming VT 24 KV, 3 FASA
- CT 20 KV, 3 Core for mesuring and protection (2000-4000/5 Class X; 5P20; 0.2)
- 3 VT 24 kV (Class 0,2 ; Class 3P)
- Trip Circuit Supervision
- Local switch, remote and supervisory
- LED for voltage indicator
- Megawatt and mvar meter 3 phase (Digital Power Meter) Class 0.5
- Test facility for metering and protection
- Busbar PT + Earthing Switch Cubicle. set 2.00 0.564

ELEKTROMEKANIK PROGRESS, Page 34 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Cubicle VT/LA 24 KV
- IED I/O, Power Meter
- 3 VT (Class 0.2; Class 3P)
- 3 Voltmeter
- Under Frequency Relay, Over Voltage and Under Voltage Relay
- Voltage Indicator for LED
- Test facility for metering and protection
- Auxiliary Transformer Cubicle. set 2.00 0.501
- LBS 25 kA, 24 kV/50 A
- IED I/O
- IED Power Meter
- Outgoing Feeder Cubicle set 16.00 6.268
- CB 25 kA, 24 kV/630 A
- IED (protection and control)
- KWh Meter
- IED Power Meter
- CT 20 KV, 2 CORE, for relay and measuring (Ratio : 300-600/5 A; Class : 5P20; Class : 0.5)

ELEKTROMEKANIK PROGRESS, Page 35 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Selector for Load Sheding and wiring to UFR
- Trip Circuit Supervision
- Local Switch, remote and supervisory
- Auto-Reclose and accessories
- LED for voltage indicator
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Metering and Protection for test facility
- Bus Section set 2.00 0.877
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Local Switch, remote and supervisory
- Auto-Reclose and accessories
- LED for voltage indicator
- Metering and Protection for test facility
- CB 25 kA, 24 kV/2000 A
- IED (Proteksi dan kontrol)
- IED Power Meter
- CT 20 KV, 2 Core, for relay and measuring (Ratio 2000-4000/5 A; Class 5P20; Class 0.5)

ELEKTROMEKANIK PROGRESS, Page 36 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Trip Circuit Supervision
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Local Switch, remote and supervisory
- Auto-Reclose and accessories
- LED for voltage indicator
- Metering and Protection for test facility
- Bus Riser Cubicle set 2.00 0.447
- 25 kA, 24 kV/2000 A
Miscellanious item including cable, accessories and necessary equipment to complete the scope of works.
7.5 Wall mounting panel Comprising : set 2.00 0.905
- IED Merging unit (number of port as required to complete scope of work) 1.00
- IED Switchgear Control Unit (number of port as required to complete scope of work) 1.00
- Optical distribution frame 1.00
- Panel and cooling system 1.00
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

ELEKTROMEKANIK PROGRESS, Page 37 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
Note: price of all Merging Unit and Switchgear Control Unit needed on 20 kV side of TRANSFORMER BAY is
include in item 7.5
7.6 3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between bus-section cubicle and bus
riser cubicle, including cable terminations and accessories for connection between sets of 20 kV switchgear to set 1.00 0.172
complete the specified scope of work
7.7 20/0.4 kV 200 kVA 3-phase station auxiliary transformer complete with necessary accessories (vector group DYn 5) sets
2.00 0.237

TOTAL PRICE ITEMS 7

8 ENERGY METERS FOR ALL TRANSFORMER FEEDER BAYS sets 2.00 0.682
Including one energy meter panel, two ethernet switch for connection station level and miscellaneous equipment &
material, rack cabinet, clamps, connectors, compression terminal, connection to individual items of equipment, test
terminal, auxiliary relay, interior lamp, heater… etc.

TOTAL PRICE ITEMS 8

ELEKTROMEKANIK PROGRESS, Page 38 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5

9 SUBSTATION AUTOMATION HARDWARE Set 1.00 5.045


9.1 Redundant HMI-Operator Station consist of : lot 1.00
- 2 Sets Operator Work Station.
- 2 Sets VDU, Keyboard & Mouse, Industrial grade KVM extender
9.2 Redundant Station unit/Server lot 1.00
- 2 Sets CPU
9.3 IED I/O lot 1.00
9.4 Ethernet Switch for station level (manageable). set 2.00
9.5 Colour Laser Printer. set 1.00
9.6 GPS Time reference clock complete with Antenna (redundant) set 2.00
9.7 Gateway or Gateway Protocol set 1.00
9.8 Router set 1.00
9.9 Modem. set 4.00
9.10 Panel, Rack/Cubicle for IED I/O, Gate Way, GPS, Modem and Ethernet Switch, etc. set 1.00
9.11 Panel, Rack/Cubicle for Work Station, Server, etc. set 1.00
9.12 Furniture. lot 1.00

ELEKTROMEKANIK PROGRESS, Page 39 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
9.13 Engineering Tools, Test Equipment (including but not limited to injecting sampling value, testing, measuring) and set 1.00
Laptop for configurating, testing and operation maintenance including software (for IED, telecommunication and
SAS equipment).
9.14 Miscellaneous item, equipment and material including cables, patch cord, pig tail, telephone cable, connectors, lot 1.00
compression terminal, connection to individual items of equipment, all necessary work (dismantling, installation,
integration, adaptation, etc in partner substation and control center), etc, to complete the scope of works.

TOTAL PRICE ITEMS 9

10 20 KV SUBSTATION AUTOMATION HARDWARE


10.1 1 Gareway or Gateway protokol Set 1.00
- Slave IEC 870-5-101, IEC 870-5-104 dan DNP3
- Master IEC 61850, IEC 870-5-101 dan DNP3
- DCC: 2 port serial, 1 port ethernet
10.2 2 Workstation Set 2.00
ELEKTROMEKANIK PROGRESS, Page 40 of 281
GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- CPU
- Keyboard & Mouse
- VDU LED 24"
- Active speaker.
- KVM extender
10.3 9 Common Lot 1.00
- IED I/O
10.4 ###Ethernet switch Set 5.00
Note : 6 cubicle 1 Ethernet
include :
- control cable and data cable
- I/O 1 system or modular
TOTAL PRICE ITEMS 10

11 SUBSTATION AUTOMATION SOFTWARE


11.1 Operating System Lot 1.00

ELEKTROMEKANIK PROGRESS, Page 41 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
1.2 Basic SA Software and Licences Lot 1.00
- SCADA
- Historical data
- Statistik & pelaporan
- Update data base
11.3 HMI Software Lot 1.00
11.4 Communication Protocol with Control Center Consist of Lot 1.00
IEC 60870 - 5 - 101, IEC 60870 - 5 - 104 and existing
Proprietary protocol (if any)
11.5 SAS Software for operation, maintenance, diagnostic, simulation and configuration Lot 1.00
TOTAL PRICE ITEMS 11

12 INVERTER FOR SUBSTATION AUTOMATION


12.1 Inverter including AC Distribution Board set 1.00 0.091
(Capacity subject to calculation result)

ELEKTROMEKANIK PROGRESS, Page 42 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5

TOTAL PRICE ITEM 12

13 TELECOMMUNICATION EQUIPMENT
SDH ADM MUX complete with terminal : (Should be identic with existing MUX in GI 150KV PLTU LONTAR and GI
13.1 Set 1.00 0.741
150KV Teluk Naga)
- STM-4 Line Interface Port 3.00
- 2 MB Interface Port 8.00
- DIU Data Interfacing Unit 64 Kbps (V.24 / RS 232) Port 4.00
- 64 Kbps G.703 Port 8.00
- VF 2/4 Wire E/M Interface Port 8.00
- VF/Subsc Interface Port 4.00
- VF /Exch.Interface Port 4.00
- Ethernet Interface + Router Port 2.00
13.2 PAX (16 trunks - 12 subscriber) complete with telephone set of each subsriber Set 1.00 0.563
13.3 MDF Main Distribution Frame Set 1.00 0.155
13.4 Panel, Rack/Cabinet for telecomunication equipment Lot 1.00 0.553

ELEKTROMEKANIK PROGRESS, Page 43 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
13.5 Digital Teleprotection Set 2.00
Note : 1 Sets to be installed in 150 kV Teluk Naga substation 0.371
Including integration and adaptation to eksisting system to complte the scope of works

13.6 Relocation, instalation and adaptation of eksisting Digital teleprotection equipment fom Teluk Naga substation to Lot 1.00
Teluk Naga 2 substation
Fiber Optic Armoured (FA) Cable 16 cores to connect OPGW (GB) to ODF in telecommunication room / substation
13.7 building, approx.200 m length
m 400.00 0.102
13.8 Optical Distribution Frame (ODF) (16 port) Set 4.00 0.125
13.9 Gantry Box for OPGW set 2.00 0.084
Miscellaneous item, equipment and material including cables, patch cord, pig tail, telephone cable, connectors,
13.1 compression terminal, connection to individual items of equipment to complete the scope of works. Lot 1.00 0.236

TOTAL PRICE ITEMS 13

14 RADIO TRANCEIVER (Low Band Frekuensi), Tower, dan Aksesoris


14.1 Radio Tranceiver (equal to Simoco) set 1.00 0.254
ELEKTROMEKANIK PROGRESS, Page 44 of 281
GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
Frequancy : 66-68 Mhz (programmable)
Power Output max : 25 W
(programmable, microphone, external speaker, power cable)
14.2 Antena Diple SMD set 1.00
14.3 Cross mount antenna set 1.00
14.4 Coaxial RG-8 Cable m 40.00
14.5 Connector PL set 1.00
14.6 Connector BNC set 1.00
14.7 Stop contact & Steker set 1.00
14.8 Tower Radio SST 25 m
1. Foundation for 25 m Tower lot 1.00 0.174
2. 25 m SST Tower lot 1.00
3. Earthing system lot 1.00
4. 25 m Tower Instalation lot 1.00

ELEKTROMEKANIK PROGRESS, Page 45 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5

TOTAL PRICE ITEM 14

15 150 kV SUBSTATION AUXILIARIES EQUIPMENT


15.1 110 V DC Battery suitable for supplying all 110 V DC load for 8 hours discharge. (Capacity of batetery is subject for
calculation for 10 bays and emergency lamp, and not less than 110V DC, 240 AH). set 2.00 1.406

15.2 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation for 110V DC Battery,
and not less than 60 A ) complete with Panel Board metering and indicators. set 2.00 0.437

15.3 110V DC Switch Board complete, incl. ATS, 2 MCB's incoming,1 MCB section and 2 x 12 MCB outgoing MCB's
minimum for 10 bays and emergency lamp. set 2.00 1.082
15.4 48 V DC Battery suitable for supplying all 48 V DC load for 8 hours discharge. (Capacity of batetery is subject for
calculation for SCADATEL of substation complete and not less than 48V DC, 200 AH). set 1.00 0.191

15.5 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation for 48V DC Battery,
and not less than 60 A ) complete with Panel Board metering and indicators. set 2.00 0.348
15.6 48V DC Switch Board complete, incl. ATS, outgoing MCB's minimum for 10 bays. set 1.00 0.342

ELEKTROMEKANIK PROGRESS, Page 46 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
15.7 400V AC Switch MCB's Distribution Board suitable for the 2 units station service transformer interchangeable to
supply the control building, yard lighting and HV equipment of minimum 10 bays, to complete the specified scope of set 1.00 0.881
work, including necessary spare MCB.
15.8 Miscellaneous material, LV power cable, control cable and accesorries and necessary equipment (cable ladder,
clamp, cable lug, terminal, etc.) to complete the specified scope of work. lot 1.00 0.497

TOTAL PRICE ITEMS 15

16 MISCELLANEOUS
16.1 Fault Recorder Equipment for 10 bays and Panel Set 1.00 1.175
- 2 Ethernet switch for process level
- Fault Recording equipment comprising necessary quantity of fault recordes equipped with oscillograph printer
to record the information of the 150 kV Bays
- The recorder shall be provided with date and line indicators and time synchronizing equipment clock via satellite

16.2 CCTV and Thermal and visual monitoring system compressed : set 1.00 1.054

ELEKTROMEKANIK PROGRESS, Page 47 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Thermal camera set 2.00
- 360 degree outdoor visual camera set 6.00
- 360 degree indoor visual camera set 4.00
- PC Server including operating system, antivirus, management and recording software set 1.00
- PC Client including operating system, antivirus, vewing and office work software set 1.00
Miscellaneous equipment and material required for completion Thermal and visual monitoring system including
Power supply, Cable Power, Cable Data, Cables, Swttch Hub, I/O Board For Alarm, Server Rack, UPS, Speakers, lot 1.00
etc scope of work
16.3 Miscellaneous equipment and material required for completion the scope of work. lot 1.00
TOTAL PRICE ITEMS 16
17 Training FOR ALL SCOPE OF PROJECT
TOTAL PRICE ITEMS 13.1 - 13.4
- Digital Substation Engineering and Design (TSS 3.3.1) : for 4 PLN engineers, 14 days Man - day 56.00 -
- Substation automation and telecommunication engineering (TSS 3.3.2 and TSS 5.17) : for 4 PLN engineers,
14 days Man - day 56.00 -

ELEKTROMEKANIK PROGRESS, Page 48 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5
- Substation operation and maintenance (TSS 3.3.2) : for 8 PLN staff, 14 days Man - day 112.00 -

TOTAL PRICE ITEMS 17

18 TEST AND COMISSIONING FOR ALL SCOPE OF PROJECT lot 1.00 -

TOTAL PRICE ITEMS 18


As Built Drawing FOR ALL SCOPE OF PROJECT in hard and soft copy (3 sets hardcopy and 2 sets
19
softcopy) lot 1.00 -
consist of :
- Soil investigation Report
- Test Report for foundation and Switchgear equipment
- Test Commissioning report
- Design Calculation
- Design Drawing
- Construction Drawing
TOTAL PRICE ITEMS 19

ELEKTROMEKANIK PROGRESS, Page 49 of 281


GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

%
1 2 3 4 5

GRAND TOTAL ITEMS 1 - 19

Approved by,
PT. PLN (Persero)
UPP JISJ 3
ELEKTROMEKANIK PROGRESS, Page 50 of 281
GI 150 KV TELUK NAGA II

PENGADAAN

ITEM URAIAN PEKERJAAN SATUAN VOLUME MATERIAL

Approved by, %
1 PT. PLN (Persero) 2 3 4 5
UPP JISJ 3

NOVAN PRASETYO
Manager Bagian Teknik

ELEKTROMEKANIK PROGRESS, Page 51 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.042 0.404 2.996 - - - - -

0.002 0.017 0.124 - - - - -


0.024 0.195 1.695 - - - - -
0.015 0.117 1.017 - - - - -
5.833 0.000

ELEKTROMEKANIK PROGRESS, Page 52 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.000 0.025 0.055 - - - - -

0.001 0.231 0.262 - - - - -

0.316 0.000

0.177 0.310 3.437 - - - - -

ELEKTROMEKANIK PROGRESS, Page 53 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

3.437 0.000

0.004 0.070 0.305 - - - - -

0.000 0.016 0.041 - - - - -

0.012 0.334 1.092 - - - - -

ELEKTROMEKANIK PROGRESS, Page 54 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.005 0.074 0.382 - - - - -


0.002 0.130 0.253 - - - - -

0.054 0.011 0.448 6.00 0.268 6.00 0.054 - 0.322 0.00 -

0.008 0.011 0.514 - - - - -

3.036 0.322

ELEKTROMEKANIK PROGRESS, Page 55 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

12.622 0.322

0.008 0.003 0.473 - - - - -

0.003 0.074 0.243 - - - - -


0.001 0.019 0.095 - - - - -
0.001 0.035 0.067 - - - - -

0.009 0.017 0.580 4.00 0.388 4.00 0.009 - 0.398 0.00 -

0.001 0.005 0.061 0.00 - - - - -

0.018 0.010 1.096 2.00 0.748 2.00 0.018 - 0.766 0.00 -

ELEKTROMEKANIK PROGRESS, Page 56 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.094 0.012 0.752 6.00 0.452 6.00 0.094 - 0.546 0.00 -

0.006 0.010 0.376 2.00 0.252 2.00 0.006 - 0.258 0.00 -

ELEKTROMEKANIK PROGRESS, Page 57 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.054 0.011 0.448 6.00 0.268 6.00 0.054 - 0.322 0.00 -

0.037 0.007 0.310 - - - - -


0.002 0.003 0.151 - - - - -
0.042 0.008 2.564 - - - - -

ELEKTROMEKANIK PROGRESS, Page 58 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.040 0.002 2.480 - - - - -

ELEKTROMEKANIK PROGRESS, Page 59 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.002 - 0.106 - - - - -

0.016 0.034 1.040 - - - - -

10.842 2.289

0.008 0.003 0.473 - - - - -

0.003 0.074 0.243 - - - - -


0.001 0.019 0.095 - - - - -
0.001 0.035 0.067 - - - - -

ELEKTROMEKANIK PROGRESS, Page 60 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.009 0.017 0.580 4.00 0.388 4.00 0.009 - 0.398 0.00 -

0.001 0.005 0.061 - - - - -

0.018 0.010 1.096 2.00 0.748 2.00 0.018 - 0.766 0.00 -

ELEKTROMEKANIK PROGRESS, Page 61 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.094 0.012 0.752 3.00 0.226 3.00 0.047 - 0.273 0.00 -

0.006 0.010 0.376 2.00 0.252 2.00 0.006 - 0.258 0.00 -

0.054 0.011 0.448 3.00 0.134 3.00 0.027 - 0.161 0.00 -

ELEKTROMEKANIK PROGRESS, Page 62 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.037 0.007 0.310 - - - - -


0.002 0.003 0.151 - - - - -
0.036 0.008 2.249 - - - - -

0.013 0.008 0.822 - - - - -

ELEKTROMEKANIK PROGRESS, Page 63 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.040 0.002 2.480 - - - - -

ELEKTROMEKANIK PROGRESS, Page 64 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.002 - 0.106 - - - - -

0.016 0.034 1.040 - - - - -

11.350 1.855

0.004 0.001 0.237 - - - - -

0.004 0.111 0.364 - - - - -

0.002 0.028 0.143 - - - - -


0.001 0.052 0.101 - - - - -

ELEKTROMEKANIK PROGRESS, Page 65 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.005 0.008 0.297 2.00 0.199 2.00 0.005 - 0.203 0.00 -

0.007 0.005 0.429 1.00 0.292 1.00 0.007 - 0.299 0.00 -

0.066 0.012 0.535 6.00 0.319 6.00 0.066 - 0.385 0.00 -

0.001 0.003 0.077 - - - - -

ELEKTROMEKANIK PROGRESS, Page 66 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9
0.057 0.008 3.495 - - - - -

0.036 0.001 2.231 - - - - -

ELEKTROMEKANIK PROGRESS, Page 67 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.001 - 0.053 - - - - -

0.008 0.017 0.520 - - - - -

8.481 0.888

0.002 0.003 0.107 - - - - -

0.002 0.037 0.182 - - - - -


0.001 0.019 0.095 - - - - -

ELEKTROMEKANIK PROGRESS, Page 68 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.007 0.017 0.420 4.00 0.278 4.00 0.007 - 0.284 0.00 -

0.001 0.005 0.061 - - - - -

0.013 0.010 0.816 2.00 0.556 2.00 0.013 - 0.569 0.00 -

ELEKTROMEKANIK PROGRESS, Page 69 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.123 0.012 0.972 6.00 0.585 6.00 0.123 - 0.709 0.00 -

0.037 0.007 0.310 - - - - -

0.002 0.003 0.151 - - - - -


0.053 0.008 3.247 - - - - -

ELEKTROMEKANIK PROGRESS, Page 70 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.056 0.002 3.471 - - - - -

ELEKTROMEKANIK PROGRESS, Page 71 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.002 - 0.106 - - - - -

0.016 0.034 1.040 - - - - -

10.978 1.562

ELEKTROMEKANIK PROGRESS, Page 72 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.002 0.003 0.097 - - - - -


0.014 0.010 0.872 - - - - -
0.858 0.073 6.602 - - - - -

ELEKTROMEKANIK PROGRESS, Page 73 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.092 0.172 5.817 - - - - -

13.388 0.000

0.016 0.190 1.006 - - - - -

0.002 0.016 0.116 - - - - -

ELEKTROMEKANIK PROGRESS, Page 74 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.000 0.002 0.025 - - - - -

0.020 0.006 1.216 - - - - -

0.009 0.006 0.579 - - - - -

ELEKTROMEKANIK PROGRESS, Page 75 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.008 0.006 0.515 - - - - -

0.104 0.046 6.417 - - - - -

ELEKTROMEKANIK PROGRESS, Page 76 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.015 0.006 0.898 - - - - -

ELEKTROMEKANIK PROGRESS, Page 77 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.007 0.006 0.460 - - - - -

0.015 0.008 0.929 - - - - -

ELEKTROMEKANIK PROGRESS, Page 78 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.003 0.023 0.197 - - - - -

0.004 0.013 0.253 - - - - -

12.611 0.000

0.011 0.010 0.704 - - - - -

0.704 0.000

ELEKTROMEKANIK PROGRESS, Page 79 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.083 0.029 5.157 - - - - -

ELEKTROMEKANIK PROGRESS, Page 80 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

5.157 0.000

ELEKTROMEKANIK PROGRESS, Page 81 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

ELEKTROMEKANIK PROGRESS, Page 82 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.002 0.002 0.095 - - - - -

ELEKTROMEKANIK PROGRESS, Page 83 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.095 0.000

0.012 0.015 0.769 - - - - -

0.009 - 0.572 - - - - -
0.003 - 0.157 - - - - -
0.009 - 0.562 - - - - -

ELEKTROMEKANIK PROGRESS, Page 84 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.006 - 0.377 - - - - -

0.002 - 0.104 - - - - -
0.002 - 0.127 - - - - -
0.001 - 0.085 - - - - -

0.004 - 0.240 - - - - -

2.993 0.000

0.004 0.015 0.274 - - - - -


ELEKTROMEKANIK PROGRESS, Page 85 of 281
WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.003 0.061 0.238 - - - - -

ELEKTROMEKANIK PROGRESS, Page 86 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.512 0.000

0.023 0.022 1.451 - - - - -

0.007 0.004 0.449 - - - - -

0.018 0.010 1.110 - - - - -

0.003 0.009 0.204 - - - - -

0.006 0.004 0.358 - - - - -

0.006 0.004 0.351 - - - - -

ELEKTROMEKANIK PROGRESS, Page 87 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

0.015 0.072 0.967 - - - - -

0.008 0.021 0.526 - - - - -

5.416 0.000

0.019 0.011 1.206 - - - - -

0.017 0.034 1.106 - - - - -

ELEKTROMEKANIK PROGRESS, Page 88 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

2.312 0.000

- 0.244 0.244 - - - - -

- 0.244 0.244 - - - - -

ELEKTROMEKANIK PROGRESS, Page 89 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9
- 0.488 0.488 - - - - -

0.975 0.000

- 1.565 1.565 - - - - -

1.565 0.000

- - - - - - - -

0.000 0.000

ELEKTROMEKANIK PROGRESS, Page 90 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % % % % %
6 7 5+6+7=8 9

100.00 6.916

Checked by,
PT. PLN (Persero) PUSMANPRO
UPMK I
ELEKTROMEKANIK PROGRESS, Page 91 of 281
WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 1 : ELEKTROMEKANIK WORK GI 150 KV

WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY
% % % % Checked by,
% % % %
6 7 5+6+7=8 PT. PLN (Persero) PUSMANPRO
9
UPMK I

DIMAS WAHYU ADHI K


KTSK BANTEN 2

ELEKTROMEKANIK PROGRESS, Page 92 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000

ELEKTROMEKANIK PROGRESS, Page 93 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

0.000 0.000

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 94 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.000 0.000

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 95 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

0.00 - 0.00 - - 6.00 0.268 6.00 0.054 0.00 - 0.322

- - - 0 - 0 - 0 - -

0.000 0.322

ELEKTROMEKANIK PROGRESS, Page 96 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.000 0.322

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

0.00 - - - 4.00 0.388 4.00 0.009 0 - 0.398

- - - 0 - 0 - 0 - -

0.00 - - - 2.00 0.748 2.00 0.018 0 - 0.766

ELEKTROMEKANIK PROGRESS, Page 97 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.00 - 0.00 - - 6.00 0.452 6.00 0.094 0.00 - 0.546

0.00 - - - 2.00 0.252 2.00 0.006 0 - 0.258

ELEKTROMEKANIK PROGRESS, Page 98 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.00 - 0.00 - - 6.00 0.268 6.00 0.054 0.00 - 0.322

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 99 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 100 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

0.000 2.289

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 101 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.00 - - - 4.00 0.388 4.00 0.009 0 - 0.398

- - - 0.00 - 0.00 - 0 - -

0.00 - - - 2.00 0.748 2.00 0.018 0 - 0.766

ELEKTROMEKANIK PROGRESS, Page 102 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.00 - 0.00 - - 3.00 0.226 3.00 0.047 0.00 - 0.273

0.00 - - - 2.00 0.252 2.00 0.006 0 - 0.258

0.00 - 0.00 - - 3.00 0.134 3.00 0.027 0.00 - 0.161

ELEKTROMEKANIK PROGRESS, Page 103 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 104 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 105 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

0.000 1.855

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 106 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.00 - - - 2.00 0.199 2.00 0.005 0 - 0.203

0.00 - - - 1.00 0.292 1.00 0.007 0 - 0.299

0.00 - 0.00 - - 6.00 0.319 6.00 0.066 0.00 - 0.385

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 107 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11
- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 108 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

0.000 0.888

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 109 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.00 - - - 4.00 0.278 4.00 0.007 0 - 0.284

- - - 0 - 0 - 0 - -

0.00 - - - 2.00 0.556 2.00 0.013 0 - 0.569

ELEKTROMEKANIK PROGRESS, Page 110 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.00 - 0.00 - - 6.00 0.585 6.00 0.123 0.00 - 0.709

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 111 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 112 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

0.000 1.562

ELEKTROMEKANIK PROGRESS, Page 113 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 114 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

0.000 0.000

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 115 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 116 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 117 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 118 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 119 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

0.000 0.000

- - - 0 - 0 - 0 - -

0.000 0.000

ELEKTROMEKANIK PROGRESS, Page 120 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 121 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.000 0.000

ELEKTROMEKANIK PROGRESS, Page 122 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

ELEKTROMEKANIK PROGRESS, Page 123 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 124 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.000 0.000

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 125 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

0.000 0.000

- - - 0 - 0 - 0 - -
ELEKTROMEKANIK PROGRESS, Page 126 of 281
PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 127 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.000 0.000

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 128 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

0.000 0.000

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 129 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.000 0.000

- - - 0 - 0 - 0 - -

- - - 0 - 0 - 0 - -

ELEKTROMEKANIK PROGRESS, Page 130 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11
- - - 0 - 0 - 0 - -

0.000 0.000

- - - 0 - 0 - 0 - -

0.000 0.000

- - - 0 - 0 - 0 - -

0.000 0.000

ELEKTROMEKANIK PROGRESS, Page 131 of 281


PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % %
10 9+10=11

0.000 6.916

Proposed by,
PT. GRID SOLUTIONS
INDONESIA
ELEKTROMEKANIK PROGRESS, Page 132 of 281
PROGRESS
THIS WEEK UP TO THIS WEEK

TRANSPORTASI JASA TOTAL MATERIAL TRANSPORTASI JASA TOTAL

WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT WEIGHT


QTY QTY QTY QTY QTY
% % % % % % Proposed by,
%
10 9+10=11 PT. GRID SOLUTIONS
INDONESIA

ARIEF RAHMAN
Site Manager

ELEKTROMEKANIK PROGRESS, Page 133 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 134 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 135 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 136 of 281


REMAKS

71.871%

ELEKTROMEKANIK PROGRESS, Page 137 of 281


REMAKS

68.484%

69.869%

ELEKTROMEKANIK PROGRESS, Page 138 of 281


REMAKS

72.611%

68.682%

ELEKTROMEKANIK PROGRESS, Page 139 of 281


REMAKS

71.871%

ELEKTROMEKANIK PROGRESS, Page 140 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 141 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 142 of 281


REMAKS

68.484%

69.869%

ELEKTROMEKANIK PROGRESS, Page 143 of 281


REMAKS

36.305%

68.682%

35.936%

ELEKTROMEKANIK PROGRESS, Page 144 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 145 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 146 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 147 of 281


REMAKS

68.529%

69.697%

72.069%

ELEKTROMEKANIK PROGRESS, Page 148 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 149 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 150 of 281


REMAKS

67.718%

69.657%

ELEKTROMEKANIK PROGRESS, Page 151 of 281


REMAKS

72.912%

ELEKTROMEKANIK PROGRESS, Page 152 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 153 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 154 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 155 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 156 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 157 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 158 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 159 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 160 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 161 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 162 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 163 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 164 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 165 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 166 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 167 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 168 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 169 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 170 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 171 of 281


REMAKS

ELEKTROMEKANIK PROGRESS, Page 172 of 281


REMAKS

Proposed by,
PT. GRID SOLUTIONS
INDONESIA
ELEKTROMEKANIK PROGRESS, Page 173 of 281
REMAKS

Proposed by,
PT. GRID SOLUTIONS
INDONESIA

ARIEF RAHMAN
Site Manager

ELEKTROMEKANIK PROGRESS, Page 174 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

SUMMARY CIVIL WORK


PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR 2 : CIVIL GI 150 KV
BILL NO 4 : REKAPITULASI HARGA CIVIL WORK GI 150 KV

GI 150 kV Teluk Naga II


PROGRESS
WEIGHT UP TO
NO. DESCRIPTION LAST WEEK THIS WEEK
THIS WEEK
REMAKS
(%) (%) (%) (%)
(1) (2) (4) (5) (6) (5+6=7)

1 BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV 20.258 0.003 0.000 0.003 0.02%

2 BILL NO 2 : SWITCHYARD FOR CIVIL WORKS GI TELUK NAGA 2 65.974 14.403 0.000 14.403 21.83%

3 BILL NO 4 : MISCELLANEOUS WORKS 13.768 10.908 0.000 10.908 79.23%

Total Proress Civil Work GI 150 kV 100.00 25.315 0.000 25.315

SUMMARY CIVIL WORK PROGRESS, Page 175 of 281


WEEKLY PROGRES
Week 42. (Period. 01 July -

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4

I Control Building SAS include corridor

1 Foundation work
Excavation of soil m3 265.00
Backfill filling (compacted) m3 106.00
Soil disposal m3 159.00
Import Soil Fill (compacted) m 3
261.00
Compacted sand layer (t = 10 cm) m 3
34.00
Lean concrete (t = 10 cm) m3 34.00
Foundation work, concrete K 300, Fe : 150 kg/m3, Formwork m3 25.00
Sloof work, concrete K 300, Fe : 150 kg/m3, Formwork m 3
17.00
Stone masonry ad 1 pc : 3 sand m 3
81.00

2 Structure and wall work


Column work, concrete K 300, Fe : 180 kg/m3, Formwork m3 19.00
Beam work, concrete K 300, Fe : 180 kg/m3, Formwork m3 18.00
Practical work, concrete K 225, Fe :120 kg/m3, Formwork m 3
5.00
Cannopy work, concrete K 300, Fe : 125 kg/m3, Formwork m3 4.00
A half brick wall ad 1 pc : 3 sand m2 507.00

3 Roof Work
Spandex metal sheet complete with accessories m2 514.00
Steel Structure frame, complete with bolt & galvanizing kg 4240.00
Purlin complete with plat simpul and steel painting kg 3016.00
Wind bracing and tie rod kg 207.00
Nok Spandek Metal m' 58.00
Thermal Insulation Glasswool, aluminium foil (single sided) with 2 (two) layer
m2 514.00
and roof mesh
Listplank Metal m' 135.00
Aluminium flashing t=0.50 mm including filler in both side m' 135.00
Water proofing membran type t= 3 mm and mortar screed m' 12.00
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 176 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
PVC pipe dia 4 inc include elbows m' 4.00

4 Floor Work
Slab floor work, concrete K 300, Fe : 150 kg/m3, Formwork m3 55.00
Rabat Concrete K 225 m 3
10.00
Ceramic floor tiles 300 x 300 mm (Control, PLC, terace, lobby, egineer room,
m2 225.00
AC/DC, Pantry, Corridor, Battery room)
Ceramic floor tiles 200 x 200 mm - anti-slip (Toilet) m2 4.00
Ceramic wall tiles 200 x 250 mm (Toilet & Battery Room) m2 78.00
Plint Ceramic 150 x 300 mm (control room, PLC, terace, lobby, egineer
m' 124.00
room, AC/DC, Pantry)
Stepnosing 100 x 300 mm (terrace) m' 22.00

5 Plastering & Grouting


Plaster ad 1 pc : 3 sand m2 1014.00
Acian m 2
936.00

6 Doors and windows


Door complete with frame and accessories:
- Type P1 unit 5.00
- Type P2 unit 0.00
- Type P3 unit 2.00
- Type P4 (Fibre door complete with frame and accessories) unit 1.00
Glass window complete with aluminium frame and accessories:
- Type J1 unit 13.00
- Type J2 unit 2.00
Glass ventilations complete with aluminium frame and accessories:
- Type V1 unit 2.00

7 Ceiling work
Ceilling Gypsum GRC, hollow frame m2 92.00
Ceiling Accoustic, alluminium frame m 2
242.00

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 177 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
8 Piping & Sanitary work
Closet Duduk Complete No 1.00
Wash Sink Complete (kitchen) No 1.00
Wastafel Complete No 2.00
Urinoir Complete No 0.00
Tempat Tisu Roll No 1.00
Tempat Sabun No 1.00
Gantungan Pakaian (multi hook) No 2.00
Installation of water supply pipe PVC dia 1/2 inc and fittings (include for all
pipes, bends, tees, albows, reducers, adaptors, taps and connections to ls 1.00
fittings, appliances, etc.)
Installation of water waste pipe PVC dia 3 inc and fittings (include for all
pipes, bends, tees, albows, reducers, adaptors, metal grill and connections to ls 1.00
fittings, appliances, etc.)
Water tank and steel structures tower ( cap : 2 m 3 ) and installation of pipe unit 1.00
Deepwell including submersible water pump 150 lt/m capacity and
set 1.00
accessories
Septictank cap 3 m3 included infiltrate cap 2 m3 complete with PVC, palm
unit 1.00
fibre and sand stone
Submersible Sewage Pump unit 2.00
Open Drainage (brick) 30/40 cm for control building
2
m' 96.00
PVC AW diameter 6'' m' 8.00

9 Cable Duct Indoor Include Metal Works


Cable Duct Type I m' 30.00
Cable Duct Type II m' 29.00
Cable Duct Type III m' 18.00

10 Painting Works
Wall and Ceiling interior painting m2 795.00
Wall and Ceiling exterior painting m 2
634.00
Steel Painting m 2
24.00

11 Electrical
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 178 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
Light type Led 9 watt including installation wiring and switch Sets 99.00
Stop contact including installation wiring Sets 29.00
Emergency lighting (30 W) including installation Sets 10.00
Panel Box MCB complete with R.S.T lamp indicator and contactor grounding Set 1.00

12 Air Conditioner and Exhaust fan


AC split 2 PK Sets 8.00
AC split 1 PK Sets 3.00
Exhaust fan wall 60 W/220 Volt (16") industrial Sets 2.00
Exhaust fan ceiling 40 W/220 Volt (10") very low noice Sets 2.00

13 Lightning Protection
Arder/ground rod icluded pipa and cable BC 25 mm2 and all accessories
clamps steel plate, material support and pole, grounding system for control Lot 1.00
building

14 Fire Alarm
Alarm bell 6" (150 mm) diameter including installation wiring Set 2.00
Smoke detector including installation wiring Sets 11.00
Fixed and rate of rise temperature detector including installation wiring Sets 11.00

MCFA (Master Control Fire Alrm) Including indication lamp, batttery rectifier a Set 1.00

15 Fire Fighting Equipment


Portable fire extinghuister type dry chemical ( 5 kg hallon ) Sets 4.00
Mobile unit powder fire extinghuister ( 50 kg hallon ) Set 1.00
Hydrant and accessories included installation of pipe, Fortable Pump for Fire
Hidrant complete = 1 unit, Hydrant Box Type C (Out Door) = 3 unit, Gate Lot 1.00
valve dia 2 1/2" kitz + Control box ( for Pipa Distribution Hidrant ) = 3 pieces
Submersible sewage pump unit 2.00
Underground Water Tank (cap : 24 m3) include jet pump unit 1.00

16 Sundries
Flagpole Stainless Steel ø 3" with acc + Foundation Set 1.00
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 179 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
Name plate "GI 150 kV TELUK NAGA II" work complete with stainless steel
pipe ø 2", stainless steel plate 1.2 mm, PLN's logo & block letter and Set 1.00
foundation of column
Key box Set 1.00

TOTAL Item 1-16 for Control Building SAS

II Control Building MV Cell


1 Foundation work
Excavation of soil m3 140.00
Backfill filling (compacted) m 3
56.00
Soil disposal m3 84.00
Import Soil Fill (compacted) m3 199.00
Compacted sand layer (t = 10 cm) m 3
30.00
Lean concrete (t = 10 cm) m 3
30.00
Foundation work, concrete K 300, Fe : 150 kg/m3, Formwork m3 24.00
Sloof work, concrete K 300, Fe : 150 kg/m3, Formwork m 3
5.00
Stone masonry ad 1 pc : 3 sand m 3
48.00

2 Structure and wall work


Column work, concrete K 300, Fe : 180 kg/m3, Formwork m3 17.00
Beam work, concrete K 300, Fe : 180 kg/m3, Formwork m 3
6.00
Practical work, concrete K 225, Fe :120 kg/m3, Formwork m 3
2.00
Cannopy work, concrete K 300, Fe : 125 kg/m3, Formwork m3 2.00
A half brick wall ad 1 pc : 3 sand m2 310.00

3 Roof Work
Spandex metal sheet complete with accessories m2 395.00
Steel Structure frame, complete with bolt & galvanizing kg 3331.00
Purlin complete with plat simpul and steel painting kg 2404.00
Wind bracing and tie rod kg 180.00
Nok Spandek Metal m' 46.00

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 180 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
Thermal Insulation Glasswool, aluminium foil (single sided) with 2 (two) layer
m2 395.00
and roof mesh
Listplank Metal m' 106.00
Aluminium flashing t=0.50 mm including filler in both side m' 106.00
Water proofing membran type t= 3 mm and mortar screed m' 11.00
PVC pipe dia 4 inc include elbows m' 4.00

4 Floor Work
Slab floor work, concrete K 300, Fe : 150 kg/m3, Formwork m3 42.00
Rabat Concrete K 225 m3 9.00
Floor hardener finished m2 218.00

5 Plastering & Grouting


Plaster ad 1 pc : 3 sand m2 568.00
Acian m2 568.00

6 Doors and windows


Door complete with frame and accessories:
- Type P1 unit 1.00
- Type P5 Steel folding door complete with frame, accessories and steel
unit 1.00
painting (3 x 2.70 m)
Ventilations complete with frame and accessories:
- Type V2 unit 16.00

7 Ceiling work
Ceilling Gypsum GRC, hollow frame m2 80.00
Ceiling Accoustic, alluminium frame m 2
210.00

8 Sanitary work
Open Drainage (brick) 30/40 cm2 for control building m' 80.00
PVC AW diameter 6' m' 5.00

9 Cable Duct Incd Metal Works


Cable Duct Type I m' 6.00
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 181 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
Cable Duct Type II m' 46.00
Cable Duct Type III m' 14.00

10 Painting Works
Wall and Ceiling interior painting m2 494.00
Wall and Ceiling exterior painting m 2
364.00
Steel Painting m2 26.00

11 Electrical
Light type Led 9 watt including installation wiring and switch Sets 82.00
Stop contact including installation wiring Sets 4.00
Emergency lighting (30w) including installation Sets 6.00
Panel Box MCB complete with R.S.T lamp indicator and contactor grounding Set 1.00

12 Air Conditioner and Exhoust fan


Exhaus fan wall 60 W/220 Volt (16") industrial Sets 16.00

13 Lightning Protection
Arder/ground rod icluded pipa and cable BC 25 mm2 and all accessories
clamps steel plate, material support and pole, grounding system for control Lot 1.00
building

14 Fire Alarm
Alarm bell 6" (150 mm) diameter including installation wiring No 2.00
Smoke detector including installation wiring No 6.00
Fixed and rate of rise temperature detector including installation wiring No 6.00

MCFA (Master Control Fire Alrm) Including indication lamp, batttery rectifier a No 1.00

15 Fire Fighting Equipment


Portable fire extinghuister type dry chemical ( 5 kg hallon ) No 2.00
Mobile unit powder fire extinghuister ( 50 kg hallon ) No 1.00

TOTAL Item 1-15 for Control Building MV Cell

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 182 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4

Total Progress for 150 KV CONTROL BUILDING SAS & 20 KV MV CELL BUILDING

Approved by, Checked by,


PT. PLN (Persero) PT. PLN (Persero)
UPP JISJ 3 PUSMANPRO
UPMK I

NOVAN PRASETYO
Manager Bagian Teknik DIMAS WAHYU ADHI K
KTSK BANTEN 2

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 183 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
OL BUILDING AND SAS & MV CELL 20KV

PROGRESS

UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11

0.058 45.36 0.010 - - 45.36 0.010 Continue


0.079 0 - - - -
0.142 0 - - - -
0.541 0 - - - -
0.275 0.34 0.003 - - 0.34 0.003 Continue
0.746 0.17 0.004 - - 0.17 0.004 Continue
2.270 - - - -
1.543 - - - -
1.528 - - - -

1.881 - - - -
1.782 - - - -
0.379 - - - -
0.336 - - - -
1.589 - - - -

2.190 - - - -
2.152 - - - -
1.531 - - - -
0.105 - - - -
0.471 - - - -

1.798 - - - -

0.176 - - - -
0.201 - - - -
0.028 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 184 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
OL BUILDING AND SAS & MV CELL 20KV

PROGRESS

UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
0.005 - - - -

4.993 - - - -
0.238 - - - -

0.966 - - - -

0.018 - - - -
0.318 - - - -

0.605 - - - -

0.088 - - - -

1.774 - - - -
0.743 - - - -

0.829 - - - -

0.175 - - - -
0.070 - - - -

2.059 - - - -
0.110 - - - -

0.031 - - - -

0.491 - - - -
1.772 - - - -

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 185 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
OL BUILDING AND SAS & MV CELL 20KV

PROGRESS

UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11

0.167 - - - -
0.014 - - - -
0.053 - - - -

0.005 - - - -
0.005 - - - -
0.010 - - - -

0.202 - - - -

0.244 - - - -

0.310 - - - -
0.164 - - - -

0.312 - - - -

0.139 - - - -
0.751 - - - -
0.024 - - - -

2.012 - - - -
1.191 - - - -
0.369 - - - -

0.731 - - - -
0.783 - - - -
0.039 - - - -

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 186 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
OL BUILDING AND SAS & MV CELL 20KV

PROGRESS

UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
1.019 - - - -
0.187 - - - -
0.159 - - - -
0.090 - - - -

2.228 - - - -
0.448 - - - -
0.378 - - - -
0.139 - - - -

0.813 - - - -

0.139 - - - -
0.547 - - - -
0.547 - - - -

0.239 - - - -

0.581 - - - -
0.696 - - - -

8.569 - - - -

0.139 - - - -
2.555 - - - -

0.030 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 187 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
OL BUILDING AND SAS & MV CELL 20KV

PROGRESS

UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11

0.149 - - - -

0.012 - - - -

64.277 0.016 0.000 0.016

0.031 - - - -
0.042 - - - -
0.075 - - - -
0.412 - - - -
0.243 - - - -
0.659 - - - -
2.179 - - - -
0.454 - - - -
0.905 - - - -

1.683 - - - -
0.594 - - - -
0.152 - - - -
0.168 - - - -
0.972 - - - -

1.683 - - - -
1.690 - - - -
1.220 - - - -
0.091 - - - -
0.373 - - - -

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 188 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
OL BUILDING AND SAS & MV CELL 20KV

PROGRESS

UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11

1.382 - - - -

0.138 - - - -
0.158 - - - -
0.026 - - - -
0.005 - - - -

3.813 - - - -
0.214 - - - -
0.809 - - - -

0.994 - - - -
0.451 - - - -

0.166 - - - -

0.235 - - - -

0.724 - - - -

0.427 - - - -
1.538 - - - -

0.626 - - - -
0.015 - - - -

0.402 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 189 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
OL BUILDING AND SAS & MV CELL 20KV

PROGRESS

UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
1.889 - - - -
0.287 - - - -

0.454 - - - -
0.449 - - - -
0.042 - - - -

0.844 - - - -
0.026 - - - -
0.095 - - - -
0.090 - - - -

3.024 - - - -

0.813 - - - -

0.139 - - - -
0.298 - - - -
0.298 - - - -

0.239 - - - -

0.290 - - - -
0.696 - - - -

35.723 0.000 0.000 0.000

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 190 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
OL BUILDING AND SAS & MV CELL 20KV

PROGRESS

UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11

100.00 0.016 0.000 0.016

ked by, Proposed by,


(Persero) PT. GRID SOLUTIONS
ANPRO INDONESIA
MK I

HYU ADHI K ARIEF RAHMAN


ANTEN 2 Site Manager

CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 191 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 2 : SWITCHYARD F

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4

I Preparatory work for Control Building , MV Cell and Switchyard

1 Site Clearing & Grubbing (Pengupasan t=20 cm) m2 19000.00


2 Topographical Survey Ls 1.00
3 Bowplank m' 463.00
4 Direksi Keet (4m x 6m) m 2
24.00
5 Site Storage (4m x 15 m) m2 60.00
6 Soil Investigation for control building :
Sondir pcs 6.00
Boring and Test Lab. pcs 3.00
Laporan Soil Investigation pcs 3.00
7 Design (calculation, detail design and drawing must be economical design) Ls 1.00
8 Exit permit, IMB and coordination to instansion Pemda Ls 1.00

Total Item I ( 1 - 8 )

II Site Works

1 Earthworks :
Excavation of Soil m3 3565.00
Soil Disposal m 3
2384.00
Backfill filling (compacted) m 3
1181.00
2 Embankment Construction :
Import Soil Fill (include compaction per layer of 20 cm) m3 40133.00
Test Sand Cone (per-layer of 20 cm) pcs 90.00
Retaining wall (stone masonry) m 3
1458.00
3 Road Works :
Compacted Subgrade m2 3098.00
Compacted Sandgravel / sirtu (t=20cm) m 2
3098.00
Lean Concrete (t =10cm) m2 3098.00
Reinforced Concrete Road K 300 m2 3098.00
CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 192 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 2 : SWITCHYARD F

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4

4 Kerbs :
Concrete Kerbs for switchyard (30x20 cm) m' 234.00
Concrete Kerbs for road and control building (40x25 cm) m' 673.00
5 Fence :
BRC 1.90 m height m' 28.00
BRC 1.50 m height m' 312.00
Brick wall 2.40 m + barbed wire 0.60 m m' 534.00
6 Gate :
Single gate BRC 1.50 m height, 1.1 m width Sets 4.00
Double gate BRC 1.50 m height, 3 m width Set 1.00
Sliding gate 2.4 m height, 6 m width Set 1.00
7 Landscaping (sodding grass) m2 586.00
8 Gravelling :
Compacted Gravel (dia 3 - 5 cm); thickness = 20 cm m3 1346.40
Sand layer below gravel (compacted sand); thickness = 5 cm m3 337.00
9 Cable trench for 150 kV (incld cover, galvanized L 50.50.5) :
Type 1 (Large, ±120 cm width ) m' 137.00
Type 2 (Medium, ± 80 cm width ) m' 94.00
Type 3 (Small, ± 60 cm width ) m' 177.00
Type 4 (Crossing road, ± 120 cm width) m' 12.00
10 Drainage :
Open Drainage stone masonry (40 x 70 cm) m' 540.00
Open Drainage brick (30 x 40 cm) m' 336.00
Sub soil Drainage dia 30 cm including gravel and Palm fibre m' 1056.00
Control Box Brick with cover (60 x 60 cm, height 70 cm) Unit 14.00
11 Post security (3,5m x 3,5 m) complete, included toilet (1,5m x 1,5m), septic tank Ls 1.00
Oil Pit Capacity 45 ton K 300, fe : 120kg/m3, Complete flashplate,
12 Unit 1.00
Galvanized steel pipe 6''
13 Phase name plate complete with fixing facilities pcs 21.00
14 Bay name plate complete with fixing facilities pcs 7.00

CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 193 of 281


WEEKLY PROGRES
Week 42. (Period. 01 July

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 2 : SWITCHYARD F

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4

15 Site and Road Lighting :


1. Mercury Vapour Flouresent light 1 x 250 W Sets 6.00
complete with lighting column 9 m high, fuse
box, grounding system and installation of cable
conduit and wiring and all accessories and
foundation of column

2. Mercury flood light 1x400 W complete with Sets 14.00


15 m height, fuse box, grounding system and
installation of cable conduit and wiring and
all accessories and foundation of column

3. Mercury Vapour Flouresent light 1 x 80 W Sets 10.00


complete with lighting column 2 m high, fuse
box, grounding system and installation of cable
conduit and wiring and all accessories and
foundation of column

4. Lighting panel outdoor complete with folo cell Set 1.00


switch fuse, mcb, grouding system
indicator wiring and all accessories (foto cell)
and foundation of panel

TOTAL ITEM II ( 1 - 16 )

III Foundation for 150 kV

1 Surge Arrester Unit 18.00


2 Capacitor Voltage Transformer Unit 18.00
3 Disconnecting Earthing Switches ( 1 set = 3 unit) Sets 4.00
4 Disconnecting Switches ( 1 set = 3 unit) Sets 14.00
5 Current Transformer Unit 24.00
6 Post Insulator Unit 12.00
7 Circuit Breaker ( 1 set = 3 unit) Sets 7.00
8 Post For Gantries TW1 (18m) Unit 24.00
9 Post For Gantries TW2 (10m) Unit 0.00
10 Post For Gantries TW3 Earthing (14m) Unit 1.00
11 Power Transformer 60 MVA Sets 2.00
12 Fire Wall Unit 1.00
CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 194 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July

PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 2 : SWITCHYARD F

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
13 Marshalling Kiosk Unit 7.00
14 Neutral Grounding Resistors (NGR) Unit 2.00
15 Support 20 kV Sets 2.00
16 Service transformers (include metal roofing and fence BRC 1.5 m) Sets 2.00

TOTAL ITEM III ( 1 - 16 )

TOTAL BILL NO 2 (Item I + II + III )

Approved by, Checked by,


PT. PLN (Persero) PT. PLN (Persero) PUSM
UPP JISJ 3 UPMK I

NOVAN PRASETYO DIMAS WAHYU ADH


Manager Bagian Teknik KTSK BANTEN 2

CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 195 of 281


Y PROGRESS REPORT
(Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
WITCHYARD FOR CIVIL WORKS

PROGRESS

WEIGHT LAST WEEK THIS WEEK UP TO THIS WEEK


REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11 12

0.580 - - - -
0.336 1.00 0.336 - - 1.00 0.336 Finish
0.158 463.00 0.158 - - 463.00 0.158 On Progress
0.264 24.00 0.264 - - 24.00 0.264 Finish
0.451 60.00 0.451 - - 60.00 0.451 Finish

0.092 6.00 0.092 - - 6.00 0.092 Finish


0.330 3.00 0.330 - - 3.00 0.330 Finish
0.046 3.00 0.046 - - 3.00 0.046 Finish

0.305 - - - -

2.562 1.676 0.000 1.676

0.240 - - - -
0.655 - - - -
0.271 - - - -

25.544 9387.16 5.9747 - - 9387.16 5.975


0.302 90.00 0.3024 - - 90.00 0.302
8.445 153.01 0.8863 - - 153.01 0.886 On Progress

0.795 - - - -
2.306 - - - -
2.089 - - - -
11.102 - - - -
CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 196 of 281
Y PROGRESS REPORT
(Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
WITCHYARD FOR CIVIL WORKS

PROGRESS

WEIGHT LAST WEEK THIS WEEK UP TO THIS WEEK


REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11 12

0.197 - - - -
0.946 - - - -

0.212 - - - -
1.618 - - - -
6.060 - - - -

0.027 - - - -
0.020 - - - -
0.117 - - - -
0.197 - - - -

3.907 - - - -
0.837 - - - -

2.085 - - - -
0.922 - - - -
1.142 - - - -
0.211 - - - -

2.296 - - - -
0.807 - - - -
1.088 - - - -
0.046 - - - -
0.547 - - - -

1.177 1.00 1.177 - - 1.00 1.177 Finish

0.038 - - - -
0.064 - - - -

CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 197 of 281


Y PROGRESS REPORT
(Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
WITCHYARD FOR CIVIL WORKS

PROGRESS

WEIGHT LAST WEEK THIS WEEK UP TO THIS WEEK


REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11 12

0.469 - - - -

0.565 - - - -

0.506 - - - -

0.046 - - - -

77.894 8.340 0.000 8.340

0.893 18.00 0.893 - - 18.00 0.893 Finish


0.998 1.00 0.055 - - 1.00 0.055 Continue
0.636 - - - -
2.226 - - - -
1.330 20.00 1.109 - - 20.00 1.109 CT & CMO
0.596 4.00 0.199 - - 4.00 0.199 Continue
1.113 - - - -
8.994 24.00 8.994 - - 24.00 8.994 Finish

0.177 - - - -
1.331 - - - -
0.565 1.00 0.565 - - 1.00 0.565 Finish
CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 198 of 281
Y PROGRESS REPORT
(Period. 01 July - 07 July 2019)

NAN GI 150 KV TELUK NAGA II


TAR 2 : CIVIL GI 150 KV
WITCHYARD FOR CIVIL WORKS

PROGRESS

WEIGHT LAST WEEK THIS WEEK UP TO THIS WEEK


REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11 12
0.120 - - - -
0.104 - - - -
0.060 - - - -
0.400 - - - -

19.544 11.815 0.000 11.815

100.00 21.831 0.000 21.831

hecked by, Proposed by,


ersero) PUSMANPRO PT. GRID SOLUTIONS
UPMK I INDONESIA

WAHYU ADHI K
K BANTEN 2 ARIEF RAHMAN
Site Manager

CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 199 of 281


WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)

PEMBANGUNAN GI 150 KV TELUK NAGA II


DAFTAR 2 : CIVIL GI 150 KV
BILL NO 3 : MISCELLANEOUS WORKS

GI 150 kV Teluk Naga II


PROGRESS
WEIGHT LAST WEEK THIS WEEK UP TO THIS WEEK
NO DESCRIPTION UNIT QTY UNIT PRICE REMAKS
(RUPIAH) WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)

1 2 3 4 5 5 6 7 8 9 6+8=10 7+9=11 8

I Miscellaneous Works

1 Concrete Works

- Concrete K 225 m3 15.00 1,556,481 0.526 - - - -

- Concrete K 300 m3 20.00 1,638,538 0.738 - - - -

2 Stone masonry 1 pc : 3 ps m3 35.00 1,232,580 0.971 - - - -

3 Reinforcement Work

- Reinforcement steel work U-24 kg 750.00 17,865 0.302 - - - -

- Reinforcement steel work U-32 kg 3,750.00 17,865 1.509 - - - -

4 Excavation Work

- Excavation of Soil m3 20.00 14,299 0.006 - - - -

5 Filling Work

- Import Soil Fill (include compaction in layer of 20 cm) m3 100.00 135,445 0.305 - - - -

6 Steel structures kg 1,500.00 33,160 1.120 - - - -

7 Driven Pile 30x30 K 450 m' 7,266.00 572,368 93.646 6147.40 79.229 - - 6147.40 79.229

8 Bored Pile Dia 40 cm K 225 m' 40.00 974,123 0.877 - - - -

TOTAL BILL NO 3 (Item I ) 100.00 79.229 0.000 79.229

Approved by, Checked by, Proposed by,


PT. PLN (Persero) PT. PLN (Persero) PUSMANPRO PT. GRID SOLUTIONS
UPP JISJ 3 UPMK I INDONESIA

NOVAN PRASETYO DIMAS WAHYU ADHI K


Manager Bagian Teknik KTSK BANTEN 2 ARIEF RAHMAN
Site Manager

CIVIL WORK PROGRESS_MISCELLANEOUS WORKS, Page 200 of 281


S CURVE
PEKERJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
Week 42. (Period. 01 July - 07 July 2019)
TAH
WEIGHT WEIGHT
SCOPE OVER ALL SEP OKT
NO DESCRIPTION
1 2 3 4 5 6 7
(%) (%) (19-23) (24-30) (01-07) (08-14) (15-21) (22-28) (29-04)

I. CIVIL WORK
A. SWITCHYARD
I Preparatory work for Control Building , MV Cell and Switchyard
1 Site Clearing & Grubbing (Pengupasan t=20 cm) 0.383% 0.115% 0.03% 0.03% 0.03% 0.03%
2 Topographical Survey 0.222% 0.067% 0.02% 0.02% 0.02% 0.02%
3 Bowplank 0.104% 0.031% 0.01% 0.01% 0.01% 0.01%
4 Direksi Keet (4m x 6m) 0.174% 0.053% 0.01% 0.01% 0.01%
5 Site Storage (4m x 15 m) 0.297% 0.090% 0.03%
Sondir 0.060% 0.018% 0.01% 0.01%
Boring and Test Lab. 0.218% 0.066% 0.03% 0.03%
Laporan Soil Investigation 0.030% 0.009% 0.01%
8 Exit permit, IMB and coordination to instansion Pemda 0.201% 0.061% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

II Site Works
1 Earthworks : 0.769% 0.232% 0.06% 0.06% 0.06% 0.06%
2 Embankment Construction : 22.623% 6.825% 0.97% 0.97%
3 Road Works : 10.748% 3.242%
4 Kerbs : 0.755% 0.228%
5 Fence : 5.205% 1.570%
6 Gate : 0.109% 0.033%
7 Landscaping (sodding grass) 0.130% 0.039%
8 Gravelling : 3.130% 0.944%
9 Cable trench for 150 kV (incld cover, galvanized L 50.50.5) : 2.876% 0.868%
10 Drainage : 2.795% 0.843%
11 Post security (3,5m x 3,5 m) complete, included toilet (1,5m x 1,5m), septic tank 0.361% 0.109%
Oil Pit Capacity 45 ton K 300, fe : 120kg/m3, Complete flashplate,
12 0.776% 0.234%
Galvanized steel pipe 6''
13 Phase name plate complete with fixing facilities 0.025% 0.008%
14 Bay name plate complete with fixing facilities 0.042% 0.013%
15 Site and Road Lighting : 1.046% 0.316%

III Foundation for 150 kV


1 Surge Arrester 0.589% 0.178%
2 Capacitor Voltage Transformer 0.658% 0.199%
3 Disconnecting Earthing Switches ( 1 set = 3 unit) 0.420% 0.127%
4 Disconnecting Switches ( 1 set = 3 unit) 1.469% 0.443%
5 Current Transformer 0.878% 0.265%
6 Post Insulator 0.393% 0.119%
7 Circuit Breaker ( 1 set = 3 unit) 0.734% 0.222%
8 Post For Gantries TW1 (18m) 5.934% 1.790%
10 Post For Gantries TW3 Earthing (14m) 0.117% 0.035%
11 Power Transformer 60 MVA 0.878% 0.265%
12 Fire Wall 0.372% 0.112%
13 Marshalling Kiosk 0.079% 0.024%
14 Neutral Grounding Resistors (NGR) 0.068% 0.021%
15 Support 20 kV 0.040% 0.012%
16 Service transformers (include metal roofing and fence BRC 1.5 m) 0.264% 0.080%

B. CONTROL BUILDING
I Control Building SAS include corridor
1 Foundation work 1.455% 0.439%
2 Structure and wall work 1.209% 0.365%
3 Roof Work 1.754% 0.529%
4 Floor Work 1.464% 0.442%
5 Plastering & Grouting 0.510% 0.154%
6 Doors and windows 0.663% 0.200%
7 Ceiling work 0.458% 0.138%
8 Piping & Sanitary work 0.486% 0.147%
9 Cable Duct Indoor Include Metal Works 0.723% 0.218%
10 Painting Works 0.315% 0.095%
11 Electrical 0.295% 0.089%
12 Air Conditioner and Exhaust fan 0.647% 0.195%
13 Lightning Protection 0.165% 0.050%
14 Fire Alarm 0.298% 0.090%
15 Fire Fighting Equipment 2.541% 0.766%
16 Sundries 0.039% 0.012%
II Control Building MV Cell
1 Foundation work 1.013% 0.306%
2 Structure and wall work 0.723% 0.218%
3 Roof Work 1.371% 0.414%
4 Floor Work 0.980% 0.296%
5 Plastering & Grouting 0.293% 0.088%
6 Doors and windows 0.228% 0.069%
7 Ceiling work 0.398% 0.120%
8 Sanitary work 0.130% 0.039%
9 Cable Duct Incd Metal Works 0.522% 0.158%
10 Painting Works 0.192% 0.058%
11 Electrical 0.214% 0.064%
12 Air Conditioner and Exhoust fan 0.613% 0.185%
13 Lightning Protection 0.165% 0.050%
14 Fire Alarm 0.197% 0.060%
15 Fire Fighting Equipment 0.200% 0.060%

C. MISCELLANEOUS
1 Concrete Works 0.174% 0.052%
2 Stone masonry 1 pc : 3 ps 0.134% 0.040%
3 Reinforcement Work 0.249% 0.075%
4 Excavation Work 0.001% 0.000%
5 Filling Work 0.042% 0.013% 0.00% 0.00% 0.00% 0.00%
6 Steel structures 0.154% 0.047%
7 Driven Pile 30x30 K 450 12.893% 3.890%
8 Bored Pile Dia 40 cm K 225 0.121% 0.036%

TOTAL CIVIL WORK 100.00% 30.17% 0.02% 0.08% 0.10% 0.12% 0.14% 1.08% 1.09%

II. ELEKTROMEKANIK WORK

1 150 KV SWITCHYARD STEEL STRUCTURES, BUSBAR, OVERHEAD GROUND WIRE (SHIELD WIRE)

1.1 Galvanized steel structure to complete the specified scope of work for switchyard with 7 Bay Do 5.833% 4.073%
1.2 Overhead Ground Wire (Shield Wire) and Accessories 0.316% 0.221%
1.3 Substation and Building Earthing System (Mesh/ Grid System and Rod Electrode) and Complete 3.437% 2.400%
1.4 150 kV Double Busbar Type U (Conductor 2 x TAL 850 mm2/phase) 3.036% 2.120%
2 150 KV LINE BAY TO PLTU LONTAR : 2 BAYS

2.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. 0.473% 0.330%
2.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/p 0.243% 0.169%
2.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to D 0.095% 0.067%
2.5 Spacer 20 cm for conductor 0.067% 0.047%
2.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm0.580% 0.405%
2.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconn 0.061% 0.043%
2.8 Circuit Breaker
Current 3 phase
Transformer 150 150 kV,kA
kV, 40 single poleBay,
for Line for line bay, Creepage
3 core, SF6, cap. distance
3150 Amp,31 40 kA, Creepage
mm/kV, 1.096%
complete with clamps and 0.765%
supporting steel structure.
Core-1 : Class PX, 2000-4000/1 A
2.9 0.752% 0.525%
Core-2 : Class 5P20, 2000-4000/1 A
2.10 Core-3 : Class switch
Disconnecting 0,5, 2000-4000/1 A
150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 0.376% 0.262%
(Option 2)
2.11 0.448% 0.313%
150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 15 VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, comp
2.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting st 0.310% 0.217%
2.13 Set of clamps, connectors and accessories for complete all installation 0.151% 0.105%
2.14 Protection and Control Cubicle for Line bay Comprising : 2.564% 1.790%
2.15 Marshaling kiosk for 150 kV Line Bay Comprising : 2.480% 1.731%
2.16 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet 0.106%
switch. 0.074%
2.17 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, ca 1.040% 0.726%

3 150 KV LINE BAY TO TELUK NAGA : 2 BAYS

3.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. 0.473% 0.330%
3.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/p 0.243% 0.169%
3.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to D 0.095% 0.067%
3.5 Spacer 20 cm for conductor 0.067% 0.047%
3.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm0.580% 0.405%
3.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconn 0.061% 0.043%
3.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage 1.096% 0.765%
3.9 (Option 3) 0.752% 0.525%
Current Transformer 150 kV, 40 kA for Line Bay, 3 core, Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
3.10 Disconnecting
Core-1 : Class switch 150 kV 3 phase
PX, 2000-4000/1 A motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, 0.376% 0.262%
Core-2 :
(Option 2)Class 5P20, 2000-4000/1 A
3.11 Core-3 : Class 0,5, 2000-4000/1 0.448%
A with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 0.313%
150kV capacitor voltage transformer 15 VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, complete with clamps, supp
3.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel struct 0.310% 0.217%
3.13 Set of clamps, connectors and accessories for complete all installation 0.151% 0.105%
3.14 Protection and Control Cubicle for Line bay Comprising : 2.249% 1.570%
3.15 IED Main Line Protection - Current differential, syncrocheck, etc, for installed in GI Teluk Naga 0.822% 0.574%
3.16 Marshaling kiosk for 150 kV Line Bay Comprising : 2.480% 1.731%
3.17 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. 0.106% 0.074%
V power cable, 3.18
control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal, … etc) to complete1.040%
the scope of works
0.726%

4 150 kV BUS COUPLER BAY : 1 BAY

4.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar. 0.237% 0.165%
4.3 Double Tension Insulator String Set for Crossbar 2 x TAL 850 mm2/phase 0.364% 0.254%
4.4 Single Suspension Insulator String Set for Crossbar 2 x TAL 850 mm2/phase 0.143% 0.100%
4.5 Spacer 20 cm for conductor 0.101% 0.071%
4.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 4000 Amp, 40 kA, Creepage distance 3 0.297% 0.207%
4.7 Circuit Breaker 3 phase 150 kV, three pole for Couple bay, SF6, cap. 4000 Amp, 40 kA, Creepa 0.429% 0.300%
4.8 (Option 3) 0.535% 0.373%
Current Transformer 150 kV, 50 kA for bus coupler bay, 2 core, Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
4.9 Set of clamps, connectors and accessories for all installation (including Inter HV equipment) 0.077% 0.054%
Core-1 : Class 5P20, 2000-4000/1
4.10 Core-2 : Class
Protection and PX, 2000-4000/1
Control Cubicle for Line bay Comprising : 3.495% 2.440%
4.11 Marshaling kiosk for 150 kV Coupler Bay Comprising : 2.231% 1.558%
4.12 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet 0.053%
switch. 0.037%
4.13 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, ca 0.520% 0.363%

5 150 kV TRANSFORMER BAY : 2 BAY(S)

5.1 Crossbar Conductor 1 x TAL 850 mm2/phase + Dropper's Busbar to DS and Crossbar Conductor to DS & 0.107% 0.075%
5.3 Single Tension Insulator String Set for installation the Crossbar, Conductor 1 x TAL 850 mm2/phase 0.182% 0.127%
5.4 Single Suspension Insulator String Set with Conductor 1 x TAL 850 mm2/phase to DS & CB 0.095% 0.067%
5.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 1250 Amp, 40 kA, Creepage distance 31 mm/kV, 0.420% 0.293%
5.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector swi 0.061% 0.043%
5.8 Circuit Breaker 3 phase 150 kV, three pole for trafo bay, SF6, cap. 1250 Amp, 40 kA, Creepage distance 0.816% 0.570%
5.9 (Option 3) 0.972% 0.679%
Current transformer 150 kV, 40 kA for transformer bay, 4 core, Creepage distance 31 mm/kV complete with clamps and supporting steel structure.
5.10 Lightning
Core-1 Arrester
: Class PX,150 kV, 20 kA
150-300/1 A for Line bay, complete with clamp, surge counter, supporting steel struct 0.310% 0.217%
Core-2 : Class 5P20, 150-300/1 A
Set of clamps, connectors and accessories for installation
5.11 Core-3 : Class PX, 2000-4000/1 A 0.151% 0.105%
5.12 Core-4 : Class
Protection and 0.5, 150-300/1
Control CubicleAfor 150/20 kV Transformer Bay Comprising : 3.247% 2.267%
5.13 Marshaling kiosk for 150 kV Transformer Bay Comprising : 3.471% 2.424%
5.14 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. 0.106% 0.074%
5.15 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, 1.040% 0.726%

6 150/20 KV POWER TRANSFORMERS AND AUXILIARIES

6.4 Single phase neutral CT for 150 kV side Class x 150-300/1A complete with clamps for restricted earth fault 0.097% 0.068%
6.5 20 kV stainless steel neutral earthing resistor rated 12 Ohm, 10 seconds. 0.872% 0.609%
6.6 Transformer online monitoring system comprising : 6.602% 4.610%
6.7 Transformer Blast and Fire Prevention equipment, complete with accessories 5.817% 4.062%

7 20 kV SWITCHGEARS AND POWER CABLES

7.1 3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between 150/20 kV power transform
1.006% 0.703%
7.2 3 phase, 1 x single core of 95 SQMM copper 20 kV XLPE power cable/phase between 20 kV auxiliary transfo0.116% 0.081%
7.3 Power cable 20 kV XLPE Alluminium single core 1 x 630 sqmm (for Neutral Cable), between 150/20 kV 0.025% 0.017%
7.4 - Incoming Cubicle. 1.216% 0.849%
- Busbar PT + Earthing Switch Cubicle. 0.579% 0.404%
- Auxiliary Transformer Cubicle. 0.515% 0.360%
- Outgoing Feeder Cubicle 6.417% 4.481%
- Bus Section 0.898% 0.627%
- Bus Riser Cubicle 0.460% 0.321%
7.5 Wall mounting panel Comprising : 0.929% 0.648%
3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between bus-section cubicle and0.197% 0.138%
7.6
20/0.4 kV 200 kVA 3-phase station auxiliary transformer complete with necessary accessories (vector gr 0.253% 0.177%
7.7

8 ENERGY METERS FOR ALL TRANSFORMER FEEDER BAYS 0.704% 0.491%

9 SUBSTATION AUTOMATION HARDWARE 5.157% 3.602%

12 INVERTER FOR SUBSTATION AUTOMATION

12.1 Inverter including AC Distribution Board 0.095% 0.066%

13 TELECOMMUNICATION EQUIPMENT

13.1 SDH ADM MUX complete with terminal : (Should be identic with existing MUX in GI 150KV P 0.769% 0.537%
13.2 PAX (16 trunks - 12 subscriber) complete with telephone set of each subsriber 0.572% 0.400%
13.3 MDF Main Distribution Frame 0.157% 0.110%
Digital Teleprotection
13.4 Panel, Rack/Cabinet for telecomunication equipment 0.562% 0.392%
Note : 1 Sets to be installed in 150 kV Teluk Naga substation
13.5 Including integration and adaptation to eksisting system to complte the scope of works 0.377% 0.263%
13.7 Fiber Optic Armoured (FA) Cable 16 cores to connect OPGW (GB) to ODF in telecommunication r 0.104% 0.073%
13.8 Optical Distribution Frame (ODF) (16 port) 0.127% 0.089%
13.9 Gantry Box for OPGW 0.085% 0.060%
13,10 Miscellaneous item, equipment and material including cables, patch cord, pig tail, telephone cab 0.240% 0.167%

14 RADIO TRANCEIVER (Low Band Frekuensi), Tower, dan Aksesoris

14.1 Radio Tranceiver (equal to Simoco) 0.274% 0.191%


14.8 Tower Radio SST 25 m
1. Foundation for 25 m Tower 0.238% 0.166%

15 150 kV SUBSTATION AUXILIARIES EQUIPMENT

15.1 110 V DC Battery suitable for supplying all 110 V DC load for 8 hours discharge. (Capacity of ba 1.451% 1.013%
15.2 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation 0.449% 0.313%
15.3 110V DC Switch Board complete, incl. ATS, 2 MCB's incoming,1 MCB section and 2 x 12 MCB 1.110% 0.775%
15.4 48 V DC Battery suitable for supplying all 48 V DC load for 8 hours discharge. (Capacity of bate 0.204% 0.142%
15.5 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation 0.358% 0.250%
15.6 48V DC Switch Board complete, incl. ATS, outgoing MCB's minimum for 10 bays. 0.351% 0.245%
15.7 400V AC Switch MCB's Distribution Board suitable for the 2 units station service transformer in 0.967% 0.675%
15.8 Miscellaneous material, LV power cable, control cable and accesorries and necessary equipment (c0.526% 0.367%

16 MISCELLANEOUS

16.1 Fault Recorder Equipment for 10 bays and Panel 1.206% 0.842%
16.2 CCTV and Thermal and visual monitoring system compressed : 1.106% 0.772%

17 Training FOR ALL SCOPE OF PROJECT

- Digital Substation Engineering and Design (TSS 3.3.1) : for 4 PLN engineers, 14 days 0.244% 0.170%
- Substation automation and telecommunication engineering (TSS 3.3.2 and TSS 5.17) : for 0.244% 0.170%
- Substation operation and maintenance (TSS 3.3.2) : for 8 PLN staff, 14 days 0.488% 0.340%

18 TEST AND COMISSIONING FOR ALL SCOPE OF PROJECT 1.565% 1.093%

TOTAL ELEKTROMEKANIK WORK 100.00% 69.83% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TOTAL OVER ALL 100.00% 0.02% 0.08% 0.10% 0.12% 0.14% 1.08% 1.09%

PLANNING PROGRESS 0.019% 0.081% 0.098% 0.125% 0.138% 1.084% 1.087%

CUMULATIVE PLANNING PROGRESS 0.019% 0.100% 0.198% 0.323% 0.460% 1.544% 2.632%
-
ACTUAL PROGRESS 0.093% 0.067% 0.000% 0.000% 0.000% 0.000% 0.000%

CUMULATIVE ACTUAL PROGRESS 0.093% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160%
-
TAHUN 2018
NOV DES JAN FEB

8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
(05-11) (12-18) (19-25) (26-02) (03-09) (10-16) (17-23) (24-30) (31-06) (07-13) (14-20) (21-27) (28-03) (04-10) (11-17) (18-24) (25-03)

0.01%
0.03% 0.03%

0.97% 0.97% 0.97% 0.97% 0.97%

0.12% 0.12% 0.12% 0.12%


0.04% 0.04% 0.04% 0.04% 0.04%
0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
0.03% 0.03% 0.03% 0.03% 0.03%
0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
0.03% 0.03% 0.03% 0.03%
0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20% 0.20%
0.01% 0.01%
0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
0.03%
0.01% 0.01%

0.02%

0.22% 0.22%
0.07%
0.03% 0.03%
0.02% 0.02%
0.03% 0.03% 0.03%
0.00% 0.00%

0.01% 0.01% 0.01% 0.01% 0.01% 0.01%


0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
0.01% 0.01% 0.01% 0.01%

1.50% 1.49% 1.46% 1.46% 1.46% 0.49% 0.50% 0.77% 0.48% 0.55% 0.55% 0.53% 0.43% 0.52% 0.46% 0.65% 0.48%

0.03% 0.03%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03%

1.50% 1.49% 1.46% 1.46% 1.46% 0.49% 0.50% 0.77% 0.48% 0.55% 0.55% 0.53% 0.43% 0.52% 0.46% 0.68% 0.51%

1.504% 1.491% 1.461% 1.461% 1.461% 0.486% 0.495% 0.771% 0.485% 0.554% 0.551% 0.526% 0.435% 0.518% 0.456% 0.677% 0.511%

4.136% 5.627% 7.088% 8.549% 10.010% 10.497% 10.992% 11.763% 12.248% 12.802% 13.353% 13.879% 14.314% 14.832% 15.287% 15.964% 16.475%

0.584% 0.030% 0.000% 0.605% 0.030% 0.000% 0.090% 0.000% 0.053% 0.000% 0.000% 0.051% 0.226% 0.263% 0.430% 0.326% 0.468%

0.744% 0.774% 0.774% 1.379% 1.409% 1.409% 1.499% 1.499% 1.552% 1.552% 1.552% 1.603% 1.829% 2.092% 2.521% 2.847% 3.315%
TAHUN 2019
MAR APR MEI JUN

25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
(04-10) (11-17) (18-24) (25-31) (01-07) (08-14) (15-21) (22-28) (29-05) (06-12) (13-19) (20-26) (27-02) (03-09) (10-16) (17-23) (24-30)

0.41%

0.12% 0.12% 0.12%


0.12% 0.12% 0.12% 0.12% 0.12% 0.12% 0.12%
0.02% 0.02% 0.02% 0.02% 0.02%
0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
0.01% 0.01% 0.01%

0.03% 0.03% 0.03%


0.01%
0.01% 0.01%
0.01% 0.01%
0.02% 0.02% 0.02%

0.07% 0.07% 0.07% 0.07%


0.18% 0.18% 0.18%
0.15% 0.15% 0.15%
0.05% 0.05% 0.05%
0.10% 0.10%
0.07% 0.07%
0.05% 0.05% 0.05%
0.07% 0.07% 0.07%
0.05% 0.05%
0.04% 0.04%
0.20%
0.02% 0.02%
0.09%
0.77%
0.00% 0.00% 0.00%
0.31%
0.05% 0.05% 0.05% 0.05%
0.21% 0.21%
0.15% 0.15%
0.09%
0.07%
0.06% 0.06%
0.02% 0.02%
0.08% 0.08%
0.06%
0.03% 0.03%
0.18%
0.02% 0.02%
0.06%
0.06%

0.27% 0.34% 0.81% 0.58% 0.49% 0.57% 0.90% 0.97% 1.50% 0.37% 0.45% 0.02% 0.02% 0.02% 0.02% 0.02% 0.41%

0.58% 0.58% 0.58% 0.58% 0.58% 0.58% 0.58%


0.03% 0.03% 0.03% 0.03% 0.03%
0.40% 0.40% 0.40% 0.40% 0.40% 0.40%
0.53% 0.53% 0.53% 0.53%
0.08% 0.08% 0.08% 0.08%
0.06% 0.06% 0.06%
0.02% 0.02% 0.02%
0.02% 0.02% 0.02%
0.10% 0.10% 0.10% 0.10%
0.01% 0.01% 0.01%
0.15% 0.15% 0.15% 0.15% 0.15%
0.18% 0.18% 0.18%
0.09% 0.09% 0.09%
0.08% 0.08% 0.08% 0.08%
0.07% 0.07% 0.07%
0.04% 0.04% 0.04%
0.45% 0.45% 0.45% 0.45%
0.58% 0.58% 0.58%
0.04% 0.04%
0.18% 0.18% 0.18% 0.18%

0.17% 0.17%
0.08% 0.08%
0.03% 0.03%
0.02% 0.02%
0.14% 0.14% 0.14%
0.02% 0.02%
0.19% 0.19% 0.19% 0.19%
0.11% 0.11% 0.11% 0.11%
0.26%
0.31%
0.07% 0.07% 0.07%
0.05% 0.05%
0.52% 0.52%
0.14% 0.14% 0.14%
0.58% 0.58%
0.02% 0.02% 0.02%
0.36% 0.36%

0.08% 0.08%
0.13%

0.12%

0.52%

0.02% 0.02%
0.20%
0.92%
0.61% 0.61% 0.61% 1.01% 1.01% 0.98% 0.98% 0.93% 0.93% 0.79% 1.10% 0.75% 1.33% 1.55% 2.38% 3.89% 5.52%

0.88% 0.95% 1.43% 1.60% 1.50% 1.55% 1.88% 1.90% 2.43% 1.16% 1.55% 0.77% 1.36% 1.57% 2.40% 3.91% 5.93%

0.884% 0.954% 1.426% 1.598% 1.504% 1.547% 1.878% 1.901% 2.429% 1.156% 1.551% 0.767% 1.355% 1.574% 2.400% 3.911% 5.927%

17.359% 18.313% 19.739% 21.338% 22.842% 24.389% 26.267% 28.167% 30.596% 31.752% 33.303% 34.070% 35.425% 36.999% 39.399% 43.310% 49.238%

0.462% 6.709% 0.154% 1.120% 0.793% 0.539% 0.288% 0.143% 0.257% 0.051% 2.026% 0.367% 0.000% 0.000% 0.000% 0.000% 0.020%

3.777% 6.709% 6.863% 7.983% 8.776% 9.315% 9.603% 9.746% 10.003% 10.054% 12.080% 12.447% 12.447% 12.447% 12.447% 12.447% 12.467%
JUL AGU SEP
REMAKS
42 43 44 45 46 47 48 49 50 51 52 53
(01-07) (08-14) (15-21) (22-28) (29-04) (05-11) (12-18) (19-25) (26-01) (02-08) (09-15) (16-19)

0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%


0.11% 0.11%
0.31% 0.31% 0.31% 0.31% 0.31%
0.02% 0.02%
0.02% 0.02%
0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13%
0.00% 0.00%
0.01% 0.01%
0.08% 0.08% 0.08% 0.08%
0.54% 0.54% 0.54% 0.54% 0.85% 0.85% 0.86% 0.53% 0.55% 0.10% 0.08% 0.00%
0.11%

0.52%
0.14%
0.58%
0.13%
0.05% 0.05%
0.04% 0.04%
0.10% 0.10%
0.10% 0.10% 0.10%
0.12% 0.12%
0.03% 0.03%
0.81% 0.81% 0.81%
0.52% 0.52%
0.02% 0.02%
0.12% 0.12% 0.12%

0.02% 0.02% 0.02%


0.04% 0.04% 0.04%
0.03% 0.03%
0.10% 0.10% 0.10%
0.02% 0.02%
0.14% 0.14% 0.14% 0.14%
0.23% 0.23% 0.23%
0.11% 0.11%
0.05% 0.05%
1.13% 1.13%
0.81% 0.81% 0.81%
0.04% 0.04%
0.18% 0.18% 0.18% 0.18%

0.02% 0.02%
0.20% 0.20%
0.92% 0.92% 0.92% 0.92%
0.81% 0.81% 0.81% 0.81% 0.81%

0.23% 0.23% 0.23%


0.04% 0.04%
0.01% 0.01%
0.28% 0.28% 0.28%
0.13% 0.13% 0.13%
0.12% 0.12% 0.12%
1.12% 1.12% 1.12% 1.12%
0.31% 0.31%
0.16% 0.16%
0.16% 0.16% 0.16% 0.16%
0.05% 0.05% 0.05%
0.06% 0.06% 0.06%

0.10% 0.10% 0.10% 0.10% 0.10%

0.72% 0.72% 0.72% 0.72% 0.72%

0.03% 0.03%

0.18% 0.18% 0.18%


0.20% 0.20%
0.11%
0.13% 0.13% 0.13%
0.13% 0.13%
0.07%
0.09%
0.03% 0.03%
0.03% 0.03% 0.03% 0.03% 0.03%

0.06% 0.06% 0.06%

0.06% 0.06% 0.06%

0.25% 0.25% 0.25% 0.25%


0.16% 0.16%
0.26% 0.26% 0.26%
0.05% 0.05% 0.05%
0.08% 0.08% 0.08%
0.12% 0.12%
0.17% 0.17% 0.17% 0.17%
0.12% 0.12% 0.12%

0.21% 0.21% 0.21% 0.21%


0.26% 0.26% 0.26%

0.04% 0.04% 0.04% 0.04%


0.04% 0.04% 0.04% 0.04%
0.09% 0.09% 0.09% 0.09%

0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16%

4.47% 3.30% 4.48% 4.73% 6.79% 7.22% 6.42% 4.45% 1.34% 0.79% 0.54% 0.24%

5.01% 3.84% 5.02% 5.27% 7.64% 8.08% 7.28% 4.98% 1.89% 0.89% 0.62% 0.24%

5.015% 3.843% 5.016% 5.269% 7.641% 8.076% 7.278% 4.983% 1.888% 0.893% 0.620% 0.241%

54.252% 58.096% 63.111% 68.381% 76.022% 84.097% 91.375% 96.358% 98.246% 99.139% 99.759% 100.00%

0.000%

12.467%
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4

CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017


PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)

I. Control Building SAS include corridor

No Description / Sketc As

1. Foundation work
Excavation of soil

==>
==>
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4

CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017


PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4

CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017


PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)

Approved by,
PT. PLN (Persero) PT. PLN
UPP JISJ 3

RIZKI JULIAWAN

I. Control Building SAS include corridor

No Description / Sketc As

1. Foundation work
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4

CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017


PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)

Compacted sand layer (t = 10 cm)


PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4

CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017


PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)

Approved by,
PT. PLN (Persero) PT. PLN
UPP JISJ 3
PEKERJAAN PEMB
Approved by,
PT. PLN (Persero)
Breakdown analisis for BILL NO
PT. PLN
Week 4
UPP JISJ 3
CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017
PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)

RIZKI JULIAWAN

I. Control Building SAS include corridor

No Description / Sketc As

1. Foundation work
Lean concrete
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4

CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017


PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4

CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017


PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)

Approved by,
PT. PLN (Persero) PT. PLN
UPP JISJ 3

RIZKI JULIAWAN
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)

Calculation Quantity

Foundation work
Excavation of soil

Elv. Ground Level = -0.45


Elv. Finish Excavation = -1.15

VOL = P x L x T x ∑. Pond
= 2.40 x 1.00 x 0.70 x 27.00 ==> of 28,00 unit Foundation
= 45.36 m3
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)

TOTAL Foundation work - Excavation of soil = 45.36


RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)

Checked by, Proposed by,


PT. PLN (Persero) PUSMANPRO PT. GRID SOLUTIONS INDO
UPMK I

BUDI YULIANTO ARIEF RAHMAN


Site Manager

Calculation Quantity

Foundation work
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)

Compacted sand layer (t = 10 cm)

VOL = P x L x T x ∑. Pond
= 1.60 x 0.70 x 0.10 x 3.00 ==> of 28,00 unit Foundation
= 0.34 m3
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)

TOTAL Foundation work - Compacted sand layer = 0.34

Checked by, Proposed by,


PT. PLN (Persero) PUSMANPRO PT. GRID SOLUTIONS INDO
UPMK I
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
Checked by, Proposed by,
for BILL NO 1(Persero)
PT. PLN : CONTROL BUILDING AND SAS & MV CELL 20KV
PUSMANPRO PT. GRID SOLUTIONS INDO
Week 42. (Period.
UPMK 01 IJuly - 07 July 2019)

BUDI YULIANTO ARIEF RAHMAN


Site Manager

Calculation Quantity

Foundation work
Lean concrete

VOL = P x L x T x ∑. Pond
= 1.60 x 0.70 x 0.05 x 3.00 ==> of 28,00 unit Foundation
= 0.17 m3
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)

TOTAL Foundation work - Compacted sand layer = 0.17

Checked by, Proposed by,


PT. PLN (Persero) PUSMANPRO PT. GRID SOLUTIONS INDO
UPMK I

BUDI YULIANTO ARIEF RAHMAN


Site Manager
Unit Kode Remarks
m3 Continue
Proposed by,
PT. GRID SOLUTIONS INDONESIA

ARIEF RAHMAN
Site Manager

Unit Kode Remarks


m3 Continue

Proposed by,
PT. GRID SOLUTIONS INDONESIA
Proposed by,
PT. GRID SOLUTIONS INDONESIA

ARIEF RAHMAN
Site Manager

Unit Kode Remarks


m3 Continue

Proposed by,
PT. GRID SOLUTIONS INDONESIA

ARIEF RAHMAN
Site Manager
PEKERJA
Brea

CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017


PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)

I. Preparatory work for Control Building , MV Cell and Switchyard

No Description / Sketc As

3 Bowplank (m')

2
3

7
Approved by,
PT. PLN (Persero) P
UPP JISJ 3

RIZKI JULIAWAN

II. Site Works

No Description / Sketc As
1 Earthworks :
Backfill filling (compacted)

1
Approved by,
PT. PLN (Persero) P
UPP JISJ 3

RIZKI JULIAWAN
PEKERJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
Breakdown analisis for Switchyard Foundation
Week 42. (Period. 01 July - 07 July 2019)

Calculation

Bowplank (m')

VOL = P x ∑ x ∑. Pond

Gantry Foundation ==> 24 unit


Vol. = 5.50 x 4.00 x 24.00
= 528.00 m'

Trafo Foundation (Block Foundation Area) ==> 2 unit

Vol. = 8.00 x 2.00 + 5.20 x 2.00 x 2.00


= 52.80 m'

Firewall Foundation ==> 1 unit

Vol. = 7.20 x 2.00 + 4.00 x 2.00 x 1.00

= 22.40 m'

SA Foundation (m10) ==> 6 unit


Vol. = 3.20 x 4.00 x 6.00
= 76.80 m'

CT Foundation (m12) ==> 6 unit


Vol. = 3.20 x 4.00 x 7.00
= 89.60 m'

OilPit Foundation (OP) ==> 1 unit

Vol. = 7.20 x 2.00 + 6.20 x 2.00 x 1.00

= 26.80 m'

CMO Foundation (m19) ==> 3 unit


Vol. = 3.20 x 4.00 x 3.00
= 38.40 m'

TOTAL Bowplank (m') =

Checked by,
PT. PLN (Persero) PUSMANPRO PT.
UPMK I

BUDI YULIANTO

Calculation
Earthworks :
Backfill filling (compacted)

Switchyard Access Road

==> Elv. Desain = 3.100


==> Elv. Rata2 Tanah Existing = 3.044
==> Elv. Deviasi = 0.056

VOL = P x L x T
= 0.00 x 0.00 x 0.000
= 0
0

Checked by,
PT. PLN (Persero) PUSMANPRO PT.
UPMK I

BUDI YULIANTO
Quantity Unit Kode Remarks

Hanya
bisa
diprogress
Hanya
bisa
diprogress
sesuai
quantity
kontrak,
Quantity
aktual
akan
diprogres
pada saat
kerja
tambah
kurang
834.80 m'

Proposed by,
PT. GRID SOLUTIONS INDONESIA

ARIEF RAHMAN
Site Manager

Quantity Unit Kode Remarks


Proposed by,
PT. GRID SOLUTIONS INDONESIA

ARIEF RAHMAN
Site Manager
Control Building , MV Cell and Switchyard

No Description / Sketc As Calculation Quantity Unit Kode Remarks

II Site Works

2 Embankment Construction : Embankment Construction :


Retaining wall (stone masonry) /m3 Retaining wall (stone masonry) /m3

=> Panjang Retaining Wall = 170.67 m' ==> South Area


Yang sudah Selesai di Periode ini = 115.79 m' ==> West Area
= 90.19 m' ==> WNorth Area
= 107.19 m' (+) ==> East Area (On Progress)
483.83 m'

=> Vol. Retaining Wall/ m' = P x L.atas + L.bawah x T


2.00

0.45 + 0.70 x 0.55


= 1.00 x 2.00

= 1.00 x 0.58 x 0.55

= 0.316 m3/m'

JADI Volume Retaini


Vol. = Vol. Retaining Wall/ m' x Panjang Retaining Wall
= 0.32 x 483.83
= 153.012 m3

TOTAL - Retaining wall (stone masonry) /m3 = 153.012 m3

Approved by, Checked by, Proposed by,


PT. PLN (Persero) PT. PLN (Persero) PUSMANPRO PT. GRID SOLUTIONS INDONESIA
UPP JISJ 3 UPMK I

RIZKI JULIAWAN BUDI YULIANTO ARIEF RAHMAN


Site Manager
SITE WEATHER REPORT (SWR)
Week 42. (Period. 01 July - 07 July 2019)

LEGEND Bright Cloudy Drizzle Rain

Date Day Hours Remarks

am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
24 Mon
Week 42. (Period. 01 July - 07 July

pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00

am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
25 Tue
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00

am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
26 Wed
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00

am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
27 Thu
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00

Fri am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
2019)

28
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00

Sat am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
THIS WEEK,

29
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00

Sun am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
30
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00

Approved by, Checked by, Proposed by,


PT. PLN (Persero) PT. PLN (Persero) PUSMANPRO PT. GRID SOLUTIONS INDONESIA
UPP JISJ 3 UPMK I

NOVAN PRASETYO DIMAS WAHYU ADHI K ARIEF RAHMAN


Manager Bagian Teknik KTSK BANTEN 2 Site Manager
DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT

UNIT PRICE MATERIAL, REMUNERATION AND RENT PRICE


NO. UNIT
OFEQUIPMENT (Rp.)

I MATERIAL :
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46

Name of Bidder :Signed of Bidder : UP. 270 of 281


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT

UNIT PRICE MATERIAL, REMUNERATION AND RENT PRICE


NO. UNIT
OFEQUIPMENT (Rp.)

47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78

II REMUNERATION
1
2
3
4
5
6
7
8
9
10

III RENT OF EQUIPMENT


1

Name of Bidder :Signed of Bidder : UP. 271 of 281


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT

UNIT PRICE MATERIAL, REMUNERATION AND RENT PRICE


NO. UNIT
OFEQUIPMENT (Rp.)

2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

Name of Bidder :Signed of Bidder : UP. 272 of 281


: BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
REMUNERATION AND RENT OF EQUIPMENT

REMARK

Name of Bidder :Signed of Bidder : UP. 273 of 281


: BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
REMUNERATION AND RENT OF EQUIPMENT

REMARK

Name of Bidder :Signed of Bidder : UP. 274 of 281


: BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
REMUNERATION AND RENT OF EQUIPMENT

REMARK

Name of Bidder :Signed of Bidder : UP. 275 of 281


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
BREAKDOWN PRICE FOR CIVIL WORKS
UNIT PRICE

UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)

Name of Bidder :Signed of Bidder : Bdprice 276 of 281; R-1


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
BREAKDOWN PRICE FOR CIVIL WORKS
UNIT PRICE

UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)

Name of Bidder :Signed of Bidder : Bdprice 277 of 281; R-1


2 : BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
DOWN PRICE FOR CIVIL WORKS
UNIT PRICE

TOTAL PRICE
LOCAL

(RUPIAH)

Name of Bidder :Signed of Bidder : Bdprice 278 of 281; R-1


2 : BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
DOWN PRICE FOR CIVIL WORKS
UNIT PRICE

TOTAL PRICE
LOCAL

(RUPIAH)

Name of Bidder :Signed of Bidder : Bdprice 279 of 281; R-1


4. BILL NO 4 : ANALYSIS UNIT PRICE
Breakdown Price for Foundation and Steel Structure for 150 kV Switchgear

Foundation : .....................................
UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)

TOTAL

Note:
1. Breakdown Price for Foundation (Fixed Price)
2. Shall be installed in BILL NO 2

Name of Bidder :Signed of Bidder : B.Price.Foundation : 280 of 281 ; R-1


BILL NO 4 : ANALYSIS UNIT PRICE
Foundation and Steel Structure for 150 kV Switchgear

TOTAL PRICE

(RUPIAH)

Name of Bidder :Signed of Bidder : B.Price.Foundation : 281 of 281 ; R-1