REPORTING PERIOD :
( 01 July - 07 July 2019)
PEKERJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
TABLE OF CONTENTS
I EXCECUTIVE SUMMARY
V ENCLOSURE
2. Breakdown
3. Daily Activity
4. SITE PICTURES
WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)
EXCECUTIVE SUMMARY
I PROJECT DESCRIPTION
Scope of Work : Full Turnkey Project (All aspects starting from desig
fabrication, civil, testing up to commissioning) for S
Digital Air Insulated Switchgear that consist of 2x15
Bay to PLTU Lontar, 2x150 kV Line Bay to Teluk N
2x150 kV Transformer Bay, 1x150 kV Coupler Bay.
EXCECUTIVE SUMMARY
- Civil Progress : 7.637%
Progress Status
No Description Unit Rem
Prev. Week This Week
IV CONSTRUCTION :
Progress
No Description Unit Rem
Contract Actual
V MEETING
No Activity Place
Progress
No Description Unit Rem
Schedule Actual
EXECUTIVE SUMMARY PROGRESS, Page 4 of 281
WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)
EXCECUTIVE SUMMARY
1 Control Building Foundation
UTIVE SUMMARY
UTIVE SUMMARY
Remarks
Remarks
Remarks
Remarks
UTIVE SUMMARY
PROGRESS
WEIGHT LAST THIS UP TO THIS
NO. DESCRIPTION
WEEK WEEK WEEK REMAKS
(%) (%) (%) (%)
(1) (2) (4) (5) (6) (5+6=7)
1 TOTAL PRICE FOR ELEKTROMEKANIK WORK GI 150 KV 69.832 4.830 0.000 4.830
2 TOTAL PRICE FOR CIVIL WORK GI 150 KV 30.168 7.637 0.000 7.637
PROGRESS
WEIGHT UP TO
NO. DESCRIPTION LAST WEEK THIS WEEK
THIS WEEK REMAKS
2 150 KV LINE BAY TO PLTU LONTAR : 2 BAYS 10.842 2.289 0.000 2.289
3 150 KV LINE BAY TO TELUK NAGA : 2 BAYS 11.350 1.855 0.000 1.855
8 ENERGY METERS FOR ALL TRANSFORMER FEEDER BAYS 0.704 0.000 0.000 0.000
14 RADIO TRANCEIVER (Low Band Frekuensi), Tower, dan Aksesoris 0.512 0.000 0.000 0.000
18 TEST AND COMISSIONING FOR ALL SCOPE OF PROJECT 1.565 0.000 0.000 0.000
As Built Drawing FOR ALL SCOPE OF PROJECT in hard and soft copy (3
19 0.000 - - -
sets hardcopy and 2 sets softcopy)
PENGADAAN
%
1 2 3 4 5
1 150 KV SWITCHYARD STEEL STRUCTURES, BUSBAR, OVERHEAD GROUND WIRE (SHIELD WIRE)
Galvanized steel structure to complete the specified scope of work for switchyard with 7 Bay Double
1.1 Busbar Type U of :
2x 150 kV Line Bays to PLTU Lontar
2x 150 kV Line Bays to Teluk Naga
2x 150 kV Transformer Bay
1x 150 kV Coupler Bay
Consist of :
- Post steel Structure Type TW-1, high 14,0 m' + steel Structure for earth wires high 4 m' Sets 24.00 2.549
- Post steel Structure Type TW-2, high 10,0 m' Sets 0.00
- Post steel Structure Type TW-3, high 14,0 m' (earthing tower) Sets 1.00 0.106
- Beam steel Structure for Busbar dan Crossbar, 12 m' Sets 20.00 1.476
- Beam steel Structure for Busbar dan Crossbar, 14 m' Sets 12.00 0.886
Sub total items 1.1
PENGADAAN
%
1 2 3 4 5
1.2 Overhead Ground Wire (Shield Wire) and Accessories
Consist of :
- Over Head Ground Wire ( with used GSW 55 mm2), Install from Post steel Structure Type1 (18m) to Post steel
Structure Type1 (parallel with Busbar and Parallel with Crossbar) lot 1.00 0.029
- Tension string set for GSW 55 mm2 (Complete jumper/ joint GSW 55 mm2 to structure and to GSW 55 mm2
other's) Sets 80.00 0.030
Substation and Building Earthing System (Mesh/ Grid System and Rod Electrode) and Complete with all
1.3 Connector Type
lot 1.00 2.950
- Copper strip or flexible conductors of the cross section specified, installed so as to form a grid system laid
directly in the ground enclosing the complete substation together with all electrodes for surge arester/LA, CVT
and Transformator equipment direct earthing (Rod Electroda).
PENGADAAN
%
1 2 3 4 5
- Copper strip of flexible conductors to connect metalclad parts of all equipment and structures to main Earth
System.Copper strip of flexible conductors to connect metalclad parts of all equipment and structures to main
Earth System (minimum CU 150 mm2).
- Copper strip of flexible conductors installed around the Building, metalclad parts of all equipment in the Building
and structures to connect to main Earth System (minimum CU 150 mm2).
- Copper strip or flexible conductors to bond all overhead line towers direct to the substation Earth System.
- Double Tension Insulator String for Busbar 2 x TAL 850 mm2/phase, with 2 x 12 Insulator/ set, 120 kN,
31mm/kV. (Complete with Connector for Jumper Busbar) Sets 54.00 0.746
PENGADAAN
%
1 2 3 4 5
- Single Suspension String Insulator Set 2 x TAL 850 mm2/phase for Jumpers of Busbar (Complete with
Sets 24.00 0.302
Connector Jumper)
- Spacer 20 cm for conductor busbar Sets 45.00 0.121
(Option 1)
- 150 kV Electronic capacitor voltage transformer (ECVT) for metering and protection (equal to class 0.2 and 3P), units 6.00
complete with clamps, supporting structure.
(Option 2)
150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3,
units 6.00 0.382
Burden 15 VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000
pF, complete with clamps, supporting structure.
- Miscellaneous equipment, LV power cable and accessories and necessary equipment (cable ladder, jumper,
clamp, cable lug, terminal, … etc)set of clamps, connectors and accessories for complete installation scope of lot 1.00 0.495
work.
PENGADAAN
%
1 2 3 4 5
2.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. lot 1.00 0.462
2.2 Conductor 2 x TAL 850 mm2/phase jumper for Inter HV Equipment (from CB to LA) and dropper from Transmission
line lot 1.00
2.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/phase Sets 12.00 0.166
2.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to DS Sets 6.00 0.076
2.5 Spacer 20 cm for conductor Sets 12.00 0.032
2.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm/kV, without
earthing switch, complete with clamps and supporting steel structure (DS Busbar). Sets 4.00 0.555
2.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
Sets 4.00 0.055
2.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV,
complete with clamps and supporting structure. Sets 2.00 1.069
PENGADAAN
%
1 2 3 4 5
2.9 (Option 1)
Electronic Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 2)
Optical Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 3)
Current Transformer 150 kV, 40 kA for Line Bay, 3 core, Creepage distance 31 mm/kV, complete with clamps and
supporting steel structure.
Core-1 : Class PX, 2000-4000/1 A units 6.00 0.645
Core-2 : Class 5P20, 2000-4000/1 A
Core-3 : Class 0,5, 2000-4000/1 A
2.10 Disconnecting switch 150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, with
earthing switch, complete with clamps and supporting steel structure (DSE). sets 2.00 0.360
PENGADAAN
%
1 2 3 4 5
2.11 (Option 1)
Electronic Capacitor Voltage Transformer (ECVT) 150 kV/√3 for metering and protection (equal to class 0.2 and units 6.00
3P), Creepage distance 31 mm/kV, complete with clamps, supporting steel structure.
(Option 2)
150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 15
VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, complete units 6.00 0.382
with clamps, supporting structure.
2.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure,and all
necessary equipment. units 6.00 0.266
2.13 Set of clamps, connectors and accessories for complete all installation lot 1.00 0.145
2.14 Protection and Control Cubicle for Line bay Comprising : sets 2.00 2.514
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) - Distance Relay, include DEF, Autorecloser, Synchrocheck, etc.
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- Optical distribution frame
ELEKTROMEKANIK PROGRESS, Page 17 of 281
GI 150 KV TELUK NAGA II
PENGADAAN
%
1 2 3 4 5
- Panel
Including but not limited to:
- miscellaneous equipment, optical cables and cord, control control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay
- all necessary work (dismantling, installation, integration, adaptation) to the existing system (SAS, Busbar
Protection, etc) in GI Lontar and adaptation in control center to complete the scope of works.
2.15 Marshaling kiosk for 150 kV Line Bay Comprising : set 2.00 2.437
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel and cooling system
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.
PENGADAAN
%
1 2 3 4 5
Note: price of all Merging Unit and Switchgear Control Unit needed on 150 KV LINE BAY TO PLTU LONTAR is
include in item 2.15
2.16 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1.00 0.104
2.17 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works lot 1.00 0.989
3.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. lot 1.00 0.462
3.2 Conductor 2 x TAL 850 mm2/phase jumper for Inter HV Equipment (from CB to LA) and dropper from Transmission
line lot 1.00
3.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/phase Sets 12.00 0.166
3.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to DS
Sets 6.00 0.076
3.5 Spacer 20 cm for conductor Sets 12.00 0.032
PENGADAAN
%
1 2 3 4 5
3.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm/kV, without
earthing switch, complete with clamps and supporting steel structure (DS Busbar). Sets 4.00 0.555
3.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
Sets 4.00 0.055
3.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV,
complete with clamps and supporting structure. Sets 2.00 1.069
3.9 (Option 1)
Electronic Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 2)
Optical Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX) units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
PENGADAAN
%
1 2 3 4 5
(Option 3)
Current Transformer 150 kV, 40 kA for Line Bay, 3 core, Creepage distance 31 mm/kV, complete with clamps and
supporting steel structure.
Core-1 : Class PX, 2000-4000/1 A units 6.00 0.645
Core-2 : Class 5P20, 2000-4000/1 A
Core-3 : Class 0,5, 2000-4000/1 A
3.10 Disconnecting switch 150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, with
earthing switch, complete with clamps and supporting steel structure (DSE). sets 2.00 0.360
3.11 (Option 1)
Electronic Capacitor Voltage Transformer (ECVT) 150 kV/√3 for metering and protection (equal to class 0.2 and
units 6.00
3P), Creepage distance 31 mm/kV, complete with clamps, supporting steel structure.
(Option 2)
150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 15
VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, complete units 6.00 0.382
with clamps, supporting structure.
PENGADAAN
%
1 2 3 4 5
3.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure,and all
necessary equipment. units 6.00 0.266
3.13 Set of clamps, connectors and accessories for complete all installation lot 1.00 0.145
3.14 Protection and Control Cubicle for Line bay Comprising : sets 2.00 2.204
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) - Current differential, syncrocheck, etc
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, rack cabinet, optical cables and cord, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.
3.15 IED Main Line Protection - Current differential, syncrocheck, etc, for installed in GI Teluk Naga sets 2.00 0.801
PENGADAAN
%
1 2 3 4 5
Including but not limited to:
- miscellaneous equipment, optical cables and cord, control control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay
- all additional hardware and software needed to connect to the existing system (SAS, Busbar Protection, etc) on GI
150 kV Teluk Naga and to operated properly with MPU IED on GI 150 kV Teluk Naga 2
- all necessary work (dismantling, installation, integration, adaptation) to the existing system (SAS, Busbar
Protection, etc) in GI Teluk Naga and adaptation in control center to complete the scope of works.
3.16 Marshaling kiosk for 150 kV Line Bay Comprising : set 2.00 2.437
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.
PENGADAAN
%
1 2 3 4 5
Note: price of all Merging Unit and Switchgear Control Unit needed on 150 KV LINE BAY TO TELUK NAGA is
include in item 3.16
3.17 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1.00 0.104
3.18 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works lot 1.00 0.989
PENGADAAN
%
1 2 3 4 5
4.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 4000 Amp, 40 kA, Creepage distance 31 mm/kV,
Sets 2.00 0.284
without earthing switch, complete with clamps and supporting steel structure (DS Busbar).
4.7 Circuit Breaker 3 phase 150 kV, three pole for Couple bay, SF6, cap. 4000 Amp, 40 kA, Creepage distance 31
Set 1.00 0.417
mm/kV, complete with clamps and supporting structure.
4.8 (Option 1)
Electronic Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 2)
Optical Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX) units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 3)
Current Transformer 150 kV, 50 kA for bus coupler bay, 2 core, Creepage distance 31 mm/kV, complete with
clamps and supporting steel structure. units 6.00 0.456
Core-1 : Class 5P20, 2000-4000/1
Core-2 : Class PX, 2000-4000/1
4.9 Set of clamps, connectors and accessories for all installation (including Inter HV equipment) lot 1.00 0.073
PENGADAAN
%
1 2 3 4 5
4.10 Protection and Control Cubicle for Line bay Comprising : sets 2.00 3.430
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) for 10 bays - Busbar Protection, DFR, etc
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, rack cabinet, optical cables and cord, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.
4.11 Marshaling kiosk for 150 kV Coupler Bay Comprising : set 1.00 2.194
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
ELEKTROMEKANIK PROGRESS, Page 26 of 281
GI 150 KV TELUK NAGA II
PENGADAAN
%
1 2 3 4 5
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.
Note: price of all Merging Unit and Switchgear Control Unit needed on 150 kV BUS COUPLER BAY and CVT Bus is
include in item 4.11
4.12 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1.00 0.052
4.13 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works. lot 1.00 0.495
PENGADAAN
%
1 2 3 4 5
5.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 1250 Amp, 40 kA, Creepage distance 31 mm/kV,
without earthing switch, complete with clamps and supporting steel structure (DS Busbar). sets 4.00 0.397
5.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
sets 4.00 0.055
5.8 Circuit Breaker 3 phase 150 kV, three pole for trafo bay, SF6, cap. 1250 Amp, 40 kA, Creepage distance 25
mm/kV, complete with clamps and supporting structure. sets 2.00 0.794
5.9 (Option 1)
Electronic Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX), units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
(Option 2)
Optical Current Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal to class 0.5 and PX) units 6.00
Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
PENGADAAN
%
1 2 3 4 5
(Option 3)
Current transformer 150 kV, 40 kA for transformer bay, 4 core, Creepage distance 31 mm/kV complete with clamps
and supporting steel structure.
Core-1 : Class PX, 150-300/1 A
Core-2 : Class 5P20, 150-300/1 A units 6.00 0.836
Core-3 : Class PX, 2000-4000/1 A
Core-4 : Class 0.5, 150-300/1 A
5.10 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure, and
units 6.00 0.266
all necessary equipment.
5.11 Set of clamps, connectors and accessories for installation lot 1.00 0.145
5.12 Protection and Control Cubicle for 150/20 kV Transformer Bay Comprising : sets 2.00 3.186
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main Transformer Protection - MPU (Trafo Differential, REF HV/LV side, DFR, etc.).
- IED Back Up Protection - BPU 1 for HV Side (Over Current, Earth Fault, Circuit Breaker Failure, DFR,
Instrument, etc.).
- IED Back Up Protection - BPU 2 for LV Side ( Over Current, Earth Fault, Stand by Earth Fault, etc).
ELEKTROMEKANIK PROGRESS, Page 29 of 281
GI 150 KV TELUK NAGA II
PENGADAAN
%
1 2 3 4 5
- IED Bay Control - BCU
- IED AVR
- Optical distribution frame
- Panel
Including, miscellaneous equipment, test block, test plug, rack cabinet, optical cables and cord, clamps,
connectors, connection to individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to
complete the scope of works.
5.13 Marshaling kiosk for 150 kV Transformer Bay Comprising : set 2.00 3.412
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.
PENGADAAN
%
1 2 3 4 5
Note: price of all Merging Unit and Switchgear Control Unit needed on 150 kV side of TRANSFORMER BAY is
include in item 5.13
5.14 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1.00 0.104
5.15 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works. lot 1.00 0.989
PENGADAAN
%
1 2 3 4 5
6.3 Single phase neutral CT for 20 kV side Class 10P20, 1000/5A complete with clamps for neutral earth fault
protection suitable for mounting outdoor on transformer tank or can be put inside the 20 kV neutral earthing resistor units 2.00
cubicle.
6.4 Single phase neutral CT for 150 kV side Class x 150-300/1A complete with clamps for restricted earth fault
units 2.00 0.092
protection suitable for mounting outdoor on transformer tank.
6.5 20 kV stainless steel neutral earthing resistor rated 12 Ohm, 10 seconds. sets 2.00 0.848
6.6 Transformer online monitoring system comprising : sets 2.00 5.671
- Tan Delta and capacitance for HV and LV Bushing and Winding
- Dissolve Gas Analysis For Transformer Oil
- Moisture/Water Content in Transformer Oil
- Partial discharge monitoring
- Oil Level Monitoring
- Oil Temperature & Winding Temperature
- OLTC monitoring
- IED Device, Including Panel
- Diagnostic Software
- Support Material
ELEKTROMEKANIK PROGRESS, Page 32 of 281
GI 150 KV TELUK NAGA II
PENGADAAN
%
1 2 3 4 5
- Industrial Class Server, Rack Mounted
- Workstatuin & VDU
Miscellaneous equipment and material required for completion the scope of work.
6.7 Transformer Blast and Fire Prevention equipment, complete with accessories sets 2.00 5.554
7.2 3 phase, 1 x single core of 95 SQMM copper 20 kV XLPE power cable/phase between 20 kV auxiliary transformer
cubicle and the auxiliary transformer, including cable support, cable termination and accessories, cable rack, etc..
to complete scope of work sets 2.00 0.099
PENGADAAN
%
1 2 3 4 5
7.3 Power cable 20 kV XLPE Alluminium single core 1 x 630 sqmm (for Neutral Cable), between 150/20 kV Power
transfomer and NGR sets 2.00 0.023
PENGADAAN
%
1 2 3 4 5
- Cubicle VT/LA 24 KV
- IED I/O, Power Meter
- 3 VT (Class 0.2; Class 3P)
- 3 Voltmeter
- Under Frequency Relay, Over Voltage and Under Voltage Relay
- Voltage Indicator for LED
- Test facility for metering and protection
- Auxiliary Transformer Cubicle. set 2.00 0.501
- LBS 25 kA, 24 kV/50 A
- IED I/O
- IED Power Meter
- Outgoing Feeder Cubicle set 16.00 6.268
- CB 25 kA, 24 kV/630 A
- IED (protection and control)
- KWh Meter
- IED Power Meter
- CT 20 KV, 2 CORE, for relay and measuring (Ratio : 300-600/5 A; Class : 5P20; Class : 0.5)
PENGADAAN
%
1 2 3 4 5
- Selector for Load Sheding and wiring to UFR
- Trip Circuit Supervision
- Local Switch, remote and supervisory
- Auto-Reclose and accessories
- LED for voltage indicator
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Metering and Protection for test facility
- Bus Section set 2.00 0.877
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Local Switch, remote and supervisory
- Auto-Reclose and accessories
- LED for voltage indicator
- Metering and Protection for test facility
- CB 25 kA, 24 kV/2000 A
- IED (Proteksi dan kontrol)
- IED Power Meter
- CT 20 KV, 2 Core, for relay and measuring (Ratio 2000-4000/5 A; Class 5P20; Class 0.5)
PENGADAAN
%
1 2 3 4 5
- Trip Circuit Supervision
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Local Switch, remote and supervisory
- Auto-Reclose and accessories
- LED for voltage indicator
- Metering and Protection for test facility
- Bus Riser Cubicle set 2.00 0.447
- 25 kA, 24 kV/2000 A
Miscellanious item including cable, accessories and necessary equipment to complete the scope of works.
7.5 Wall mounting panel Comprising : set 2.00 0.905
- IED Merging unit (number of port as required to complete scope of work) 1.00
- IED Switchgear Control Unit (number of port as required to complete scope of work) 1.00
- Optical distribution frame 1.00
- Panel and cooling system 1.00
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.
PENGADAAN
%
1 2 3 4 5
Note: price of all Merging Unit and Switchgear Control Unit needed on 20 kV side of TRANSFORMER BAY is
include in item 7.5
7.6 3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between bus-section cubicle and bus
riser cubicle, including cable terminations and accessories for connection between sets of 20 kV switchgear to set 1.00 0.172
complete the specified scope of work
7.7 20/0.4 kV 200 kVA 3-phase station auxiliary transformer complete with necessary accessories (vector group DYn 5) sets
2.00 0.237
8 ENERGY METERS FOR ALL TRANSFORMER FEEDER BAYS sets 2.00 0.682
Including one energy meter panel, two ethernet switch for connection station level and miscellaneous equipment &
material, rack cabinet, clamps, connectors, compression terminal, connection to individual items of equipment, test
terminal, auxiliary relay, interior lamp, heater… etc.
PENGADAAN
%
1 2 3 4 5
PENGADAAN
%
1 2 3 4 5
9.13 Engineering Tools, Test Equipment (including but not limited to injecting sampling value, testing, measuring) and set 1.00
Laptop for configurating, testing and operation maintenance including software (for IED, telecommunication and
SAS equipment).
9.14 Miscellaneous item, equipment and material including cables, patch cord, pig tail, telephone cable, connectors, lot 1.00
compression terminal, connection to individual items of equipment, all necessary work (dismantling, installation,
integration, adaptation, etc in partner substation and control center), etc, to complete the scope of works.
PENGADAAN
%
1 2 3 4 5
- CPU
- Keyboard & Mouse
- VDU LED 24"
- Active speaker.
- KVM extender
10.3 9 Common Lot 1.00
- IED I/O
10.4 ###Ethernet switch Set 5.00
Note : 6 cubicle 1 Ethernet
include :
- control cable and data cable
- I/O 1 system or modular
TOTAL PRICE ITEMS 10
PENGADAAN
%
1 2 3 4 5
1.2 Basic SA Software and Licences Lot 1.00
- SCADA
- Historical data
- Statistik & pelaporan
- Update data base
11.3 HMI Software Lot 1.00
11.4 Communication Protocol with Control Center Consist of Lot 1.00
IEC 60870 - 5 - 101, IEC 60870 - 5 - 104 and existing
Proprietary protocol (if any)
11.5 SAS Software for operation, maintenance, diagnostic, simulation and configuration Lot 1.00
TOTAL PRICE ITEMS 11
PENGADAAN
%
1 2 3 4 5
13 TELECOMMUNICATION EQUIPMENT
SDH ADM MUX complete with terminal : (Should be identic with existing MUX in GI 150KV PLTU LONTAR and GI
13.1 Set 1.00 0.741
150KV Teluk Naga)
- STM-4 Line Interface Port 3.00
- 2 MB Interface Port 8.00
- DIU Data Interfacing Unit 64 Kbps (V.24 / RS 232) Port 4.00
- 64 Kbps G.703 Port 8.00
- VF 2/4 Wire E/M Interface Port 8.00
- VF/Subsc Interface Port 4.00
- VF /Exch.Interface Port 4.00
- Ethernet Interface + Router Port 2.00
13.2 PAX (16 trunks - 12 subscriber) complete with telephone set of each subsriber Set 1.00 0.563
13.3 MDF Main Distribution Frame Set 1.00 0.155
13.4 Panel, Rack/Cabinet for telecomunication equipment Lot 1.00 0.553
PENGADAAN
%
1 2 3 4 5
13.5 Digital Teleprotection Set 2.00
Note : 1 Sets to be installed in 150 kV Teluk Naga substation 0.371
Including integration and adaptation to eksisting system to complte the scope of works
13.6 Relocation, instalation and adaptation of eksisting Digital teleprotection equipment fom Teluk Naga substation to Lot 1.00
Teluk Naga 2 substation
Fiber Optic Armoured (FA) Cable 16 cores to connect OPGW (GB) to ODF in telecommunication room / substation
13.7 building, approx.200 m length
m 400.00 0.102
13.8 Optical Distribution Frame (ODF) (16 port) Set 4.00 0.125
13.9 Gantry Box for OPGW set 2.00 0.084
Miscellaneous item, equipment and material including cables, patch cord, pig tail, telephone cable, connectors,
13.1 compression terminal, connection to individual items of equipment to complete the scope of works. Lot 1.00 0.236
PENGADAAN
%
1 2 3 4 5
Frequancy : 66-68 Mhz (programmable)
Power Output max : 25 W
(programmable, microphone, external speaker, power cable)
14.2 Antena Diple SMD set 1.00
14.3 Cross mount antenna set 1.00
14.4 Coaxial RG-8 Cable m 40.00
14.5 Connector PL set 1.00
14.6 Connector BNC set 1.00
14.7 Stop contact & Steker set 1.00
14.8 Tower Radio SST 25 m
1. Foundation for 25 m Tower lot 1.00 0.174
2. 25 m SST Tower lot 1.00
3. Earthing system lot 1.00
4. 25 m Tower Instalation lot 1.00
PENGADAAN
%
1 2 3 4 5
15.2 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation for 110V DC Battery,
and not less than 60 A ) complete with Panel Board metering and indicators. set 2.00 0.437
15.3 110V DC Switch Board complete, incl. ATS, 2 MCB's incoming,1 MCB section and 2 x 12 MCB outgoing MCB's
minimum for 10 bays and emergency lamp. set 2.00 1.082
15.4 48 V DC Battery suitable for supplying all 48 V DC load for 8 hours discharge. (Capacity of batetery is subject for
calculation for SCADATEL of substation complete and not less than 48V DC, 200 AH). set 1.00 0.191
15.5 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation for 48V DC Battery,
and not less than 60 A ) complete with Panel Board metering and indicators. set 2.00 0.348
15.6 48V DC Switch Board complete, incl. ATS, outgoing MCB's minimum for 10 bays. set 1.00 0.342
PENGADAAN
%
1 2 3 4 5
15.7 400V AC Switch MCB's Distribution Board suitable for the 2 units station service transformer interchangeable to
supply the control building, yard lighting and HV equipment of minimum 10 bays, to complete the specified scope of set 1.00 0.881
work, including necessary spare MCB.
15.8 Miscellaneous material, LV power cable, control cable and accesorries and necessary equipment (cable ladder,
clamp, cable lug, terminal, etc.) to complete the specified scope of work. lot 1.00 0.497
16 MISCELLANEOUS
16.1 Fault Recorder Equipment for 10 bays and Panel Set 1.00 1.175
- 2 Ethernet switch for process level
- Fault Recording equipment comprising necessary quantity of fault recordes equipped with oscillograph printer
to record the information of the 150 kV Bays
- The recorder shall be provided with date and line indicators and time synchronizing equipment clock via satellite
16.2 CCTV and Thermal and visual monitoring system compressed : set 1.00 1.054
PENGADAAN
%
1 2 3 4 5
- Thermal camera set 2.00
- 360 degree outdoor visual camera set 6.00
- 360 degree indoor visual camera set 4.00
- PC Server including operating system, antivirus, management and recording software set 1.00
- PC Client including operating system, antivirus, vewing and office work software set 1.00
Miscellaneous equipment and material required for completion Thermal and visual monitoring system including
Power supply, Cable Power, Cable Data, Cables, Swttch Hub, I/O Board For Alarm, Server Rack, UPS, Speakers, lot 1.00
etc scope of work
16.3 Miscellaneous equipment and material required for completion the scope of work. lot 1.00
TOTAL PRICE ITEMS 16
17 Training FOR ALL SCOPE OF PROJECT
TOTAL PRICE ITEMS 13.1 - 13.4
- Digital Substation Engineering and Design (TSS 3.3.1) : for 4 PLN engineers, 14 days Man - day 56.00 -
- Substation automation and telecommunication engineering (TSS 3.3.2 and TSS 5.17) : for 4 PLN engineers,
14 days Man - day 56.00 -
PENGADAAN
%
1 2 3 4 5
- Substation operation and maintenance (TSS 3.3.2) : for 8 PLN staff, 14 days Man - day 112.00 -
PENGADAAN
%
1 2 3 4 5
Approved by,
PT. PLN (Persero)
UPP JISJ 3
ELEKTROMEKANIK PROGRESS, Page 50 of 281
GI 150 KV TELUK NAGA II
PENGADAAN
Approved by, %
1 PT. PLN (Persero) 2 3 4 5
UPP JISJ 3
NOVAN PRASETYO
Manager Bagian Teknik
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.316 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
3.437 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
3.036 0.322
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
12.622 0.322
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.002 - 0.106 - - - - -
10.842 2.289
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.002 - 0.106 - - - - -
11.350 1.855
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.001 - 0.053 - - - - -
8.481 0.888
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.002 - 0.106 - - - - -
10.978 1.562
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
13.388 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
12.611 0.000
0.704 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
5.157 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.095 0.000
0.009 - 0.572 - - - - -
0.003 - 0.157 - - - - -
0.009 - 0.562 - - - - -
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.006 - 0.377 - - - - -
0.002 - 0.104 - - - - -
0.002 - 0.127 - - - - -
0.001 - 0.085 - - - - -
0.004 - 0.240 - - - - -
2.993 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.512 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
5.416 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
2.312 0.000
- 0.244 0.244 - - - - -
- 0.244 0.244 - - - - -
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
0.975 0.000
- 1.565 1.565 - - - - -
1.565 0.000
- - - - - - - -
0.000 0.000
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
100.00 6.916
Checked by,
PT. PLN (Persero) PUSMANPRO
UPMK I
ELEKTROMEKANIK PROGRESS, Page 91 of 281
WEEKLY PROGRESS REPORT
Week 42. (Period. 01 July - 07 July 2019)
WEIGHT
PENGADAAN LAST WEEK
JASA
GRAND TOTAL
PEMASANGAN
TRANSPORTA MATERIAL TRANSPORTASI JASA TOTAL MATERIAL
SI
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.322
0.000 0.322
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 2.289
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0.00 - 0.00 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 1.855
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.888
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 1.562
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
ELEKTROMEKANIK PROGRESS, Page 126 of 281
PROGRESS
THIS WEEK UP TO THIS WEEK
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
0.000 0.000
- - - 0 - 0 - 0 - -
0.000 0.000
0.000 6.916
Proposed by,
PT. GRID SOLUTIONS
INDONESIA
ELEKTROMEKANIK PROGRESS, Page 132 of 281
PROGRESS
THIS WEEK UP TO THIS WEEK
ARIEF RAHMAN
Site Manager
71.871%
68.484%
69.869%
72.611%
68.682%
71.871%
68.484%
69.869%
36.305%
68.682%
35.936%
68.529%
69.697%
72.069%
67.718%
69.657%
72.912%
Proposed by,
PT. GRID SOLUTIONS
INDONESIA
ELEKTROMEKANIK PROGRESS, Page 173 of 281
REMAKS
Proposed by,
PT. GRID SOLUTIONS
INDONESIA
ARIEF RAHMAN
Site Manager
1 BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV 20.258 0.003 0.000 0.003 0.02%
2 BILL NO 2 : SWITCHYARD FOR CIVIL WORKS GI TELUK NAGA 2 65.974 14.403 0.000 14.403 21.83%
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A
1 2 3 4
1 Foundation work
Excavation of soil m3 265.00
Backfill filling (compacted) m3 106.00
Soil disposal m3 159.00
Import Soil Fill (compacted) m 3
261.00
Compacted sand layer (t = 10 cm) m 3
34.00
Lean concrete (t = 10 cm) m3 34.00
Foundation work, concrete K 300, Fe : 150 kg/m3, Formwork m3 25.00
Sloof work, concrete K 300, Fe : 150 kg/m3, Formwork m 3
17.00
Stone masonry ad 1 pc : 3 sand m 3
81.00
3 Roof Work
Spandex metal sheet complete with accessories m2 514.00
Steel Structure frame, complete with bolt & galvanizing kg 4240.00
Purlin complete with plat simpul and steel painting kg 3016.00
Wind bracing and tie rod kg 207.00
Nok Spandek Metal m' 58.00
Thermal Insulation Glasswool, aluminium foil (single sided) with 2 (two) layer
m2 514.00
and roof mesh
Listplank Metal m' 135.00
Aluminium flashing t=0.50 mm including filler in both side m' 135.00
Water proofing membran type t= 3 mm and mortar screed m' 12.00
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 176 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A
1 2 3 4
PVC pipe dia 4 inc include elbows m' 4.00
4 Floor Work
Slab floor work, concrete K 300, Fe : 150 kg/m3, Formwork m3 55.00
Rabat Concrete K 225 m 3
10.00
Ceramic floor tiles 300 x 300 mm (Control, PLC, terace, lobby, egineer room,
m2 225.00
AC/DC, Pantry, Corridor, Battery room)
Ceramic floor tiles 200 x 200 mm - anti-slip (Toilet) m2 4.00
Ceramic wall tiles 200 x 250 mm (Toilet & Battery Room) m2 78.00
Plint Ceramic 150 x 300 mm (control room, PLC, terace, lobby, egineer
m' 124.00
room, AC/DC, Pantry)
Stepnosing 100 x 300 mm (terrace) m' 22.00
7 Ceiling work
Ceilling Gypsum GRC, hollow frame m2 92.00
Ceiling Accoustic, alluminium frame m 2
242.00
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 177 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A
1 2 3 4
8 Piping & Sanitary work
Closet Duduk Complete No 1.00
Wash Sink Complete (kitchen) No 1.00
Wastafel Complete No 2.00
Urinoir Complete No 0.00
Tempat Tisu Roll No 1.00
Tempat Sabun No 1.00
Gantungan Pakaian (multi hook) No 2.00
Installation of water supply pipe PVC dia 1/2 inc and fittings (include for all
pipes, bends, tees, albows, reducers, adaptors, taps and connections to ls 1.00
fittings, appliances, etc.)
Installation of water waste pipe PVC dia 3 inc and fittings (include for all
pipes, bends, tees, albows, reducers, adaptors, metal grill and connections to ls 1.00
fittings, appliances, etc.)
Water tank and steel structures tower ( cap : 2 m 3 ) and installation of pipe unit 1.00
Deepwell including submersible water pump 150 lt/m capacity and
set 1.00
accessories
Septictank cap 3 m3 included infiltrate cap 2 m3 complete with PVC, palm
unit 1.00
fibre and sand stone
Submersible Sewage Pump unit 2.00
Open Drainage (brick) 30/40 cm for control building
2
m' 96.00
PVC AW diameter 6'' m' 8.00
10 Painting Works
Wall and Ceiling interior painting m2 795.00
Wall and Ceiling exterior painting m 2
634.00
Steel Painting m 2
24.00
11 Electrical
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 178 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A
1 2 3 4
Light type Led 9 watt including installation wiring and switch Sets 99.00
Stop contact including installation wiring Sets 29.00
Emergency lighting (30 W) including installation Sets 10.00
Panel Box MCB complete with R.S.T lamp indicator and contactor grounding Set 1.00
13 Lightning Protection
Arder/ground rod icluded pipa and cable BC 25 mm2 and all accessories
clamps steel plate, material support and pole, grounding system for control Lot 1.00
building
14 Fire Alarm
Alarm bell 6" (150 mm) diameter including installation wiring Set 2.00
Smoke detector including installation wiring Sets 11.00
Fixed and rate of rise temperature detector including installation wiring Sets 11.00
MCFA (Master Control Fire Alrm) Including indication lamp, batttery rectifier a Set 1.00
16 Sundries
Flagpole Stainless Steel ø 3" with acc + Foundation Set 1.00
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 179 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A
1 2 3 4
Name plate "GI 150 kV TELUK NAGA II" work complete with stainless steel
pipe ø 2", stainless steel plate 1.2 mm, PLN's logo & block letter and Set 1.00
foundation of column
Key box Set 1.00
3 Roof Work
Spandex metal sheet complete with accessories m2 395.00
Steel Structure frame, complete with bolt & galvanizing kg 3331.00
Purlin complete with plat simpul and steel painting kg 2404.00
Wind bracing and tie rod kg 180.00
Nok Spandek Metal m' 46.00
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 180 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A
1 2 3 4
Thermal Insulation Glasswool, aluminium foil (single sided) with 2 (two) layer
m2 395.00
and roof mesh
Listplank Metal m' 106.00
Aluminium flashing t=0.50 mm including filler in both side m' 106.00
Water proofing membran type t= 3 mm and mortar screed m' 11.00
PVC pipe dia 4 inc include elbows m' 4.00
4 Floor Work
Slab floor work, concrete K 300, Fe : 150 kg/m3, Formwork m3 42.00
Rabat Concrete K 225 m3 9.00
Floor hardener finished m2 218.00
7 Ceiling work
Ceilling Gypsum GRC, hollow frame m2 80.00
Ceiling Accoustic, alluminium frame m 2
210.00
8 Sanitary work
Open Drainage (brick) 30/40 cm2 for control building m' 80.00
PVC AW diameter 6' m' 5.00
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A
1 2 3 4
Cable Duct Type II m' 46.00
Cable Duct Type III m' 14.00
10 Painting Works
Wall and Ceiling interior painting m2 494.00
Wall and Ceiling exterior painting m 2
364.00
Steel Painting m2 26.00
11 Electrical
Light type Led 9 watt including installation wiring and switch Sets 82.00
Stop contact including installation wiring Sets 4.00
Emergency lighting (30w) including installation Sets 6.00
Panel Box MCB complete with R.S.T lamp indicator and contactor grounding Set 1.00
13 Lightning Protection
Arder/ground rod icluded pipa and cable BC 25 mm2 and all accessories
clamps steel plate, material support and pole, grounding system for control Lot 1.00
building
14 Fire Alarm
Alarm bell 6" (150 mm) diameter including installation wiring No 2.00
Smoke detector including installation wiring No 6.00
Fixed and rate of rise temperature detector including installation wiring No 6.00
MCFA (Master Control Fire Alrm) Including indication lamp, batttery rectifier a No 1.00
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 182 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July -
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 1 : CONTROL BUILDING A
1 2 3 4
Total Progress for 150 KV CONTROL BUILDING SAS & 20 KV MV CELL BUILDING
NOVAN PRASETYO
Manager Bagian Teknik DIMAS WAHYU ADHI K
KTSK BANTEN 2
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 183 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)
PROGRESS
UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
1.881 - - - -
1.782 - - - -
0.379 - - - -
0.336 - - - -
1.589 - - - -
2.190 - - - -
2.152 - - - -
1.531 - - - -
0.105 - - - -
0.471 - - - -
1.798 - - - -
0.176 - - - -
0.201 - - - -
0.028 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 184 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)
PROGRESS
UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
0.005 - - - -
4.993 - - - -
0.238 - - - -
0.966 - - - -
0.018 - - - -
0.318 - - - -
0.605 - - - -
0.088 - - - -
1.774 - - - -
0.743 - - - -
0.829 - - - -
0.175 - - - -
0.070 - - - -
2.059 - - - -
0.110 - - - -
0.031 - - - -
0.491 - - - -
1.772 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 185 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)
PROGRESS
UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
0.167 - - - -
0.014 - - - -
0.053 - - - -
0.005 - - - -
0.005 - - - -
0.010 - - - -
0.202 - - - -
0.244 - - - -
0.310 - - - -
0.164 - - - -
0.312 - - - -
0.139 - - - -
0.751 - - - -
0.024 - - - -
2.012 - - - -
1.191 - - - -
0.369 - - - -
0.731 - - - -
0.783 - - - -
0.039 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 186 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)
PROGRESS
UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
1.019 - - - -
0.187 - - - -
0.159 - - - -
0.090 - - - -
2.228 - - - -
0.448 - - - -
0.378 - - - -
0.139 - - - -
0.813 - - - -
0.139 - - - -
0.547 - - - -
0.547 - - - -
0.239 - - - -
0.581 - - - -
0.696 - - - -
8.569 - - - -
0.139 - - - -
2.555 - - - -
0.030 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 187 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)
PROGRESS
UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
0.149 - - - -
0.012 - - - -
0.031 - - - -
0.042 - - - -
0.075 - - - -
0.412 - - - -
0.243 - - - -
0.659 - - - -
2.179 - - - -
0.454 - - - -
0.905 - - - -
1.683 - - - -
0.594 - - - -
0.152 - - - -
0.168 - - - -
0.972 - - - -
1.683 - - - -
1.690 - - - -
1.220 - - - -
0.091 - - - -
0.373 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 188 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)
PROGRESS
UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
1.382 - - - -
0.138 - - - -
0.158 - - - -
0.026 - - - -
0.005 - - - -
3.813 - - - -
0.214 - - - -
0.809 - - - -
0.994 - - - -
0.451 - - - -
0.166 - - - -
0.235 - - - -
0.724 - - - -
0.427 - - - -
1.538 - - - -
0.626 - - - -
0.015 - - - -
0.402 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 189 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)
PROGRESS
UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
1.889 - - - -
0.287 - - - -
0.454 - - - -
0.449 - - - -
0.042 - - - -
0.844 - - - -
0.026 - - - -
0.095 - - - -
0.090 - - - -
3.024 - - - -
0.813 - - - -
0.139 - - - -
0.298 - - - -
0.298 - - - -
0.239 - - - -
0.290 - - - -
0.696 - - - -
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 190 of 281
LY PROGRESS REPORT
2. (Period. 01 July - 07 July 2019)
PROGRESS
UP TO THIS WEEK
WEIGHT LAST WEEK THIS WEEK
THIS WEEK
REMAKS
WEIGHT WEIGHT WEIGHT
QTY QTY QTY
(%) (%) (%) (%)
5 6 7 8 9 6+8=10 7+9=11
CIVIL WORK PROGRESS_Control Building And SAS MV Cell 20KV, Page 191 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 2 : SWITCHYARD F
1 2 3 4
Total Item I ( 1 - 8 )
II Site Works
1 Earthworks :
Excavation of Soil m3 3565.00
Soil Disposal m 3
2384.00
Backfill filling (compacted) m 3
1181.00
2 Embankment Construction :
Import Soil Fill (include compaction per layer of 20 cm) m3 40133.00
Test Sand Cone (per-layer of 20 cm) pcs 90.00
Retaining wall (stone masonry) m 3
1458.00
3 Road Works :
Compacted Subgrade m2 3098.00
Compacted Sandgravel / sirtu (t=20cm) m 2
3098.00
Lean Concrete (t =10cm) m2 3098.00
Reinforced Concrete Road K 300 m2 3098.00
CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 192 of 281
WEEKLY PROGRES
Week 42. (Period. 01 July
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 2 : SWITCHYARD F
1 2 3 4
4 Kerbs :
Concrete Kerbs for switchyard (30x20 cm) m' 234.00
Concrete Kerbs for road and control building (40x25 cm) m' 673.00
5 Fence :
BRC 1.90 m height m' 28.00
BRC 1.50 m height m' 312.00
Brick wall 2.40 m + barbed wire 0.60 m m' 534.00
6 Gate :
Single gate BRC 1.50 m height, 1.1 m width Sets 4.00
Double gate BRC 1.50 m height, 3 m width Set 1.00
Sliding gate 2.4 m height, 6 m width Set 1.00
7 Landscaping (sodding grass) m2 586.00
8 Gravelling :
Compacted Gravel (dia 3 - 5 cm); thickness = 20 cm m3 1346.40
Sand layer below gravel (compacted sand); thickness = 5 cm m3 337.00
9 Cable trench for 150 kV (incld cover, galvanized L 50.50.5) :
Type 1 (Large, ±120 cm width ) m' 137.00
Type 2 (Medium, ± 80 cm width ) m' 94.00
Type 3 (Small, ± 60 cm width ) m' 177.00
Type 4 (Crossing road, ± 120 cm width) m' 12.00
10 Drainage :
Open Drainage stone masonry (40 x 70 cm) m' 540.00
Open Drainage brick (30 x 40 cm) m' 336.00
Sub soil Drainage dia 30 cm including gravel and Palm fibre m' 1056.00
Control Box Brick with cover (60 x 60 cm, height 70 cm) Unit 14.00
11 Post security (3,5m x 3,5 m) complete, included toilet (1,5m x 1,5m), septic tank Ls 1.00
Oil Pit Capacity 45 ton K 300, fe : 120kg/m3, Complete flashplate,
12 Unit 1.00
Galvanized steel pipe 6''
13 Phase name plate complete with fixing facilities pcs 21.00
14 Bay name plate complete with fixing facilities pcs 7.00
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 2 : SWITCHYARD F
1 2 3 4
TOTAL ITEM II ( 1 - 16 )
PEMBANGUNAN GI 150 KV
DAFTAR 2 : CIVIL G
BILL NO 2 : SWITCHYARD F
1 2 3 4
13 Marshalling Kiosk Unit 7.00
14 Neutral Grounding Resistors (NGR) Unit 2.00
15 Support 20 kV Sets 2.00
16 Service transformers (include metal roofing and fence BRC 1.5 m) Sets 2.00
PROGRESS
0.580 - - - -
0.336 1.00 0.336 - - 1.00 0.336 Finish
0.158 463.00 0.158 - - 463.00 0.158 On Progress
0.264 24.00 0.264 - - 24.00 0.264 Finish
0.451 60.00 0.451 - - 60.00 0.451 Finish
0.305 - - - -
0.240 - - - -
0.655 - - - -
0.271 - - - -
0.795 - - - -
2.306 - - - -
2.089 - - - -
11.102 - - - -
CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 196 of 281
Y PROGRESS REPORT
(Period. 01 July - 07 July 2019)
PROGRESS
0.197 - - - -
0.946 - - - -
0.212 - - - -
1.618 - - - -
6.060 - - - -
0.027 - - - -
0.020 - - - -
0.117 - - - -
0.197 - - - -
3.907 - - - -
0.837 - - - -
2.085 - - - -
0.922 - - - -
1.142 - - - -
0.211 - - - -
2.296 - - - -
0.807 - - - -
1.088 - - - -
0.046 - - - -
0.547 - - - -
0.038 - - - -
0.064 - - - -
PROGRESS
0.469 - - - -
0.565 - - - -
0.506 - - - -
0.046 - - - -
0.177 - - - -
1.331 - - - -
0.565 1.00 0.565 - - 1.00 0.565 Finish
CIVIL WORK PROGRESS_SWITCHYARD FOR CIVIL WORKS, Page 198 of 281
Y PROGRESS REPORT
(Period. 01 July - 07 July 2019)
PROGRESS
WAHYU ADHI K
K BANTEN 2 ARIEF RAHMAN
Site Manager
1 2 3 4 5 5 6 7 8 9 6+8=10 7+9=11 8
I Miscellaneous Works
1 Concrete Works
3 Reinforcement Work
4 Excavation Work
5 Filling Work
- Import Soil Fill (include compaction in layer of 20 cm) m3 100.00 135,445 0.305 - - - -
7 Driven Pile 30x30 K 450 m' 7,266.00 572,368 93.646 6147.40 79.229 - - 6147.40 79.229
I. CIVIL WORK
A. SWITCHYARD
I Preparatory work for Control Building , MV Cell and Switchyard
1 Site Clearing & Grubbing (Pengupasan t=20 cm) 0.383% 0.115% 0.03% 0.03% 0.03% 0.03%
2 Topographical Survey 0.222% 0.067% 0.02% 0.02% 0.02% 0.02%
3 Bowplank 0.104% 0.031% 0.01% 0.01% 0.01% 0.01%
4 Direksi Keet (4m x 6m) 0.174% 0.053% 0.01% 0.01% 0.01%
5 Site Storage (4m x 15 m) 0.297% 0.090% 0.03%
Sondir 0.060% 0.018% 0.01% 0.01%
Boring and Test Lab. 0.218% 0.066% 0.03% 0.03%
Laporan Soil Investigation 0.030% 0.009% 0.01%
8 Exit permit, IMB and coordination to instansion Pemda 0.201% 0.061% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
II Site Works
1 Earthworks : 0.769% 0.232% 0.06% 0.06% 0.06% 0.06%
2 Embankment Construction : 22.623% 6.825% 0.97% 0.97%
3 Road Works : 10.748% 3.242%
4 Kerbs : 0.755% 0.228%
5 Fence : 5.205% 1.570%
6 Gate : 0.109% 0.033%
7 Landscaping (sodding grass) 0.130% 0.039%
8 Gravelling : 3.130% 0.944%
9 Cable trench for 150 kV (incld cover, galvanized L 50.50.5) : 2.876% 0.868%
10 Drainage : 2.795% 0.843%
11 Post security (3,5m x 3,5 m) complete, included toilet (1,5m x 1,5m), septic tank 0.361% 0.109%
Oil Pit Capacity 45 ton K 300, fe : 120kg/m3, Complete flashplate,
12 0.776% 0.234%
Galvanized steel pipe 6''
13 Phase name plate complete with fixing facilities 0.025% 0.008%
14 Bay name plate complete with fixing facilities 0.042% 0.013%
15 Site and Road Lighting : 1.046% 0.316%
B. CONTROL BUILDING
I Control Building SAS include corridor
1 Foundation work 1.455% 0.439%
2 Structure and wall work 1.209% 0.365%
3 Roof Work 1.754% 0.529%
4 Floor Work 1.464% 0.442%
5 Plastering & Grouting 0.510% 0.154%
6 Doors and windows 0.663% 0.200%
7 Ceiling work 0.458% 0.138%
8 Piping & Sanitary work 0.486% 0.147%
9 Cable Duct Indoor Include Metal Works 0.723% 0.218%
10 Painting Works 0.315% 0.095%
11 Electrical 0.295% 0.089%
12 Air Conditioner and Exhaust fan 0.647% 0.195%
13 Lightning Protection 0.165% 0.050%
14 Fire Alarm 0.298% 0.090%
15 Fire Fighting Equipment 2.541% 0.766%
16 Sundries 0.039% 0.012%
II Control Building MV Cell
1 Foundation work 1.013% 0.306%
2 Structure and wall work 0.723% 0.218%
3 Roof Work 1.371% 0.414%
4 Floor Work 0.980% 0.296%
5 Plastering & Grouting 0.293% 0.088%
6 Doors and windows 0.228% 0.069%
7 Ceiling work 0.398% 0.120%
8 Sanitary work 0.130% 0.039%
9 Cable Duct Incd Metal Works 0.522% 0.158%
10 Painting Works 0.192% 0.058%
11 Electrical 0.214% 0.064%
12 Air Conditioner and Exhoust fan 0.613% 0.185%
13 Lightning Protection 0.165% 0.050%
14 Fire Alarm 0.197% 0.060%
15 Fire Fighting Equipment 0.200% 0.060%
C. MISCELLANEOUS
1 Concrete Works 0.174% 0.052%
2 Stone masonry 1 pc : 3 ps 0.134% 0.040%
3 Reinforcement Work 0.249% 0.075%
4 Excavation Work 0.001% 0.000%
5 Filling Work 0.042% 0.013% 0.00% 0.00% 0.00% 0.00%
6 Steel structures 0.154% 0.047%
7 Driven Pile 30x30 K 450 12.893% 3.890%
8 Bored Pile Dia 40 cm K 225 0.121% 0.036%
TOTAL CIVIL WORK 100.00% 30.17% 0.02% 0.08% 0.10% 0.12% 0.14% 1.08% 1.09%
1 150 KV SWITCHYARD STEEL STRUCTURES, BUSBAR, OVERHEAD GROUND WIRE (SHIELD WIRE)
1.1 Galvanized steel structure to complete the specified scope of work for switchyard with 7 Bay Do 5.833% 4.073%
1.2 Overhead Ground Wire (Shield Wire) and Accessories 0.316% 0.221%
1.3 Substation and Building Earthing System (Mesh/ Grid System and Rod Electrode) and Complete 3.437% 2.400%
1.4 150 kV Double Busbar Type U (Conductor 2 x TAL 850 mm2/phase) 3.036% 2.120%
2 150 KV LINE BAY TO PLTU LONTAR : 2 BAYS
2.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. 0.473% 0.330%
2.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/p 0.243% 0.169%
2.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to D 0.095% 0.067%
2.5 Spacer 20 cm for conductor 0.067% 0.047%
2.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm0.580% 0.405%
2.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconn 0.061% 0.043%
2.8 Circuit Breaker
Current 3 phase
Transformer 150 150 kV,kA
kV, 40 single poleBay,
for Line for line bay, Creepage
3 core, SF6, cap. distance
3150 Amp,31 40 kA, Creepage
mm/kV, 1.096%
complete with clamps and 0.765%
supporting steel structure.
Core-1 : Class PX, 2000-4000/1 A
2.9 0.752% 0.525%
Core-2 : Class 5P20, 2000-4000/1 A
2.10 Core-3 : Class switch
Disconnecting 0,5, 2000-4000/1 A
150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 0.376% 0.262%
(Option 2)
2.11 0.448% 0.313%
150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 15 VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, comp
2.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting st 0.310% 0.217%
2.13 Set of clamps, connectors and accessories for complete all installation 0.151% 0.105%
2.14 Protection and Control Cubicle for Line bay Comprising : 2.564% 1.790%
2.15 Marshaling kiosk for 150 kV Line Bay Comprising : 2.480% 1.731%
2.16 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet 0.106%
switch. 0.074%
2.17 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, ca 1.040% 0.726%
3.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. 0.473% 0.330%
3.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/p 0.243% 0.169%
3.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to D 0.095% 0.067%
3.5 Spacer 20 cm for conductor 0.067% 0.047%
3.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm0.580% 0.405%
3.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconn 0.061% 0.043%
3.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage 1.096% 0.765%
3.9 (Option 3) 0.752% 0.525%
Current Transformer 150 kV, 40 kA for Line Bay, 3 core, Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
3.10 Disconnecting
Core-1 : Class switch 150 kV 3 phase
PX, 2000-4000/1 A motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, 0.376% 0.262%
Core-2 :
(Option 2)Class 5P20, 2000-4000/1 A
3.11 Core-3 : Class 0,5, 2000-4000/1 0.448%
A with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 0.313%
150kV capacitor voltage transformer 15 VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, complete with clamps, supp
3.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel struct 0.310% 0.217%
3.13 Set of clamps, connectors and accessories for complete all installation 0.151% 0.105%
3.14 Protection and Control Cubicle for Line bay Comprising : 2.249% 1.570%
3.15 IED Main Line Protection - Current differential, syncrocheck, etc, for installed in GI Teluk Naga 0.822% 0.574%
3.16 Marshaling kiosk for 150 kV Line Bay Comprising : 2.480% 1.731%
3.17 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. 0.106% 0.074%
V power cable, 3.18
control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal, … etc) to complete1.040%
the scope of works
0.726%
4.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar. 0.237% 0.165%
4.3 Double Tension Insulator String Set for Crossbar 2 x TAL 850 mm2/phase 0.364% 0.254%
4.4 Single Suspension Insulator String Set for Crossbar 2 x TAL 850 mm2/phase 0.143% 0.100%
4.5 Spacer 20 cm for conductor 0.101% 0.071%
4.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 4000 Amp, 40 kA, Creepage distance 3 0.297% 0.207%
4.7 Circuit Breaker 3 phase 150 kV, three pole for Couple bay, SF6, cap. 4000 Amp, 40 kA, Creepa 0.429% 0.300%
4.8 (Option 3) 0.535% 0.373%
Current Transformer 150 kV, 50 kA for bus coupler bay, 2 core, Creepage distance 31 mm/kV, complete with clamps and supporting steel structure.
4.9 Set of clamps, connectors and accessories for all installation (including Inter HV equipment) 0.077% 0.054%
Core-1 : Class 5P20, 2000-4000/1
4.10 Core-2 : Class
Protection and PX, 2000-4000/1
Control Cubicle for Line bay Comprising : 3.495% 2.440%
4.11 Marshaling kiosk for 150 kV Coupler Bay Comprising : 2.231% 1.558%
4.12 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet 0.053%
switch. 0.037%
4.13 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, ca 0.520% 0.363%
5.1 Crossbar Conductor 1 x TAL 850 mm2/phase + Dropper's Busbar to DS and Crossbar Conductor to DS & 0.107% 0.075%
5.3 Single Tension Insulator String Set for installation the Crossbar, Conductor 1 x TAL 850 mm2/phase 0.182% 0.127%
5.4 Single Suspension Insulator String Set with Conductor 1 x TAL 850 mm2/phase to DS & CB 0.095% 0.067%
5.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 1250 Amp, 40 kA, Creepage distance 31 mm/kV, 0.420% 0.293%
5.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector swi 0.061% 0.043%
5.8 Circuit Breaker 3 phase 150 kV, three pole for trafo bay, SF6, cap. 1250 Amp, 40 kA, Creepage distance 0.816% 0.570%
5.9 (Option 3) 0.972% 0.679%
Current transformer 150 kV, 40 kA for transformer bay, 4 core, Creepage distance 31 mm/kV complete with clamps and supporting steel structure.
5.10 Lightning
Core-1 Arrester
: Class PX,150 kV, 20 kA
150-300/1 A for Line bay, complete with clamp, surge counter, supporting steel struct 0.310% 0.217%
Core-2 : Class 5P20, 150-300/1 A
Set of clamps, connectors and accessories for installation
5.11 Core-3 : Class PX, 2000-4000/1 A 0.151% 0.105%
5.12 Core-4 : Class
Protection and 0.5, 150-300/1
Control CubicleAfor 150/20 kV Transformer Bay Comprising : 3.247% 2.267%
5.13 Marshaling kiosk for 150 kV Transformer Bay Comprising : 3.471% 2.424%
5.14 Fiber Optic Armoured (FA) Cable 16 cores (multi mode) to connect marshalling kiosk to ethernet switch. 0.106% 0.074%
5.15 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, 1.040% 0.726%
6.4 Single phase neutral CT for 150 kV side Class x 150-300/1A complete with clamps for restricted earth fault 0.097% 0.068%
6.5 20 kV stainless steel neutral earthing resistor rated 12 Ohm, 10 seconds. 0.872% 0.609%
6.6 Transformer online monitoring system comprising : 6.602% 4.610%
6.7 Transformer Blast and Fire Prevention equipment, complete with accessories 5.817% 4.062%
7.1 3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between 150/20 kV power transform
1.006% 0.703%
7.2 3 phase, 1 x single core of 95 SQMM copper 20 kV XLPE power cable/phase between 20 kV auxiliary transfo0.116% 0.081%
7.3 Power cable 20 kV XLPE Alluminium single core 1 x 630 sqmm (for Neutral Cable), between 150/20 kV 0.025% 0.017%
7.4 - Incoming Cubicle. 1.216% 0.849%
- Busbar PT + Earthing Switch Cubicle. 0.579% 0.404%
- Auxiliary Transformer Cubicle. 0.515% 0.360%
- Outgoing Feeder Cubicle 6.417% 4.481%
- Bus Section 0.898% 0.627%
- Bus Riser Cubicle 0.460% 0.321%
7.5 Wall mounting panel Comprising : 0.929% 0.648%
3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between bus-section cubicle and0.197% 0.138%
7.6
20/0.4 kV 200 kVA 3-phase station auxiliary transformer complete with necessary accessories (vector gr 0.253% 0.177%
7.7
13 TELECOMMUNICATION EQUIPMENT
13.1 SDH ADM MUX complete with terminal : (Should be identic with existing MUX in GI 150KV P 0.769% 0.537%
13.2 PAX (16 trunks - 12 subscriber) complete with telephone set of each subsriber 0.572% 0.400%
13.3 MDF Main Distribution Frame 0.157% 0.110%
Digital Teleprotection
13.4 Panel, Rack/Cabinet for telecomunication equipment 0.562% 0.392%
Note : 1 Sets to be installed in 150 kV Teluk Naga substation
13.5 Including integration and adaptation to eksisting system to complte the scope of works 0.377% 0.263%
13.7 Fiber Optic Armoured (FA) Cable 16 cores to connect OPGW (GB) to ODF in telecommunication r 0.104% 0.073%
13.8 Optical Distribution Frame (ODF) (16 port) 0.127% 0.089%
13.9 Gantry Box for OPGW 0.085% 0.060%
13,10 Miscellaneous item, equipment and material including cables, patch cord, pig tail, telephone cab 0.240% 0.167%
15.1 110 V DC Battery suitable for supplying all 110 V DC load for 8 hours discharge. (Capacity of ba 1.451% 1.013%
15.2 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation 0.449% 0.313%
15.3 110V DC Switch Board complete, incl. ATS, 2 MCB's incoming,1 MCB section and 2 x 12 MCB 1.110% 0.775%
15.4 48 V DC Battery suitable for supplying all 48 V DC load for 8 hours discharge. (Capacity of bate 0.204% 0.142%
15.5 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation 0.358% 0.250%
15.6 48V DC Switch Board complete, incl. ATS, outgoing MCB's minimum for 10 bays. 0.351% 0.245%
15.7 400V AC Switch MCB's Distribution Board suitable for the 2 units station service transformer in 0.967% 0.675%
15.8 Miscellaneous material, LV power cable, control cable and accesorries and necessary equipment (c0.526% 0.367%
16 MISCELLANEOUS
16.1 Fault Recorder Equipment for 10 bays and Panel 1.206% 0.842%
16.2 CCTV and Thermal and visual monitoring system compressed : 1.106% 0.772%
- Digital Substation Engineering and Design (TSS 3.3.1) : for 4 PLN engineers, 14 days 0.244% 0.170%
- Substation automation and telecommunication engineering (TSS 3.3.2 and TSS 5.17) : for 0.244% 0.170%
- Substation operation and maintenance (TSS 3.3.2) : for 8 PLN staff, 14 days 0.488% 0.340%
TOTAL ELEKTROMEKANIK WORK 100.00% 69.83% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TOTAL OVER ALL 100.00% 0.02% 0.08% 0.10% 0.12% 0.14% 1.08% 1.09%
CUMULATIVE PLANNING PROGRESS 0.019% 0.100% 0.198% 0.323% 0.460% 1.544% 2.632%
-
ACTUAL PROGRESS 0.093% 0.067% 0.000% 0.000% 0.000% 0.000% 0.000%
CUMULATIVE ACTUAL PROGRESS 0.093% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160%
-
TAHUN 2018
NOV DES JAN FEB
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
(05-11) (12-18) (19-25) (26-02) (03-09) (10-16) (17-23) (24-30) (31-06) (07-13) (14-20) (21-27) (28-03) (04-10) (11-17) (18-24) (25-03)
0.01%
0.03% 0.03%
0.02%
0.22% 0.22%
0.07%
0.03% 0.03%
0.02% 0.02%
0.03% 0.03% 0.03%
0.00% 0.00%
1.50% 1.49% 1.46% 1.46% 1.46% 0.49% 0.50% 0.77% 0.48% 0.55% 0.55% 0.53% 0.43% 0.52% 0.46% 0.65% 0.48%
0.03% 0.03%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03%
1.50% 1.49% 1.46% 1.46% 1.46% 0.49% 0.50% 0.77% 0.48% 0.55% 0.55% 0.53% 0.43% 0.52% 0.46% 0.68% 0.51%
1.504% 1.491% 1.461% 1.461% 1.461% 0.486% 0.495% 0.771% 0.485% 0.554% 0.551% 0.526% 0.435% 0.518% 0.456% 0.677% 0.511%
4.136% 5.627% 7.088% 8.549% 10.010% 10.497% 10.992% 11.763% 12.248% 12.802% 13.353% 13.879% 14.314% 14.832% 15.287% 15.964% 16.475%
0.584% 0.030% 0.000% 0.605% 0.030% 0.000% 0.090% 0.000% 0.053% 0.000% 0.000% 0.051% 0.226% 0.263% 0.430% 0.326% 0.468%
0.744% 0.774% 0.774% 1.379% 1.409% 1.409% 1.499% 1.499% 1.552% 1.552% 1.552% 1.603% 1.829% 2.092% 2.521% 2.847% 3.315%
TAHUN 2019
MAR APR MEI JUN
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
(04-10) (11-17) (18-24) (25-31) (01-07) (08-14) (15-21) (22-28) (29-05) (06-12) (13-19) (20-26) (27-02) (03-09) (10-16) (17-23) (24-30)
0.41%
0.27% 0.34% 0.81% 0.58% 0.49% 0.57% 0.90% 0.97% 1.50% 0.37% 0.45% 0.02% 0.02% 0.02% 0.02% 0.02% 0.41%
0.17% 0.17%
0.08% 0.08%
0.03% 0.03%
0.02% 0.02%
0.14% 0.14% 0.14%
0.02% 0.02%
0.19% 0.19% 0.19% 0.19%
0.11% 0.11% 0.11% 0.11%
0.26%
0.31%
0.07% 0.07% 0.07%
0.05% 0.05%
0.52% 0.52%
0.14% 0.14% 0.14%
0.58% 0.58%
0.02% 0.02% 0.02%
0.36% 0.36%
0.08% 0.08%
0.13%
0.12%
0.52%
0.02% 0.02%
0.20%
0.92%
0.61% 0.61% 0.61% 1.01% 1.01% 0.98% 0.98% 0.93% 0.93% 0.79% 1.10% 0.75% 1.33% 1.55% 2.38% 3.89% 5.52%
0.88% 0.95% 1.43% 1.60% 1.50% 1.55% 1.88% 1.90% 2.43% 1.16% 1.55% 0.77% 1.36% 1.57% 2.40% 3.91% 5.93%
0.884% 0.954% 1.426% 1.598% 1.504% 1.547% 1.878% 1.901% 2.429% 1.156% 1.551% 0.767% 1.355% 1.574% 2.400% 3.911% 5.927%
17.359% 18.313% 19.739% 21.338% 22.842% 24.389% 26.267% 28.167% 30.596% 31.752% 33.303% 34.070% 35.425% 36.999% 39.399% 43.310% 49.238%
0.462% 6.709% 0.154% 1.120% 0.793% 0.539% 0.288% 0.143% 0.257% 0.051% 2.026% 0.367% 0.000% 0.000% 0.000% 0.000% 0.020%
3.777% 6.709% 6.863% 7.983% 8.776% 9.315% 9.603% 9.746% 10.003% 10.054% 12.080% 12.447% 12.447% 12.447% 12.447% 12.447% 12.467%
JUL AGU SEP
REMAKS
42 43 44 45 46 47 48 49 50 51 52 53
(01-07) (08-14) (15-21) (22-28) (29-04) (05-11) (12-18) (19-25) (26-01) (02-08) (09-15) (16-19)
0.52%
0.14%
0.58%
0.13%
0.05% 0.05%
0.04% 0.04%
0.10% 0.10%
0.10% 0.10% 0.10%
0.12% 0.12%
0.03% 0.03%
0.81% 0.81% 0.81%
0.52% 0.52%
0.02% 0.02%
0.12% 0.12% 0.12%
0.02% 0.02%
0.20% 0.20%
0.92% 0.92% 0.92% 0.92%
0.81% 0.81% 0.81% 0.81% 0.81%
0.03% 0.03%
4.47% 3.30% 4.48% 4.73% 6.79% 7.22% 6.42% 4.45% 1.34% 0.79% 0.54% 0.24%
5.01% 3.84% 5.02% 5.27% 7.64% 8.08% 7.28% 4.98% 1.89% 0.89% 0.62% 0.24%
5.015% 3.843% 5.016% 5.269% 7.641% 8.076% 7.278% 4.983% 1.888% 0.893% 0.620% 0.241%
54.252% 58.096% 63.111% 68.381% 76.022% 84.097% 91.375% 96.358% 98.246% 99.139% 99.759% 100.00%
0.000%
12.467%
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4
No Description / Sketc As
1. Foundation work
Excavation of soil
==>
==>
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4
Approved by,
PT. PLN (Persero) PT. PLN
UPP JISJ 3
RIZKI JULIAWAN
No Description / Sketc As
1. Foundation work
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4
Approved by,
PT. PLN (Persero) PT. PLN
UPP JISJ 3
PEKERJAAN PEMB
Approved by,
PT. PLN (Persero)
Breakdown analisis for BILL NO
PT. PLN
Week 4
UPP JISJ 3
CONTRACT NO. : 151.PJ/DAN.02.02/UIP ISJ/2017, tanggal 01 November 2017
PORTION : CIVIL WORKS - SWITCHING STATION FOUNDATION
LOCATION : GI TELUK NAGA II 150kV (DIGITAL SUBSTATION)
RIZKI JULIAWAN
No Description / Sketc As
1. Foundation work
Lean concrete
PEKERJAAN PEMB
Breakdown analisis for BILL NO
Week 4
Approved by,
PT. PLN (Persero) PT. PLN
UPP JISJ 3
RIZKI JULIAWAN
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)
Calculation Quantity
Foundation work
Excavation of soil
VOL = P x L x T x ∑. Pond
= 2.40 x 1.00 x 0.70 x 27.00 ==> of 28,00 unit Foundation
= 45.36 m3
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)
Calculation Quantity
Foundation work
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)
VOL = P x L x T x ∑. Pond
= 1.60 x 0.70 x 0.10 x 3.00 ==> of 28,00 unit Foundation
= 0.34 m3
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)
Calculation Quantity
Foundation work
Lean concrete
VOL = P x L x T x ∑. Pond
= 1.60 x 0.70 x 0.05 x 3.00 ==> of 28,00 unit Foundation
= 0.17 m3
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)
RJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
for BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV
Week 42. (Period. 01 July - 07 July 2019)
ARIEF RAHMAN
Site Manager
Proposed by,
PT. GRID SOLUTIONS INDONESIA
Proposed by,
PT. GRID SOLUTIONS INDONESIA
ARIEF RAHMAN
Site Manager
Proposed by,
PT. GRID SOLUTIONS INDONESIA
ARIEF RAHMAN
Site Manager
PEKERJA
Brea
No Description / Sketc As
3 Bowplank (m')
2
3
7
Approved by,
PT. PLN (Persero) P
UPP JISJ 3
RIZKI JULIAWAN
No Description / Sketc As
1 Earthworks :
Backfill filling (compacted)
1
Approved by,
PT. PLN (Persero) P
UPP JISJ 3
RIZKI JULIAWAN
PEKERJAAN PEMBANGUNAN GI 150kV TELUK NAGA II
Breakdown analisis for Switchyard Foundation
Week 42. (Period. 01 July - 07 July 2019)
Calculation
Bowplank (m')
VOL = P x ∑ x ∑. Pond
= 22.40 m'
= 26.80 m'
Checked by,
PT. PLN (Persero) PUSMANPRO PT.
UPMK I
BUDI YULIANTO
Calculation
Earthworks :
Backfill filling (compacted)
VOL = P x L x T
= 0.00 x 0.00 x 0.000
= 0
0
Checked by,
PT. PLN (Persero) PUSMANPRO PT.
UPMK I
BUDI YULIANTO
Quantity Unit Kode Remarks
Hanya
bisa
diprogress
Hanya
bisa
diprogress
sesuai
quantity
kontrak,
Quantity
aktual
akan
diprogres
pada saat
kerja
tambah
kurang
834.80 m'
Proposed by,
PT. GRID SOLUTIONS INDONESIA
ARIEF RAHMAN
Site Manager
ARIEF RAHMAN
Site Manager
Control Building , MV Cell and Switchyard
II Site Works
= 0.316 m3/m'
am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
24 Mon
Week 42. (Period. 01 July - 07 July
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
25 Tue
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
26 Wed
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
27 Thu
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Fri am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
2019)
28
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Sat am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
THIS WEEK,
29
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
Sun am 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
30
pm 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00
I MATERIAL :
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
II REMUNERATION
1
2
3
4
5
6
7
8
9
10
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
REMARK
REMARK
REMARK
UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)
UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)
TOTAL PRICE
LOCAL
(RUPIAH)
TOTAL PRICE
LOCAL
(RUPIAH)
Foundation : .....................................
UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)
TOTAL
Note:
1. Breakdown Price for Foundation (Fixed Price)
2. Shall be installed in BILL NO 2
TOTAL PRICE
(RUPIAH)