Productivity Rate PDF
Productivity Rate PDF
Productivity Rate PDF
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
8 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay 18.9 24.4 30.3 m3/hr
9 Load Spoil to Barge, capacity 2,000m3 - 8.0 - hrs
10 Load Spoil to Barge, capacity 1,500m3 - 6.5 - hrs
11 Load Spoil to Barge, capacity 1,000m3 - 5.5 - hrs
12 Spoil conveyor, 600mm belt, 150m/min - 260.0 - m3/hr
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
24 Crawler Shovel, 0.6m3 bucket, over 200m2, Boulder Clay 22.2 33.8 45.4 m3/hr
25 Crawler Shovel, 1.2m3 bucket, 50-200m2, Sand/Soil 43.5 48.0 52.6 m3/hr
26 Crawler Shovel, 1.2m3 bucket, over 200m2, Sand/Soil 55.5 61.1 66.7 m3/hr
27 Crawler Shovel, 1.2m3 bucket, 50-200m2, Gravel 43.8 48.3 52.9 m3/hr
28 Crawler Shovel, 1.2m3 bucket, over 200m2, Gravel 55.5 61.1 66.7 m3/hr
29 Crawler Shovel, 1.2m3 bucket, 50-200m2, Hardcore 37.1 40.3 43.5 m3/hr
30 Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore 47.6 51.6 55.6 m3/hr
31 Crawler Shovel, 1.2m3 bucket, 50-200m2, Boulder Clay 43.8 45.7 47.6 m3/hr
32 Crawler Shovel, 1.2m3 bucket, over 200m2, Boulder Clay 55.6 59.1 62.5 m3/hr
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
34 Columns, Round Sides, Steel Mould, 3.0-4.0m dia 5.2 6.5 7.5 m2/hr
35 Columns, Sloping Column Heads, extra over rate - 2.5 3.5 hrs/no
36 Staircases, Stair Soffit, Sloping 0.7 0.8 1.0 m2/hr
37 Staircases, Stair Soffit, Flat Landing 0.8 0.9 1.2 m2/hr
38 Staircases, Wall Strings 0.4 0.6 - m2/hr
39 Staircases, Open Strings 0.7 0.8 - m2/hr
40 Staircases, Riser Boards fixed to strings - 2.5 2.8 m2/hr
41 Staircases, Risers fixed to Strings - 2.3 2.6 m2/hr
42 Waffle Flooring, 2.4m grid 1.1 1.4 1.8 m2/hr
43 Shaft Slip Forming - 300.0 500.0 mm/hr
44 Table Form, Aluminum System, 400m2 bays 2.1 3.2 3.8 m2/hr
45 Table Form, H-Frame Steel Falsework, 400m2 bays 1.9 3.0 3.5 m2/hr
46 Tunnel Forms, Wall and Slab poured as one - 15.6 17.5 m2/hr
47 Hollorib Decking, lay deck - 43.5 47.5 m2/hr
48 Hollorib Decking, shear connecting studs - 29.3 31.2 m2/hr
49 Stop Ends, no perforations 2.8 3.5 4.2 m2/hr
50 Stop Ends, minor perforations 1.2 1.5 1.9 m2/hr
51 Stop Ends, dense perforations 0.9 1.1 1.4 m2/hr
52 Box Outs, 0.01-0.05m2 7.6 8.2 9.1 no/hr
53 Box Outs, over 0.05m2 3.1 3.9 4.5 no/hr
54 Dummy Frames, under 3.0m2 4.5 6.2 7.1 no/hr
55 Dummy Frames, over 3.0m2 3.1 3.7 4.5 no/hr
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Typical Productivity Rates (Example)
These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to
calculate their productivity depending on the resources available and conditions of work.
Appendix I