Professional Documents
Culture Documents
Report
Report
This manual presents the current Department guidelines pertaining to roadway design
provides a means of developing uniformity and safety in the design of a highway system
It is recognized that situations occur where good engineering judgment will dictate
deviation from the current Department design guidelines. Any such deviations from
1
Controlling Design Elements (Roadway) Stopping Sight Distance (vertical curves,
Shoulder Width
Design Speed (a design exception for a reduction in the design speed will not be
approved)
2
The above Controlling Design Element (CDE) list is in accordance with the Design
Exception Manual.
The guidelines contained in this manual, other than the CDE’s shown above, are
attaining good design. Deviations from this information or guidance do not require a
design exception.
It is not the intent of this manual to reproduce all the information that is adequately
covered by textbooks and other publications which are readily available to designers
and technicians.
This manual, when used in conjunction with engineering knowledge of highway design
and good judgment, should enable the designer to perform their job more efficiently.
The geometric design of streets and highways not on the State Highway system should
and Streets. The design of traffic barriers and drainage systems shall conform to the
3
Planning with respect to road construction takes into account present and future uses of
the transportation system to assure maximum service with a minimum of financial and
environmental cost. The main objective of this initial phase of road development is to
establish specific goals and prescriptions for road network development along with the
more general location needs. These goals must result from a coordinated effort
between the road engineer and the land manager, forester, geologist, soil scientist,
regarding alternatives or solutions to specific problems. The pattern of the road network
The road pattern which will give the least density of roads per unit area while
maintaining minimum hauling distance is the ideal to be sought. Keeping the density of
roads to an economical minimum has initial cost advantages and future advantages in
road maintenance costs and the acreage of land taken out of production.
Sediment control design criteria may be the same as, or parallel to, other design criteria
which will result in an efficient, economical road system. Examples of overlap or parallel
criteria are
4
1. Relating road location and design to total forest resource, including short and
long term harvest patterns, reforestation, fire prevention, fish and wildlife
2. Relating road location and design to current and future timber harvesting
methods.
3. Preparing road plans and specifications to the level of detail appropriate and
independent contractor, the scope of the project, and thus allow for proper
estimates.
5
5. Analyzing specific road elements for "up-front" cost versus annual maintenance
cost (for instance, culvert and embankment repair versus bridge installation, ditch
pavement or lining versus ditches in natural soil, paved or lined culverts versus
versus placing and maintaining large embankments and fill slopes, roadway
The route planning phase is the time to evaluate environmental and economic tradeoffs
and should set the stage for the remainder of the road development process. Although
inclusion of design criteria for sediment control may increase initial capital outlay, it does
not necessarily increase total annual cost over the life of the road which might come
erosional impacts should be a primary concern. In some areas, this may dictate the
location of control points or may in fact eliminate certain areas from consideration for
6
ITEM NO. 2 : GENERAL DESIGN CRITERIA
2.1 General Geometric design is the design of the visible dimensions of a highway with
the objective of forming or shaping the facility to the characteristics and behavior of
drivers, vehicles, and traffic. Therefore, geometric design deals with features of location,
classified into a set of sub-systems, described below, based on the way each roadway
is used. Central to this process is an understanding that travel rarely involves movement
along a single roadway. Rather each trip or sub-trip initiates at a land use, proceeds
through a sequence of streets, roads and highways, and terminates at a second land
use. The highway classification process is required by federal law. Each state must
assign roadways into different classes in accordance with standards and procedures
have been established for rural and urban areas. For a further description of the
7
2.2.2 Principal Arterial Highways Principal arterial highways form an inter-connected
network of continuous routes serving corridor movements having the highest traffic
volumes and the longest trip lengths. In rural areas, travel patterns should be indicative
carry a high proportion of total urban area travel on a minimum of mileage. The principal
highways. However, because of the function of principal arterial highways, the concept
major traffic movements. For facilities within the subclass of other principal arterials in
urban areas, mobility is often balanced against the need to provide direct access as well
right exists for access to a principal highway, and the rights of the traveling public to a
8
2.2.3 Minor Arterial Highways Minor arterial highways interconnect with and augment
the principal highway system. In urban areas, minor arterial highways are usually
included in the Federal-aid urban system (FAUS), and serve trips of moderate length at
minimized to facilitate traffic flow and safety. In rural areas, minor arterial highways will
usually be included in the Federal consolidated primary (FAP) system, and serve trip
lengths and travel densities greater than those served by collector roads. Rural minor
arterials should provide relatively high overall travel speeds, with minimum interference
to through movements consistent with the context of the project area and considering
the range or variety of users. Because of the high speeds, access to abutting property
2.2.4 Collector Roads Collector roads primarily serve trips of intracounty rather than
statewide importance. Travel speeds and volumes are less than on arterial roadways,
but are still high relative to local roads. These roads provide for both land access and
traffic circulation. In urban areas, these roads connect neighborhoods or other districts
with the arterial system, and will usually be part of the Federal-aid urban system
(FAUS). In rural areas, these roads may be subclassified into two groups:
9
Major collectors - Serve important intracounty traffic corridors and provide service
to major county traffic generators. These roads will usually be included in the
Minor collectors - Serve smaller places and towns and connect locally important
2.2.5 Local Roads The local street and road system constitutes all roads not included in
the higher classifications. These streets and roads provide direct access to abutting
land and permit access to the roads of higher classification. They offer the lowest level
especially in urban areas. The local road system contains the large majority of all
roadway mileage in a state, but only a small percentage of total traffic. For example, in
New Jersey local roads include 72 percent of total road mileage, but only 16 percent of
10
2.3 Design Controls 2.3.1 General The location and geometric design of highways are
affected by numerous factors and controlling features. These may be considered in two
Highway Classification
Traffic
B. Secondary Controls
Design Speed
Design Vehicle
Capacity
A. Highway Classification
Separate design standards are appropriate for different classes of roads, since the
classes serve different types of trips and operate under different conditions of both
speed and traffic volume. The design of streets and highways on the State highway
system should conform to the guidelines as indicated in this manual. In special cases of
restrictive or unusual conditions, it may not be practical to meet these guide values. For
detailed descriptions of the various guide values, please refer to the appropriate
11
The location and the geometric features of a highway are influenced to a large degree
by the topography, physical features, and land use of the area traversed. The character
of the terrain has a pronounced effect upon the longitudinal features of the highway, and
frequently upon the cross sectional features as well. Geological conditions may also
affect the location and the geometrics of the highway. Climatic, soil and drainage
conditions may affect the profile of a road relative to existing ground. Man-made
features and land use may also have considerable effect upon the location and the
design of the highway. Industrial, commercial, and residential areas will each dictate
C. Traffic
The traffic characteristics, volume, composition and speed, indicate the service for
which the highway improvement is being made and directly affects the geometric
features of design. The traffic volume affects the capacity, and thus the number of lanes
required. For planning and design purposes, the demand of traffic is generally
expressed in terms of the design-hourly volume (DHV), predicated on the design year.
The design year for new construction and reconstruction is to be 20 years beyond the
anticipated date of Plans, Specifications and Estimate (PS&E), and 10 years beyond the
anticipated date of PS&E for resurfacing, restoration and rehabilitation projects. The
which affects the location and geometrics of highways. Types, sizes and load-power
characteristics are some of the aspects taken into account. The following definitions
12
ADT Average Daily Traffic - The total volume during a given time period greater than
one day but less than one year divided by the number of days actually counted.
AADT Average Annual Daily Traffic - The total yearly volume in both directions of travel
divided by 365 days. BDC16MR-02 NJDOT Roadway Design Manual 2-4 General
Design Criteria
DHV Design-Hourly Volume - Normally estimated as the 30th highest hour two-way
D The directional distribution of traffic during the design hour. It is the one-way volume
of DHV.
A. Design Speed
"Design Speed" is a selected speed used to determine the various design features of
the roadway.
The assumed design speed should be a logical one with respect to topography,
anticipated operating speed, the adjacent land use, the presence of bicycle and
pedestrian accommodations, and the functional classification of the highway. Except for
13
local streets where speed controls are frequently included intentionally, every effort
should be made to use as high a design speed as practicable to attain a desired degree
economics, aesthetics and social or political impacts. Once the design speed is
selected, all of the pertinent features of the highway should be related to it to obtain a
balanced design. Above minimum design values should be used, where practical. On
lower speed facilities, use of above-minimum design criteria may encourage travel at
speeds higher than the design speed. Some design features, such as curvature,
superelevation, and sight distance are directly related to and vary appreciably with
design speed. Other features, such as widths of lanes and shoulders, and clearances to
walls and rails, are not directly related to design speed, but they affect vehicle speeds.
Therefore, wider lanes, shoulders, and clearances should be considered for higher
design speeds. Thus, when a change is made in design speed, many elements of the
Since design speed is predicated on the favorable conditions of climate and little or no
These three factors apply only to the selection of a specific design speed within a
part. The design speed (mph) as it relates to the posted speed (mph) is shown below:
14
B. Design Vehicle
The physical characteristics of vehicles and the proportions of the various size vehicles
using the highways are positive controls in geometric design. A design vehicle is a
selected motor vehicle, the weight, dimensions and operating characteristics of which
type. The symbols and dimensions of design vehicles are shown in Table 2-2.
15
Improving an existing highway is preferred to the constructing a new one. Highways are
improved to meet general traffic needs, to eliminate or reduce negative impacts caused
by traffic or when changes in land use so require. A new highway shall be constructed
when the existing highway network no longer meets the requirements of traffic or land
use, and these requirements cannot be satisfactorily met or eliminated through road
Reasons to improve existing highways and construct new ones include the following:
• Requirements better serve the transport needs of industrial and commercial activities.
• Increasing mobility during working hours and free time and growth of the car fleet.
• Need to make highways safer and reduce negative impacts on the environment
caused by traffic.
• Aim to improve pedestrian and bicycle traffic conditions, and the use of public
transport.
16
17
ITEM NO. 3 : DEFINITIONS AND TERMINOLOGY
3.1 General
This section includes general terminology associated with the road cross-section and
AASHTO, 1968.
The elements of the road cross-section are illustrated in Figure 3-A and Figure 3-B and
defined as follows:
1. Highway - A general term denoting a public way for purposes of vehicular travel,
including the entire area within the right-of-way lines. Recommended usage in urban
2. Highway Section - The portion of the highway included between top of slopes in cut
3. Roadway - The portion of the highway, including shoulders, for vehicular use.
4. Traveled Way - The portion of the roadway provided for the movement of vehicles,
5. Median - The portion of a divided highway separating the traveled ways for traffic in
opposite directions.
6. Shoulder - The portion of the roadway contiguous with the traveled way for
accommodation of stopped vehicles for emergency use, and for lateral support of the
18
base and surface courses. The shoulder may be used for bicycle travel where allowed.
7. Surfaced Right Shoulder - That portion of the outside paved shoulder to provide all
8. Surfaced Left Shoulder - The portion of the median shoulder paved to provide all
9. Profile Line - The point for control of the vertical alignment. Also, normally the point of
10. Pavement Cross Slope – Lateral slope across the pavement. See Section 5.2.2.
11. Shoulder Cross Slope – Lateral slope across the shoulder. See Section 5.4.3.
12. Base Course - The layer or layers of specified or selected material of designed
subgrade to support a base course. BDC15MR-01 NJDOT Roadway Design Manual 3-2
accommodate the traffic load, the top layer of which resists skidding, traffic abrasion,
and the disintegrating effects of climate. 15. Pavement Structure - The combination of
subbase, base course and surface course placed on a subgrade to support the traffic
19
16. Shoulder Surface Course
18. Subgrade - The top surface of the roadbed upon which the pavement structure and
24. Hinge Point (P.V.I.) - The intersection of shoulder slope planes with fill or cut slope
planes.
26. Median Barrier - A longitudinal barrier used to prevent an errant vehicle from
crossing the portion of a divided highway separating the traveled ways for traffic in
opposite directions.
27. Guide Rail - A barrier whose primary function is to prevent penetration and safely
28. Top of Slope - The intersection of the cut slope and the original ground.
29. Toe of Slope - The intersection of the fill slope and the original ground.
20
30. Outer Separation - The portion of an arterial highway, between the traveled ways of
31. Frontage Road - Also called marginal road or street. A local road, or street auxiliary,
to and located on the side of an arterial highway for service to abutting property and
32. Roadside - The area adjoining the outer edge of the roadway (normally applies to
freeways). The term "border" or "sidewalk area" is usually referred to street type
facilities.
33. Outer Separation Island - The space in the outer edge of roadway shoulder and
frontage roadway shoulder and frontage road or street which may be landscaped or
34. Buffer Strip - The space in the border area provided to separate the sidewalk from
35. Sidewalk - An exterior pathway with a prepared surface (concrete, bituminous, brick,
Highway planning is based on the Highway Act and Decree, and other legislation
concerning land use planning. The state is responsible for maintaining and planning
highways. The Finnish Transport Agency acts as the responsible organisation at state
level. The Centres for Economic Development, Transport and the Environment (EDTE
Centres) are regional-level authorities. The EDTE Centre commissions the planning,
21
addition to highways maintained by the state, there are streets in urban areas,
constructed and maintained by the municipalities. In addition, many private roads exist,
especially in rural areas, which are the responsibility of shareholders or the owner of the
22
ITEM NO. 4 : DESIGN CRITERIA AND FUNCTIONAL CLASSIFICATION OF
HIGHWAYS
–Functional classification
–Topography–Available Funding
–Safety–Politics
–Right-of-Way (ROW)
–Costs
–Principal arterials
–Minor arterials
–Major collectors
–Minor collectors
23
Each functional classification can is termed either urban or rural depending on the
plans for traffic, land use and areas are all integrated. Co-operation is therefore
necessary between the different parties involved in planning. Road maintaining and
resulting in plans and programmes to achieve these goals. These in turn direct actions
within different segments, such as the planning of road projects. Road management
programmes are drawn up in co-operation with the other parties involved in community
planning. There are programmes with three time scales: long-term plan (LTP, 10 to 30
years), operational and financial plan (OFP, 4 years) and an annual implementation
plan based on the state budget. Major road network development projects are drawn up
budget debates. Other road projects are drawn up in the regional Centres for Economic
24
ITEM NO. 5 : COMPLETE STREETS
“Complete Streets” involves designing streets not just for the automobile but for all
users. Generally, the elements that make up a complete street, according to the
National Complete Streets Coalition, are sidewalks, bicycle lanes, shared-use paths,
designated bus lanes, safe and accessible transit stops, and frequent and safe
crossings for pedestrians, including median islands, accessible pedestrian signals, and
curb extensions. There is no one design for complete streets since different areas have
different road uses. However, all complete street designs should balance safety and
The MTP recommends the development and adoption of Complete Streets policies.
design the right-of-way to accommodate all users – drivers, transit riders, pedestrians,
and bicyclists, as well as for older people, children, and people with disabilities.
Complete streets provide a safer and more accessible transportation system for all
users.
25
Sample Complete Streets Resolution for NWA Communities:
The planning of road projects is a process becoming more detailed stage by stage. At
accordance with land use planning. The planning process has four stages: feasibility
planning. In minor road projects with limited impacts, planning and decision-making
highway is planned, the planning must be based on a land use plan meeting the
26
requirements of the Land Use and Building Act. Road planning phases are connected to
• At the feasibility study phase, the necessity and timing of road projects are studied at
the same approximate planning level as the regional land use plan and the local master
plan.
local master plan or a local detailed plan. A preliminary engineering plan determines the
approximate location and space requirement of the road and its relation to the
surrounding environment.
• Final engineering planning is planning at the same level of detail as local land use
plans.
performed before and during construction. In different phases of the planning process,
alternatives are reduced as road planning becomes more accurate. As the process
27
progresses, planning can be more and more focused. For the public and other parties to
the planning process, it is important to participate in the planning at the right time.
Planning can also be interrupted, if sufficient reasons no longer exist to continue the
planning process.
28
ITEM NO. 6 : MINOR STREETS
Minor streets can be further optimized for bicycle travel by applying bicycle
Parking may be permitted or prohibited based on demand and adjacent land use.
Planning a transport system involves interactive planning of land use and traffic. Thus, a
framework is created for the arrangement of different traffic modes and land use.
Planning generates traffic policy objectives and goals, network plans for different traffic
modes, implementation strategies for the system and assessments of the impacts. More
detailed plans for pedestrian and bicycle traffic, public transport, parking etc. are made
when needed.
29
Transport system plans have been drawn up for many urban areas and some
provinces. In smaller urban areas, the planning emphasis is usually on traffic network
planning.
For various purposes, feasibility studies can have different names and content. The
most common project-specific feasibility studies are the development study, needs
The starting points of a feasibility study are existing land use and current road and traffic
conditions. Societal development causes changes in travel needs and traffic conditions.
These changes are examined during the feasibility study phase and the actions required
to meet the goals set for the development of traffic conditions are planned. The outcome
of the feasibility study is a project or several projects for which preliminary examinations
have been conducted of possible alternative actions, including the related impacts and
costs. During the feasibility study, the need for interaction varies according to the nature
30
of the project. Participation by municipalities and regional councils are usually
The decision to begin planning can be made based on the feasibility study. Such a
decision consists of the road authority’s statements concerning the necessity, timing
and further planning of development actions. Actions deemed necessary proceed for
31
ITEM NO. 7 : COLLECTOR STREETS
areas. Collects traffic from local streets in neighborhoods and channels it into the
arterial system.
Function
• Design Service Volume: 4,000 vpd; 6,000 vpd with left turn bays
Preliminary engineering planning determines the approximate location of the road, the
road’s connections to the existing and future road network and land use, basic technical
and traffic solutions and the principles underlying the prevention of negative impacts to
the environment. Planning is performed at a level of detail which ensures that the plan is
32
environmental impact assessment (EIA), the road project’s environmental impact is
The approval decision is made on the preliminary engineering plan. The project can
Agency’s operating and financial plan, the programmes of the Centres for Economic
33
Because the location and quality of the highway and the highway’s impacts on people’s
living conditions and the environment are determined in the preliminary engineering
plan, this phase has the most important effect on the road project. An approved
preliminary engineering plan may limit Preliminary Engineering Plan other construction
general, principles approved in the preliminary engineering plan are usually no longer
discussed in the final engineering planning phase. Customarily, when the final
34
ITEM NO. 8 : MINOR ARTERIAL
Function Connects higher functional class facilities, activity centers, regions of the area,
and major county roads at the edge of the metropolitan area. Traffic is composed
Provides service to traffic at a somewhat lower level of travel mobility than principal
Design Service Volume: 12,200 vpd; 14,800 vpd with left turn bays
Final engineering planning determines the precise location of the highway, areas
required for the highway, intersections of highways and private roads and solutions for
other road connections, solutions for pedestrian and bicycle traffic and public transport,
and other detailed solutions such as measures necessary to the prevention of negative
traffic impacts. Because the final engineering plan settles all issues directly affecting
land owners and other parties concerned, interaction is focused on issues to be agreed
with them.
35
The approval decision is made on the final engineering plan, allowing the road authority
the right to take possession of the area required for the highway. It is sometimes
necessary to make a revision plan to an approved final engineering plan. This process
is similar to the original plan, unless the impact of the change is so minor that
agreement with real-estate owners is sufficient. Once financing has been ensured,
Construction planning belongs to the road construction phase and covers the drafting of
the documents required for construction. In many cases, the contractor is often
responsible for drawing up the construction plan. Within limits of the final engineering
plan, interaction between road constructors and landowners and other concerned
parties continues throughout the entire planning and construction phase. In minor
projects, the final engineering and construction planning phases can be combined.
Compensation is paid for any damage caused to external property during final
36
ITEM NO. 9 : MAJOR ARTERIAL
Function
and major urban activity centers within the metropolitan area. Traffic is composed
Access may be controlled through medians or by the limitation of curb cuts through the
• Design Service Volume: 17,600 vpd – 20,600 vpd with left turn lane
37
ITEM NO. 10 : FREEWAY/EXPRESSWAY
Function
High speed, multi-lane facilities with a high degree of access control. These facilities
serve the major centers of activity of the metropolitan area and are well integrated with
the urban arterials and major rural arterials routes entering the region. They should
provide a high level of traffic service to travelers who do not have local destinations and
• Lanes: Four or more 12-foot lanes; 10-foot outside shoulders and 6-foot inside
shoulders
• Median: Either acceptable depressed median or raised median with safety barrier
38
soils), traffic requirements, and traffic service levels. Objectives should be established
for each road and may be expressed in terms of the area and resources to be served,
life of the facility and functional classification. Additional objectives may also be defined
1. Resource management objectives: Why is the road being built; what is the
purpose of the road (i.e., timber harvesting, access to grazing lands, access to
communities, etc.)?
2. Physical and environmental factors: What are the topographic, climatic, soil and
geologic conditions, high rainfall intensities. Examples of the latter include land
ownership boundaries, state of the local economy, and public opinion about a
given project.
39
4. Traffic requirements: Average daily traffic (ADT) should be estimated for different
user groups. For example, a road can have mixed traffic--log or cattle trucks and
5. Traffic service level: This defines the type of traffic that will make use of the road
network and its characteristics. Table 3 lists descriptions of four different levels of
traffic service for forest roads. Each level describes the traffic characteristics
which are significant in the selection of design criteria and describe the operating
conditions for the road. Each level also reflects a number of factors, such as
40
speed,travel time,traffic interruptions, freedom to maneuver, safety, driver
comfort, convenience, and operating cost. Traffic density is a factor only if heavy
non-logging traffic is expected. These factors, in turn, affect: (1) number of lanes,
(2) turnout spacing, (3) lane widths, (4) type of driving surface, (5) sight
distances, (6) design speed, (7) clearance; (8) horizontal and vertical alignment,
traffic requirements and traffic service level criteria selected above, will define the
types of vehicles that are to use the proposed road. Specific vehicle
standards" to be adopted when proceeding to the road design phase. The land
manager has to distinguish between the "design vehicle" and the "critical
41
vehicle". The design vehicle is a vehicle which ordinarily uses the road, such as
dual axle flatbed trucks in the case of ranching or farming operations, or dump
trucks in the case of a mining operation. The critical vehicle represents a vehicle
which is necessary for the contemplated operation (for instance, a livestock truck
in the case of transporting range livestock) but uses the road infrequently. Here,
the design should allow for the critical vehicle to pass the road with assist
types will be utilizing the same road. Safety requirements such as stopping
distance, sight distance, and allowable design speed can determine the selected
8. Road uses: The users of the contemplated road should be defined by categories.
For example, timber harvest activities will include all users related to the planned
crews, and construction and maintenance crews, as well as the logging crews.
42
include stock herders and rangeland management specialists and will have a
different set of objectives than timber objectives. An estimate of road use for
each category is then made (e.g., numbers of vehicles per day). For each
should be indicated. For instance, a road is to be built first for (1) the harvest of
timber from a tract of land, then (2) access for the local population for firewood
evaluations.
As part of this process a "roads objectives documentation" plan should be carried out.
This process consists of putting the road management objectives and design criteria in
Table 3. Traffic service levels definitions used to identify design parameters (from U.S.
43
44
ITEM NO. 11 : ACCESS MANAGEMENT
safety and system reliability. It calls for effective ingress and egress to a facility, efficient
spacing and design to preserve the functional integrity and overall operational viability of
street and road systems. Good access management promotes safe and efficient use of
NWARPC has worked toward development of regional policies and a Model Access
local governments to use and tailor to their unique and specific needs and situations.
Access Management should address, among other things, the following areas:
• Facility hierarchy
• Driveway spacing
• Street connections
45
In areas of rapid land development, it is important for jurisdictions to develop access
standards that achieve a balance between property access and functional integrity of
the road system. Studies show that implementing access management provides three
• Reduced crashes
1) Limit the number of conflict points at driveway locations. Conflict points are
indicators of the potential for accidents. The more conflict points that occur at an
intersection, the higher is the potential for vehicular crashes. When left turns and cross
street through movements are restricted, the number of conflict points is significantly
46
2) Separate conflict areas. Intersections created by streets and driveways represent
basic conflict areas. Adequate spacing between intersections allows drivers to react to
3) Reduce interference for through traffic. Through traffic often needs to slow down for
vehicles exiting, entering, or turning across the roadway. Providing turning lanes,
designing driveways with appropriate turning radii, and restricting turning movements in
and out of driveways allows turning traffic to get out of the way of through traffic.
signalized intersections reduces conflict areas and increases the potential for smooth
traffic progression.
5) Provide adequate on-site circulation and storage. The design of good internal vehicle
circulation in parking areas and on local streets reduces the number of driveways that
governments can use to control access to highways, major arterials, and other
• Access Spacing: Increasing the distance between traffic signals improves the flow of
traffic on major arterials, reduces congestion, and improves air quality for heavily
traveled corridors.
• Driveway Spacing: Fewer driveways spaced further apart allow for more orderly
47
• Safe Turning Lanes: Dedicated left and right-turn, indirect left-turns and U-turns, and
reduce an intersection with many conflict points or a severe crash history (T-bone
crashes) to one that operates with fewer conflict points and less severe crashes
medians are examples of some of the most effective means to regulate access and
reduce crashes.
widening, good sight distance, access location, and other access-related issues.
A road design standard consists of such elements as the definitive lengths, widths, and
depths of individual segments (e.g., 4.3 meter traveled way, 0.6 meter shoulders, 3/4:1
illustrates the road structural terms that will be used throughout the rest of this
handbook. Selection of the appropriate road design standard is critical to the overall
efficiency of the road network to be installed, and certain elements will have a more rigid
standard than others depending on the location of the road or road segment. The entire
range of values for each standard must be evaluated and selected according to their
appropriateness for a given segment. Then, the various design elements must undergo
testing to ensure that the final design meets the previously agreed upon management
objectives. For instance, on steeper grades vertical alignment has a greater effect on
travel speed than horizontal alignment. Therefore, surfacing and horizontal alignment
48
should not be improved to increase speed where the road gradient is the controlling
element.
49
ITEM NO. 12 : CHARACTERISTICS OF THE CSS PRODUCTS OR DESIGN
The project is a safe facility for all users and the community.
The project solves problems and satisfies the purpose and needs identified by a
The project exceeds the expectations of both designers and stakeholders and is
The project involves efficient and effective use of resources (time, budget) of all
involved parties.
CSS projects consider new and emerging technologies, funding sources, and public
policy issues aimed at addressing major drivers such as energy supply, climate change,
and sustainability initiatives. CSS projects also address livability issues such as bicycle
and pedestrian facilities, transit, and multimodal connections. Additionally, CSS projects
50
ITEM NO. 13 : CONGESTION MANAGEMENT PROCESS
The CMP is intended to serve as a systematic process that provides for safe and
• Collection of data and system performance monitoring to define the extent and
The goal of the CMP is to ensure optimal performance of the transportation system by
51
The CMP network includes 224.5 centerline miles of roadway spread over 13 different
roadways divided into 234 directional links bound by a traffic signal, stop sign, or major
cross street. Of the 242 directional miles studied in the morning peak and afternoon
peak periods, it was determined to classify the top 15 percent of the segments as
congested including both the results of the AM and PM periods. The AM period was
defined from 7:00-9:00 AM, while the PM period was defined from 4:30-6:30 PM. Map
52
ITEM NO. 14 : CONGESTION MANAGEMENT MEASURES
The purpose of the CMP Study was to identify and quantify problem areas in the region
using 2013 private sector travel speed data and AHTD volume data. Private sector 2013
travel speed data was procured for the region which covered the National Highway
System (NHS) and arterial network in the urbanized area. Through the use of private
NWARPC has introduced the use of congestion index (CI) as one element of
performance in the CMP. This performance measure allows easy comparison of the
efficiency of roadways as a ratio of average travel speed to the posted speed limit. The
second measure is volume delay per mile. This performance measure calculates the
delay or amount of time drivers wait as compared to traveling at the posted speed. Also,
by multiplying it by the link volume, the overall impact of the delay can be measured. CI
is purely a measure of delay time, but does not relate the number of cars in the delay. In
many cases the minor or secondary roads are high on the CI ranking but rank lower on
the volume delay because fewer vehicles and people are affected on these secondary
roads. The CMP segments vary in length across the board between those on arterials
and freeways. In order to standardize the results and allow direct comparison across the
network, the volume-delay results were divided by the length. This measure provides a
result with the units of vehicle hours of delay per mile, thus allowing a more direct
determined and used to identify the operating results of each link of the CMP network.
53
Based on the local conditions in the region, attention was focused on the peak periods.
The duration of congestion and other performance measures were not as much of a
concern with the short peaking of congestion within the region. This also is applicable in
most areas of the region to performance measures based on volume. There are a few
areas within the region where capacity is an issue, but most delay occurs at the node
level and is not a link problem. Because volume is measured mid-block and does not
consider the operations of the nodes (intersections), attention is being focused at the
location where the MPO can get the most benefit. The primary performance measure is
volume delay per mile. In order to narrow the focus on those roadway segments that
need attention and commonly have recurring delay, the results were tabulated and the
highest 15 percent of the network was categorized as congested. Over time, with future
updates, the region will be able to revisit these thresholds and adjust as desired. FHWA
encourages flexibility with the process and customization of the methodology and
54
ITEM NO. 15 : CONGESTION MANAGEMENT STRATEGIES
Access Management
of access points, the location of access points, the number of access points allowed
within a given distance (access density), and the roadway median treatment. Generally,
the number of access points is minimized and regularly spaced from each other so that
Signal Timing
by appropriately allocating green time among competing phases. This allows more
traffic to pass through the signal with less delay. By adjusting cycle lengths and offsets,
drivers can travel longer distances along a corridor before having to stop for a red light.
This decreases travel time and improves air quality. Both signal timing optimization and
traffic signal progression are low cost improvements to make the best use of existing
capacity and optimize allocation of funding. The cost for a signal timing improvement
55
project varies depending on the number of traffic signals, the controller capabilities, the
location of the traffic signals and adjacent signals, the number of timing plans required,
and implementation and fine-tuning needs. Adaptive signal control as has been
implemented along Hwy. 71B in Springdale and Rogers and Hwy. 62 in Rogers and will
be more expensive per intersection than just occasional signal optimization, but
Signal timing is an area that deserves attention within the region to allow maximum
efficiency of the existing system before costly widening to add capacity. The results will
be very evident as has been demonstrated previously with localized projects. A regional
perspective would produce consistent travel time runs even when crossing from one
city/agency to another.
many regions across the country. It has been clearly proven locally and nationally that
operational improvements provide the highest benefit/ cost ratio and on a regional scale
as compared to local capacity projects that benefit a smaller portion of the area. 2040
Operations, and System Performance 8-19 Data collection, development of a model for
each desired timing plan, signal timing optimization, and implementation can be
accomplished along a corridor for around $3,000 per intersection (not including any
The methods will vary as to how to accomplish the desired results depending on the
signal hardware currently in place and the expansion capabilities. It can be as simple as
56
installing a GPS clock at each intersection ($500) to synchronizing the controller clocks,
to more advanced systems where each intersection needs vehicle detection ($15,000)
and wireless communications ($2,500) between signals. Either way, the benefit/cost
stop intersections or intersections with heavy major-street and cross-street traffic. This
reduces delay for previously stop-controlled movements but may increase delay for
movements that were not controlled. As traffic volumes increase, traffic signals or other
can result in big reductions in delays through bottleneck mitigation. Local improvements
57
Incident Management
reducing delays and secondary incidents. By identifying incidents early and having
quick responses from tow trucks available in close proximity that may be stationed or
possible.
Crossings
Safety projects reduce crash rates and the severity of crashes. The region should
continue to deploy rumble strips as needed, cable median barriers, enhanced signing at
curves and high friction pavements to reduce crash rates on the CMP network.
58
Additionally, two Razorback Regional Greenway trail crossings have been grade
separated (MLK/Hwy 180, and S. Walton Blvd./Hwy. 71B) on the CMP network which
Within the MPA, AHTD has installed approximately 46 miles of cable barrier with 24
miles of cable barriers along I-49 between Fayetteville and Bentonville (Table 8.2). The
safety project was completed in 2012 between Fayetteville and Rogers. AHTD reported
that from 2007 to 2011, before the cable barriers were installed, there were 17 serious
median crossover crashes that resulted in 10 fatalities along I-49, an average of two
fatalities per year. In areas where I-49 is being widened, a concrete barrier wall will
59
Capacity
Roadway widening is necessary where traffic signal timing and access management are
unable to provide enough capacity for heavy traffic volumes. Some segments may
improve in the short term with optimized signal timing, but may ultimately warrant
additional capacity through widening. Widening could include adding a through lane for
60
ITEM NO. 16 : PERFORMANCE MANAGEMENT AND SYSTEM MEASURES
AHTD and MoDOT are required to develop plans and programs that help achieve the
national goals for (1) Safety, (2) Infrastructure Condition, (3) Congestion Reduction, (4)
Over the next several years, final rules on performance measures and targets will be
published by FHWA and FTA. MoDOT, AHTD, and NWARPC will continue to work
61
62
ITEM NO. 17 : SAFETY
Safety of the transportation system is one of the national goals and a performance
individual state, and by county based on data reported to the States and U.S. DOT.
Safety performance is generally measured by calculating the fatality and serious injury
rates of the system based on vehicle miles of travel (VMT) and 100,000 population.
Travel is measured as vehicle miles of travel (VMT) and is calculated and published
each year by AHTD in the Road and Street Mileage Report. This annual calculation is
based on the Annual Average Daily Traffic (AATD) counts and mileage of the
Travel).
The rate of fatalities is generally expressed as rate per 100,000 population and as 100
million annual vehicle miles of travel (100 million VMT). These rates are generally
NWARPC has provided the fatality and serious injury rates expressed in per 100,000
population and 100 million VMT. The Arkansas portion of the MPA boundary (Benton
and Washington County) is calculated as one rate and McDonald County is calculated
separately utilizing the Fatality Analysis Reporting System (FARS) and the Arkansas
The rates shown should be viewed as a baseline data for the region in anticipation of
future safety performance targets and performance measures as required by the final
rule making by FHWA and FTA. NWARPC will work with its planning partners as AHTD,
63
MoDOT, and NWARPC identify and develop safety performance targets and/or
Safety Analysis
From 2009–2013, Benton and Washington County, Arkansas averaged 43 fatalities and
318 serious injuries each year. The total number of fatalities has ranged from 49 in 2011
to 33 in 2015.
64
In 2013, Benton and Washington County fatalities per 100 million vehicles traveled was
0.84 which was below the national and state rate. The Arkansas rate was 1.44 fatalities
per 100M VMT and the U.S. rate of 1.09 fatalities per 100M VMT
The Arkansas rates per 100 million VMT and 100K population have declined over the
last four years but are still higher than the U.S. rate.
This section reviews data for crashes involving pedestrians and bicyclists in Benton and
Washington Counties (2009- 2013), as reported by the Arkansas State Police. There
65
are approximately 75-110 reported crashes annually that have resulted in 245 or more
injuries and 27 fatalities over the course of five years. While 2013 saw a dip, bicyclist
crashes in particular appear to be trending upwards, perhaps reflecting the fact that
bicycling is becoming more common. Additional data on the number of bicycle trips that
took place each year would be needed to understand if the crash rate (i.e., crashes per
State highway system safety is addressed through the Arkansas Strategic Highway
Safety Plan – 2013 (AHTD) and the Arkansas Highway Safety Office (Arkansas State
Police). Both plans have goals, performance measures, and specific strategies to
reduce the number of fatalities and serious injuries rates on the state highway system.
66
Arkansas Strategic Highway Safety Plan’s focus is “Toward Zero Deaths.” This goal
supports the national goal of a “Toward Zero Death” strategy. The 2013 plan is
organized into primary, secondary and special emphasis areas with a focus on specific
rate of fatalities and serious injuries. The Arkansas State Police-Arkansas Highway
effective use of federal and state highway safety funds and other resources to save
The annual Highway Safety Plan is prepared by the Highway Safety Office and includes
safety goals, objectives and recommended projects each year. The plan outlines the
goal of reducing fatalities by “identifying driver behaviors that cause fatal crashes and
targeting problem areas where fatal crashes occur.” The plan has focused in areas of
67
ITEM NO. 18 : CONSIDERATIONS FOR SELECTION OF ROAD RESTRAINT
SYSTEMS
2.46 VRS are commonly known as crash barriers and are primarily used to protect
carriageways. Much research and investigation has been carried out over the years and
this has led to the development of the BS EN 1317 which has drawn together best
practice and developed a standard way of testing and evaluating the performance of
VRS. BS EN 1317 allows Systems tested under the same conditions to be compared
2.47 No vehicle impact with a barrier is the same as another. Vehicles differ in mass,
shape, rigidity and impact barriers at different angles and speed. A barrier tested to BS
EN 1317 will not tell you how it will perform when impacted by all errant vehicles, but it
will give confidence as to how it will perform in the majority of cases. The performance
of the barrier in terms of impact will vary according to the location of the installation, the
2.48 Figure 2-2 summarises the general factors that need to be taken into account by
the designer/contractor when selecting suitable VRS for most situations. Further
guidance on particular factors relating to specific situations is given in the text in the
68
69
ITEM NO. 19 : ANTI-GLARE SCREENS
11.1 The advice given for this topic is applicable to both rural and urban roads.
11.2 There are two standards for anti-glare systems for roads. They are BS EN 12676-
1: Performance and characteristics and BS EN 12676-2: Test Methods. All new anti-
glare systems must conform to the above standards and the specific requirements
11.3 The purpose of an anti-glare screen or barrier is to cut off light from oncoming
vehicle headlights. They must be designed so that light directed towards the driver at
oblique angles (12° to 20°) is reduced whilst relatively open vision (around 70°) is
maintained in the sideways direction. The height to effectively screen headlight glare
11.4 Screens and barriers can be made of various occluding materials. Where a screen
above a safety barrier have also been found to be effective in meeting anti-glare
11.5 Research carried out on a heavily trafficked motorway where an anti-glare screen
had been installed on top of a deformable safety barrier in the central reserve showed
drivers experienced no major problems. One effect of the combined safety barrier and
anti-glare screen was that the installation caused screen shyness. The effect of screen
shyness caused approximately 3% of all car drivers in the middle and offside lanes of a
70
three-lane motorway to change their position away from the safety barrier/screen, by a
11.6 Anti-glare screens have been recorded as creating extra usage of main beam
lights to the extent that drivers of preceding vehicles are aware of this. However, there
lengths of road when tested; the effects on non-injury accidents were not determined.
71
ITEM NO. 20 : TRAFFIC CALMING
"Traffic calming is the combination of mainly physical measures that reduce the
negative effects of motor vehicle use, alter driver behavior and improve conditions for
72