ITT 2011-0146 Level 5 3A UPDATE 09-Aug-19 10:53

Activity ID Activity Name Activity % Original Start Finish Budgeted Total BL Project Finish 2011 2012 2013
Complete Duration Cost
F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J
ITT 2011-0146 Level 5 378 04-May-11 A 14-Aug-12 SR0.00 25-Oct-12

Logistic Non Support Area 299 06-Jul-11 A 14-Jul-12 SR0.00 05-Sep-12

GARAGE 250 15-Sep-11 A 21-May-12 SR0.00 21-May-12


WAREHOUSE & GARAGE 182 09-Oct-11 A 07-Apr-12 SR0.00 07-Apr-12
Milestone LNSA 18 25-Mar-12 11-Apr-12 SR0.00 11-Apr-12 LSA
LSA
LSA
Non
Non
Non
Process
Proc.BLD-Rigging
Proc.BLD-E.M.C.
Proc.BLD-E.M.C.
Building - &
E.M.C.
: ACV
LV
:Scaffolding
Warehouse
Garage
Hangar
: Paint,Store
Lube
Stores
& Workshop
MRF and Job Cards Preparation 387 06-Jul-11 A 08-Apr-12 SR0.00 26-Jul-12 LSA Non Process Bldg - MRFEngineer
issue AFC by Company
Test Pack Preparation 90 18-Mar-12 A 13-May-12 SR0.00 15-Jun-12
WAREHOUSE 257 22-Sep-11 A 04-Jun-12 SR0.00 04-Jun-12
HANGAR 267 12-Oct-11 A 04-Jul-12 SR0.00 04-Jul-12
Red Line Preparation 65 25-Mar-12 28-May-12 SR0.00 28-May-12
Material segregation / Packing 418 16-Jul-11 A 18-Apr-12 SR0.00 05-Sep-12 LSA (NPB) - Material segregat/packing at Kuryk
Material delivery 352 15-Sep-11 A 28-Apr-12 SR0.00 31-Aug-12 LSA Non Process Bldg - Material at Island D
No Sub Areas 212 15-Sep-11 A 14-Jul-12 SR0.00 14-Jul-12 Rigging
Scafolding
Paint
Chemical
Oil,
Flammable
Lube
Store
Store
&Store
Grease
Store
Store Store
Logistic Support Area 365 23-May-11 A 14-Aug-12 SR0.00 25-Oct-12

Milestone LSA 91 25-Mar-12 23-Jun-12 SR0.00 23-Jun-12


LSHT93 LSA Logistic Support Area - LSA HVAC Room MC 0% 0 25-Mar-12* SR0.00 25-Mar-12 LSA Logistic Support Area - LSA HVAC Room MC
LSHT95 LSA Logistic Support Area - PR Series 18 MC 0% 0 25-Mar-12* SR0.00 25-Mar-12 LSA Logistic Support Area - PR Series 18 MC
LSHT94 LSA Logistic Support Area - Wabas Building MC 0% 0 31-Mar-12* SR0.00 31-Mar-12 LSA Logistic Support Area - Wabas Building MC
LSHT96 LSA Logistic Support Area - LSA LER MC 0% 0 26-Apr-12* SR0.00 26-Apr-12 LSA Logistic Support Area - LSA LER MC
LSHT97 LSA Logistic Support Area - IBEEV LER MC 0% 0 23-Jun-12* SR0.00 23-Jun-12 LSA Logistic Support Area - IBEEV LER MC
MRF and Job Cards Preparation 480 23-May-11 A 18-May-12 SR0.00 13-Sep-12
LSB00700LSA Log.Sup.Area - MRF 100% 0 23-May-11 A SR0.00 LSA Log.Sup.Area - MRF
LSB007002Piping MRF preparation/issuance 100% 265 23-May-11 A 27-Nov-11 A SR0.00 11-Feb-12 Piping MRF preparation/issuance
LSB007001Structure MRF preparation/issuance 100% 245 11-Jun-11 A 28-Dec-11 A SR0.00 10-Feb-12 Structure MRF preparation/issuance
LSB007004Mechanical equipment MRF preparation/issuance 100% 102 01-Jul-11 A 10-Oct-11 A SR0.00 10-Oct-11 Mechanical equipment MRF preparation/issuance
LSB007005Architectural & HVAC MRF preparation/issuance 100% 205 01-Jul-11 A 25-Oct-11 A SR0.00 21-Jan-12 Architectural & HVAC MRF preparation/issuance
LSB00040Engineer AFC by Company 100% 0 25-Dec-11 A SR0.00 25-Dec-11 Engineer AFC by Company
LSB007007Insulation MRF preparation/issuance 50% 130 05-Feb-12 A 28-Apr-12 SR0.00 13-Jun-12 Insulation MRF preparation/issuance
LSB007006Painting MRF preparation/issuance 90% 215 12-Feb-12 A 18-May-12 SR0.00 13-Sep-12 Painting MRF preparation/issuance
LSB007009IBEEV Utility Bldg MRF preparation/issuance 80% 67 04-Mar-12 A 08-Apr-12 SR0.00 09-May-12 IBEEV Utility Bldg MRF preparation/issuance
LSB007010Bridge between M12 & IBEEV Bldg. MRF prepar/iss. 80% 55 04-Mar-12 A 05-Apr-12 SR0.00 27-Apr-12 Bridge between M12 & IBEEV Bldg. MRF prepar/iss.
LSB007011Bridge between IBEEV & Pontoon MRF prepar/iss 80% 28 04-Mar-12 A 30-Mar-12 SR0.00 31-Mar-12 Bridge between IBEEV & Pontoon MRF prepar/iss
Test Pack Preparation 221 22-Nov-11 A 12-Jul-12 SR0.00 29-Jun-12
LSB00770Test Pack Preparation and Compiling 55% 221 22-Nov-11 A 12-Jul-12 SR0.00 29-Jun-12 Test Pack Preparation and Compiling
Red Line Preparation 205 25-Nov-11 A 01-Aug-12 SR0.00 16-Jun-12
LSB00775Red Line Preparation 60% 205 25-Nov-11 A 01-Aug-12 SR0.00 16-Jun-12 Red Line Preparation
Material segregation / Packing 505 02-Jun-11 A 28-May-12 SR0.00 18-Oct-12
LSC007820LSA Log.Sup.Area - Material segregation at Kuryk 100% 0 02-Jun-11 A SR0.00 LSA Log.Sup.Area - Material segregation at Kuryk
LSC0078202
Piping Material segregation at Kuryk 85% 283 02-Jun-11 A 03-May-12 SR0.00 10-Mar-12 Piping Material segregation at Kuryk
LSC0078201
Structural Material segregation at Kuryk 65% 234 21-Jun-11 A 18-Apr-12 SR0.00 09-Feb-12 Structural Material segregation at Kuryk
LSC0078204
Mechanical Eq. Material segregation at Kuryk 60% 102 30-Sep-11 A 23-Apr-12 SR0.00 09-Jan-12 Mechanical Eq. Material segregation at Kuryk
LSC0078205
Arch/HVAC Material segregation at Kuryk 100% 221 29-Jan-12 A 26-Feb-12 A SR0.00 05-Sep-12 Arch/HVAC Material segregation at Kuryk
LSC0078206
Painting Material segregation at Kuryk 75% 243 19-Feb-12 A 28-May-12 SR0.00 18-Oct-12 Painting Material segregation at Kuryk
LSC0078207
Insulation Material segregation at Kuryk 50% 130 29-Feb-12 A 23-May-12 SR0.00 07-Jul-12 Insulation Material segregation at Kuryk
LSC0078209
IBEEV Utility Bldg Material segregation at Kuryk 40% 77 18-Mar-12 A 28-Apr-12 SR0.00 02-Jun-12 IBEEV Utility Bldg Material segregation at Kuryk
LSC0078210
Bridges M12/IBEEV Material segregation at Kuryk 40% 65 18-Mar-12 A 30-Apr-12 SR0.00 21-May-12 Bridges M12/IBEEV Material segregation at Kuryk
LSC0078211
Bridges IBEEV/Pontoon Mat. segregation at Kuryk 40% 40 18-Mar-12 A 18-Apr-12 SR0.00 26-Apr-12 Bridges IBEEV/Pontoon Mat. segregation at Kuryk
Material delivery 496 18-Jun-11 A 12-Jun-12 SR0.00 25-Oct-12
LSC007840LSA Log.Sup.Area - Material delivery to D-Island 100% 0 18-Jun-11 A SR0.00 LSA Log.Sup.Area - Material delivery to D-Island
LSC0078402
Piping Material delivery to D-Island 70% 283 18-Jun-11 A 18-May-12 SR0.00 26-Mar-12 Piping Material delivery to D-Island

Actual Work Critical Remaining Work Page 1 of 3 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


ITT 2011-0146 Level 5 3A UPDATE 09-Aug-19 10:53

Activity ID Activity Name Activity % Original Start Finish Budgeted Total BL Project Finish 2011 2012 2013
Complete Duration Cost
F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J
LSC0078404
Mechanical Eq. Material delivery to D-Island 55% 102 08-Aug-11 A 08-May-12 SR0.00 17-Nov-11 Mechanical Eq. Material delivery to D-Island
LSC0078401
Structural Material delivery to D-Island 55% 193 25-Sep-11 A 03-May-12 SR0.00 04-Apr-12 Structural Material delivery to D-Island
LSC0078405
Arch/HVAC Material delivery to D-Island 100% 221 29-Jan-12 A 26-Feb-12 A SR0.00 05-Sep-12 Arch/HVAC Material delivery to D-Island
LSC0078406
Painting Material delivery to D-Island 70% 243 26-Feb-12 A 12-Jun-12 SR0.00 25-Oct-12 Painting Material delivery to D-Island
LSC0078409
IBEEV Utility Bldg Material delivery to D-Island 0% 50 25-Mar-12 13-May-12 SR0.00 13-May-12 IBEEV Utility Bldg Material delivery to D-Island
LSC0078407
Insulation Material delivery to D-Island 0% 74 26-Mar-12 07-Jun-12 SR0.00 07-Jun-12 Insulation Material delivery to D-Island
LSC0078410
Bridges M12/IBEEV Material delivery to D-Island 0% 40 06-Apr-12 15-May-12 SR0.00 15-May-12 Bridges M12/IBEEV Material delivery to D-Island
LSC0078411
Bridges IBEEV/Pontoon Mat. delivery to D-Island 0% 25 09-Apr-12 03-May-12 SR0.00 03-May-12 Bridges IBEEV/Pontoon Mat. delivery to D-Island
GENERAL AREA 9 13-Jul-12 21-Jul-12 SR0.00 21-Jul-12
LSS0005 S-LSA-S-3405- Rev 0 0% 9 13-Jul-12 21-Jul-12 SR0.00 21-Jul-12 S-LSA-S-3405- Rev 0
UTILITY ISLAND BA1H5 HOOK-UP 32 07-Aug-11 A 19-Feb-12 A SR0.00 07-Sep-11
LSP0140 S-LSA-P-0140- Rev 2 100% 3 07-Aug-11 A 14-Feb-12 A SR0.00 09-Aug-11 S-LSA-P-0140- Rev 2
LSP0155 S-LSA-P-0155- Rev 0 100% 5 08-Aug-11 A 03-Jan-12 A SR0.00 12-Aug-11 S-LSA-P-0155- Rev 0
LSP0202 S-LSA-P-0240- Rev 0 100% 5 09-Aug-11 A 17-Feb-12 A SR0.00 13-Aug-11 S-LSA-P-0240- Rev 0
LSP0136 S-LSA-P-0136- Rev 2 100% 3 14-Aug-11 A 25-Nov-11 A SR0.00 16-Aug-11 S-LSA-P-0136- Rev 2
LSP0203 S-LSA-P-0241- Rev 0 100% 5 29-Aug-11 A 19-Feb-12 A SR0.00 02-Sep-11 S-LSA-P-0241- Rev 0
LSP0134 S-LSA-P-0134- Rev 0 100% 5 03-Sep-11 A 20-Dec-11 A SR0.00 07-Sep-11 S-LSA-P-0134- Rev 0
UTILITY ISLAND BA1H6 HOOK-UP 20 23-Jul-11 A 27-Mar-12 SR0.00 11-Aug-11
LSP0157 S-LSA-P-0157- Rev 1 94.1% 20 23-Jul-11 A 27-Mar-12 SR0.00 11-Aug-11 S-LSA-P-0157- Rev 1
UTILITY ISLAND HOOK-UP PR18H1 307 17-Jul-11 A 18-May-12 SR0.00 18-May-12
UTILITY ISLAND HOOK-UP PR18H10 217 12-Jul-11 A 23-Feb-12 A SR0.00 13-Feb-12
UTILITY ISLAND HOOK-UP PR18H11 38 02-Jul-11 A 27-Mar-12 SR0.00 08-Aug-11
UTILITY ISLAND HOOK-UP PR18H12 31 06-Jul-11 A 29-Mar-12 SR0.00 05-Aug-11
UTILITY ISLAND HOOK-UP PR18H13 22 14-Jul-11 A 27-Mar-12 SR0.00 04-Aug-11
UTILITY ISLAND HOOK-UP PR18H2 233 04-Jul-11 A 26-Mar-12 SR0.00 21-Feb-12
UTILITY ISLAND HOOK-UP PR18H3 283 02-Jul-11 A 09-Apr-12 SR0.00 09-Apr-12
UTILITY ISLAND HOOK-UP PR18H5 34 13-Jul-11 A 29-Mar-12 SR0.00 15-Aug-11
UTILITY ISLAND HOOK-UP PR18H6 224 20-Jul-11 A 02-Apr-12 SR0.00 28-Feb-12
UTILITY ISLAND HOOK-UP PR18H7 153 05-Jul-11 A 07-Apr-12 SR0.00 04-Dec-11
UTILITY ISLAND HOOK-UP PR18H8 296 03-Jul-11 A 23-Apr-12 SR0.00 23-Apr-12
UTILITY ISLAND HOOK-UP PR18H9 27 04-Jul-11 A 25-Jan-12 A SR0.00 30-Jul-11
UTILITY ISLAND ACV HANGAR&B4-730-XY-200 171 15-Oct-11 A 02-Apr-12 SR0.00 02-Apr-12
UTILITY ISLAND IBEEV AREA 255 19-Nov-11 A 30-Jul-12 SR0.00 30-Jul-12
UTILITY ISLAND LSAH1 / Barge to PR18 236 23-Aug-11 A 14-Apr-12 SR0.00 14-Apr-12
UTILITY ISLAND 272 29-Jul-11 A 25-Apr-12 SR0.00 25-Apr-12
UTILITY ISLAND PIPE RACK 18.10 231 12-Aug-11 A 29-Mar-12 SR0.00 29-Mar-12
LSP0159 S-LSA-P-0159- Rev 0 93.7% 24 12-Aug-11 A 29-Mar-12 SR0.00 04-Sep-11 S-LSA-P-0159- Rev 0
LSP0200 S-LSA-P-0238- Rev 0 92.4% 8 15-Aug-11 A 27-Mar-12 SR0.00 22-Aug-11 S-LSA-P-0238- Rev 0
LSP0152 S-LSA-P-0152- Rev 1 100% 10 25-Aug-11 A 04-Feb-12 A SR0.00 03-Sep-11 S-LSA-P-0152- Rev 1
LSP0131 S-LSA-P-0131- Rev 1 100% 3 30-Aug-11 A 02-Jan-12 A SR0.00 01-Sep-11 S-LSA-P-0131- Rev 1
LSP0135 S-LSA-P-0135- Rev 1 100% 2 30-Aug-11 A 18-Dec-11 A SR0.00 31-Aug-11 S-LSA-P-0135- Rev 1
LSP0137 S-LSA-P-0137- Rev 0 100% 2 01-Sep-11 A 24-Nov-11 A SR0.00 02-Sep-11 S-LSA-P-0137- Rev 0
LSP0151 S-LSA-P-0151- Rev 0 100% 10 06-Sep-11 A 26-Dec-11 A SR0.00 15-Sep-11 S-LSA-P-0151- Rev 0
LSP0138 S-LSA-P-0138- Rev 1 91% 9 15-Sep-11 A 27-Mar-12 SR0.00 23-Sep-11 S-LSA-P-0138- Rev 1
LSP0201 S-LSA-P-0239- Rev 0 100% 2 16-Sep-11 A 11-Feb-12 A SR0.00 17-Sep-11 S-LSA-P-0239- Rev 0
LSP0153 S-LSA-P-0153- Rev 1 93.1% 9 19-Sep-11 A 26-Mar-12 SR0.00 27-Sep-11 S-LSA-P-0153- Rev 1
LSP0199 S-LSA-P-0237- Rev 0 93.3% 5 04-Oct-11 A 26-Mar-12 SR0.00 08-Oct-11 S-LSA-P-0237- Rev 0
LSP0130 S-LSA-P-0130- Rev 0 100% 3 07-Dec-11 A 04-Feb-12 A SR0.00 09-Dec-11 S-LSA-P-0130- Rev 0
LSP0141 S-LSA-P-0141- Rev 0 81.4% 8 11-Dec-11 A 27-Mar-12 SR0.00 18-Dec-11 S-LSA-P-0141- Rev 0
LSP0139 S-LSA-P-0139- Rev 0 100% 3 07-Jan-12 A 24-Mar-12 A SR0.00 09-Jan-12 S-LSA-P-0139- Rev 0
LSP0156 S-LSA-P-0156- Rev 1 77.9% 8 22-Mar-12 A 28-Mar-12 SR0.00 29-Mar-12 S-LSA-P-0156- Rev 1

Actual Work Critical Remaining Work Page 2 of 3 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


ITT 2011-0146 Level 5 3A UPDATE 09-Aug-19 10:53

Activity ID Activity Name Activity % Original Start Finish Budgeted Total BL Project Finish 2011 2012 2013
Complete Duration Cost
F M A M J Jul A S Oct N D J F M A M J Jul A S Oct N D J F M A M J
UTILITY ISLAND PIPE RACK 18.9 282 07-Aug-11 A 14-May-12 SR0.00 14-May-12 Completion of foundation by ENKA (Water Booster)
UTILITY ISLAND STORES&CONTAIN. TANK AREA 263 07-Aug-11 A 25-Apr-12 SR0.00 25-Apr-12
UTILITY ISLAND SEA WATER TRANSFER PUMP 263 31-Aug-11 A 19-May-12 SR0.00 19-May-12 Foundation Handover from ENKA
UTILITY ISLAND SLOP TANK AREA 225 15-Aug-11 A 30-Mar-12 SR0.00 26-Mar-12 Completion of foundation by ENKA (Slop Tank)
UTILITY ISLAND TRIM LINE 116 26-Jan-12 A 20-May-12 SR0.00 20-May-12
UTILITY ISLAND TREATED SANITARY WATER 320 03-Sep-11 A 18-Jul-12 SR0.00 18-Jul-12 Installation of Technical Water Tanks
No Sub Areas 293 02-Jul-11 A 14-Aug-12 SR0.00 26-Aug-12 LSA
Loose
Sanitary
Pedestal
Bridges
HookUp
Cable
IBEEV
Completion
Completion
Log.Supp
Logistic
Completion
Completion
Trays
Completion
Items
Pontoon
(2)
Str.
Piping
Water
Crane
Between
in
IBEEV
of
Supp
Completion
IBEEV
Hydrotest
Tanks
Area-PR
Piperacks
LER
WABAS
IBEEV
Hydrotest
IBEEV
Access
Hydrotest
Hydrotest
Hydrotest
Area-Supp.Struct.for
Area
Utility
&M12
Utility
and
HVAC
Utility
Utility
Stairs
Building
--LER
Series18(from
Series18(from18.9
Bldg
Paint,
Slop
WABAS
Crane,
IBEEV
-Hydrotest
Series
and
Pumps
ACV
Bldg
- Building
LSA
Bldg
-Building
-LSA
LSA
&&
IBEEV
TLube,
ank
Hanger
HVAC
&
Pontoon
Crane
LER
18
&Pontoon
HVAC
Building
WABAS
-Pontoon
Skid
LSA
Chemical
Building
Room
supp.&
18.0
&Bridge
Room
Area
PR
IBEEV
Workshop
Area
Building
to
to
Area
Series
18.10)
18.8)
A1
...Sto
LER 18
Train Bridge 1 293 04-May-11 A 27-May-12 SR0.00 26-Jun-12 TrainTrain
1Train
Train
Bridge
1 1Bridge
1Bdg
Bridge
- INfill
Bridge
- -Material
MRF
Deck
- A7
A1.1
A1.2
A1.3
A1.4
A3.1
A3.2
Material
4-6
Engineer
Segregat/packing
Hook
delivery
up
AFC
Piping
toby
D-Island
Company
Spools
at Hook
Train
Kurykin1up
Train
Bridge
Structures
1 -Bridges
Bridge
in Train
A1
Area
A31 Bridges
A7 MC Area

Actual Work Critical Remaining Work Page 3 of 3 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation