Professional Documents
Culture Documents
INPUTS
INPUTS
No LEVEL DUR RELATIONSHIP ACT CODE RESOURCES UPDATE ( Data Date ran December 1 )
PREDECESSOR BOQ EQP MANPOWER ( Man-Day ) Activity Actual Actual
budgeted Nos MAN Total Man Day % Complete Start Date Finish Date
CONSTRUCTION units
BELOW GRADE
STRUCTURAL
1 Excavation 10 CIVIL 20,000 4 3 30 100% 1-Sep-19 8-Sep-19
18 GF Slab/Beam-Scafolding Erection
5 FS ( 17 ) CIVIL 50,000 12 60
ELECTRICAL
29 Lighting System 30 FS ( 21 ) ; FF ( 48 )LAG -7 ELECT 90,000 7 210
MECHANICAL
33 Hvac 45 SS (45) LAG +7 MECH 90,000 7 315
ARCHITECTURAL
45 Blockworks 20 FS ( 21 ) ARC 70,000 7 140
HAND OVER
49 Demobilization 7 FS(48) FS(29)
50 Project Completion 0 FS 49