BUILDING

No LEVEL DUR RELATIONSHIP ACT CODE RESOURCES UPDATE ( Data Date ran December 1 )
PREDECESSOR BOQ EQP MANPOWER ( Man-Day ) Activity Actual Actual
budgeted Nos MAN Total Man Day % Complete Start Date Finish Date

CONSTRUCTION units

BELOW GRADE
STRUCTURAL
1 Excavation 10 CIVIL 20,000 4 3 30 100% 1-Sep-19 8-Sep-19

2 Lean Concrete 7 FS ( 1 ) CIVIL 14,000 5 35 100% 8-Sep-19 12-Sep-19

3 Foundation- Steel Fixing 18 FS ( 2 ) CIVIL 85,000 7 126 100% 12-Sep-19 2-Oct-19

4 Foundation- Forming 18 SS ( 3 )LAG +7 CIVIL 14,000 7 126 100% 19-Sep-19 7-Oct-19

5 Foundation- Pouring 7 FS ( 3 ) ; FF ( 4 ) CIVIL 100,000 1 7 49 100% 23-Sep-19 7-Oct-19

6 Columnneck -Steel Fixing 10 FS ( 5 ) CIVIL 30,000 7 70 100% 9-Oct-19 16-Oct-19

7 Column neck- Forming 10 SS ( 6 ) LAG +2 CIVIL 7,000 7 70 100% 14-Oct-19 20-Oct-19

8 Columnneck- Pouring 4 FS ( 7 ) LAG -2 CIVIL 50,000 7 28 100% 20-Oct-19 25-Oct-19

9 Tiebeam- Steel Fixing 10 FS ( 8 ) CIVIL 45,000 1 7 70 100% 27-Oct-19 2-Nov-19

10 Tiebeam-Forming 10 SS ( 9 )LAG +4 CIVIL 7,000 7 70 100% 30-Oct-19 4-Nov-19

11 Tiebeam-Pouring 4 FS ( 9 ); FS ( 10 ) CIVIL 40,000 7 28 100% 4-Nov-19 8-Nov-19

12 Gradeslab- Steel Fixing 21 FS ( 11 ) CIVIL 250,000 10 210 70% 8-Nov-19

13 Gradeslab-Forming 21 SS ( 12 ) LAG +7 CIVIL 20,000 10 210 70% 10-Nov-19

14 Grade Slab-Pouring 10 FF ( 13 ) LAG 4 CIVIL 300,000 2 10 100 70% 12-Nov-19


PROJECT HAND OVER
STRUCTURAL
15 GF Column -Steel Fixing 21 FS ( 14 ) CIVIL 80,000 12 252 30% 19-Nov-19

16 GF Column - Forming 21 SS ( 15 ) LAG +4 CIVIL 10,000 12 252 20% 19-Nov-19

17 GF Column- Pouring 14 FF ( 16 ) LAG +4 CIVIL 120,000 2 12 168 10% 21-Nov-19

18 GF Slab/Beam-Scafolding Erection
5 FS ( 17 ) CIVIL 50,000 12 60

19 GF Slab/Beam-Steel Fixing 21 FS ( 18 ) CIVIL 120,000 12 252

20 GF Slab/Beam-Forming 21 SS ( 19) LAG +4 CIVIL 25,000 12 252

21 GF Slab/Beam-Pouring 14 FF ( 20 ) LAG 3 CIVIL 340,000 12 168

ELECTRICAL
29 Lighting System 30 FS ( 21 ) ; FF ( 48 )LAG -7 ELECT 90,000 7 210

30 Power System 30 SS ( 46 ) LOG 14 ELECT 80,000 7 210

31 Firealarm 30 FS ( 21 ) LAG +7 ; FF ( 47 )LAG +14 ELECT 70,000 7 210

32 Low Voltage System 30 FS ( 46 ) ELECT 60,000 7 210

MECHANICAL
33 Hvac 45 SS (45) LAG +7 MECH 90,000 7 315

34 Plumbing 45 FS ( 45 ) MECH 80,000 7 315

35 Sanitary Fixtures 21 SS ( 34 ) LAG +5; FF48) -10 MECH 70,000 7 147

36 FireProtection 30 FS ( 34 ) LAG MECH 60,000 7 210

ARCHITECTURAL
45 Blockworks 20 FS ( 21 ) ARC 70,000 7 140

46 Plastering 14 SS ( 45 ) LAG +14 ARC 40,000 7 98

47 Ceiling 30 FS ( 46 ) ARC 120,000 7 210

48 Paint 30 FS ( 47 ) ARC 120,000 7 210

HAND OVER
49 Demobilization 7 FS(48) FS(29)
50 Project Completion 0 FS 49