INCIDENT REPORT
FILLED BY: Faraz Aslam (TAL HSE Supervisor) DATE: 25th October 2018 HOUR: 14:25 hrs
(Note: This report must be completed and signed by sub-contractor within 24 hours to KT. In any case, a preliminary
incident report must be delivered to KT Construction Manager as soon as possible, immediately after the incident)
DESCRIPTION:
On 25th October 2018 at 14:30 got an information from Mr.Amanullah Ghazi (QC piping
inspector) of technimont Arabia about incident of RTR 2inch pipe burst on 14.8 bar pressure
near joint # 9 at north side of sru sewer line near structure F area during hydrotest activity
which was continues from 12:30 by hydrotest forman named Ramazan Kural without obtaining
work permit. No personnel injury reported.
IMMEDIATE ADOPTED MEASURES:
CORRECTIVE ACTION:
Given warning letter to activity Forman regarding to start the work without obtaining work
permit.
ACTION ADDRESSEE:
Verification KT
Expected Completion Date Actual Completion Date
(Date and Signature)
25.10.2018 25.10.2018