CRITICAL

ID Task Name Duration Start Finish


January 11 March 21 June 1 August 11
3/18 4/22 5/27 7/1 8/5 9/9 10/14
1 DIVISI 1. UMUM 172 daysMon 4/9/18 Fri 9/28/18 0%
2 Mobilisasi 30 days Mon 4/9/18 Fri 9/28/18 0%
3 Manajemen dan Keselamatan Lalu Lintas 172 days Mon 4/9/18 Fri 9/28/18 0%
4
5 DIVISI 2. DRAINASE 15 days Fri 5/18/18 Sat 6/2/18 0%
6 Galian Untuk Selokan Drainase dan Saluran Air
7 days Fri 5/18/18 Fri 5/25/18 0%
7 Pasangan Batu Dengan Mortar 7 days Sat 5/26/18 Sat 6/2/18 0%
8
9 DIVISI 3. PEKERJAAN TANAH 31 days Tue 4/24/18 Fri 5/25/18 0%
10 Galian Biasa 7 days Tue 4/24/18 Tue 5/1/18 0%
11 Timbunan Biasa dari Galian 7 days Wed 5/2/18 Wed 5/9/18 0%
12 Penyiapan Badan Jalan 15 days Thu 5/10/18 Fri 5/25/18 0%
13
14 DIVISI 5. PERKERASAN BERBUTIR 114 daysSat 5/26/18 Mon 9/17/18 0%
15 Lapis Pondasi Agregat Kelas A 30 days Mon 6/11/18 Wed 7/11/18 0%
16 Lapis Pondasi Agregat Kelas B 15 days Sat 5/26/18 Sun 6/10/18 0%
17 Perkerasan Beton Semen 45 days Fri 8/3/18 Mon 9/17/18 0%
18 Lapis Pondasi bawah Beton Kurus 21 days Thu 7/12/18 Thu 8/2/18 0%

Critical Finish-only Manual Summary


Critical Split Duration-only Project Summary
Critical Progress Baseline External Tasks
Task Baseline Split External Milestone
Split Baseline Milestone Inactive Task
Task Progress Milestone Inactive Milestone
Manual Task Summary Progress Inactive Summary
Start-only Summary Deadline

HASRIYADI
NIM. 2015.21.058