Professional Documents
Culture Documents
Power Systems Engineering Research Center (PS) : Mission
Power Systems Engineering Research Center (PS) : Mission
PSERC
1
Mission PSERC
1
PSERC Universities
PSERC
Research Program
PSERC
2
Electric Service Reliability
Fernando L. Alvarado
Professor, University of Wisconsin
Invited Presentation
43rd NARUC Program
East Lansing, Michigan, August 15, 2001
Outline PSERC
3
Traditional reliability concepts
• End-user perspective:
• Any involuntary loss of power is a
reliability event
• Bulk system perspective:
• Any system condition leading to loss of
load is a reliability event
• Only those leading to widespread or extended
outages are considered true reliability events
• The outage of a component is not an event
4
Reliability Time Frames PSERC
• A “planning” concept
• Based on random outage of generators,
what is the probability that the available
generators will be insufficient to meet
the anticipated load
• Measured in frequency of expected outages
• EDNS extends the concept to
consider energy “not served”
10
5
The n-1 security criterion PSERC
12
6
Why do systems fail? PSERC
• Cascading overloads
• A simple line or transformer outage is
not enough except in radial situations
• Most distribution systems are radial
• Loss of system stability
• Transient or dynamic
• Voltage collapse
• Insufficiency of generation
13
Reserves PSERC
14
7
What is the ACE? PSERC
16
8
Reserve margins PSERC
17
9
Temporal classification PSERC
• Spinning reserves
• Fast-responding, usually instantaneously
• Supplemental reserves
• You can bring resources on-line quickly
• Backup reserves
• They can be brought on line after some
time
19
10
What is reliability anyway? PSERC
21
Economics 101
PSERC
Demand function
Price
(value of electricity
to customers)
Consumer
surplus Price
Quantity
11
Economics 101
PSERC
Production function
Price (cost of electricity
to producers)
Price
Producer
surplus
Equilibrium
Total producer
surplus (area)
Quantity
Economics 102
PSERC
Total consumer
Price
surplus (area)
Price
Equilibrium
Total producer
surplus (area)
Quantity
12
Some realities PSERC
25
A market problem
PSERC
Price
Price
No Equilibrium?
Quantity
13
A market failure
PSERC
Price
Inelastic
demand
No Equilibrium
Quantity
28
14
Assumptions PSERC
29
Security Margin
Price
Demand (inelastic)
Maximum
available
power
Available supply
Quantity (power)
Clearing
price
15
Deterministic Demand and Supply, high demand case
Clearing
price
Price
Demand (inelastic)
Maximum
available
power
Available supply
Quantity (power)
No intersection
16
The effect of demand elasticity
Interruptible demand
17
Probabilistic Demand, high demand case
Generator 2
Generator 3
Generator 4
18
The effect of a generator outage
Old
Outaged supply
generator limit
New
supply
limit
Probability p1
n-1 secure
insecure
19
Generator 1A
Generator 2A
System A
System A
n-1 secure
Low price
Secure
Low price
Generator 3A
Generator 4A
Generator 5A
Generator 6A
Generator 1B
Generator 2B
System B
System B
n-1 secure
High price
n-1 insecure
High price
Generator 3B
Generator 4B
Generator 5B
20
System B
Flow
System A
Low price
Low price n-1 secure
n-1 secure
Low price
n-1 secure
21
Situation with line transmission limits
Max
flow
System B
Flow
System A
Low price
Low price n-1 insecure
n-1 secure
Outaged
generator Normal conditions
Max
Unable flow
to clear
22
Reality PSERC
45
Equilibrium
point
Equilibrium Price
region
Congestion
level Surplus
Total producer
net loss
surplus (area)
Quantity
23
Who gets what
PSERC
Producer
Price surplus
loss
Producer
surplus Price
gain
Congestion
level
Quantity
Price
Congestion
Consumer level
surplus gain
Quantity
24
The incentive to congest
Gain: ∆p*C PSERC
Producer Loss: ∆C*p
surplus
Price gain
Producer
surplus Price
loss p
Congestion
C level
Quantity
Price
p
Equilibrium when:
∆p*C = ∆C*p, or
C
∆p/ ∆C=p/C
Quantity
25
The effect of congestion
PSERC
52
26
Features of the example PSERC
53
Observations PSERC
27
Reliability and price spikes*PSERC
$/MWh PJM daily average on-peak spot price and max load MW
800.00
Price 78000
600.00 Maxload
70000
400.00
62000
200.00
54000
0.00
46000
-200.00
38000
-400.00
-600.00 30000
-800.00 22000
4/97 6/97 8/97 10/97 12/97 2/98 4/98 6/98 8/98 10/98 12/98 2/99 4/99 6/99 8/99 10/99 12/99 2/00 4/00
date
28
Assorted PJM offer curves
PJM Offer Curves at 5pm from April to August (last Tuesday)
1200 Offer Price April (4/27/99) : $29.4/MWh 28.2GW/h
1000
800
600
400
200
0
0 10 20 30 40 50 60 70
29
Observations PSERC
59
Market Power?
30
Market Power: Assumptions
• There are exactly two technologies
• Each technology has a fixed marginal price
• ∞ availability of the expensive technology
• Limited availability of the cheap technology
• Cheap technology has fixed costs (investments) to recover
• Demand is inelastic
• All suppliers but a schedule all their cheap power
• a owns P MW in n≥1 equal-sized generators
• Supplier a can “withhold” one or more generators
• Bidding above marginal cost is not allowed, withholding is
Supplier a generator 1
Other suppliers
31
Red generator decides to withhold one generator
Clearing
price
blue supplier
Surplus for
red supplier
Surplus for
Withheld
generator
Clearing
Now it is not possible for red
price
supplier to withhold and gain
32
If demand is uncertain Probability p that
withholding will
result in surplus
π2
Price
P1
price π1
Quantity (power)
66
33
Effect of “granularity”
Surplus is P*(π2-π1) for
demand above this level
34
Effect of “granularity”
Surplus
With n=1, there is no surplus
Demand level
35
Effect of number of suppliers on supply curve
Price
p lier
ers
u p
es
s
rs
On
lier
10 suppli
lie
pp
u pp
su
3s
2
Demand
Demand
36
The effect of demand uncertainty on investment recovery
Price
Demand
37
Investment recovery without market power (∞ suppliers)
250
95%
100
90%
50
80%
0
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2
60%
Even for high
Investment recovery (thousands per MW-year)
180 70%
80%
160
90%
95%
demand levels, some
demand variance
140
is essential for
120 cost recovery
100
80
60
40
20
0
0 2 4 6 8 10 12 14 16 18 20
Demand Variance (percent)
38
15 suppliers, demand level as a parameter
250
50
0
0 2 4 6 8 10 12 14 16 18 20
Demand Variance (percent)
250
200
For high demand levels
demand variance can become
irrelevant
150
60%
70%
80%
100 90%
95%
50
0
0 2 4 6 8 10 12 14 16 18 20
Demand Variance (percent)
39
6 suppliers, demand level as a parameter
400
300
250
200
60%
100
investments
50
0
0 2 4 6 8 10 12 14 16 18 20
Demand Variance (percent)
400
350
300
100
50
0
0 2 4 6 8 10 12 14 16 18 20
Demand Variance (percent)
40
3 suppliers, demand level as a parameter
450
350
60%
300 70%
80%
90%
250 95%
200
With three or less suppliers, it becomes feasible
150 at high variances to recover investments by
100
withholding at low demand
50
0
0 2 4 6 8 10 12 14 16 18 20
Demand Variance (percent)
45 10 suppliers
6 suppliers
4 suppliers
40 3 suppliers
35
30
25
20
At low demand and low
variance it is impossible
15
to recover investments
10
0
0 2 4 6 8 10 12 14 16 18 20
Demand Variance (percent)
41
Dem and lev e l 70% , num ber of suppliers as a param e ter
120
∞ s upplie rs
15 s upplie rs
80
60
40
At higher demand with 3 suppliers
it is possible to recover
20 costs at low variance
0
0 2 4 6 8 10 12 14 16 18 20
De m and Variance (pe rce nt)
350
300
50
0
0 2 4 6 8 10 12 14 16 18 20
De m and Variance (pe rce nt)
42
Dem and lev e l 95% , num ber of suppliers as a param e ter
450
350
300
250
200
150
100
∞ s upplie rs
Only in the case 15 s upplie rs
10 s upplie rs
50 of infinite suppliers is it 6 s upplie rs
4 s upplie rs
0
impossible to recover costs 3 s upplie rs
0 2 4 6 8 10 12 14 16 18 20
De m and Variance (pe rce nt)
43
Final remarks PSERC
Reliability
Reserves
Price spikes
44