Professional Documents
Culture Documents
HGJGJGHCJC
HGJGJGHCJC
Schedule/ Target M1 M2
Site Activity Total
Start Finish 1 2 3 4 1 2 3
STRINGING
PRE-COMM 33 KV Cable
24
90
May June
30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14
0 0 0 0 0 0 0 3 2 2 2 1 0
0 0 0 0 0 0 0 0 4 4 4 4 0
0 0 0 0 0 0 0 0 0 0 0 0 7
M2 M3 M4 M5 M6 M7
4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2
June
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
31.000/55 886
886/2= 443
31000
250 124
250 MV-TIC
1 ke 5 1 0 pole
500 seminggu
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
Agustus
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Total Progress
29 30 31 Progress Percentage
21 87.50%
24 100.00%
17 70.83%
42 46.67%
76.25%
#REF!
Schedule/ Target May
Site Activity Total
Start Finish 23 24 25 26 27 28 29 30 31 1 2
Excavation 24 3 3 0 0 0 0 0 0 0 0 0
Pole delivery 23-May-18 31-Jul-18 24 4 0 0 0 0 0 0 0 0 0
Sengkol
Pole erection 24 0 0 0 0 0 0 0 0 0 0 0
Accessories 14-Jul-18 15-Aug-18 90
69
Schedule/ Target M1 M2 M3 M4
Site Activity Total
Start Finish 1 2 3 4 1 2 3 4 1 2 3 4 1 2
BATU BOR POLE FOUNDATION
FT 1-40
FT 41-80
FT 81-120
FT 121-160
FT 161-200
FT 201-240
FT 241-280
FT 281-310
FT 311-350
FT 351-390
FT 391-430
FT 431-470
FT 471-510
FT 511-550
FT 551-600
FT 601-640
FT 641-680
FT 681-720
FT 721-760
FT 761-800
FT 801-850
FT 851-860
STRINGING FULL
FT 1-40
FT 41-80
FT 81-120
FT 121-160
FT 161-200
FT 201-240
FT 241-280
FT 281-310
FT 311-350
FT 351-390
FT 391-430
FT 431-470
FT 471-510
FT 511-550
FT 551-600
FT 601-640
FT 641-680
FT 681-720
FT 721-760
FT 761-800
FT 801-850
FT 851-860
PRE-COMM Transmission Line 33 KV Cable
24
90
June
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7
0 0 0 3 2 2 2 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 4 4 4 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 7 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
886/2= 443
750 21.4286
Agu
26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
Agustus Total
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Progress
21
24
17
42
Progress
Percentage
87.50%
100.00%
70.83%
46.67%
76.25%
#REF!