Technique Execution Methods AND Constrution Work Progress: Project: Hanoi Sky Lake Resort Golf Club House

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 51

CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG

Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

TECHNIQUE EXECUTION METHODS


AND
CONSTRUTION WORK PROGRESS

Project: Hanoi sky lake resort golf club


house
Location: Chuong My town- Ha Tay province

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

PART A
TECHNIQUE AND PROGRESS CONTENT
A.I:EXECUTION METHOD EXPLANATION
A.I.1: INTRODUCTION
Project: Hanoi sky lake resort golf club house
Location: Chuong My town- Ha Tay province
1) Content of bidding package
Construction work is built on the area of golf court in Chuong My
town Ha Tay province
Work area: Building all the club building
2) Scale
 Architecture solution
- Construction work is 3 floor building and 1 pit floor, concreted
roofing with art tile
 Structure solution
- Construction work is designed body structure solution using
column, beam, and 250# reinforced concrete floor
 Execution method:
- Construction work is 3 floor building and 1 pit floor, built and
belong to central area, thus, execution method must guarantee
following factors:

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- Execution method must meet standards about noise, safety,


cleaning and next construction works, ensure not affect to
surrounding
- Transportation means must be cleaned, not dirty tires, no
garbage on the street
A.I.2: PREPARATION WORK
Contractor confirms preparation with large decision to
quality of construction. After searching for drawing contractor
sees that this work requires high quality art, these are some
preparation of contractor before execution
1) Document
After searching for contractor’s drawing which manage quality work, setting up legal
document management is through out from company to construction site such as: employee
document includes labor contract, labor safety commitment; material equipment management
file includes tested material quality results, checking equipment; completion certificate. In
Contractor office, there a team of skillful engineer who sets up solution method execution
progress for each work in details. Pursuant to execution progress file, contractor has planed to
prepare manpower, materials, and construction equipments. Document is proceeded by
contractor and finished when starting execution.
2. Human Resource. Contractor will appoint a vice director who controls execution
directly.
_ Technology department of contractor has an experienced
team of staff who regularly follows up quality of construction
work
_ Manpower: Contractor has been executing many project of
Taiwan, China, Korea and Japan, so contractor has a skillful and
responsible team in construction work. However, contractor
still confirm quality of human resource to the success of
TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88
Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

contractor. Hence, staffs are still trained to enhance ability and


especially, 100% of workers are must work with good health
skills and safety.
_ Human resource: Contractor arranges human resource
depend on work, especially main work like concrete building,
plaster will be guaranteed for production line. Professional
labor team divided into plaster, building, plaster, steel,
concrete, electricity, water supply, equipment installation is
combined tightly with each other in execution to ensure
progress.
3. Material, equipment
_ Material and supply: Investor must test material before
using, quality of main material must be tested. Material must
be estimated to be suitable for progress and construction plan
in each period. In this work contractor focuses on concerning
about things for high quality and artic construction work.
_ Equipment: Contractor has plan to use equipment
reasonably, depends on work amount and progress, to supply
on execution time, right standard
4. Plan
Plan preparation affects to execution progress and
construction work quality significantly. To arrange reasonable
plan, contractor will proceed survey and search for plane,
confirming plan of execution, set up execution progress in
detail for each category to define office location, store,

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

material ground, mixing machine area and entrance during


execution time
Contractor proceeds preparation such as locating
construction, calculating material transport road, transport
land, necessary area for mixing concrete ground, small
structure, installation, mixing mortar, brick ground and
formworks, steel ground and ensure arranged reasonable plan.
After calculating for necessary, contractor proceed to protect
from dust for environment
 Main requirement
After calculating above floor limiting fallen materials as well
as dust.
After executing floors, Contractor will proceed to spread

A.I.3-ARRANGE PLAN
Plan must be installed electricity, water supply, control
office, tent, depot, other tents are arranged to be convenient
for execution
Construction concrete is fresh concrete and use concrete
pump
1. Requirements when arranging execution plan
When arranging the execution plane, contractor will
calculate to ensure following factors:

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- Offices and depots: Ensure enough area, satisfy functions of


office.
- Store floor is embanked high and chocked for damp-proof to
cement
- Inflammable materials are put separately and packet in
buckets
- Fire extinguishers in offices and depots
- Security office: Near the entrance and observable to
everywhere in the construction site. Fixed telephone, fire
extinguishers, security equipments in security office
- Reinforcement executing ground: Tent floor is built high and
have satchels
- Formwork assembling ground: Contractor uses most of
corrugated ion formwork. The system to support formwork
is log of wood and steel log. Contractor is responsible for
maintaining formwork.
Contractor also uses both steel and wooden formwork.
Thus, processed formwork must be far away from depots
2. Water supply
Contractor must contact with investor and local government
to have water for execution
Water supply system is tight in the ground and far from road
3. Sewage system
Contractor installs a temporary sewage system, connect
water from many areas and pump water to gas hole.
4. Electricity

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Contractor supplies electricity and private wire to electricity


box. Moreover, contractor prepares generator to guarantee
electricity. Using rubber covered cables with 3 phases or 4
cores. There is electricity clock to measure electricity numbers
There are 2 main power sources:
- For equipments and machines
- For other activities
Contractor installs tension pole across roads, wire is larger
than or equal 4 m
5. Lighting system
Contractor installs headlights around the work, Light system
to protect and serve for execution at night
Moreover, contractor supplies another dynamo.40KVA
ensures lighting of work and serve machines in case of power
cut or executing process at night
Arrange plan, contractor guarantee the standard of work,
environment, security and safety.
A.I.4. EXECUTION METHOD
GENERAL REQUIREMENT
Guarantee execution steps as same as design
Guarantee safety for people, machines and work
Guarantee surrounding environment
Avoid making noise
Clean transport means when leaving the work
Contractor covers the boot of bike when going out the wor
 Execution method

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Base on the drawing, contractor gives the method


presented following
 Survey method
Contractor surveys when beginning executing work. Survey
engineers help experiences and take part in many works
In order to set up, maintain figures in work correctly, survey
team receives a border line and investor’s standard
(receivable certificate). Then, team is responsible for
defending border line and fix.
Base on border line high standard to main pivot, set up
pitch system to confirm the pivot. Setting up pitch by: each
pitch is confirmed by center point. This point is set up to use
easily and exactly, not affect to execution. In execution,
contractor bases on pitch and height to execute according to
requirement of investor and drawing
Survey is always checked and noted in detail. Figures are
announced to investor
A.I.4.1 FOUNDATION EXCUTION METHOD
1)Excavation method
Due to large amount of land, we use both method of
machine and manuals. Excavating by machine is used
regularly, using manuals to fix foundation hole. Excavating
and fixing foundation hole follow to designed depth.
Around hole, drainage ditches and arrange pump to
absorb water continuously in case of rain.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Excavation process is suitable for restriction to


guarantee the stability of roof. In case of less stable place, we
process to build stake.
Dimension, form, height of foundation hole must be
suitable for design. Taking over before going on next work.
* Risk of excavation
Digging in the heavy rain causes soil fall. After rain, filling
in hole, change 15cm in hole in comparison to designed level.
After fixing each ground layer, replacing foundation by
concrete bricks.
There is “underground rock” or other, replace by mixing
sand and crushed rock.
Filling up foundation hole
After executing foundation concrete, filling foundation hole.
* Technical requirement in filling land
When covering sand, guarantee that foundation sand has
moisture in restricted area. Dry sand needs to be watered;
reduce moisture for much humid sand.
Cover sand and distribute into each layer and stamp.
*Technical method
Use compactor and worker.
Stamp layer to another tightly
Fill sand by line
2. Foundation work
After finishing foundation, place and fix it.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Pour the lean concrete layer for foundation. Use survey


machine to confirm centre and mark on the surface of middle
layer concrete. Proceeding steel installation when the concrete
commit to the hardness. Use block for small concrete with the
same depth as concrete layer for steel. Label of this is equal to
one of foundation concrete.
After reinforcement assembling, installing casing used iron
formwork. Foundation formwork commit to designed type.
Foundation casing is kept by steel column which is wrapped
and wooden column. It is important for contractor to
guarantee stability of formwork.
Checking steel formwork and cleaning before pouring
concrete.
Pour foundation concrete: Replace mixed concrete into
concrete pump. Material of concrete commits to clean
standard.
Use stamping concrete d=45-60mm to stamp
concrete. The concrete is poured into each layer and damped
following to technique. Surface of foundation is smooth by
hawk, guarantee flat degree and designed level.
Covering foundation is only proceeded after maintaining
concrete following technique finishing, underground work and
accepted by investor.
A.I.4.2: CONCRETE EXECUTION METHODS FOR BODY PART
RAW MASONARY
1. Execution of wall, concrete, steel, pit floor

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Base on structure design contractor estimate, design using


casing and recycling during work.
Reinforcement assembling
Tie block concrete with the same thickness as protected
concrete and grade as one of structure concrete.
Preliminary acceptance for reinforcement
Drill concrete floor to hammer steel to fix wall thickness
Formwork assembling in one side only
Pour concrete for wall
2. Reinforcement assembling
Before install steel for the wall, contractor uses survey
machine to define centre of pivots on the concrete floor
Base on pointed centre on the concrete, check the
right position of steel, tight steel to other steel in case of right
position
* Wall reinforcement procedure
- Drill to create roughness of wall foot concrete and clean
- Adjust straight ahead steel bar, ensure distance between
steel bar
- Connect straight steel bars with another
- Install cross-bar
- Adjust steel bars to guarantee size and distance between
bar
- Tie steel and concrete block into one side, the number of
block mass ensure to make steel stable and unbroken.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- After finishing work, investor checks steel. Contractor only


proceeds to combine formwork if it reaches requirement.
a. Wall formwork combination
Contractor confirms: Formwork combination must make
wall straight, flat, smooth. Thus, formwork must be hermetic,
stable. Corrugated iron formworks have the same size as
structure size.
In case of missing corrugated iron formworks, contractor
uses wooden formwork. Contractor cleans and paints a petrol
layer before using to untie easily.
* Formwork assembling procedure
Base on defined centre of pivot. Line 2 lines to wall edge.
Drilled hole D12, distance 1.5m per 1 hole.
Hammer steel pieces D12 following to line in order to
become bolt inside formwork
Combine one side corrugated iron form work.
Install steel boxes into 3 lines:
Line 1: 20cm from bottom of concrete wall
Line 2: 60cm from Line 1
Line 3: 15cm from wall surface
Boxes control thickness of concrete wall. If thickness of wall
always commit to standard, casing will not be deformed.
After installing and fixing boxes bar, conducting to tie
concrete block into other steel wall side. Then, clean wall foot
and combine casing.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

After combining, casings are propped up by length control


machine. Contractor uses D12 cable with control machine to
control and to pull casing inverse to propulsive force of pulled bar
in order to balance pressing force on casing, guarantee stability
of casing and control wall casing to the right or the left easily.
After combining casing, contractor invites investor to check.
Next, contractor prepares to pour concrete.
b. Pit floor concrete wall pouring.
 Method
By concrete pump
Concrete is poured on the partition with the thickness of
30cm with many times to guarantee solid and adhesive
degree.
 Pit floor wall concrete stamping method
Before pouring concrete wall, contractor uses pump to
water wall foot brick and pour a cement layer with rate ½ and
mix additive for damp-proof. After pouring mortar, pouring
concrete immediately.
Wall concrete has 14cm- landslide, distance between wall
steel is large. Thus, contractor uses stamping machine with
diameter D50, radius is equal as 1/3 as length of power hammer.
When covering next layer on previous layer, power hammer is
staked out with the depth of more than 5cm.
 Concrete pour requirements
Avoid changing position of steel, formwork and guarantee
the depth of protected concrete layer.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Pouring concrete continuously in oder to avoid separately of


concrete until finishing any structure following to design.
The height of falling concrete is smaller than 1.5m to avoid
classifying. If it is higher than 1.5m, pour concrete by sloping
conduit or movable pipe. Material conduit must be smooth and
hermetic. Material conduit width is as 3.5 times as the largest
diameter of reinforcement. Slope of conduit is guaranteed for
concrete not stuck.
 Pouring concrete note:
Formwork, scaffold and reinforcement are tested tightly in
case of trouble.
Concrete is stamped by stamping machine. All position is
stamped in the right way.
Canvas is available to cover concrete when rain. Concrete is
not poured because of problems, wait until it reaches at
25kg/cm2. Before pouring, roughness flat is handled, pour solid
cement, mix additive for damp-proof.
Thickness of concrete layer bases on concrete supply,
transport distance, type of stamping power, characteristic of
structure and it doesn’t exceed standards:
Straight stamping: Length of each layer <= 1.25
length of stamping
Across stamping: Length of each layer is 12- 20cm.
Following and noting contents in periods of pouring
concrete:
Beginning and ending time

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Concrete grade, depression


Concrete amount in each period
Check concrete sample
Temperature
Concrete temperature
Concrete maintenance: Useful for developing speed of
concrete according to design requirement, method, and concrete
maintenance procedure TCVN 5592-1991. “Heavy concrete
requires natural warm maintenance”. Moisture maintenance
procedure divided into 2 periods: first maintenance and following
maintenance. 2 periods is continuous.
+ First maintenance: cover concrete surface by humid
material to keep water for concrete.
+ Following maintenance: proceed after following
maintenance until stopping. Watering for concrete surface
regularly, times per day depend on temperature, weather to
keep it humid. Maintenance times last from 5 to 6 days.
1) Reinforcement concrete column execution method
a. Casing, reinforcement
Reinforcement column belong to system that burden all
loading capacity of work, thus, contractor concern about
seriously
Base on size of each structure, contractor uses casing of
contractor as formwork column.
To executing column, contractor gives execution order:
Use Theologize to place centre of pivot

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Confirm size of column circumference


Drill and hammer D12 onto edge
Install reinforcement concrete column
Tie steel concrete block
Acceptance for column reinforcement
Combine 3-size formwork of column
Adjust, fix 3-size formwork box on the right position
Adjust straight reinforcement column, block to guarantee
protected layer for reinforcement around column
Clean pivot foot
Combine other size of formwork
Adjust; prop up formwork in the centre of pivot and straight
Acceptance for column formwork
Method of propping up and adjusting formwork column
When pouring the floor concrete, contractor calculate to
place anchor on the floor surface to be point to hook cable.
To control column, contractor estimates to prop up
First line is next to floor surface
Second line is 1.4m from floor
Third line is 50 cm from column
(Base on specific height of each column, contractor adjusts
distance of 2 columns)
To balance force and pull in or pull out easily, contractor
uses column to pull by steel and cable with diameter 8-12mm.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

To check vertical of formwork column, contractor equips


plumb bob for each team, combine with survey team to check
straight level of formwork.
The column with the height of more than 1.5m, contractor
arranges concrete door across formwork column so that height of
concrete <= 1.5m. Concrete door is next to the largest. In
column foot, contractor arranges 1 toilet door to clean that.
Contractor install waiting steel to combine wall
After taking quality of formwork column, contractor invites
investor to check and conduct to pour concrete.
Contractor swept a petrol layer to prevent formwork to
absorb cement to untie casing easily.
b. Concrete column execution
Contractor waters column foot then close cleaning door in
column foot.
Avoid separating concrete; contractor pours a yellow sand
layer mortar with rate 1/2 in foot column before pouring
concrete.
With high concrete column, contractor pours concrete into
many layers. Thickness of layer <= 40cm. After finishing,
contractor continues to pours other. When stamping, power-
hammer is staked out into previous layer to guarantee
separation.
Contractor knocks surrounding casing so that concrete
surface is smooth besides stamping.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

To control the height of concrete column, contractor uses


theodolite to confirm stamping bottom. Stamping bottom is used
to pour concrete column. Contractor marks red paint line on the
surface of formwork column as control landmark for height.
Concrete column requirements
After untying casing, concrete surface must be smooth
solid.
Untied column has square sharp, angles aren’t changeable.
Right position for column
Column must be straight
c. Formwork combination notices
If there is any leaky hole, it needs maintaining and
preparing casing.
2. Reinforcement , casing and concrete floor beam
Execution order this procedure affects to progress and
quality of work. Contractor gives casing execution procedure so
that execution procedure is circulated:
Use survey machine to check beam
Install beam untie system
Adjust top column to beam bottom
Install satchel
Cover corrugated-iron formwork as beam formwork
Use survey machine to check or beam bottom
Adjust beam bottom according to design
Check beam bottom casing
Install beam steel

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Install formwork into beam


Install column to prop up floor
Cover formwork into floor formwork
Check casing and beam
Install floor reinforcement
Check floor beam casing and floor beam steel installation
a. Floor beam casing execution
General requirement
Casing and column structure bases on casing structure,
commit to following requirement:
- Guarantee right size and sharp
- Guarantee tight to avoid loss of cement
This affects to execution progress and work quality
significantly.
Contractor uses Pal and Minh Khai scaffold casing combining
with wooden formwork so that work gets high quality and
execution process. The system is installed to guarantee the high
stability. These materials are used to execute the following
casings:
- The system of propping scaffold combining steel column
constriction.
- The combination between U steel cross bar and wooden
satchel.
- The combination among casing corrugated iron and
wooden pressing casing.
* Preparation steps:

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- Contractor calculates the height of scaffold which is used for


the propping straight for each girder, floor system based on
the building height.
- Calculate the capacity which presses into wooden satchel in
order to define the height it.
- Define the general height of all materials:
 The height of scaffold.
 The height of wooden satchel of girder and floor.
 The thickness of corrugated – iron formwork.
Contractor arranges the executing formwork team
based on the amount of work.
The system of PAL and Minh Khai scaffold will be put upon
the jack system to adjust height. The foot jack will be put
upon the thick casing to avoid its concentrating force to
concrete casing.
Minh Khai scaffold will be used to plaster and build work.
Contractor uses steel bar alternated wooden propping to
ensure safety and right techniques for stair execution.
Contractor will put the parts of materials available in
concrete such as bolt, iron hook… to use for the works of later
parts, pipe other materials following design.
Floor casing is installed by fixing steel casing which
connects to each other to form a large part. The system of
casing will be put upon the system of steel satchel and PAL
scaffold.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Adjust the system of casing, floor according to design.


Contractor uses foot jack, top jack of scaffold system which
can be adjusted up and down with the check of measuring
devices.
Contractor will organize to take over casing to avoid later
unfortunate mistake before installing reinforcement. The take-
over content includes rechecking centre, rod, the height of
casing according to design. Check shape, size, smooth, clean,
stability of casing. Check the stability of casing, scaffold and
floor.
Contractor ensures the right time, ensure concrete attain
the right volume and contractor also ensure to have enough
take-over note which attain the result.
b. Reinforcement and casing execution
Contractor proceeds installing reinforcement upon the
system of already finished casing right after installing them.
The type of reinforcement will be put at least 45cm high
from the floor and stay in the roof factory area before and
after being curved. Reinforcement must be ensured to be
cleaned before pouring concrete without oil or other
poisonous substance.
Contractor will arrange enough materials, machine which
serve for processing cool curving, installing reinforcement
according to design which is registered by investor and TCVN
8874-91. Reinforcement work will be processed right at
construction and then installed at right position according to

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

design and located reliably. Constructor arranges each steel


team which is delivered the specific works with different
department.
Floor reinforcement, stair are installed right upon the system
of floor casing. Constructor will install main reinforcement beam
right after installing the system of bottom casing beam.
Constructor will install secondary reinforcement beam outside
and then locate at beam’s design position.
Reinforcement is connected with each other soft steel line
(0.8-1mm) to ensure the stability when pouring concrete. Nut
and code connect surely to straight steel by tying or wielding.
Wielding reinforcement work will be processed according to TCVN
5724-93(VN STANDARD 5724-93). The wielded beams are
suitable with necessary demand and they will not be crust over
and swollen. Contractor will cast the concrete mortar
blocks which has the height equal to reinforcement protection
concrete of each structure according to design to ensure the
later pouring concrete work .
Contractor follows all the reinforcement work according to
design notice and investor.
Contractor will invite investor’s technical supervisor to take
over and sign the papers about reinforcement.
c. Floor concrete beam execution
Concrete work is processed right after taking over
reinforcement installation, the take-over documents are
complete. Contractor also does the check of casing system,

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

scaffold to ensure the stability in pouring concrete process


before officially pouring concrete.
Concrete beam, floor use commodity concrete poured by
pamp.
Contractor calculates to pour each concrete within a
day. Concrete will calculate to guarantee technical demands
about circuit.
Execution circuit and execution circuit method.
Concrete must be stopped pouring according to
restriction about circuit if the pause time of pouring concrete is
up to 90min in any circumstances.
Contractor will commit to TCVN 4453-95 standard
about concrete pouring circuit.
Floor concrete pouring circuit is 1/3 span to the
perpendicular direction to short side and to the pouring
concrete direction.
Circuit must have 1mm flexible steel net to connect
later section; it must be blocked so that concrete will not be
flown.
After stopping pouring concrete, if the next block
concrete is poured, the circuit contact must be carved roughly
and watered by solid cement, at this point, we use washer
water proof and glue layer. Contractor will pour a mortar layer
with rate 1:2 with damp proof additive.
Notice when pouring concrete contacts with circuit:

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

1- Concrete at circuit can not mixed with large rock or in


pouring concrete process rocks are concentrated in circuit,
they must be given away.
2- Stamping carefully without any mistake.
 Concrete pouring method for floor
Divide pouring concrete part: Concrete part is defined for each small pour so
that the pouring time is not up to 60min after being finished. This method is to cut concrete
pouring work in order to not be concentrated; therefore, concrete will not be separated.
Moreover, after pouring the later concrete layer, the previous begins
Pour the floor concrete, contractor applies myriopod method.
When pouring each layer, contractor uses stick to cover in order
to the thickness of concrete is 1 cm bigger than one of floor.
Then, compacting carefully until there is an appearance of
concrete layer .This the time, contractor stops compacting and
conducting to complete the concrete surface.
To confirm the thickness of floor concrete, contractor uses
a stick connected to a bar .The thickness of concrete commits to
standard when when concrete surface meets the bar. Besides
checking method, contractor arranges a survey machine to
combine flat level and high level in pouring concrete.

Maintenance method after pouring concrete:

Contractor needs to prepare satchel, casing to prevent rain


or sunlight which affects to the quality of concrete
Concrete maintenance is an important part to have stable
concrete and prevent structure surface from split. To
guarantee the quality of concrete, contractor maintain

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

concrete after 7 hours. For the floor, contractor focuses on


damp-proof.
After pouring concrete and complete concrete surface,
contractor prevent work from radiation of the sun according
to requirements and TCXDVN: 318-2004 about maintenance
and concrete structure
Concrete needs maintaining at least 7 days continuously
and watered during that time
 Requirements in concrete execution of the work
Before using, contractor gives investor quality certificate
to guarantee no alkali reaction
After designing concrete, contractor gets the sample to
check. Materials with standard is kept in the construction
site to compare with other
In case of the rain, contractor covers against water
Concrete experiment:
After pouring concrete, contractor gets concrete samples
in the work .The sample must have date, month, year, work
name .Each sample group includes 6 pieces.3 pieces have
age of 7 days and 3 pieces of 28 days.
Contractor guarantees experiment equipments in the
construction site and maintains during execution time:
+ Standard screen system
+ Suitable weighbridge, equipments to identify moisture
+ Gauge glass
+ Concrete test equipments:

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Cudgel and beam


16 metal patterns with 150mm to try cube
sample
Cistern 1. 2*1.2*0.6 to maintain concrete
Shovel
Steel ruler 300mm
Contractor maintains experiment to check work quality during
execution time. Experiment results are restored in work
After maintenance, contractor and investor check concrete
4. Construction
a. Material requirement
Construction is very important in execution. Thus, contractor
conducts maintenance methods to guarantee techniques from the
beginning.
Bricks must be solid, not separated and reach the standard. Half
baked bricks, brickbats are rejected.
Mortar commits to design. Using mixing mortar after 30 minutes,
not using mixing mortar for a long time.
b. Preparation
In the construction, contractor puts lead of waited steel to
connect wall to reduce plasticity of construction blocks and
concrete structure. Thus, there is no leak between concrete blocks
and concrete structure.
c. Execution order and methods

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Base on the centre of column when conducting to place column


in the formwork combination and concrete pour process .Mark ink
border lines
Clean the wall foot by watering
Stretch the horizontal line .Building fontanels
Stretch vertical line (Use plum line)
d. Construction method
Stretch mortar on the bricks, near to wall edges 1-1.5 cm
The length of mortar layer leads to length of each brick (in the
drawings)
Knock on the brick to subside the mortar
Put the brick on the subsided mortar layer. Thickness of
mortar vein is 1.2-1.5 cm. Thickness of mortar vein is 1.5
cm. Use trowel to dredge two veins of wall to make it deeper
0.5 cm.
e. Construction blocks demands:
Contractor ensures all construction block to be built at right
position according to design and stop point restriction.
The construction block must be put stably, tight across and
straight circuit, must be straight perpendicular to floor. Across
wall beam, door beam must have right geometric shape,
structure and position according to height, smooth design.
In building process, let holes, water pipe drains, air-ducts
and decorating position, unnecessary position can not be let
holes to weaken walls.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Crossing, contact position of construction blocks must be


built at the same time.
Contractor will put perpendicular measure and plumb line
to at least 2directions, the height of each construction period is
about 50-60cm after drying mortar, build the next.
When building pillar next to wall, do not let pillar have
straight circuit.
Only after building pressing force structure of downstairs,
we will build the upper stairs.
Do not collide with already built wall in order to fallen it or
affect the stability of wall structure.
Already built wall after 8 hours must be watered maintain
layer so that the mortar have enough water to participate in
physicochemical reaction; therefore, it will not be brittle, which
ensures the construction volume.
Contractor will use standard steel plumb line to check the
vertical degree, and wooden or aluminum alloy measurer which
have parallel and straight sides (2-2.5m) to check the smooth of
construction blocks. Contractor will use angle protractor to check
the angle of construction blocks before building.
Contractor will equip protractor for each team, it is a light
alloy which marks construction lines, beam position, windows
and other parts.
Already building walls, mortar layer is not unit degree
when raining. Contractor will use canvases to cover the mortar
layer.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Technical engineer guides directly and checks regularly


in construction during the daily building process.
A.I.4.3. COMPLETION METHODS FOR FINISHING WORK
1. Plaster
Mortar of wall which has been kept for a long time. Then,
conducting to mortar to guarantee quality of mortar and affect to
surrounding work.
Before conducting mortar, contractor invites investor to
check column centre, wall flat degree, tight mortar pulse.
Contractor conducts to mortar, contractor waters on walls,
make wall surface and mortar adhesive. Mortar layer do not
elastic
Mortar follows to design, thickness depends on structure
Create drainage ditches to sink wire column and technical
box.
Mortar surface must be equal and solid
Type of mortar and thickness of mortar base on design
standard 15-20mm and divide mortar into 2 periods. Vertical
deviation is 0.5% and horizontal deviation is 0.8%
General requirements
Mortar surface is smooth
Angle has square shape
Guarantee structure standards
Contractor is responsible for mortar and completion. In
mortaring angles, contractor uses angle ruler to check straight
and square shape

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Contractor maintains mortar layer after plastering 24 hours


Engineer team completes and are in works regularly
2. Pressing and plastering work:
 Plaster brick is up to the following factors:
Contractor’s title are up to these following parameters:
Absorbent degree Hp<0,2%.
Pressing degree Rn>500kg/cm2.
Curving degree Ru>500n/mm2
Abrasion degree Mn<130mm2.
Durable degree with acid, base, not mouldy surface.
Bricks used must be brand new.
When carrying bricks to rooms for plastering, Contractor will put
them along with the wall side in order not to affect structure.
 Plastering work:
Plastering work begins when structure work is finished. The
plaster floor is smooth and clean.
Plaster material is in right sizes, colors, design. Plaster brick
is at high standard. Cut bricks must be smooth.
Plaster floor is smooth, not rough. Checked by 2m long
protractor. Slots between plaster floor and protractor <=2mm.
Slopping degree and direction are at right design.
Between plaster floor and bricks is full of mortar. Check
solid degree by knocking lightly on the plaster floor.
The thickness of cement layer <=15mm. The circuit
between bricks is pure cement and water.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

At compulsory positions about damp-proof, check the damp-


proof layer and other details before plastering.
Plaster floor must be built according to design about pattern
color, height, smooth, plopping, connection to floor degree.
Pressing and plastering work will be ensured the whole
enamel surface of producer by the contractor after being
finished.
 Pressing work:
Pressing work is installed after building and taking over
electricity and water departments and other underground parts.
Press structure surface is according to straight direction.
Across pressing circuit needs being full of mortar building
pressing and building producer.
Clean the press floor after pressing each part or all parts.
Cleaning the press floor is processed only after pressing circuit
gets hard.
Press floor must be followed the following demands:
General press floor is ensured the right shape and
geometric size. The color must be the same.
Across and straight mortar circuit is sharp, straight, regular.
Mortar between structure and pressing bit is solid.
There is no stained point of paint and lime. When checking
by 2m protractor, slot between pressing bit and protractor is <=
2mm.
3. Painting work:

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

After checking that all walls are so smooth, we do the


painting. In painting process, check every angle by lights. All
mistakes must be corrected at once.
Painting layer surface is smooth, not rough.
Protection method must be made in crowded areas.
4. Glazing execution:
Structure is stable, no dirty, oil before Glazing.
To guarantee the connection between smooth mortar layer
and floor, the smooth surface needs watering. If having the lined
smooth layer divides 10 – 15cm areas.
The last smooth layer uses cement sand mortar with
maximum material rod<= 2mm. After 4-6 hours, depending on
the weather, moisture and air temperature, we finish by
spreading a concrete line or thin mortar concrete.
The smooth surface must be guaranteed about surface
finish according to design. Grinding process is done at the same
time with mending general tit and tear surface.
Thread bend work is done right after painting. Thread line
need regular about weight, depth and sharpness. If use roller
with anti-smooth material, roll right after color cement layer is
not solid.
Areas and positions have demand about high damp-proof
such as: toilet, water tank, conduit….must process damp-proof
layer according to design.
Quality of smooth surface must guarantee about taper,
plane ness.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

5. Door installation:
- Wooden doors and aluminum-glass frame doors are
manufactured in workshop according to design and rechecked
through practical execution. Contractor will give product quality
certification to investor before execution.
- Contractor guarantees installing with right technique and
experienced team. Check carefully straight, door frame smooth
degree when installing.
-Aluminum-glass frame doors are checked by high pressure
pump. The connection between door and wall is processed by
glue and damp-proof.
- Coefficient of hardness of door must be high and no
deformation.
- Detail installing must be accuracy. Doors must move
smoothly. Bolt lock, hinge are tight, fine art.
- Door surface must be smooth, no cement mortar or closed
chemical on it.
- Glass is up-to standard product, no ripple.
- The filled connection is used with transparent and good
silicon glue which is not changed color when sun and rain.
- Installing windows and doors are processed late. It is
guaranteed not to spoil already work such as ceiling, wall…
- Hinge must have good incompetence and be installed
tightly and accuracy. Handgrip, door lock must be installed
tightly and accuracy.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- All door and glass wattle must have good incompetence,


against windstorm according to design.
6. Electricity, thunder protection
Electricity execution
Contractor appoints a skillful and experienced engineer and
technical team
Investor checks materials like conduit, wire protected pipes,
plug foot protected pipe...
Contractor checks electricity system before giving for
investor
Electricity execution divided into 2 steps:
Step1: Stretch underground -wire
Step2: Installation floated wire equipments
 Stretch underground wire
Investor checks quality of wire, conduit, and wire protected
pipes, plug foot protected pipe….Then, contractor starts to install
Before plastering walls, ceilings, contractor estimates wire
plan, position of connection boxes, sockets, electricity box
 Under ground wire pipe installation follow steps:
- Base on electricity drawings, line electricity map on the wall
- Cut pipe to help install pipes on right position
- Contractor puts plated corrugated or zinc pipe with thickness
of 15mm. Thickness is equal to length of wall or floor. Contractor
uses cement mortar to keep wall or floor

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- Guarantee distance between hot pipes and other heat surface


is 15cm. After installing pipes, it must be dry and contractor
uses glue to connect pipes by pike
- At bend point, contractor uses spring – mattress and not
reduce pipe area .Inside radius is not smaller than pipe diameter
- Pipes must guarantee: Straight, covered, smooth
- Rim pipe tight, avoid water and other objectives
- Clip pipe carefully ,clip point is not exceed 200mm from
electricity box edge .Distance between clips is not exceed 1000
mm and 800 mm to the straight direction
- Before using pipe, if it is humid, contractor uses air
compresses to make dry. After installing, contractor surveys and
invites investor to check. Cover XR mortar on the pipes before
finishing survey
 ocket foot, switch foot, connection box, and electricity box
Distance between socket and floor according to design
Distance between switch and floor according to design
Distance between electricity box and floor according to
design
 Requirements:
Box foot, contractor estimates to prominence to make foot
and wall equal
Inside wall box are the same in types
 Above electricity installation
Equipments are executed at last, after finishing others

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Investor checks types of equipments .Quality of work must


be checked. Packets are labeled dates and location, features.
Contractor gives certificates to investor
After checking products, contractor installs equipments to
be suitable for design. Equipments must be clipped carefully.
After installation, contractor invites investor to try and
check
 Thunder protections
Thunder protection system includes: Thunder collected
needle D16 with length of 0.8m; Thunder collected line D10
placed on wall and ceiling. Ground connection steel line D14
connecting steel line and ground connection column is 63*63*6
with the length of 2.5 cm
After installing, contractor investor to check, contractor
guarantee features : Underground connected resistance R<= 4
7. Drainage and supply water system
Consist of running water, fire fighting supply system and
drainage system for completion
Drainage and supply water system is galvanized and PVC
and do according to requirement
Inside wall equipments are placed by contractor. After
installing, contractor will test run to check pressure and takeover
Pressure for drainage system is 0.7 kg/cm2 and trial run
time is 12 hour, reducing pressure to be smaller than 0.005
kg/cm2.Contractor gives trial methods to investor to try

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

In executing water supply system, contractor


guarantees tight and is not leaked out
Base on design and requirement of contraction
document, checking and taking over types. Then, contractor
starts to install equipments
Sanitation equipments must be clean until taking over.
Avoiding remained sand, collected funnel is without cement,
sand, paint…
Forbid using before sanitation equipments except in
experiment
8. Damp-roof work
- Damp-roof work is very important because it affects to using
and aesthetic. Thus, contractor supervises tightly execution.
- Damp-roof work demands the combination of many phases,
even BTCT execution will be noticed carefully.
- Aggregates (sand, rock) must be cleaned by fresh water before
concrete pouring. This part of reinforcement concrete needs
additive material to improve damp-proof competence of
structure. Additive material is used following to supervisor.
- Proof floor and toilet floor must be soaked with cement water
during 20 days.
- Concrete surface must be cleaned before damp-proof
execution. Its surface must be dry and cleaned by pressure-
blower.
- Damp-proof surface must be filled with a pure cement mortar
layer before plastering or bottom concrete pouring. Concrete

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

pouring work to make slope needs executing when mortar layer


is still wet so that it is guaranteed mortar layer is not harmed.
- The second damp-proof by glue is processed above the surface
of slope to satisfy the demand of smooth slope. After that, it is
swept according to design.
- In the position of drainage pipe must be used metal, no plastic
funnel.
A.II. CONSTRUCTION EXECUTION PROGRESS AND
CONSTRUCTION PROGRESS GUARANTEE.
- Construction has a beautiful view and demands fine art quality
and high technique. In order to guarantee about fine art quality,
high technique and progress construction, contractor will arrange
staff team and experienced engineers to manage the structure.
- Contractor will use a suitable method to manage manpower.
Each employee will receive detail work and have high
responsibility.
- Contractor ensures to use qualified employee.
Progress construction diagram:
- Ensure to follow the right design, contract document and
requirement of investor.
- Ensure to execute with good quality, safety and the right
process.
- Arrange myriapod, flexible method according to the details
work.
- Arrange manpower to be suitable with process, each work and
guarantee process line is suitable and not overlap and waste.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- Supplying material is guaranteed to be on time and never to be


in shortage condition.
- Machine is supplied to be on right time according to process.
Contractor uses mechanization into process. In necessary case,
contractor will add more machines to hasten the process
according to investor.
- Supply enough formwork, scaffold for concrete pouring and 3
floors and avoiding the death time.
- Guarantee to combine and impart the investor’s idea.
Contractor and represented investor always check process
and plan on every Monday to guarantee the rate of progress.
With this aim and plan, Contractor guarantees to finish all
of work within 190 days.
A.III GUARANTEE METHOD OF CONSTRUCTION QUALITY
A.III.1. General Explanation.
Contractor especially appreciates building construction
quality management. Building construction quality is the main
aim of contractor. Building construction quality also is the main
factor which creates stable belief of investor to contractor and
this makes contractor successful.
A.III.2. THE EXPLANATION ABOUT MATERIAL AND
MACHINE SUPPLY. CONTRACTOR WII APPLY WORK
STANDARD TO GUARANTEE QUALITY ACCORDING TO
DESIGN.
1. Main materials

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Contractor guarantees the standard quality for all material


according to technical stipulation design. All material will
have certificated quality result, finished bill, quality register
of producer, experienced result to present to investor before
using. Contractor will guarantee to supply 100% newly
material according to design.
 Cement
Using Porland PC30 cement following to TCVN 2682-92
standard. The spare time of batch of cement before use is within
3 months. Manufactured date and year is on the wrapping or
have certificated producer.
 Sand, Rock
Construction uses mainly yellow, black sand. Rock is
stable enough, no impurities not to influence to concrete’s
volume, stability and damp-proof. Rock is grinded by machines.
Contractor guarantees not to use exploited, manual rock.
 Mixed concrete
Contractor will supply fully fresh concrete to be
suitable with process according to design’s label and have
enough quality certification.
 Reinforcement
Use Thai Nguyen steel or qualified steel according to
investor’s demand.
 Other material
Other material using in construction will be guaranteed
about quality according to investor.
2. Equipments
TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88
Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Contractor will have plans to supply motor bike, detail


execution equipment to each period according to the amount of
work. Contractor guarantees to have the best effect and right
process.
Contractor will add more amount of motor bike in necessary
case according to work and process.
Contractor will contact directly and have necessary
permission to transport all type material and machine to
construction. Contractor supplies the amount of scaffold,
formwork in right demand.
A.III.3. HUMAN RESOUCE ARRANGMENT
1. Technical supervisors
Construction engineers, responsible skillful and experienced
supervisors includes:
+Technical engineers (Machine, Construction equipment) : 1
person
+ Construction technical engineers (plan, materials) : 1
person
+ Supervisor :2
persons
+ Construction engineers (Execution) :2
persons
Execution methods for each specific work, check working
procedure of workers
Combine with controllers to check and take over works, set
up checking certificate, completion document

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Checking quality of materials, safety


2. Engineers, technical engineers and workers in work
Arranging technical staffs in work who are generic,
experienced, and healthy. These staffs guide and check
work regularly work
+ Geodesic engineers : 01 person
+ Electric and water engineers : 02 persons
+ Construction engineers : 03 persons
+ Architect : 03 persons
Checking and taking over inside between supervisors of
company and water construction company. After finishing,
investor concludes
Set up construction work document diary, other certificates
3. Workers
Skillful workers have grade of more than 3/7 and are trained
about construction field. This team took part in many works
A.III.4. EQUIPMENT FOR EXECUTION
Equipments are equipped for execution of workers; ensure
quality, capacity as following:
+ Mason:
- Ruler , hard aluminum ruler
- Plumb bob
- Nivo
- Square angle ruler
- Nylon line
- Steel scaffold

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- Brick and concrete cutting machines


+ Home decorated carpenters are quipped:
Electric– saw, planer, air compressor, nail gun, rulers,
and plumb bob
+ Steel man is equipped:
Cutting machine, curved steel machine, wielding machine
Use all general equipments to serve execution
effectively and fast like: using excavation machine, car, steel
scaffold, formwork in execution and equip light system at night…
Equip computers, telephone, fax, mobile phone…
+ Survey department
Arrange staffs, survey engineer with experience
Use measurement machines for survey:
- 02 theodolite machines
- 02 water box machines
- Steel ruler with length of 100m
These kinds of machines must be tested and licensed
Survey team must be in construction work
Survey team must be in construction work from the beginning to
completing work.
Set up axis center, construction work center, border
Serve completion work, measure to complete the work.
A.III.5 .EXECUTION ARRANGEMENT
Plan execution progress in detail every week; combine
between concrete, raw construction, plaster, ashlar pave
Combine execution works to avoid overlapping

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Prepare space reasonably, avoid making noise and dirty to


surrounding works
A.III.6. ACCEPTANCE
Check and take over according to order, from inside contractor
to contractor and technical supervisor. At last, transfer work.
Basis of taking over is:
- Tested design document
- Technical regulations and instructions of producers to
maintain materials
- Test results, experiment and equipment volume are done
during construction process
A.III.7.MATERIAL SUPPLY
Choose high -quality material factories and supply sources
Quality material test: It is very important to guarantee work
quality. Materials must be tested before transferring to the work
and investor to test quality
Main materials must be tested:
- Reinforcement
- Concrete
- Cement
- Brick … ( Serve for building, plasting…)
A.III.8. LIST OF MAIN MATERIALS USED IN CONSTRUCTION
No Main material Manufactured source
1 PC30 cement Hoang Mai, Bim Son, Nghi Son or
so on
2 White cement Hai Phong white cement or so on
3 Mixed rete Mixed station

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

4 Steel types Thai Nguyen steel


5 Thread brick Label A1 type factory>=75
6 Sand types Vietnam standard fresh sand
7 Macadam types Grinder by machine standard
rock Kien Khe-Phu Ly
8 Paint KOVA paint, Mexilitex or so on
9 Pressing non-slip brick Viglacera brick
10 Plastering ceramic brick Viglacera, Long Hau, Hong Ha
brick
11 Door types Depend on design type
12 Material and equipment According to design
electricity
13 Material and equipment According to design
drainage
14 Casing, formwork Fixative corrugated casing and
wooden pressing casing
15 Scaffold, satchel PAL, Minh Khai scaffold; steel
constriction satchel

Besides, all material will be supplied into construction


according to design and investor’s demand.
A.III.9.TECHNICAL METHOD TO GUARANTEE WORK
QUALITY
General explanation
Contractor is responsible for work execution according to
agreement, guarantee work quality according to technical
drawings, procedure and execution, construction standard,
construction quality.
Contractor guarantees high quality to any articles
concerning to work, from space preparation, land survey,
dimension precise, material quality and work completion
TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88
Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Contractor notices to investor to consider and deal with if


there is any problem. Contractor deals with by themselves. After
discussing with investor, contractor prepares and dismounts
Contractor notices to investor if there is any problem in
design document as well as petition method for contractor to
consider and approve.
Materials are transferred in work like: cement,
reinforcement, sand, rock, brick. Concrete must are tested
Materials for damp- proof must be tested
Materials have resources
At last, all materials must be allowed by contractor and
Supervisor.
Once more time, contractor confirms each work quality
1. Reinforcement
Read, look at design drawing: pivot, beam, floor, stair…
Use right type of reinforcement designed in drawings and
only using when having certificate
Test dimension of reinforcement
Execution following to restriction, technical standard
processed by Vietnam
Reinforcement is processed, installed according to drawings
Workers have grade and experience
Provide equipments fully for reinforcement
Reinforcement in concrete must be tested and accepted by
engineer supervisor
Forbid cutting concrete by Acetylene

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

2. Concrete execution
Concrete execution plays an important role in deciding
tonnage burden of work
Check landslide degree in concrete pour place and note in
document (responsibility of contractor)
Cast concrete sample in concrete place (sample volume
according to restrictions)
Press concrete sample done in laboratory (Age result 7 days
and 28 days)
Form of cement, sand, rock and concrete samples are
noted full
Concrete pour and concrete beam are done according
to restrictions of supervisors, investors and contractors
Concrete meets to standard in Vietnam
Concrete maintenance is done after 24h from pouring time,
then, maintain within 7 days continuously.
- Use pump to water
- Use equipments to cover direct light
- Distribute people to maintain everyday
Largest height for concrete is 1.5m. Using pipe to pour
concrete when structure is greater than 30cm
Thickness of structure is larger than 60 cm, pour, and beam
into each layer of 30 cm thick
Forbid using additive having Canxi
3. Formwork combination

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

Untie reinforcement, steel columns with steel beam and


wooden satchel with dimension of more than 10*12 cm
Formwork used with thickness of more than 3 cm. Thickness of
corrugated ion formwork is 1.5 to 2 cm
Adjust partition formwork by method: Soft line with tender
Use theololite to check straight degree of formwork system
before pouring or using plumb bob to adjust
Use water box machine to check beam formwork system
Clean before pouring concrete
Use bolt and clip instead of nail
4. Construction
Use survey to place the position to build wall on the space
Bricks have right types, grade
Water bricks before construction from 20 to 30 minutes
Mix mortar by machine according to grade. Mixed materials
are calculated carefully
Use nylon line to create square angles
Circuit meets to requirement
Full mortar between bricks

A.III.10. APPLYING PROGRESSIVE SCIENCE AND


TECHNOLOGY IN CONSTRUCTION
Contractor applies progressive science and technology to
execute construction in order to guarantee process and quality.
Contractor uses execution machine at maximum level to improve
work quality and reduce process time.

TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88


Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

- Contractor uses fixative steel type with materials such as:


scaffold, satchel, casing to improve work quality and reduce
process time.
- Contractor uses elevator system to transport material to
high position. This system is tidy and have high feature.
- Contractor uses experienced engineer and employee to
execute this construction.
- Contractor supplies adequate amount of fixative formwork,
scaffold of all floors on time to guarantee process of
construction.
- Supply adequate material on time according to design
- Set up and control process of each detail work
- Contractor will equip communication and electricity
system in order to guarantee about regular contact.

A.III.11. LIST OF MAIN MACHINE AND


EQUIPMENT IN CONSTRUCTION
EXECUTION
N Machine, equipment Quantity Parameter Made in
o name
I Main execution
equipment
4 KOBELCO tire digger 01 Vg=0.8 m3 Japan
5 IFA, KAMAZ lorry 07 5-12 ton German,
Russia
6 Sperm compressor 02 20 Cv China
7 Concrete mixing machine 02 2.8 Kw; China
250l
TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88
Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

8 Mortar mixing concrete 03 150l China


9 Concrete pumping car 01 80m3/h German
1 Concrete rammer- 05 1.1 KW China
0 drilling rammer
1 Concrete rammer- floor 03 1.5 KW China
1 rammer
1 Iron cutting machine 02 1998 China
2
1 Iron curving machine 02 1998 China
3
1 Wielding machine 02 24 KVA Vietnam
4
1 Electric generator 01 40 KVA Japan
5
1 Concrete driller 02 2.5 KW German
6
1 Theodolite 02 Japan
7
1 02 Japan
8
1 Pump 03 15-30 m3/h Korea,
9 Italia
2 MISAKA rammer 02 60-80 Kg Japan
0
2 Handle machine 20 Japan,
1 Korea,
China,
Vietnam
2 Minh Khai finish machine 1200 Vietnam
2 single
unit
2 PAL combination scaffold 600 Vietnam
3 single
TƯ VẤN DỊCH VỤ HỒ SƠ XÂY DỰNG MIỄN PHÍ 24/7: 0904.87.33.88
Nhận Lập hồ sơ dự thầu , thanh toán, quyết toán, nghiệm thu ,dịch vụ chứng chỉ xây dựng …
CÔNG TY CỔ PHẦN DỊCH VỤ XÂY DỰNG
Tầng 11, Tòa nhà Bắc Hà Tower, 17 Tố Hữu, Quận Từ Liêm, Hà Nội
Tel: 0904.87.33.88 – Hotline: 0912.07.64.66
Web: https://hosoxaydung.com -
https://hosoxaydung.vn

unit
2 D68 steel satchel 300 Vietnam
4
2 Casing types 5000m2 Plywood, Vietnam
5 metal
2 Safe net, sign 02 unit Vietnam
6
II Experiment check
equipment
1 02 unit Vietnam
2 Shape casting concrete 06 unit Vietnam
3 Pressing experiment 01 Spain
concrete machine
4 Pouring concrete spout 01 Switzerlan
d
5 Experiment steel 01 China
machine

All machines are proved to guarantee process. Contractor


commits to supply adequate all machines and equipment for
execution and have more machines if necessary