Professional Documents
Culture Documents
Air and Flue Gas Tightness Test
Air and Flue Gas Tightness Test
INDEX:-
1) OBJECTIVE
2) PROPOSAL
3) PRE-COMMISSIONING CHECKS
5) COMPLETION CRITERIA
A) OBJECTIVE
The air & gas tightness test is carried out in Boiler furnace, air and Gas ducts, in
order to find out
The leaks, incomplete weld joints, left out portion of the weld, flange joint leaks, etc
and to arrange
for repair/ rectification.
The air tightness test is only a Test to find out the tightness of the Boiler furnace, air
and gas ducts
With the respect to the outside environment and is not performed to assess the
strength to withstand
the operating pressure.
B) PROPOSAL
The test will be carried out by furnace leak detection method in the following Stages.
C) SERVICES REQUIRED
1. Soap water.
2. Bucket & Mug.
3. Cotton waste.
4. Marker.
5. Lighting arrangement.(Hand Lamps).
6. Man power for conducting the Test.
D) PRECOMMISSIONING CHECKS
REFERENCE
STATUS
S.NO. ACTIVITY DOC/ACCEPTANC
ok/not ok
E CRITERIA
Ensure completion of erection of Boiler first Refer filled up log
pass/horizontal/rear passes, sheet of the
1.
IDF/FDF/PAF/APH and all ducting of air & erection Quality
flue gases system. plan.
Check the clearance is obtained from ducting
2. system, Fans, AH and main Boiler erection
group.
3. Check the following in the ducts( ID
suction /discharge, ESP inlet /outlet/ inter-
connection, AH O/L to ESP I/L,FD discharge,
AH I/L & O/L, WIND BOX, PA DISCHARGE,, Cold
air bus tampering air, mill I/L.
A) Completion of all supports/sliding
points.
B) Completion of all instruments point.
C) Completion of all bracing.
D) No visible leakage point.
E) Removal of the expansion bellows
locking.
F) Completion of erection &
commissioning of the damper.
G) Tightness of the flange joint.
H) Completion of the flange joint.
4 Check AH for any visible leakage point.
Check ID/FD/PA/Seal air fans for any visible
5
leakage points in the casing.
6 Check wind box for any visible leakage points.
Check the ESP casing, shaft/support
insulator covers Hoppers etc for any visible
7
leakage points.
REF.
S.No.
DOCUMENT /
ACTIVITY STATUS
ACCEPTANCE
CRITERIA
1 Repeat the tests
Run ID/FD Fans & pressurize furnace to +25 till all leakages
to +50 mmWc. Check air leakages points in are attended
various ducting, ID/FD Fans. ESP. Spread
soap solution on the pent house roof & check
the leakages and rear arch leakages to be
checked physically.
2 Run PA Fan & pressurized PA & Milling Repeat the tests
System ( keeping burner I/L gate closed) till all leakages
and check the air leakages in the duct, are attended &
casing, mill body, Pf piping & Seal air fan Test is declared
suction duct ( physical leakage detection) over when all
the leakages are
attended.
3 Run the seal air fan and check for the air Repeat the tests
leakages in the seal air discharge & seal air till all leakages
filter cleaning air duct .( Physical leak are attended &
detection.) Test is declared
over when all
the leakages are
attended.
4 Run the scanner air fan & check for air Repeat the tests
leakages in scanner air duct( physical leak till all leakages
detection) are attended &
Test is declared
over when all
the leakages are
attended.
F. COMPLETION CRITERIA
Air and gas tightness for any stage declared complete when identified all the leakages
point attended satisfactorily.
Insulation work for any stage could be taken up after completion of the
Air & Gas tightness Test.