PROJECT 7 ACRES - TRACKING Classic Schedule Layout 12-Jul-19 09:37 AM

Activity ID Activity Name Original BL Project Start BL Project Finish Actual Start Actual Finish Duration % Variance - BL 2019
Duration Complete Project Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
PROJECT 7 ACRES - TRACKING 937.00d 01-Dec-18 09:00 AM 16-Apr-21 06:00 PM 01-Dec-18 09:00 AM 23.59% -121.00d

PHASE - 1 - BLOCK A, B, C & AMENITIES 695.00d 01-Dec-18 09:00 AM 25-Nov-20 06:00 PM 01-Dec-18 09:00 AM 31.8% -21.00d

BLOCK - A 633.00d 01-Dec-18 09:00 AM 29-Sep-20 06:00 PM 01-Dec-18 09:00 AM 34.91% -16.00d
SUB STRUCTURE 236.00d 01-Dec-18 09:00 AM 23-Jun-19 06:00 PM 01-Dec-18 09:00 AM 93.64% -31.00d 24-Jul-19 06:00 PM, SUB STRUCTURE
A1000 Mass Excavation 60.00d 01-Dec-18 09:00 AM 29-Jan-19 06:00 PM 01-Dec-18 09:00 AM 29-Jan-19 06:00 PM 100% 0.00d Mass Excavation
A1010 Retaining Wall - Foundation 35.00d 30-Jan-19 09:00 AM 05-Mar-19 06:00 PM 30-Jan-19 09:00 AM 05-Mar-19 06:00 PM 100% 0.00d Retaining Wall - Foundation
A1030 Retaining Wall 1st Lift - 97.10lvl 30.00d 18-Feb-19 09:00 AM 19-Mar-19 06:00 PM 18-Feb-19 09:00 AM 19-Mar-19 06:00 PM 100% 0.00d Retaining Wall 1st Lift - 97.10lvl
A1040 Foundation - Footing, Pedestals, Plinth & Lift, 56.00d 16-Feb-19 09:00 AM 12-Apr-19 06:00 PM 16-Feb-19 09:00 AM 15-Apr-19 06:00 PM 100% -3.00d Foundation - Footing, Pedestals, Plinth & Lift,
A1050 Compaction & Consoldation - Foundation, Plinth Beam & Retainng
20.00d Wall
29-Mar-19 09:00 AM 17-Apr-19 06:00 PM 29-Mar-19 09:00 AM 17-Apr-19 06:00 PM 100% 0.00d Compaction & Consoldation - Foundation, Plinth Beam & Retainng Wall
A1060 Basement - 1 - Slab Casting - 97.10lvl - Pour - 1 28.00d 09-May-19 09:00 AM 05-Jun-19 06:00 PM 02-May-19 09:00 AM 18-May-19 06:00 PM 100% 11.00d Basement - 1 - Slab Casting - 97.10lvl - Pour - 1
A1070 Basement - 1 - Slab Casting - 97.10lvl - Pour - 2 28.00d 12-May-19 09:00 AM 08-Jun-19 06:00 PM 15-May-19 09:00 AM 03-Jun-19 06:00 PM 100% 8.00d Basement - 1 - Slab Casting - 97.10lvl - Pour - 2
A1080 Basement - 1 - Slab Casting - 97.10lvl - Pour - 3 28.00d 15-May-19 09:00 AM 11-Jun-19 06:00 PM 15-May-19 09:00 AM 03-Jun-19 06:00 PM 100% 8.00d Basement - 1 - Slab Casting - 97.10lvl - Pour - 3
A1090 Basement - 1 - Slab Casting - 97.10lvl - Pour - 4 28.00d 18-May-19 09:00 AM 14-Jun-19 06:00 PM 01-Jun-19 09:00 AM 14-Jun-19 06:00 PM 100% 14.00d Basement - 1 - Slab Casting - 97.10lvl - Pour - 4
A1100 Retaining Wall 2nd Lift - 100.60lvl 15.00d 01-Jun-19 09:00 AM 15-Jun-19 06:00 PM 0% 0.00d Retaining Wall 2nd Lift - 100.60lvl
A1160 Retaining Wall Bacfilling 15.00d 09-Jun-19 09:00 AM 23-Jun-19 06:00 PM 0% 0.00d Retaining Wall Bacfilling
A1170 South East Side Access Ramp at Block - A 40.00d 19-Apr-19 09:00 AM 28-May-19 06:00 PM 03-Jun-19 09:00 AM 12-Jul-19 06:00 PM 100% 0.00d South East Side Access Ramp at Block - A
SUPER STRUCTURE 249.00d 06-Jun-19 09:00 AM 16-Feb-20 06:00 PM 10-Jun-19 09:00 AM 14.86% -12.00d
GROUND FLOOR 101.20 Lvl & PODIUM -1 27.00d 06-Jun-19 09:00 AM 02-Jul-19 06:00 PM 10-Jun-19 09:00 AM 22.22% -24.00d 30-Jul-19 06:00 PM, GROUND FLOOR 101.20 Lvl & PO
A1260 Pour - 1 18.00d 06-Jun-19 09:00 AM 23-Jun-19 06:00 PM 10-Jun-19 09:00 AM 08-Jul-19 06:00 PM 100% -11.00d Pour - 1
A1270 Pour - 2 18.00d 09-Jun-19 09:00 AM 26-Jun-19 06:00 PM 02-Jul-19 09:00 AM 11-Jul-19 06:00 PM 100% 8.00d Pour - 2
A1280 Pour - 3 18.00d 12-Jun-19 09:00 AM 29-Jun-19 06:00 PM 02-Jul-19 09:00 AM 0% -8.00d Pour - 3
A1290 Pour - 4 18.00d 15-Jun-19 09:00 AM 02-Jul-19 06:00 PM 29-Jun-19 09:00 AM 0% -14.00d Pour - 4
1st FLOOR 104.20 Lvl 26.00d 24-Jun-19 09:00 AM 19-Jul-19 06:00 PM 0% 0.00d 04-Aug-19 06:00 PM, 1st FLOOR 104.20 Lvl
A1330 Pour - 1 17.00d 24-Jun-19 09:00 AM 10-Jul-19 06:00 PM 0% 0.00d Pour - 1
A1340 Pour - 2 17.00d 27-Jun-19 09:00 AM 13-Jul-19 06:00 PM 0% 0.00d Pour - 2
A1350 Pour - 3 17.00d 30-Jun-19 09:00 AM 16-Jul-19 06:00 PM 0% 0.00d Pour - 3
A1360 Pour - 4 17.00d 03-Jul-19 09:00 AM 19-Jul-19 06:00 PM 0% 0.00d Pour - 4
2nd FLOOR 107.20 Lvl 21.00d 11-Jul-19 09:00 AM 31-Jul-19 06:00 PM 0% 0.00d 16-Aug-19 06:00 PM, 2nd FLOOR 107.20 Lvl
A1400 Pour - 1 15.00d 11-Jul-19 09:00 AM 25-Jul-19 06:00 PM 0% 0.00d Pour - 1
A1410 Pour - 2 15.00d 13-Jul-19 09:00 AM 27-Jul-19 06:00 PM 0% 0.00d Pour - 2
A1420 Pour - 3 15.00d 15-Jul-19 09:00 AM 29-Jul-19 06:00 PM 0% 0.00d Pour - 3
A1430 Pour - 4 15.00d 17-Jul-19 09:00 AM 31-Jul-19 06:00 PM 0% 0.00d Pour - 4
3rd FLOOR 110.20 Lvl 21.00d 26-Jul-19 09:00 AM 15-Aug-19 06:00 PM 0% 0.00d 31-Aug-19 06:00 PM, 3rd FLOOR 110.20 Lv
4th FLOOR 113.20 Lvl 21.00d 10-Aug-19 09:00 AM 30-Aug-19 06:00 PM 0% 0.00d 21-Sep-19 06:00 PM, 4th FLOOR 11
5th FLOOR 116.20 Lvl 21.00d 25-Aug-19 09:00 AM 20-Sep-19 06:00 PM 0% 0.00d 15-Oct-19 06:00 PM, 5th FL
6th FLOOR 119.20 Lvl 21.00d 12-Sep-19 09:00 AM 14-Oct-19 06:00 PM 0% 0.00d 02-Nov-19 06:00 PM
7th FLOOR 122.20 Lvl 21.00d 09-Oct-19 09:00 AM 01-Nov-19 06:00 PM 0% 0.00d 17-Nov-19 06:0
8th FLOOR 125.20 Lvl 21.00d 24-Oct-19 09:00 AM 16-Nov-19 06:00 PM 0% 0.00d 02-Dec-1
9th FLOOR 128.20 Lvl 21.00d 11-Nov-19 09:00 AM 01-Dec-19 06:00 PM 0% 0.00d 17-D
10th FLOOR 131.20 Lvl 21.00d 26-Nov-19 09:00 AM 16-Dec-19 06:00 PM 0% 0.00d
11th FLOOR 134.20 Lvl 21.00d 11-Dec-19 09:00 AM 04-Jan-20 06:00 PM 0% 0.00d
12th FLOOR 137.20 Lvl 21.00d 28-Dec-19 09:00 AM 22-Jan-20 06:00 PM 0% 0.00d
TERRACE FLOOR 140.20 Lvl 21.00d 17-Jan-20 09:00 AM 07-Feb-20 06:00 PM 0% 0.00d
STAIRCASE, LIFT MACHINE ROOM & OVER HEAD TANKS 15.00d 02-Feb-20 09:00 AM 16-Feb-20 06:00 PM 0% 0.00d
FINISHES - FIRST FIX 244.00d 03-Jul-19 09:00 AM 15-Apr-20 06:00 PM 0% 12.00d
EXTERNAL PLASTERING 90.00d 13-Jan-20 09:00 AM 11-May-20 06:00 PM 0% 0.00d
LIFTS 30.00d 12-May-20 09:00 AM 10-Jun-20 06:00 PM 0% 0.00d
FINISHES - SECOND FIX 202.00d 08-Feb-20 09:00 AM 22-Sep-20 06:00 PM 0% 0.00d
EXTERNAL PAINTING 10.00d 12-May-20 09:00 AM 21-May-20 06:00 PM 0% 0.00d
SNAGS & HANDOVER 7.00d 23-Sep-20 09:00 AM 29-Sep-20 06:00 PM 0% 0.00d
BLOCK - C 568.00d 04-Feb-19 09:00 AM 27-Sep-20 06:00 PM 04-Feb-19 09:00 AM 27.46% -18.00d
SUB STRUCTURE 205.00d 04-Feb-19 09:00 AM 21-Jun-19 06:00 PM 04-Feb-19 09:00 AM 76.1% -67.00d 27-Aug-19 06:00 PM, SUB STRUCTURE
A6621 Mass Excavation 35.00d 04-Feb-19 09:00 AM 10-Mar-19 06:00 PM 04-Feb-19 09:00 AM 07-Mar-19 06:00 PM 100% 3.00d Mass Excavation
A6622 Retaining Wall - Fondation 35.00d 11-Mar-19 09:00 AM 14-Apr-19 06:00 PM 0% 0.00d Retaining Wall - Fondation
A6623 Retaining Wall 1st Lift - 93.60lvl 30.00d 30-Mar-19 09:00 AM 28-Apr-19 06:00 PM 0% 0.00d Retaining Wall 1st Lift - 93.60lvl
A6624 Foundation - Footing, Pedestals, Plinth & Lift 45.00d 15-Mar-19 09:00 AM 28-Apr-19 06:00 PM 20-Mar-19 09:00 AM 02-May-19 06:00 PM 100% 1.00d Foundation - Footing, Pedestals, Plinth & Lift
A6625 Compaction & Consoldation - Foundation, Plinth Beam & Retainng
20.00d Wall
13-Apr-19 09:00 AM 02-May-19 06:00 PM 04-Apr-19 09:00 AM 19-May-19 06:00 PM 100% -26.00d Compaction & Consoldation - Foundation, Plinth Beam & Retainng Wall
A6626 Basement - 2 - Slab Casting - 93.60lvl - Pour - 1 28.00d 07-May-19 09:00 AM 03-Jun-19 06:00 PM 22-May-19 09:00 AM 03-Jun-19 06:00 PM 100% 15.00d Basement - 2 - Slab Casting - 93.60lvl - Pour - 1

Project Baseline Bar Remaining Work Milestone Page 1 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
PROJECT 7 ACRES - TRACKING Classic Schedule Layout 12-Jul-19 09:37 AM
Activity ID Activity Name Original BL Project Start BL Project Finish Actual Start Actual Finish Duration % Variance - BL 2019
Duration Complete Project Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A6627 Basement - 2 - Slab Casting - 93.60lvl - Pour - 2 28.00d 10-May-19 09:00 AM 06-Jun-19 06:00 PM 28-May-19 09:00 AM 13-Jun-19 06:00 PM 100% 11.00d Basement - 2 - Slab Casting - 93.60lvl - Pour - 2
A6628 Basement - 2 - Slab Casting - 93.60lvl - Pour - 3 28.00d 13-May-19 09:00 AM 09-Jun-19 06:00 PM 04-Jun-19 09:00 AM 13-Jun-19 06:00 PM 100% 18.00d Basement - 2 - Slab Casting - 93.60lvl - Pour - 3
A6629 Basement - 2 - Slab Casting - 93.60lvl - Pour - 4 28.00d 16-May-19 09:00 AM 12-Jun-19 06:00 PM 10-Jun-19 09:00 AM 25-Jun-19 06:00 PM 100% 12.00d Basement - 2 - Slab Casting - 93.60lvl - Pour - 4
A6630 Retaining Wall 2nd Lift - 97.70lvl 15.00d 30-May-19 09:00 AM 13-Jun-19 06:00 PM 0% 0.00d Retaining Wall 2nd Lift - 97.70lvl
A6631 Retaining Wall Bacfilling 15.00d 07-Jun-19 09:00 AM 21-Jun-19 06:00 PM 0% 0.00d Retaining Wall Bacfilling
SUPER STRUCTURE 249.00d 04-Jun-19 09:00 AM 14-Feb-20 06:00 PM 24-Jun-19 09:00 AM 14.86% 2.00d
GROUND FLOOR 97.70Lvl & PODIUM -1 61.00d 04-Jun-19 09:00 AM 30-Jun-19 06:00 PM 24-Jun-19 09:00 AM 60.66% -13.00d 02-Aug-19 06:00 PM, GROUND FLOOR 97.70Lvl & P
A7841 Pour - 1 18.00d 04-Jun-19 09:00 AM 21-Jun-19 06:00 PM 24-Jun-19 09:00 AM 08-Jul-19 06:00 PM 100% 3.00d Pour - 1
A7842 Pour - 2 18.00d 07-Jun-19 09:00 AM 24-Jun-19 06:00 PM 30-Jun-19 09:00 AM 0% -10.00d Pour - 2
A7843 Pour - 3 18.00d 10-Jun-19 09:00 AM 27-Jun-19 06:00 PM 0% 0.00d Pour - 3
A7844 Pour - 4 18.00d 13-Jun-19 09:00 AM 30-Jun-19 06:00 PM 0% 0.00d Pour - 4
1st FLOOR 100.70 Lvl 26.00d 22-Jun-19 09:00 AM 17-Jul-19 06:00 PM 0% 0.00d 04-Aug-19 06:00 PM, 1st FLOOR 100.70 Lvl
A7845 Pour - 1 17.00d 22-Jun-19 09:00 AM 08-Jul-19 06:00 PM 0% 0.00d Pour - 1
A7846 Pour - 2 17.00d 25-Jun-19 09:00 AM 11-Jul-19 06:00 PM 0% 0.00d Pour - 2
A7847 Pour - 3 17.00d 28-Jun-19 09:00 AM 14-Jul-19 06:00 PM 0% 0.00d Pour - 3
A7848 Pour - 4 17.00d 01-Jul-19 09:00 AM 17-Jul-19 06:00 PM 0% 0.00d Pour - 4
2nd FLOOR 103.70 Lvl 21.00d 09-Jul-19 09:00 AM 29-Jul-19 06:00 PM 0% 0.00d 16-Aug-19 06:00 PM, 2nd FLOOR 103.70 Lvl
A7849 Pour - 1 15.00d 09-Jul-19 09:00 AM 23-Jul-19 06:00 PM 0% 0.00d Pour - 1
A7850 Pour - 2 15.00d 11-Jul-19 09:00 AM 25-Jul-19 06:00 PM 0% 0.00d Pour - 2
A7851 Pour - 3 15.00d 13-Jul-19 09:00 AM 27-Jul-19 06:00 PM 0% 0.00d Pour - 3
A7852 Pour - 4 15.00d 15-Jul-19 09:00 AM 29-Jul-19 06:00 PM 0% 0.00d Pour - 4
3rd FLOOR 106.70Lvl 21.00d 24-Jul-19 09:00 AM 13-Aug-19 06:00 PM 0% 0.00d 31-Aug-19 06:00 PM, 3rd FLOOR 106.70Lv
4th FLOOR 109.70Lvl 21.00d 08-Aug-19 09:00 AM 28-Aug-19 06:00 PM 0% 0.00d 21-Sep-19 06:00 PM, 4th FLOOR 1
5th FLOOR 112.70 Lvl 21.00d 23-Aug-19 09:00 AM 15-Sep-19 06:00 PM 0% 0.00d 15-Oct-19 06:00 PM, 5th FL
6th FLOOR 115.70 Lvl 21.00d 07-Sep-19 09:00 AM 12-Oct-19 06:00 PM 0% 0.00d 02-Nov-19 06:00 PM
7th FLOOR 118.70 Lvl 21.00d 28-Sep-19 09:00 AM 30-Oct-19 06:00 PM 0% 0.00d 17-Nov-19 06:0
8th FLOOR 121.70 Lvl 21.00d 22-Oct-19 09:00 AM 14-Nov-19 06:00 PM 0% 0.00d 02-Dec-1
9th FLOOR 124.70 Lvl 21.00d 09-Nov-19 09:00 AM 29-Nov-19 06:00 PM 0% 0.00d 17-D
10th FLOOR 127.70 Lvl 21.00d 24-Nov-19 09:00 AM 14-Dec-19 06:00 PM 0% 0.00d
11th FLOOR 130.70 Lvl 21.00d 09-Dec-19 09:00 AM 02-Jan-20 06:00 PM 0% 0.00d
12th FLOOR 133.70 Lvl 21.00d 26-Dec-19 09:00 AM 20-Jan-20 06:00 PM 0% 0.00d
TERRACE FLOOR 136.70 Lvl 21.00d 12-Jan-20 09:00 AM 05-Feb-20 06:00 PM 0% 0.00d
STAIRCASE, LIFT MACHINE ROOM & OVER HEAD TANKS 15.00d 31-Jan-20 09:00 AM 14-Feb-20 06:00 PM 0% 0.00d
FINISHES - FIRST FIX 241.00d 01-Jul-19 09:00 AM 13-Apr-20 06:00 PM 0% 15.00d
EXTERNAL PLASTERING 90.00d 11-Jan-20 09:00 AM 19-Apr-20 06:00 PM 0% 0.00d
LIFTS 30.00d 10-May-20 09:00 AM 08-Jun-20 06:00 PM 0% 0.00d
FINISHES - SECOND FIX 202.00d 06-Feb-20 09:00 AM 20-Sep-20 06:00 PM 0% 0.00d
EXTERNAL PAINTING 10.00d 10-May-20 09:00 AM 19-May-20 06:00 PM 0% 0.00d
SNAGS & HANDOVER 7.00d 21-Sep-20 09:00 AM 27-Sep-20 06:00 PM 0% 0.00d
BLOCK - B 635.00d 01-Dec-18 09:00 AM 25-Nov-20 06:00 PM 30-Jan-19 09:00 AM 25.35% 39.00d
SUB STRUCTURE 216.00d 30-Jan-19 09:00 AM 12-Aug-19 06:00 PM 30-Jan-19 09:00 AM 74.54% -21.00d 02-Sep-19 06:00 PM, SUB STRUCTURE
A6098 Mass Excavation 45.00d 30-Jan-19 09:00 AM 15-Mar-19 06:00 PM 30-Jan-19 09:00 AM 15-Mar-19 06:00 PM 100% 0.00d Mass Excavation
A6099 Retaining Wall - Fondation 35.00d 31-Mar-19 09:00 AM 04-May-19 06:00 PM 31-Mar-19 09:00 AM 04-May-19 06:00 PM 100% 0.00d Retaining Wall - Fondation
A6100 Retaining Wall 1st Lift - 97.10lvl 30.00d 15-Apr-19 09:00 AM 14-May-19 06:00 PM 15-Apr-19 09:00 AM 14-May-19 06:00 PM 100% 0.00d Retaining Wall 1st Lift - 97.10lvl
A6101 Foundation - Footing, Pedestals, Plinth & Lift 60.00d 05-May-19 09:00 AM 03-Jul-19 06:00 PM 10-Apr-19 09:00 AM 75% -46.00d Foundation - Footing, Pedestals, Plinth & Lift
A6103 Compaction & Consoldation - Foundation, Plinth Beam & Retainng
20.00d Wall
19-Jun-19 09:00 AM 08-Jul-19 06:00 PM 04-May-19 09:00 AM 50% -57.00d Compaction & Consoldation - Foundation, Plinth Beam & Re
A6104 Basement - 1 - Slab Casting - 97.10lvl - Pour - 1 28.00d 03-Jul-19 09:00 AM 30-Jul-19 06:00 PM 0% 0.00d Basement - 1 - Slab Casting - 97.10lvl - Pour - 1
A6105 Basement - 1 - Slab Casting - 97.10lvl - Pour - 2 28.00d 06-Jul-19 09:00 AM 02-Aug-19 06:00 PM 0% 0.00d Basement - 1 - Slab Casting - 97.10lvl - Pour -
A6106 Basement - 1 - Slab Casting - 97.10lvl - Pour - 3 28.00d 09-Jul-19 09:00 AM 05-Aug-19 06:00 PM 0% 0.00d Basement - 1 - Slab Casting - 97.10lvl - Pour
A6107 Basement - 1 - Slab Casting - 97.10lvl - Pour - 4 28.00d 12-Jul-19 09:00 AM 08-Aug-19 06:00 PM 0% 0.00d Basement - 1 - Slab Casting - 97.10lvl - Pour
A6108 Basement - 1 - Slab Casting - 97.10lvl - Pour - 5 28.00d 15-Jul-19 09:00 AM 11-Aug-19 06:00 PM 0% 0.00d Basement - 1 - Slab Casting - 97.10lvl - Pou
A6109 Retaining Wall 2nd Lift - 100.60lvl 18.00d 26-Jul-19 09:00 AM 12-Aug-19 06:00 PM 0% 0.00d Retaining Wall 2nd Lift - 100.60lvl
A6112 Retaining Wall Bacfilling 15.00d 24-Jun-19 09:00 AM 08-Jul-19 06:00 PM 0% 0.00d Retaining Wall Bacfilling
SUPER STRUCTURE 230.00d 31-Jul-19 09:00 AM 17-Apr-20 06:00 PM 0% 0.00d
GROUND FLOOR 101.20 Lvl & PODIUM -1 30.00d 31-Jul-19 09:00 AM 29-Aug-19 06:00 PM 0% 0.00d 25-Sep-19 06:00 PM, GROUND F
A4579 Pour - 1 18.00d 31-Jul-19 09:00 AM 17-Aug-19 06:00 PM 0% 0.00d Pour - 1
A4580 Pour - 2 18.00d 03-Aug-19 09:00 AM 20-Aug-19 06:00 PM 0% 0.00d Pour - 2
A4581 Pour - 3 18.00d 06-Aug-19 09:00 AM 23-Aug-19 06:00 PM 0% 0.00d Pour - 3

Project Baseline Bar Remaining Work Milestone Page 2 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation
PROJECT 7 ACRES - TRACKING Classic Schedule Layout 12-Jul-19 09:37 AM
Activity ID Activity Name Original BL Project Start BL Project Finish Actual Start Actual Finish Duration % Variance - BL 2019
Duration Complete Project Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A4582 Pour - 4 18.00d 09-Aug-19 09:00 AM 26-Aug-19 06:00 PM 0% 0.00d Pour - 4
A4642 Pour - 5 18.00d 12-Aug-19 09:00 AM 29-Aug-19 06:00 PM 0% 0.00d Pour - 5
1st FLOOR 104.20 Lvl 29.00d 18-Aug-19 09:00 AM 21-Sep-19 06:00 PM 0% 0.00d 21-Oct-19 06:00 PM, 1st
A7743 Pour - 1 17.00d 18-Aug-19 09:00 AM 03-Sep-19 06:00 PM 0% 0.00d Pour - 1
A7744 Pour - 2 17.00d 21-Aug-19 09:00 AM 06-Sep-19 06:00 PM 0% 0.00d Pour - 2
A7745 Pour - 3 17.00d 24-Aug-19 09:00 AM 12-Sep-19 06:00 PM 0% 0.00d Pour - 3
A7746 Pour - 4 17.00d 27-Aug-19 09:00 AM 15-Sep-19 06:00 PM 0% 0.00d Pour - 4
A7747 Pour - 5 17.00d 30-Aug-19 09:00 AM 21-Sep-19 06:00 PM 0% 0.00d Pour - 5
2nd FLOOR 107.20 Lvl 23.00d 04-Sep-19 09:00 AM 11-Oct-19 06:00 PM 0% 0.00d 04-Nov-19 06:00 PM
A7748 Pour - 1 15.00d 04-Sep-19 09:00 AM 24-Sep-19 06:00 PM 0% 0.00d Pour - 1
A7749 Pour - 2 15.00d 06-Sep-19 09:00 AM 26-Sep-19 06:00 PM 0% 0.00d Pour - 2
A7750 Pour - 3 15.00d 11-Sep-19 09:00 AM 28-Sep-19 06:00 PM 0% 0.00d Pour - 3
A7751 Pour - 4 15.00d 13-Sep-19 09:00 AM 09-Oct-19 06:00 PM 0% 0.00d Pour - 4
A7752 Pour - 5 15.00d 15-Sep-19 09:00 AM 11-Oct-19 06:00 PM 0% 0.00d Pour - 5
3rd FLOOR 110.20 Lvl 23.00d 25-Sep-19 09:00 AM 29-Oct-19 06:00 PM 0% 0.00d 19-Nov-19 06:
4th FLOOR 113.20 Lvl 23.00d 19-Oct-19 09:00 AM 13-Nov-19 06:00 PM 0% 0.00d 04-Dec-1
5th FLOOR 116.20 Lvl 23.00d 06-Nov-19 09:00 AM 28-Nov-19 06:00 PM 0% 0.00d 19-
6th FLOOR 119.20 Lvl 23.00d 21-Nov-19 09:00 AM 13-Dec-19 06:00 PM 0% 0.00d
7th FLOOR 122.20 Lvl 23.00d 06-Dec-19 09:00 AM 30-Dec-19 06:00 PM 0% 0.00d
8th FLOOR 125.20 Lvl 23.00d 21-Dec-19 09:00 AM 19-Jan-20 06:00 PM 0% 0.00d
9th FLOOR 128.20 Lvl 23.00d 09-Jan-20 09:00 AM 04-Feb-20 06:00 PM 0% 0.00d
10th FLOOR 131.20 Lvl 23.00d 28-Jan-20 09:00 AM 19-Feb-20 06:00 PM 0% 0.00d
11th FLOOR 134.20 Lvl 23.00d 12-Feb-20 09:00 AM 06-Mar-20 06:00 PM 0% 0.00d
12th FLOOR 137.20 Lvl 23.00d 28-Feb-20 09:00 AM 26-Mar-20 06:00 PM 0% 0.00d
TERRACE FLOOR 140.20 Lvl 23.00d 17-Mar-20 09:00 AM 10-Apr-20 06:00 PM 0% 0.00d
STAIRCASE, LIFT MACHINE ROOM & OVER HEAD TANKS 15.00d 03-Apr-20 09:00 AM 17-Apr-20 06:00 PM 0% 0.00d
PODIUM 97.00d 11-Apr-20 09:00 AM 05-Aug-20 06:00 PM 0% 0.00d
FINISHES - FIRST FIX 440.00d 01-Dec-18 09:00 AM 22-Oct-20 06:00 PM 0% 200.00d
EXTERNAL PLASTERING 30.00d 18-Mar-20 09:00 AM 18-Apr-20 06:00 PM 0% 0.00d
LIFTS 30.00d 19-Apr-20 09:00 AM 07-Jun-20 06:00 PM 0% 0.00d
FINISHES - SECOND FIX 202.00d 11-Apr-20 09:00 AM 18-Nov-20 06:00 PM 0% 0.00d
EXTERNAL PAINTING 10.00d 19-Apr-20 09:00 AM 18-May-20 06:00 PM 0% 0.00d
SNAGS & HANDOVER 7.00d 19-Nov-20 09:00 AM 25-Nov-20 06:00 PM 0% 0.00d
AMENITIES BLOCK 384.00d 01-Dec-18 09:00 AM 19-May-20 06:00 PM 0% 100.00d
PHASE - 2 - BLOCK D, E & F 633.00d 01-Dec-18 09:00 AM 23-Jan-21 06:00 PM 0% 100.00d

PHASR - 3 - PACKAGES COMMON TO ALL 716.00d 01-Dec-18 09:00 AM 16-Apr-21 06:00 PM 0% 100.00d

Project Baseline Bar Remaining Work Milestone Page 3 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work Summary © Oracle Corporation