Professional Documents
Culture Documents
S.No Description Format No Rev Remarks
S.No Description Format No Rev Remarks
Area / Location :
Not
S.No Description Satisfied NA Remarks
Satisfied
A Checks Before concreting
1 Marking done as per drawing
2 Loose strata/material removed
3 Level marks provided as per specified thick for PCC
Dewatering of area done before concrete placement
4
starts & area kept dry till initials setting
5 Pcc / Plum concrete surface levelled (horizontal)
6 Formwork checked for dimensions and level, supports
7 Ensure for Vibrator if thickness of PCC is more than 150mm
B Checks During Concreting (RMC)
8 Certified concrete mix design report available
9 Batch sheet corelated with Approved Mix design report
Concrete placement done within initial setting time (In
10
cast of RMC)
11 workability checked ( slump) and Cubes are cast
C Checks for After Concreting
12 Levels of the finished PCC top checked
13 Curing done for 7 days
Comments
During Execution
Post Completion
Location/grid
Description of item
Quantity of Concrete
Date :
Not
S. No Description Of Item Satisfied NA Remarks
Satified
A REINFORCEMENT
1 Check reinforcement dia as per detail
Check spacing as per detail in both directions / Number of bars as per structural
2
details
7 Check Whether the Proper supports are provided for the Reinforcement
B SHUTTERING
4 Check level/Height
Comments:-
CHABBRA'S
Location of Dimensions of Plinth beam height of UPRNNL
S.No Date Footing top Quantity ASSOSIATE Remarks
Pedestal pedestal Bottom pedestal Representative
Representative
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Format No : P7A/QA/CL/004
SHUTTERING & REINFORCEMENT CHECK LIST - Retaining Wall / Lift Wall
Project PROJECT 7 ACRES
Contractor
Ref Drg No.
Location/grid
B REINFORCEMENT
13 Check for the reinforcement dia as per drawing
26 Check for the Arrangement fo the curing and Marking of the date
Description of item
PLINTH BEAM - REINFORCEMENT,SHUTTERING & CONCRETING
Quantity of Concrete
Date of Checking
Not
S. No Description Of Item Satisfied NA Remarks
Satified
A REINFORCEMENT
1 Check reinforcement dia as per detail
2 Number of bars as per structural details - Bottom Extra & Top Extra
3 Check whether Sufficient cover provided
Have additional rings/stirrups provided above the Beam top (Master
4
Ring)
5 Check whether reinforcement tied properly
6 Check for the plumb of the Verticals above the Beam
7 Check Whether the Proper supports are provided for the Reinforcement
B SHUTTERING
Location/grid
Description of item
4 Check level/Height
B REINFORCEMENT
14 Check for the reinforcement dia as per drawing
19 Check Whether the sufficient bearing provided for beam and slab reinforcement
28 Check for the Dimensions of the column on the Top, Middle and Bottom
29 Check for the Arrangement for the curing and Marking of the date
Description of item
SHUTTERING - SLAB
Quantity of Concrete
Date of Checking
S.No Description Of Item Frontline PSA Remarks
1 Check Whether proper access provided
Comments:-
Description of item
REINFORCEMENT - SLAB
11
B Postpour Check
Comments :
Not
Sl No DESCRIPTION Satisfied NA REMARKS
Satified
11 Checked and ensured all the lintels/lofts been completed & hacked
properly?
12 Checked and ensured switch boxes are covered by dry
sand/thermocol sheets?
13 Checked and ensured PVC rings are fixed at electrical junctions
ACTIVITY : WOODWORK
Project : Checklist No : P7A/QA/CL/012
Location :
A PRE-EXECUTION CHECKS
1
Ensured the materials brought to site are tested
as per ITP.
2 Is the availability of required tools & materials
ensured at site?
3 Checked and ensured Door and window
clearance is done and approved?
Checked and ensured the shutters and
4
architraves are free from
bend,warpage,scratches and chipped edges prior
Checked and ensured the colour of the shutters
5 to use?
and architraves are matching?
B CHECKS DURING EXECUTION
10
Checked and ensured foam is filled from one side
till it reaches the other side?
11
Checked and ensured the frame is cleaned prior
to architrave placing?
Checked and ensured the architrave is fixed to
12
the frames using headless nails?
Checked and ensured the hinges location is
13
matched with the shutter and frame?
C POST-EXECUTION CHECKS
Dwg No : Date
Note : Please þappropriate box as per requirements
Not
S.No Description Satisfy NA Remarks
Satisfy
1 Latest shop drawing available at site
2 Work executed are as per the shop drawing
3 Consultant drawings available at site for
reference
Conduits and accessories used are as per
4
specifications
All the conduits laid properly tied with
5
binding wire
Is the proper space maintained between 2
6 conduits for easy flow of concrete.
Are all the conduits joints sealed with
7
approved solvent.
Are all the fan box, junction boxes,drops are
8 covered with thermocoal/Masking tape.
Comments :
FL Representative PSA
Representative
Checklist for Painting works
Checklist No : PSA/QA/CL/014
Project :
Location :
Dwg No : Date
Note : Please þappropriate box as per requirements
Not
S.No Description Approved
Approved
Remarks