Professional Documents
Culture Documents
Draft TOR Dankuni Chanditala 02.11.2016
Draft TOR Dankuni Chanditala 02.11.2016
1. General
1.1 West Bengal Highway Development Corporation Limited (WBHDCL) has
decided to upgrade the Kalyani Expressway West Bengal to at least four
lane standards.
1.2 WBHDCL will be the employer and executing agency for the consultancy
services and the standards of output required from the appointed
consultants are of best practices both in terms of quality and adherence
to the agreed time schedule.
2. Background
2.1 The alignment of Dankuni – Chanditala Road having total length of 5.00
km from the starting point on NH -2 and ends at Chanditala from where
the Chanditala – Champadanga road is started. The part of the project
stretch consists of two parts from (i) Dankuni on NH 2 to the meeting
point of the SH 15 (started from NH-6 at Eksara) at Kalipur at a distance
of 2.00 km of the project road and thereafter (ii) it follows SH 15 upto
Chanditala at 5.00 km and which is the end point of the project stretch.
3. Objective
3.1 The main objective of the consultancy service is to establish the
technical, environmental and economical viability of the project and
prepare detailed project reports and bid documents for civil works for
upgrading the existing road to 2 lane configuration (strengthening
and/or little widening as far as possible).
0
3.2 The Detailed Project Report would inter-alia include detailed highway
design, design of pavement and overlay with options for flexible and
rigid pavements, and cross drainage structures and quantities of
various items, detailed working drawings, detailed cost estimates,
economic viability analyses, environmental impact assessment, as
appropriate and p r e p a r a t i o n o f b i d d o c u m e n t required for a
competitive bidding.
4. Scope of Services
4.1 As far as possible, the widening/improvement work to 2 lane shall be
within the existing right of way avoiding land acquisition, alignment
corrections, improvement of intersections may be considered necessary
and as far as possible as practicable and t o t h e cost effective.
4.2 The general scope of services is given in the sections that follow.
However, the entire scope of services would, inter-alia, include the items
mentioned TOR. The Consultant will also make suitable proposals for
improvement of the existing road to 2 lane and strengthening of the
carriageways, as required at the appropriate time to maintain the level
of service over the design period.
4.3 All ready to implement ‘good for construction’ drawings shall be prepared.
4.4 Wherever required, consultant will liaise with concerned authorities and
arrange all clarifications. Approval of all drawings including GAD and
detail engineering drawings will have to be obtained by the consultant
from the Irrigation department. Consultant will incorporate i n the
estimates c o s t for shifting of utilities of all types involved and the
estimate shall have to be obtained from concerned local authorities.
4.5 Consultant shall obtain all types of necessary clearances required for
implementation of the project on the ground from the concerned
Authorities. WBHDC shall provide the necessary supporting letters and
any official fees as per the demand note issued by such concerned
authorities from whom the clearances are being sought to enable
implementation.
5. General
5.1 Primary Tasks
General Scope of Services shall cover but be not limited to the following
major tasks
i. Review of all available reports and published information about the
project road and the project influence area;
ii. Improvement proposal to upgrade the entire stretch to 2 -lane
configuration will have to be done considering the utilization of
partially completed work in a cost effective manner.
iii. Detailed reconnaissance;
2
iv. Identification of possible improvements in the existing
alignment, and other considerations and recommendations
regarding most appropriate option;
v. Traffic studies including traffic surveys and Axle load survey and
forecasting traffic demand for next thirty years, analysis of
increment in traffic due to proposed connection.
vi. Inventory and condition surveys for road;
vii. Inventory and condition surveys for existing cross-drainage
structures and drainage provisions;
viii. Detailed topographic surveys using Total Stations and GPS;
ix. Pavement investigations;
x. sub-grade characteristics and strength: investigation of sub-grade
and sub- soil characteristics and strength r e q u i r e d for road
and embankment design.
xi. Identification of sources of construction materials;
xii. Detailed design of road geometrics, its x-sections, horizontal and
vertical alignment and design of embankment of height m o re
than 6m an d also in poor soil conditions an d w h ere den sit y
consideration require, even for lesser height of embankment.
Detailed design of cross-drainage structures wherever required,
preparation of GAD and construction drawings,
xiii. Identification of the type and the design of intersections if feasible
xiv. within the existing ROW;
Design of complete drainage system, wherever required, and
xv. Project costing;
xvi. Economic analyses;
xvii. Contract packaging and implementation schedule.
xviii Strip plan indicating the scheme for carriageway widening,
location of all existing utility services (both over- and underground)
and the scheme for their relocation, trees to be
felled and planted and reports, documents and drawings,
arrangement of estimates for cutting of trees and shifting of
utilities from the concerned department;
xix. Preparation of detailed project report which shall include cost
estimate, approved construction drawings, rate analysis, detailed bill
of quantities, bid documents for execution of civil works through
budgeting resources.
xx. Vetting of all structural design & pavement design from IIT
Kharagpur / IIEST Shibpur.
5.2 Considering the existing ground reality the scope of service has been
identified and summarized. However the scope of service are not limited to
this guideline but will be finalized in consultation with WBHDCL as per
requirement of IRC codal provision.
3
5.3 Standards and Codes of Practices
1. All activities related to field studies, design and documentation
shall be done as per the latest guidelines/ circulars of MoRT&H
and relevant publications of the Indian Roads Congress (IRC) and
Bureau of Indian Standards (BIS). For aspects not covered by IRC
and BIS, international standard practices, such as, British and
American S t a n d a r d s may be adopted. The Consultants,
upon award of the Contract, may finalise this in consultation
with WBHDCL and reflect the same in the inception report.
Consultant should also look at international best practices and
try to adopt them wherever there is scope for value addition.
i. Climate;
ii. road inventory
iii road condition, year of original construction, year and
type of major maintenance/rehabilitation works;
iv. condition of existing bridge / ROB and cross-drainage
structures;
4
5.5. Traffic Surveys
All traffic surveys and studies will be completed in feasibility studies.
5.5.1 Number and Location of Survey Stations
1. The type of traffic surveys and the minimum number of
survey stations shall normally be as under, unless otherwise
specifically mentioned.
Minimum Number of
Sl. No. Description
Survey Stations
1. Classified Traffic Volume Count 2 (7 days)
5
Bus Mini Bus
Standard Bus
LCV LCV-Passenger LCV-
Freight
Truck MCV : 2-Axle Rigid Chassis
HCV : 3-Axle Rigid Chassis
MAV Semi Articulated
Articulated
6
movement of traffic shall be furnished by the Consultant.
2. The methodology for the surveys shall be as per IRC: SP: 41-
1994. The details including location and duration of surveys shall be
finalized in consultation with WBHDCL officials.
3. The data derived from the survey shall be analysed to identify
requirements of suitable remedial measures, such as construction of
underpasses, fly-overs, interchanges, grade-separated intersections
along the project road alignment. Intersections with high traffic
volume requiring special treatments either presently or in future shall
be identified.
The axle load surveys shall normally be done using axle load
pads The location(s) of count station(s) and the survey
methodology including the data formats and the instrument
type to be used shall be finalised before taking up the axle
load surveys.
7
segregation of local traffic, smooth flow of through traffic and
traffic safety. These measures would include the provision of
bypasses, under-passes, fly-overs, interchanges, grade-separated
intersections and service roads.
f. The traffic forecasts shall also be made for both diverted and
generated traffic.
g. Overall traffic forecast thus made shall form the basis for the
design of each pavement type and other facilities/ancillary works.
9
utilised for planning and programming the detailed surveys and
investigations. All field studies including the traffic surveys should
be taken up on the basis of information derived from the
reconnaissance surveys.
10
than
0.3 metre) oil and gas lines etc. falling within the extent
of survey.
11
cover the following:
i. Longitudinal section levels along final centre line at every 25 m
interval, at the locations of curve points, small streams,
intersections and at the locations of change in elevation.
ii. Cross sections at every 50 m interval in full extent of survey
covering sufficient number of spot levels on existing
carriageway and adjacent ground for profile correction
course and earth work calculations. Cross sections shall be
taken at closer interval at curves.
iii. Longitudinal section for cross roads for length adequate for
design and quantity estimation purposes.
iv. Longitudinal and cross sections for major and minor streams as
per recommendations contained in IRC Special Publication No.
13 (Guidelines for the Design of Small Bridges and Culverts)
and IRC:5-1998 (“Standard Specifications & Code of Practice
for Road Bridges, Section 1 - General Features of Design”).
12
1. Detailed road inventory surveys shall be carried out to collect
details of all existing road and pavement features along the
existing road sections. The inventory data shall include but not
limited to the following:
i. terrain (flat, rolling, mountainous);
ii. land-use (agricultural, commercial, forest, residential etc )
@ every kilometer;
iii. carriageway width, surfacing type @ every 500m and
every change of feature whichever is earlier;
iv. shoulder surfacing type and width @ every 500m and
every change of feature whichever is earlier;
v. sub-grade / local soil type (textural classification) @ every 500m
and every change of feature whichever is earlier;
vi. horizontal curve; vertical curve
vii. road intersection type and details, at every
occurrence;
viii. retaining structures and details, at every occurrence;
ix. location of water bodies (lakes and reservoirs), at
every occurrence; and,
x. height of embankment or depth of cut @ every 200m and
every change of feature whichever is earlier.
xi. land width i.e. ROW
xii. culverts, bridges and other structures (type, size, span
arrangement and location)
xiii. Roadside arboriculture
xiv. Existing utility services on either side within ROW.
xv. General drainage conditions
xvi. Design speed of existing road
xvii. Inventory of all road sides facilities for the public including
educational, health, communication facilities and road user
based facilities such as tea shops, dhaba, vehicle service shops
etc
1. Pavement Composition
i. The data concerning the pavement composition may be
already available with the WBHDCL. However, the
consultants shall make trial pits to ascertain the pavement
composition. The test pit interval will be as per Para 4 below.
ii. For each test pit, the following information shall be recorded:
• test pit reference (Identification number, location):
• pavement composition (material type and thickness); and
• subgrade type (textural classification) and condition
(dry, wet)
2. Road and Pavement Condition Surveys
13
i. Detailed field studies shall be carried out to collect road
and pavement surface conditions. The data should generally
cover:
• pavement condition (surface distress type and extent);
• shoulder condition;
• embankment condition; and
• drainage condition
Pavement
Cracking (narrow and wide cracking), % of pavement area
affected;
Ravelling, % of pavement area affected;
Potholing, % of pavement area affected;
Edge break, length (m); and,
Rut depth, mm
Shoulder
Unpaved: material loss, rut depth and corrugation,
Edge drop, mm.
Embankment
General condition; and
Extent of slope erosion
The data obtained from the condition surveys should be analysed and
the road segments of more or less equal performance may be
identified using the criteria given in IRC: 81-1997.
15
whichever is more. A minimum of three samples should be
tested corresponding to each homogenous segment.
16
3. The testing for subgrade soil shall include:
i. in-situ density and moisture content at each test pit
ii. field CBR using DCP at each test
pit
iii. characterization (grain size and Atterberg limits) at each test
pit and,
iv. laboratory moisture-density characteristics (modified AASHTO
compaction);
v. laboratory CBR (unsoaked and 4-day soak compacted at
three energy levels) and swell.
4. For problematic soils, the testing shall be more rigorous. The
characteristics with regard to permeability and consolidation shall
also be determined for these soils. The frequency of sampling
and testing of these soils shall be finalised in consultation with
the WBHDCL officers after the problematic soil types are identified
along the road sections.
5. The laboratory for testing of material should be got approved
from WBHDCL before start of work.
17
available past records, local inquiries and visible signs, if any, on
18
the structural components and embankments. Local inquiries shall
also be made with regard to the road sections getting
overtopped during heavy rains.
19
5.8 Detailed Design of Road and Pavements, Bridges and Structures
5.8.1General
The Consultants are to carryout detailed designs and prepare working
drawings for the following:
i. high speed highway with divided carriageway configuration
complete in all respects with service roads at appropriate
locations;
ii. design of pavement for the additional lanes and overlay for the
existing road, paved shoulders, medians, verges;
iii. at-grade and grade-separated intersections, interchanges (if required);
iv. prepare alignment plans, longitudinal sections and cross-sections
@ 50m intervals;
v. designs for road furniture and road safety/traffic control features;
vi. designs and drawings for service road/under passes/overpass /
cattle passes tree planting/fencing at locations where necessary /
required
viii. drainage design showing location of turnouts, out falling structures,
separate drawings sheet for each 5 km. stretch.
ix. bridges and structures rehabilitation plan with design and drawings
20
as poor geometric features, pavement condition etc.) of accidents
should be investigated into and suitable cost- effective remedial
measures suggested for implementation.
4) The detailed design for geometric elements shall cover, but not
be limited to the following major aspects:
i. horizontal alignment;
ii. longitudinal profile;
iii. cross-sectional elements, including refuge lane (50m) at every
2kms.
iv. junctions, intersections and interchanges;
21
account the strength of the existing pavement vis-à-vis the
remaining life. The overlay thickness requirements shall be
worked out for each road segment homogenous with respect
to condition, strength and sub-grade characteristics. The
rehabilitation provisions should also include the provision of
regulating layer. For existing pavement with acceptable levels
of cracking, provision of a crack inhibiting layer should also be
included.
6. The pavement design task shall also cover working out the
maintenance and strengthening requirements and periodicity and
timing of such treatments.
5.8.5 Design of Embankments
1. The embankments design should provide for maximum utilization
of locally available materials consistent with economy. Use of
fly ash wherever available with in economical leads must
be considered. In accordance with Government instructions, use
of fly ash within 100 km from Thermal Power Stations is
mandatory.
2. The Consultants shall carry out detailed analysis and design for
all embankments of height greater that 6 m based on relevant IRC
publications.
3. The design of embankments should include the requirements for
protection works and traffic safety features
Drainage System
a) The requirement of roadside drainage system and the integration of
the same with proposed cross-drainage system shall be worked out for
the entire length of the project road section.
22
The Consultants shall work out appropriate plan for planting of trees
(specifying type of plantation), horticulture, on the surplus land of the
right-of-way if there any with a view to beautify the highway and
making the environment along the highway pleasing. The existing trees /
plants shall be retained to the extent possible.
Miscellaneous works
1. The Consultants shall make suitable designs and
layout for miscellaneous works including bus bays,
telecommunication facilities etc. wherever appropriate.
2. The Consultants shall prepare the detailed scheme and lay out
plan for the works mentioned in Para 1.
3. The Consultants shall prepare detailed plan for the traffic
management and safety during the construction period.
5.9 Environment
The consultant shall assess the details of felling of trees of different type of
girth within the periphery of the proposed improvement and widening of the
road. He / they will submit the value estimate of such trees based on realistic
rates obtainable from concerned district forest office. Determination of areas
for sufficient number of tree plantation as per survey for areas within the
ROW in lieu of the number of trees felling within the proposed improvement
and widening of the road to be done by the consultant.
The consultant shall coordinate with respective Government departments,
Panchayats & Zilla Parishads and secure approval of tree cutting from forest /
environment department and as well as from Panchayats & Zilla Parishads.
The consultant shall traverse the total area within the periphery of the road
and analyze criteria to include environment; social, technical / design
alignment alternatives within the existing ROW, bypass road configuration
alternatives and other engineering alternatives within the project area.
The environment plan shall be coordinate with the engineering design for
tree planting, pond protection, road side landscaping measures and on
median verge.
Engineering details and appropriate reference to engineering drawings where
necessary for wells / hand pumps / water pipe lines / water taps to be
identified for relocating or enhancement, water bodies for enhancement
proposed bus bays, major & minor intersections to be identified for
enhancements / provisions.
Utility relocation plan – this would clearly show within existing ROW and
pertinent topographic details including buildings, major trees, fencings and
other installations such as water-mains, telephone, electric poles and lines,
transformers and authorized hoardings and suggest relocation of services
along with their crossings at designated locations as required and as
prepared necessary details for submission to the respective service
departments.
23
(considering designs and mass haul diagram) and project cost for
the entire project (civil packages wise), including the cost of
environmental and social safeguards proposed based on
MORT&H’s Standard Data Book and market rate for the inputs.
The estimation of quantities shall be based on detailed design
of various components of the projects. The estimation of
each civil work Package as defined in this TOR.
2. The Consultants shall make detailed analysis for computing the unit
rates for the different items of works. The unit rate analysis shall
duly take into account the various inputs and their basic rates,
suggested location of plants and respective lead distances for
mechanized construction. The unit rate for each item of works
shall be worked out in terms of manpower, machinery and
materials.
3. The project cost estimates so prepared are to be checked against
rates for similar on-going works in West Bengal under
PWD/MORT&H/NHAI sector projects.
24
out below. All the survey and design work should commence without
waiting for feasibility study to be completed.
Time schedule in respect of all such stages has been indicated in the
next para. Consultant shall be required to complete, to the satisfaction
of the Authority, all the different stages of study within the time frame
indicated in the schedule of submission in para 10 pertaining to Reports
and Documents for becoming eligible for payment for any part of the next
stage.
25
STAGE 1
i. Project appreciation;
26
STAGE 2:
D. The strip plans shall clearly indicate the scheme for widening if
there be any. The views and suggestions of the concerned State
PWDs should be duly taken into account while working out the
widening scheme (left, right or symmetrical). The widening
scheme shall be finalised in consultation with WBHDCL.
E. Kilometre-wise Strip Plans for each section (Package) shall be
prepared separately for each concerned agency and suggested by
WBHDCL.
Re po r ts
i. Vo l ume - I , Ma i n Re po r t: This report will present the project
background, details of surveys and investigations carried out,
analysis
and interpretation of survey and investigation data, traffic studies
and demand forecasts, designs, cost estimation, environmental
aspects,
economic and commercial analyses and conclusions. The report shall
include Executive Summary giving brief accounts of the findings of
the study and recommendations.
The Report shall also include maps, charts and diagrams showing
locations and details of existing features and the essential features
of improvement and upgrading.
The Report shall also include updated cost estimates and updated
economic analysis.
The basic data (including its summary) obtained from the field
studies and investigations and input data used for the preliminary
design shall be submitted in a separate volume as an Appendix to Main
Report.
The detailed design for all features should be carried out as per the
requirements of the Design Standards for the project. However,
there may be situations wherein it has not been possible to strictly
adhere to the design standards due to the existing site conditions,
restrictions and other considerations. The report should clearly
bring out the details of these aspect and the standards adopted.
viii. Vo l ume - V III, D r awi n g Vo l ume : All drawings forming part of this
volume shall be ‘good for construction’ drawings. All plan and
profile drawings will be prepared in scale 1:250V and 1:2500H
scale to cover one km in one sheet. In addition this volume will
containing ‘good for construction’ drawings for the following:
a. Location Map
b. Horizontal Alignment and Longitudinal Profile.
c. Cross-section @ 50m interval along the alignment within ROW
d. Typical Cross-Sections with details of pavement structure.
e. Detailed Working Drawings for individual Culverts and
Cross-Drainage Structures.
f. Detailed Working Drawings for individual Bridges, tunnels and
Structures.
g. Detailed Drawings for Improvement of At-Grade and Grade-
Separated Intersections and Interchanges.
h. Drawings for Road Sign, Markings, Toll Plazas and other
Facilities.
i. Schematic Diagrams (linear chart) indicating but be
not limited to be following:
• Widening scheme;
• Locations of median openings, intersections,
interchanges, underpasses, overpasses, bypasses;
• location of traffic signals, traffic signs, road markings,
safety features; and,
• locations of bus bays, telecommunication facilities, if
any.
Total 100%
After completion of services the final contract amount shall be
worked out on the basis of inputs and services actually carried
out and the payment shall be adjusted accordingly.
SI.
No Key Personnel
3 Traffic Engineer
4 Material Engineer
Note: Consultants have to provide a certificate that all the key personnel as
envisaged in the Contract Agreement have been actually deployed in the
projects.
33
Enclosure-II
i) Educational Qualification
38
Enclosure-II(contd.)
i) Educational Qualification
39
Enclosure-II(contd.)
Traffic Engineer
i) Educational Qualification
41
Enclosure-II (contd.)
Material Engineer
i) Educational Qualification
42
Enclosure-II(contd.)
i) Educational Qualification
43
Enclosure-II (contd.)
i) Educational Qualification
44
Enclosure-III
Schedule for Submission Time of Reports and Documents
deliverable w.e.f Date of Commencement of Consultancy Services
(in days)
Stag No. of
e Activity Time Period for
No. copies assignment
F.S. REPORT
KD2
i) Draft Feasibility Report 4 Progressively upto 45
D.P. REPORT
KD4
i) Draft Detailed Project
Report including LA reports 6 Progressively upto 90
KD5
ii) Final Detailed Project Report including 6 Progressively upto 120
Bid Documents ( within 7 days of receiving
comments from WBHDCL on Draft DPR)
KD6 Good for Construction Drawings for 4 Progressively upto
highway, Bridges, CD Works, Drawings etc 135
including any other
component necessary as per
Bidding Documents.
KD7 Any Clarification, Revisions of drawings, 4 Progressively upto
design etc with hard 150
copy and soft copy required by
WBHDCL or its supervision consultants
during execution, as per site requirement or
rectification of errors in submission of
consultant. This shall include securing
approval of utility shifting plan and tree
cutting from respective Government
Departments and agencies.
45
46
46