MC2 Progress Galian-Timbunan CGP

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 36

LEMBAR PERHITUNGAN LUAS PENAMPANG

PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+100.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 5.587 648.727 1,812.20
2 - 648.722 1,144.02 Sket :
3 (3.527) 648.956 87.08
651.000
4 (3.796) 649.044 1,874.71
5 (9.572) 648.929 134.66
6 (9.985) 648.790 1,127.25 650.000
7 (13.456) 648.518 (619.66)
8 (11.545) 648.531 (1,743.31) 649.000
9 (6.165) 648.316 (161.00)
10 (5.667) 648.175 (1,836.56)
11 - 648.161 (1,326.14) 648.000
12 4.092 648.099 (2,100.99)
13 10.575 648.014 (1,978.85) 647.000
14 16.679 647.807 463.11
15 15.267 648.513 3,140.59
16 5.587 648.727 646.000
17
18 645.000
19 (20.000) (10.000) - 10.000 20.000
20

Luas Penampang 39+100.00 17.12

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+125.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 16.228 648.434 1,873.23
2 10.458 648.723 2,117.46 Sket :
3 3.932 648.853 1,275.73
652.000
4 - 648.895 1,402.59
5 (4.323) 648.888 1,558.94
6 (9.128) 648.892 1,469.47 651.000
7 (13.656) 648.810 18.50
8 (13.711) 648.703 (1,108.05) 650.000
9 (10.295) 648.723 (1,482.01)
10 (5.726) 648.723 (1,857.06)
11 - 648.640 (1,347.55) 649.000
12 4.155 648.493 (611.39)
13 6.038 648.091 (1,733.82) 648.000
14 11.386 647.819 (2,058.98)
15 17.740 647.678 496.25
16 16.228 648.434 647.000
17
18 646.000
19 (20.000) (10.000) - 10.000 20.000
20

Luas Penampang 39+125.00 13.32


LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+150.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 5.227 648.855 1,695.95
2 - 648.918 1,312.11 Sket :
3 (4.044) 649.034 1,171.14
651.000
4 (7.654) 649.217 239.22
5 (8.389) 649.052 2,052.20
6 (14.713) 649.091 300.06 650.000
7 (15.627) 648.634 (1,864.90)
8 (9.876) 648.587 (1,853.04)
9 (4.161) 648.527 (1,349.02) 649.000
10 - 648.412 (952.52)
11 2.938 648.237 (754.90)
12 5.266 648.000 (2,433.52) 648.000
13 12.775 647.769 (1,899.41)
14 18.634 647.468 627.25
15 16.723 648.423 1,860.23 647.000
16 10.991 648.626 1,870.60
17 5.227 648.855
18 646.000
19 (20.000) (10.000) - 10.000 20.000 30.000
20

Luas Penampang 39+150.00 21.44

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+175.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 10.536 648.499 1,305.46
2 6.512 648.629 2,111.99 Sket :
3 - 648.646 2,015.02
651.000
4 (6.213) 648.891 1,306.95
5 (10.241) 648.864 1,551.60
6 (15.022) 648.738 (968.71) 650.000
7 (12.031) 648.561 (1,361.18)
8 (7.831) 648.429 (1,116.47)
9 (4.387) 648.398 (404.10) 649.000
10 (3.139) 648.168 (1,017.27)
11 - 648.148 (368.80)
12 1.138 648.022 (193.64) 648.000
13 1.735 647.654 (1,482.25)
14 6.312 647.544 (1,471.96)
15 10.857 647.412 (1,618.93) 647.000
16 15.856 647.279 (1,078.71)
17 19.187 647.197 479.42
646.000
18 17.727 647.927 2,334.75
(20.000) (10.000) - 10.000 20.000 30.000
19 10.536 648.499
20
Luas Penampang 39+175.00 23.18
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+200.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 12.405 647.516 2,076.91
2 5.993 647.673 1,940.80 Sket :
3 - 647.688 2,014.63
651.000
4 (6.221) 647.865 1,778.55
5 (11.713) 648.023 1,633.83
6 (16.745) 647.783 316.73 650.000
7 (17.716) 647.737 1,127.72
8 (21.144) 646.022 (1,453.77) 649.000
9 (16.646) 646.279 (502.82)
10 (15.093) 646.637 (922.72) 648.000
11 (12.235) 646.726 (2,022.50)
12 (5.973) 646.660 (1,928.89)
13 647.000
- 646.538 (1,521.24)
14 4.712 646.435 (1,574.21)
15 9.588 646.349 (2,163.62) 646.000
16 16.289 646.344 (1,477.33)
17 20.858 646.238 549.64 645.000
18 19.184 647.075 2,197.38
19 12.405 647.516
644.000
20
(30.000) (20.000) (10.000) - 10.000 20.000 30.000

Luas Penampang 39+200.00 69.09

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+225.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 20.046 646.209 2,380.93
2 12.691 646.658 2,402.86 Sket :
3 5.265 646.945 1,703.04
651.000
4 - 646.927 3,132.10
5 (9.683) 646.765 1,359.57 650.000
6 (13.879) 646.630 1,582.05
649.000
7 (18.763) 646.489 436.42
8 (20.093) 646.009 1,041.05 648.000
9 (23.256) 644.292 (1,545.45) 647.000
10 (18.460) 644.490 (918.69)
11 (15.612) 644.808 (809.76) 646.000
12 (13.096) 644.884 (1,985.91) 645.000
13 (6.929) 644.794 (500.06)
14 (5.381) 645.657 (1,735.23) 644.000
15 - 645.692 (1,727.49) 643.000
16 5.357 645.734 (1,690.63)
17 10.593 645.697 (1,970.37) 642.000
18 16.694 645.571 (1,673.32) 641.000
19 21.873 645.376 308.52 (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 20.932 645.822 290.15
21 20.046 646.209
Luas Penampang 39+225.00 79.77
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+250.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 15.646 646.419 1,712.27
2 10.353 646.614 2,391.97 Sket :
3 2.955 646.642 955.41
651.000
4 - 646.638 1,135.82
5 (3.513) 646.417 1,934.84 650.000
6 (9.491) 646.018 2,084.38 649.000
7 (15.938) 646.031 1,551.19
8 648.000
(20.731) 645.920 1,379.19
9 (24.928) 643.821 (1,099.90) 647.000
10 (21.507) 643.868 (1,459.54) 646.000
11 (16.970) 643.954 (2,019.01)
12 (10.691) 643.873 (778.09) 645.000
13 (8.284) 644.844 (1,207.39) 644.000
14 (4.534) 644.919 (1,459.87) 643.000
15 - 644.846 (1,613.66)
16 5.011 644.784 (1,601.45) 642.000
17 9.979 644.861 (1,944.95) 641.000
18 16.009 644.721 (2,331.30)
640.000
19 23.240 644.665 821.00 (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 20.738 645.916 1,649.60
21 15.646 646.419
Luas Penampang 39+250.00 100.50

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+275.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 20.428 645.884 2,260.74


2 13.438 646.224 1,840.73 Sket :
3 7.745 646.410 2,502.31
650.000
4 - 646.175 2,424.77
5 (7.505) 645.832 1,821.08 649.000
6 (13.134) 645.464 1,489.99
648.000
7 (17.743) 645.385 1,459.68
8 (22.252) 645.077 968.42 647.000
9 (25.197) 643.605 (614.96) 646.000
10 (23.282) 643.654 (1,263.75)
11 (19.348) 643.627 (2,358.98) 645.000
12 (12.011) 643.610 (696.18) 644.000
13 (9.862) 644.712 (1,557.59)
14 (5.023) 644.654 (1,616.86) 643.000
15 - 644.578 (1,447.66) 642.000
16 4.498 644.641 (1,684.01)
17 9.722 644.549 (1,630.91) 641.000
18 14.782 644.507 (1,568.79) 640.000
19 19.648 644.412 (1,190.24) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 23.342 644.427 956.19
21 20.428 645.884
Luas Penampang 39+275.00 93.98
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+300.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 20.383 645.719 46.07


2 20.242 645.789 2,210.04 Sket :
3 13.409 646.152 2,258.80
650.000
4 6.418 646.178 2,073.02
5 - 646.002 1,406.73 649.000
6 (4.349) 645.517 2,467.26
7 (11.986) 645.356 1,847.33 648.000
8 (17.698) 644.990 1,432.46
9 (22.130) 644.859 388.32 647.000
10 (23.316) 644.490 756.60
646.000
11 (25.616) 643.340 (1,315.96)
12 (21.522) 643.432 (2,258.18) 645.000
13 (14.503) 643.623 (855.57)
14 (11.856) 644.414 (1,919.38) 644.000
15 (5.894) 644.479 (1,897.32)
16 - 644.492 (1,416.92) 643.000
17 4.397 644.468 (1,564.88)
642.000
18 9.253 644.416 (1,665.73)
19 14.422 644.365 (1,746.18) 641.000
20 19.839 644.238 (946.36)
21 22.775 644.168 320.31 640.000
22 21.802 644.783 467.81 (30.000) (20.000) (10.000) - 10.000 20.000 30.000
23 20.383 645.719
Luas Penampang 39+300.00 88.28

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+325.000 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 20.139 645.653 4.97
2 20.124 645.654 2,588.43 Sket :
3 12.117 646.007 2,343.01
4 4.866 646.158 1,571.05 650.000
5 - 645.724 2,116.04 649.000
6 (6.554) 645.274 2,514.87
7 (14.345) 644.906 2,424.58 648.000
8 (21.862) 644.808 487.61 647.000
9 (23.361) 644.413 746.73
10 (25.637) 643.274 (901.56) 646.000
11 (22.840) 643.419 (2,314.60) 645.000
12 (15.651) 643.579 (587.24)
13 644.000
(13.842) 644.233 (1,459.02)
14 (9.314) 644.302 (1,171.96) 643.000
15 (5.676) 644.296 (1,828.63)
642.000
16 - 644.337 (1,506.46)
17 4.676 644.301 (1,608.61) 641.000
18 9.669 644.254 (1,476.57) 640.000
19 14.252 644.199 (1,692.59) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 19.507 644.205 (1,137.20)
21 23.038 644.204 950.19
22 20.139 645.653
Luas Penampang 39+325.00 63.04
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+350.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 19.285 645.893 2,192.09
2 12.501 646.032 1,978.62 Sket :
3 6.372 645.849 2,057.39
4 - 645.759 1,920.16 650.000
5 (5.947) 645.399 1,839.49
649.000
6 (11.645) 645.147 1,748.62
7 (17.065) 645.100 1,938.67 648.000
8 (23.070) 644.904 779.55
9 (25.445) 643.716 (1,551.16) 647.000
10 (20.631) 643.844 (2,110.48)
11 (14.083) 644.090 (2,605.24) 646.000
12 (5.995) 644.166 (1,930.87) 645.000
13 - 644.159 (1,913.15)
14 5.940 644.157 (3,055.69) 644.000
15 15.427 644.114 (2,437.62)
16 22.994 644.038 1,215.85 643.000
17 19.285 645.893
18 642.000
19 641.000
20 (30.000) (20.000) (10.000) - 10.000 20.000 30.000

Luas Penampang 39+350.00 66.23

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+375.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 21.002 644.847 2,254.62
2 14.036 645.682 2,245.16 Sket :
3 7.085 645.837 2,287.54
4 - 645.741 1,620.49 650.000
5 (5.019) 645.513 2,286.35
649.000
6 (12.101) 645.280 1,622.15
7 (17.134) 645.561 1,810.01 648.000
8 (22.732) 645.201 233.75
9 (23.445) 644.872 592.27 647.000
10 (25.255) 644.134 (2,732.93) 646.000
11 (16.771) 644.174 (2,677.27)
12 (8.459) 644.184 (2,724.45) 645.000
13 - 644.155 (2,403.02)
644.000
14 7.461 644.205 (2,234.19)
15 14.396 644.096 (2,598.14) 643.000
16 22.464 644.116 479.21
17 21.002 644.847 642.000
18
641.000
19
(30.000) (20.000) (10.000) - 10.000 20.000 30.000
20

Luas Penampang 39+375.00 61.54


LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+400.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 12.052 645.784 2,066.88
2 5.654 645.952 1,826.12 Sket :
3 - 645.958 1,699.52
4 (5.262) 645.942 2,209.87 650.000
5 (12.103) 645.781 184.42
649.000
6 (12.667) 645.400 686.34
7 (14.793) 645.356 408.22 648.000
8 (16.065) 645.657 2,337.05
9 (23.295) 645.284 128.02 647.000
10 (23.685) 645.096 521.24
11 (25.274) 644.371 (2,709.15) 646.000
12 (16.868) 644.429 (2,451.53)
645.000
13 (9.258) 644.367 (2,982.78)
14 - 644.368 (2,308.45) 644.000
15 7.165 644.329 (2,497.00)
16 14.915 644.267 (2,304.21) 643.000
17 22.065 644.128 388.86
18 20.878 644.721 2,856.15 642.000
19 12.052 645.784
641.000
20
(30.000) (20.000) (10.000) - 10.000 20.000 30.000

Luas Penampang 39+400.00 59.55

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+425.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 19.657 645.145 2,298.10
2 12.559 646.009 2,012.81 Sket :
3 6.330 646.139 2,045.38
4 - 646.250 1,916.45 649.000
5 (5.931) 646.052 2,163.59
6 (12.628) 645.957 1,449.12 648.000
7 (17.111) 645.765 2,201.19
8 (23.915) 645.263 150.62 647.000
9 (24.373) 645.024 292.11
10 (25.262) 644.588 (2,529.57) 646.000
11 (17.413) 644.572 (3,144.90)
12 (7.653) 644.502 (2,465.92) 645.000
13 - 644.431 (2,510.38)
14 7.791 644.372 (2,254.04) 644.000
15 14.787 644.365 (2,172.09)
16 21.525 644.210 611.84 643.000
17 19.657 645.145
18
642.000
19
(30.000) (20.000) (10.000) - 10.000 20.000 30.000
20

Luas Penampang 39+425.00 64.33


LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+450.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 17.808 645.881 1,739.56
2 12.431 646.246 1,826.50 Sket :
3 6.781 646.384 2,191.71
4 - 646.427 1,647.42 649.000
5 (5.097) 646.174 1,989.94
6 (11.255) 646.029 1,916.94 648.000
7 (17.184) 645.711 1,619.77
8 (22.197) 645.560 653.83 647.000
9 (24.207) 645.107 262.05
10 (25.005) 644.709 (1,557.20)
646.000
11 (20.172) 644.662 (2,345.86)
12 (12.895) 644.688 (2,365.22)
13 (5.558) 644.716 (1,791.52) 645.000
14 - 644.662 (1,878.87)
15 5.829 644.566 (2,638.17) 644.000
16 14.014 644.468 (2,211.10)
17 20.873 644.348 1,003.67 643.000
18 17.808 645.881
19 642.000
20 (30.000) (20.000) (10.000) - 10.000 20.000 30.000

Luas Penampang 39+450.00 63.45

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+475.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 17.897 645.649 1,758.57
2 12.462 646.081 1,975.87 Sket :
3 6.351 646.365 2,052.74
4 - 646.429 1,817.76 649.000
5 (5.624) 646.295 1,972.37
6 (11.726) 646.109 2,232.74 648.000
7 (18.635) 645.980 1,307.33
8 (22.675) 645.717 565.14 647.000
9 (24.395) 644.856 (1,476.65)
10 (19.818) 644.924 (1,912.64) 646.000
11 (13.891) 645.066 (2,523.20)
12 (6.066) 644.976 (1,956.12) 645.000
13 - 644.947 (2,386.63)
14 7.401 644.832 (2,410.15) 644.000
15 14.876 644.808 (1,586.20)
16 19.793 644.701 620.56 643.000
17 17.897 645.649
18
642.000
19
(30.000) (20.000) (10.000) - 10.000 20.000 30.000
20

Luas Penampang 39+475.00 51.48


LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+500.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 15.536 646.642 1,324.59
2 11.431 646.289 1,978.03 Sket :
3 5.313 646.469 1,717.92
649.000
4 - 646.684 1,564.98
5 (4.840) 646.570 1,629.82
6 (9.880) 646.377 2,057.29 648.000
7 (16.244) 646.273 1,675.47
8 (21.425) 646.113 58.63 647.000
9 (21.606) 646.107 579.76
10 (23.368) 645.129 (178.63)
11 (22.823) 645.366 (2,866.96) 646.000
12 (13.946) 645.585 (2,414.60)
13 (6.467) 645.647 (2,087.63) 645.000
14 - 645.625 (1,947.85)
15 6.034 645.532 (2,355.37)
16 13.330 645.378 (1,526.82) 644.000
17 18.062 645.379 826.28
18 15.536 646.642 643.000
19 (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20

Luas Penampang 39+500.00 34.91

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+525.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 - 646.299 1,484.23
2 (4.593) 646.094 425.25 Sket :
3 (5.910) 646.112 (1,908.41)
649.000
4 - 645.877 (1,929.23)
5 5.974 645.922 (2,035.59)
6 12.275 645.718 (1,603.80) 648.000
7 17.240 645.603 43.01
8 17.109 645.669 233.35
9 16.388 645.744 120.96 647.000
10 16.022 646.084 1,163.07
11 12.428 646.341 1,495.40
12 7.793 645.940 2,518.30 646.000
13 - 646.299

14 (12.381) 646.139 (1,752.26) 645.000


15 (6.957) 646.126 1,037.54
16 (10.169) 646.169 1,730.60
17 (15.526) 646.202 1,731.72 644.000
18 (20.884) 646.132 239.65
19 (21.623) 646.054 (305.13)
643.000
20 (20.679) 646.063 (2,681.30)
(30.000) (20.000) (10.000) - 10.000 20.000
21 (12.381) 646.139
Luas Penampang 39+525.00 7.37
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+550.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 17.829 645.120 830.88
2 15.258 645.280 1,338.90 Sket :
3 11.101 644.976 1,583.02
648.000
4 6.189 644.788 1,319.83
5 2.095 644.773 675.63
6 - 644.991 1,710.84 647.000
7 (5.305) 644.755 891.54
8 (8.068) 644.437 (589.50) 646.000
9 (6.239) 644.486 (2,010.61)
10 - 644.530 (1,631.63) 645.000
11 5.063 644.553 (2,308.98)
12 12.228 644.605 (2,181.46)
13 644.000
18.995 644.537 381.16
14 17.829 645.120
643.000
15 (8.571) 644.423 1,361.35
16 (12.797) 644.478 1,795.52 642.000
17 (18.364) 644.226 616.46
18 (20.274) 644.087 (2,579.66)
641.000
19 (12.271) 644.323 (1,192.53)
(30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 (8.571) 644.423
Luas Penampang 39+550.00 10.77

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+575.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (6.068) 643.928 2,206.75
2 (12.926) 644.350 1,698.21 Sket :
3 (18.199) 644.446 2,027.66
648.000
4 (24.489) 644.350 508.60
5 (26.020) 643.107 (1,873.38)
6 (20.200) 643.246 (2,172.01)
7 (13.451) 643.382 (2,285.32) 646.000
8 (6.350) 643.529 (1,735.09)
9 (0.958) 643.615 1,644.15
10 (6.068) 643.928
11 644.000
12
13
14
642.000
15
16
17
18 640.000
19 (40.000) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20

Luas Penampang 39+575.00 19.57


LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+600.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 - 644.463 1,910.19
2 (5.928) 644.353 1,743.06 Sket :
3 (11.337) 644.217 1,479.38
648.000
4 (15.928) 644.114 1,485.70
5 (20.541) 644.108 1,981.30
6 (26.668) 643.322 334.98
7 (27.685) 642.730 (2,521.23) 646.000
8 (19.840) 642.742 (2,257.48)
9 (12.821) 642.921 (2,125.09)
10 (6.210) 642.908 (1,996.48)
644.000
11 - 642.990 (2,098.72)
12 6.528 643.109 (2,661.28)
13 14.804 643.080 (2,030.36)
14 21.119 643.101 426.09 642.000
15 19.815 643.752 2,636.22
16 11.625 643.750 2,785.67
17 2.965 643.446 955.42
640.000
18 - 644.463
(40.000) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
19
Luas Penampang 39+600.00 47.36

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+625.00 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 - 644.362 1,627.01
2 (5.050) 644.314 1,858.58 Sket :
3 (10.818) 644.165 1,880.50
648.000
4 (16.656) 644.131 1,822.79
5 (22.316) 644.143 1,355.44 647.000
6 (26.516) 643.893 910.21
7 (29.286) 642.508 (2,073.39) 646.000
8 (22.834) 642.552 (2,203.82)
9 (15.978) 642.653 (2,322.68) 645.000
10 (8.751) 642.710 (2,812.31)
11 - 642.740 (1,963.57) 644.000
12 6.110 642.688 (2,691.92)
13 14.487 642.682 (2,344.57) 643.000
14 21.781 642.583 435.20
15 20.449 643.249 1,634.98 642.000
16 15.369 643.359 3,009.10
17 641.000
6.013 643.290 1,457.98
(40.000) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
18 1.479 643.170 476.51
19 - 644.362
20

Luas Penampang 39+625.00 56.05


LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+642.506 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 - 644.328 1,548.96
2 (4.808) 644.227 1,184.30 Sket :
3 (8.483) 644.007 222.81
4 648.000
(9.170) 643.631 1,847.98
5 (14.909) 643.395 2,167.60
6 (21.645) 643.309 1,971.53 647.000
7 (27.771) 643.221 276.30
8 (28.612) 642.801 (1,860.55) 646.000
9 (22.822) 642.768 (1,976.27)
10 (16.671) 642.719 (1,966.36) 645.000
11 (10.552) 642.714 (1,801.93)
12 (4.945) 642.730 (1,589.10)
13 644.000
- 642.711 (1,502.02)
14 4.674 642.678 (1,780.62)
15 10.215 642.642 (2,025.73) 643.000
16 16.518 642.556 (1,637.68)
17 21.613 642.478 449.52 642.000
18 20.237 643.166 1,261.97
19 16.316 643.263 2,556.59 641.000
20 8.367 643.256 2,203.87 (40.000) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
21 1.512 643.043 487.11
22 - 644.328
Luas Penampang 39+642.51 38.28

Lokasi Jalan Utama Zona C Periode 26 September - 25 Oktober 2016


Station 39+645.270 No. Item I.2
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (8.829) 643.315 2,211.54
2 (15.702) 643.137 1,882.78 Sket :
3 (21.557) 643.137 2,050.80
4 648.000
(27.935) 643.140 222.69
5 (28.612) 642.801 (1,860.55)
6 (22.822) 642.768 (1,976.27) 647.000
7 (16.671) 642.719 (1,966.36)
8 (10.552) 642.714 (1,801.93) 646.000
9 (4.945) 642.730 (1,589.10)
10 - 642.711 (1,502.02) 645.000
11 4.674 642.678 (1,780.62)
12 10.215 642.642 (2,025.73) 644.000
13 16.518 642.556 (1,637.68)
14 21.613 642.478 447.88 643.000
15 20.242 643.164 1,453.21
16 15.720 643.059 1,811.96 642.000
17 10.081 642.913 1,807.49
18 4.459 642.965 1,433.66
641.000
19 - 643.043 2,538.09
(40.000) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 (7.894) 642.971 299.23
21 (8.829) 643.315
Luas Penampang 39+645.27 19.06
LEMBAR PERHITUNGAN VOLUME
PT. PERENTJANA DJAJA

Lokasi : Jalan Utama Zona C


Pekerjaan : Timbunan
No. Item : I.2
Item Pekerjaan : Borrow Material

LUAS PANJANG VOLUME


NO STATION LUAS (M2) KETERANGAN
RATA-RATA (M2) (M1) (M3)
1 39+075.000 5.85 Sertifikat 1
11.48 25.00 287.08
2 39+100.000 17.12 Sertifikat 2
15.22 25.00 380.49
3 39+125.000 13.32 Sertifikat 2
17.38 25.00 434.49
4 39+150.000 21.44 Sertifikat 2
22.31 25.00 557.69
5 39+175.000 23.18 Sertifikat 2
46.14 25.00 1153.39
6 39+200.000 69.09 Sertifikat 2
74.43 25.00 1860.77
7 39+225.000 79.77 Sertifikat 2
90.13 25.00 2253.28
8 39+250.000 100.50 Sertifikat 2
97.24 25.00 2430.90
9 39+275.000 93.98 Sertifikat 2
91.13 25.00 2278.14
10 39+300.000 88.28 Sertifikat 2
75.66 25.00 1891.45
11 39+325.000 63.04 Sertifikat 2
64.64 25.00 1615.93
12 39+350.000 66.23 Sertifikat 2
63.88 25.00 1597.11
13 39+375.000 61.54 Sertifikat 2
60.54 25.00 1513.60
14 39+400.000 59.55 Sertifikat 2
61.94 25.00 1548.50
15 39+425.000 64.33 Sertifikat 2
63.89 25.00 1597.18
16 39+450.000 63.45 Sertifikat 2
57.47 25.00 1436.63
17 39+475.000 51.48 Sertifikat 2
43.20 25.00 1079.88
18 39+500.000 34.91 Sertifikat 2
21.14 25.00 528.43
19 39+525.000 7.37 Sertifikat 2
9.07 25.00 226.65
20 39+550.000 10.77 Sertifikat 2
15.17 25.00 379.17
21 39+575.000 19.57 Sertifikat 2
33.46 25.00 836.56
22 39+600.000 47.36 Sertifikat 2
51.70 25.00 1292.60
23 39+625.000 56.05 Sertifikat 2
47.17 17.51 825.70
24 39+642.506 38.28 Sertifikat 2
28.67 2.76 79.25
25 39+645.270 19.06 Sertifikat 2
23.32 4.73 110.30
26 39+650.000 27.58 Sertifikat 1

TOTAL VOLUME 28,195.16 M3

Disetujui oleh: Dibuat dan diajukan oleh:


Kontraktor Pelaksana Subkontraktor
Nindya Karya - Jaya Konstruksi, KSO PT Citra Guna Perkasa

Sabir Said, S.T.


Site Engineering Manager
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+750.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 2.106 641.431 675.80


2 - 641.790 1,784.18 Sket :
3 (5.560) 641.820 1,893.56
4 644.000
(11.462) 641.982 1,782.36
5 (17.016) 642.056 1,050.52
6 (20.290) 642.100 (117.53) 643.000
7 (19.839) 639.428 (493.63)
8 (18.293) 639.363 (710.89) 642.000
9 (16.122) 641.206 (1,768.20)
10 (10.602) 641.016 (1,667.08) 641.000
11 (5.400) 640.978 (1,730.51)
12 - 640.928 (1,524.32) 640.000
13 4.757 640.915 (1,567.89)
14 9.650 641.013 (788.72) 639.000
15 12.109 640.915 (1,223.69)
16 15.928 640.917 (9.25) 638.000
17 15.955 640.856 (189.35)
18 16.515 639.600 (744.02) 637.000
19 18.843 639.657 (212.67) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 19.578 642.018 1,263.03
21 15.635 641.758 1,427.86
22 11.178 641.464 1,372.05
23 6.897 641.285 1,536.70
24 2.106 641.431
Luas Penampang 38+750.00 38.31

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+775.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 20.328 642.198 1,212.21


2 16.552 642.179 2,194.32 Sket :
3 9.717 642.140 1,623.53
4 645.000
4.660 642.116 1,496.51
5 - 642.281 1,710.07
6 (5.325) 642.448 2,172.70 644.000
7 (12.090) 642.592 2,058.88
8 (18.499) 642.643 707.06 643.000
9 (20.700) 642.661 5.54
10 (20.700) 642.125 (89.92) 642.000
11 (20.361) 640.297 (792.85)
12 (17.882) 640.219 (612.82) 641.000
13 (16.009) 641.702 (1,799.85)
14 (10.400) 641.727 (1,723.49) 640.000
15 (5.026) 641.568 (1,303.22)
16 (0.962) 641.413 (180.30) 639.000
17 (0.400) 641.424 (256.57)
18 0.400 641.424 (2,966.55) 638.000
19 9.650 641.609 (1,226.62) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 13.471 641.456 (804.49)
21 15.980 641.475 (277.64)
22 16.808 639.964 (959.97)
23 19.808 639.961 (144.16)
24 20.328 642.198
Luas Penampang 38+775.00 42.36
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+800.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 5.897 642.777 1,895.77


2 - 642.962 2,029.83 Sket :
3 (6.314) 643.081 216.29
4 645.000
(6.985) 642.910 1,620.22
5 (12.025) 642.886 1,959.24
6 (18.123) 643.039 828.11 644.000
7 (20.700) 643.087 4.73
8 (20.700) 642.630 (187.80) 643.000
9 (20.030) 639.976 (935.90)
10 (17.107) 640.033 (320.07) 642.000
11 (16.168) 642.322 (1,383.77)
12 (11.860) 642.348 (2,316.60) 641.000
13 (4.644) 642.181 (1,491.16)
14 - 642.189 (1,696.66) 640.000
15 5.284 642.159 (374.06)
16 6.449 642.141 (1,027.59) 639.000
17 9.650 642.205 (1,018.11)
18 12.819 642.078 (1,153.81) 638.000
19 16.413 642.090 (176.23) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
20 16.941 641.271 (1,033.66)
21 20.150 640.711 (23.54)
22 20.275 642.342 1,542.38
23 15.477 642.487 3,079.76
24 5.897 642.777
Luas Penampang 38+800.00 37.35

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+825.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 5.167 643.339 1,662.07


2 - 643.339 1,835.77 Sket :
3 (5.707) 643.430 1,998.20
4 (11.919) 643.532 1,850.48 646.000
5 (17.673) 643.693 973.46
6 (20.700) 643.778 18.89
645.000
7 (20.700) 641.953 (575.48)
8 (18.903) 641.828 (183.77)
9 (18.308) 641.069 (478.70) 644.000
10 (16.819) 641.225 (185.78)
11 (16.281) 642.805 (1,761.51) 643.000
12 (10.801) 642.832 (2,085.85)
13 (4.315) 643.044 (1,387.31)
14 - 643.017 (389.03) 642.000
15 1.210 642.941 (1,418.11)
16 5.621 642.770 (317.09) 641.000
17 6.607 642.740 (977.61)
18 9.650 642.801 (1,075.23)
19 12.993 642.667 (788.47) 640.000
20 15.448 642.706 (127.45)
21 15.814 641.433 (1,119.51) 639.000
22 19.302 641.325 (34.21) (30.000) (20.000) (10.000) - 10.000 20.000 30.000
23 19.457 642.917 1,522.25
24 14.722 642.945 2,400.76
25 7.255 642.989 672.55
26 5.167 643.339
Luas Penampang 38+825.00 29.32
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+850.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (13.652) 643.543 (1,835.13)
2 (7.950) 643.600 (2,015.78) Sket :
3 (1.686) 643.607 (542.45)
4 - 643.474 (480.03)
5 1.492 643.576 (1,395.96) 0
6 (25.000) (20.000) (15.000) (10.000) (5.000).00 - 5.000 10.000 15.000 20.000 25.000
5.830 643.524 (1,059.41) 9
63
7 9.121 643.386 (170.04)
8 9.650 643.397 (688.75)
9 11.790 643.311 (1,034.66)
10 15.005 643.230 (80.49)
11 15.255 643.224 (143.45)
12 15.659 641.452 (1,020.53)
13 18.843 641.537 (19.33)
14 18.922 642.175 14.79
15 18.922 643.738 1,140.14
16 15.377 643.645 1,215.59
17 11.597 643.528 1,715.87
18 6.269 643.788 2,018.15
19 - 643.850 2,314.96
20 (7.191) 644.024 1,717.95
21 (12.526) 644.020 1,328.40
22 (16.653) 644.106 730.33
23 (18.922) 644.153 16.19
24 (18.922) 642.442 (13.73)
25 (18.870) 642.130 (883.38)
26 (16.116) 642.042 (110.46)
27 (15.758) 641.488 (377.38)
28 (14.580) 641.430 (313.03)
29 (13.652) 643.543
Luas Penampang 38+850.00 28.38
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+875.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (14.917) 644.186 (1,266.31)
2 (10.984) 644.121 (2,997.98) Sket :
3 (1.677) 644.224 (540.24)
4 647.000
- 644.289 (1,526.00)
5 4.737 643.963 (973.64)
646.000
6 7.761 643.956 (608.12)
7 9.650 643.994 (245.71)
645.000
8 10.413 643.963 (1,288.83)
9 14.416 643.998 (281.69)
644.000
10 15.252 642.264 (1,051.15)
11 18.525 642.253 (66.00)
643.000
12 18.787 644.200 782.93
13 16.356 644.201 2,169.69
642.000
14 9.620 644.203 2,098.19
15 3.106 644.207 1,000.60 641.000
16 - 644.301 1,678.73
17 (5.211) 644.462 2,134.82 640.000
18 (11.837) 644.571 1,540.06
19 (16.614) 644.486 707.33 639.000
20 (18.808) 644.447 19.04 (25.000) (20.000) (15.000) (10.000) (5.000) - 5.000 10.000 15.000 20.000 25.000
21 (18.808) 642.422 (227.39)
22 (18.099) 642.385 (1,038.33)
23 (14.917) 644.186
Luas Penampang 38+875.00 19.99

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+900.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (14.705) 644.779 (1,873.99)
2 (8.891) 644.727 (1,640.59) Sket :
3 (3.799) 644.527 (1,224.51)
4 648.000
- 644.647 (1,529.75)
5 4.746 644.640 (1,479.77)
647.000
6 9.337 644.640 (1,791.45)
7 14.896 644.710 (208.75) 646.000
8 15.507 643.127 (1,183.02)
9 19.184 643.045 (21.82) 645.000
10 19.273 643.759 13.31
11 19.273 645.140 794.87 644.000
12 16.807 645.074 1,211.25
13 13.049 644.973 2,015.48 643.000
14 6.797 644.865 2,192.38
642.000
15 - 645.101 2,725.87
16 (8.451) 645.123 1,672.72 641.000
17 (13.640) 645.373 1,233.94
18 (17.469) 645.612 580.71 640.000
19 (19.271) 645.724 26.96 (25.000) (20.000) (15.000) (10.000) (5.000) - 5.000 10.000 15.000 20.000 25.000
20 (19.271) 642.926 (1,458.95)
21 (14.722) 642.575 (21.69)
22 (14.705) 644.779
Luas Penampang 38+900.00 33.21
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+925.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (15.451) 645.363 (1,454.96)
2 (10.943) 645.403 (1,740.04) Sket :
3 (5.551) 645.409 (1,791.18)
4 648.000
- 645.355 (1,997.05)
5 6.189 645.377 (1,632.19)
6 11.247 645.366 (1,485.94) 647.000
7 15.851 645.311 (214.06)
8 16.476 643.747 (1,167.58) 646.000
9 20.100 643.612 (158.84)
10 20.668 645.997 381.80 645.000
11 19.485 645.965 283.46
12 18.607 645.942 1,877.16
644.000
13 12.790 645.786 2,499.17
14 5.048 645.682 1,629.95
15 643.000
- 645.781 1,726.50
16 (5.347) 645.750 2,427.41
17 (12.866) 645.858 1,782.44 642.000
18 (18.392) 646.179 255.26
19 (19.183) 646.225 (77.13) 641.000
20 (18.862) 643.440 (1,027.96) (25.000) (20.000) (15.000) (10.000) (5.000) - 5.000 10.000 15.000 20.000 25.000
21 (15.666) 643.413 (84.44)
22 (15.451) 645.363
Luas Penampang 38+925.00 31.78

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+950.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (14.847) 645.994 (2,442.96)
2 (7.281) 645.882 (2,351.37) Sket :
3 - 645.891 (382.04)
4 647.000
1.183 645.863 (1,539.49)
5 5.950 645.730 (357.25)
6 7.057 645.731 (837.17) 646.000
7 9.650 645.783 (387.66)
8 10.850 645.735 (630.59)
645.000
9 12.803 645.737 (774.19)
10 15.199 645.664 (919.88)
11 18.052 645.807 (68.51) 644.000
12 18.270 646.025 1,483.38
13 13.682 646.151 11.78 643.000
14 13.645 646.141 450.11
15 12.253 646.182 1,753.95
16 6.822 646.077 2,203.85 642.000
17 - 646.100 2,309.16
18 (7.148) 646.293 1,866.91 641.000
19 (12.926) 646.358 1,590.36 (25.000) (20.000) (15.000) (10.000) (5.000) - 5.000 10.000 15.000 20.000 25.000
20 (17.848) 646.409 304.21
21 (18.789) 646.416 (108.65)
22 (18.379) 643.861 (681.88)
23 (16.264) 643.969 (472.72)
24 (14.847) 645.994
Luas Penampang 38+950.00 19.34
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 38+975.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (1.422) 647.296 3,517.99
2 (12.292) 647.382 759.76 Sket :
3 (14.641) 647.464 31.14
4 648.000
(14.735) 647.371 96.02
5 (15.025) 647.086 1,305.65
6 (19.062) 647.152 897.79
7 (21.838) 647.197 (112.81)
8 (21.477) 646.837 (1,020.19)
647.000
9 (18.319) 646.724 (1,005.61)
10 (15.206) 646.613 (1,312.84)
11 (11.146) 646.641 (1,875.92)
12 (5.344) 646.643 (1,727.50)
13 - 646.520 (239.72) 646.000
14 0.742 646.578 239.86
15 - 646.896 459.94
16 (1.422) 647.296
17
18 645.000
19 (25.000) (20.000) (15.000) (10.000) (5.000) - 5.000
20

Luas Penampang 38+975.00 13.57

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 39+000.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (2.619) 647.120 1,480.88
2 (7.196) 647.160 1,646.39 Sket :
3 (12.284) 647.157 1,621.51
4 648.000
(17.298) 647.305 1,305.53
5 (21.331) 647.287 (155.76)
6 (20.834) 646.789 (1,399.99)
7 (16.507) 646.865 (2,096.52)
(10.027) 646.947 (1,353.27)
647.000
8 (5.843) 646.918 (1,889.98)
9 - 646.920 (1,164.06)
10 3.599 646.854 (1,956.91)
11 9.650 646.975 (440.26)
12 11.010 646.921 (50.81) 646.000
13 11.167 646.921 206.94
14 10.531 647.124 2,460.03
15 2.929 647.183 947.64
16 - 647.072 847.34
17 (2.619) 647.120 645.000
18 (25.000) (20.000) (15.000) (10.000) (5.000) - 5.000 10.000 15.000
19

Luas Penampang 39+000.00 8.71


LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Agustus - 25 September 2016


Station 39+025.00 No. Item I.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (12.896) 647.795 1,886.89
2 (18.724) 647.895 (196.01) Sket :
3 (18.101) 647.272 (1,657.35)
4 (12.988) 647.577 (1,098.06)
5 (9.596) 647.541 (1,739.92) 0 0
(20.000) (15.000) (10.000) (5.000)
6 .0 - 5.000 10.000
6 (4.220) 647.401 (1,280.61) 64
7 (0.264) 647.386 (99.56)
8 0.044 647.386 (1,092.48)
9 3.419 647.463 1,106.81
10 - 647.468 1,769.21
11 (5.465) 647.522 2,405.12
12 (12.896) 647.795
13
14
15
16
17
18
19
20

Luas Penampang 39+025.00 4.04


LEMBAR PERHITUNGAN VOLUME
PT. PERENTJANA DJAJA

Lokasi : Jalan Utama Zona C


Pekerjaan : Galian
No. Item : I.1
Item Pekerjaan : Galian Biasa untuk Timbunan di dalam Rumija Proyek

LUAS PANJANG VOLUME


NO STATION LUAS (M2) KETERANGAN
RATA-RATA (M2) (M1) (M3)
1 38+750.000 38.31 Sertifikat 1
40.34 25.00 1008.44
2 38+775.000 42.36 Sertifikat 1
39.86 25.00 996.40
3 38+800.000 37.35 Sertifikat 1
33.33 25.00 833.32
4 38+825.000 29.32 Sertifikat 1
28.85 25.00 721.18
5 38+850.000 28.38 Sertifikat 1
24.18 25.00 604.62
6 38+875.000 19.99 Sertifikat 1
26.60 25.00 664.97
7 38+900.000 33.21 Sertifikat 1
32.49 25.00 812.34
8 38+925.000 31.78 Sertifikat 1
25.56 25.00 639.03
9 38+950.000 19.34 Sertifikat 1
16.46 25.00 411.42
10 38+975.000 13.57 Sertifikat 1
11.14 25.00 278.49
11 39+000.000 8.71 Sertifikat 1
6.38 25.00 159.39
12 39+025.000 4.04 Sertifikat 1
2.02 25.00 50.55
13 39+050.000 0.00

TOTAL VOLUME 7,180.17 M3

Disetujui oleh: Dibuat dan diajukan oleh:


Kontraktor Pelaksana Subkontraktor
Nindya Karya - Jaya Konstruksi, KSO PT Citra Guna Perkasa

Sabir Said, S.T.


Site Engineering Manager
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi UP Nyamat 1 Periode 26 Agustus - 25 September 2016


Station 00+905.810 No. Item III.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (6.676) 645.553 (244.49)
2 (5.915) 645.173 (1,383.62) Sket : 648.000
3 (1.625) 645.128 (524.20)
4 - 645.168 (429.68)
5 1.332 645.151 (1,330.18) 647.000
6 5.456 645.339 (891.13)
7 8.231 646.931 438.05
8 6.877 646.934 1,847.30 646.000
9 1.166 646.928 176.83
10 0.619 646.755 111.01
11 0.275 645.991 88.83 645.000
12 - 646.017 364.68
13 (1.129) 646.007 418.62
14 (2.425) 645.994 183.18 644.000
15 (2.992) 645.963 111.10
16 (3.335) 645.748 1,079.04
17 (6.676) 645.553 643.000
18
(8.000) (6.000) (4.000) (2.000) - 2.000 4.000 6.000 8.000 10.000 12.000
19
20
Luas Penampang 00+905.810 15.33

Lokasi UP Nyamat 1 Periode 26 Agustus - 25 September 2016


Station 00+925.000 No. Item III.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 8.513 647.759 (474.83)
2 9.993 648.826 1,480.00 Sket : 650.000
3 5.431 648.826 164.46
4 4.924 648.820 11.21 649.000
5 4.885 648.236 488.19
6 3.379 648.264 100.72 648.000
7 3.066 647.827 477.72
8 1.591 647.793 407.13 647.000
9 0.334 647.777 108.18
10 - 647.763 257.49 646.000
11 (0.795) 647.744 154.56
12 645.000
(1.272) 647.731 6.75
13 (1.293) 647.711 321.22
644.000
14 (2.283) 646.777 963.83
15 (5.263) 646.658 1,187.80
643.000
16 (8.937) 646.665 (1,365.44)
17 (4.688) 644.806 (374.69) 642.000
18 (3.526) 644.822 (8.38) (15.000) (10.000) (5.000) - 5.000 10.000 15.000 20.000
19 (3.500) 644.835 (322.46)
20 (2.500) 644.861 (322.46)
21 (1.500) 644.886 (483.69)
22 - 644.925 (483.69)
23 1.500 644.886 (322.46)
24 2.500 644.861 (322.46)
25 3.500 644.835 (1.77)
26 3.505 644.832 (298.76)
27 4.432 644.817 (1,309.23)
28 8.513 647.759
Luas Penampang 00+925.000 38.91
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi UP Nyamat 1 Periode 26 Agustus - 25 September 2016


Station 00+940.670 No. Item III.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 8.883 647.426 (305.41)
2 9.837 648.215 637.51 Sket : 649.000
3 7.869 648.127 647.63
4 5.868 647.918 488.82
5 4.357 647.687 355.83 648.000
6 3.257 647.503 93.93
7 2.967 647.529 419.90 647.000
8 1.670 647.515 85.80
9 1.405 647.519 (0.39)
10 1.405 646.970 454.58 646.000
11 - 647.091 464.93
12 (1.437) 645.009 1,082.61
13 (4.794) 645.062 434.64 645.000
14 (6.141) 645.043 (398.23)
15 (4.900) 644.339 (700.89)
644.000
16 (2.725) 644.407 (282.67)
17 (1.848) 644.403 (112.03)
18 (1.500) 644.412 (483.34) 643.000
19 - 644.451 (290.79)
20 0.902 644.428 (441.92)
21 2.274 644.476 (946.83) 642.000
22 5.212 644.391 (1,174.87) (10.000) (5.000) - 5.000 10.000 15.000
23 8.883 647.426
Luas Penampang 00+940.670 28.82

Lokasi UP Nyamat 1 Periode 26 Agustus - 25 September 2016


Station 00+950.000 No. Item III.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 9.330 646.704 (197.55)
2 9.947 647.138 819.48 Sket : 648.000
3 7.415 647.166 211.81
4 6.749 646.168 169.54
5 6.224 646.144 430.15 647.000
6 4.893 646.190 378.56
7 3.721 646.145 348.62
8 2.641 645.983 834.81
9 0.056 645.944 18.16 646.000
10 - 645.849 197.95
11 (0.613) 644.815 1,128.75
12 (4.114) 644.823 531.96 645.000
13 (5.763) 644.730 (497.36)
14 (4.213) 643.891 (214.81)
15 (3.546) 643.967 (14.94) 644.000
16 (3.500) 643.990 (65.31)
17 (3.297) 643.995 (265.55)
18 (2.473) 644.089 (558.43)
19 (0.739) 644.061 (237.94) 643.000
20 - 644.080 (176.84)
21 0.549 644.066 (684.91)
22 2.676 644.131 (977.43) 642.000
23 5.711 644.160 (1,158.34) (10.000) (5.000) - 5.000 10.000 15.000
24 9.330 646.704
Luas Penampang 00+950.000 20.36
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi UP Nyamat 1 Periode 26 Agustus - 25 September 2016


Station 00+975.000 No. Item III.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 6.255 643.865 668.22
2 4.179 643.791 1,344.79 Sket : 646.000
3 - 643.595 1,643.88
4 (5.108) 644.275 (807.39)
5 (2.594) 643.255 (420.24) 645.000
6 (1.287) 643.154 (347.69)
7 (0.206) 643.072 (65.75)
8 (0.001) 643.077 (69.28)
644.000
9 0.214 643.071 (742.30)
10 2.523 643.237 (864.87)
11 5.213 643.344 (334.09)
12 6.255 643.865 643.000
13
14
15 642.000
16
17
18 641.000
19 (10.000) (8.000) (6.000) (4.000) (2.000) - 2.000 4.000 6.000 8.000
20
Luas Penampang 00+975.000 5.28

Lokasi UP Nyamat 1 Periode 26 Agustus - 25 September 2016


Station 00+982.000 No. Item III.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 8.670 649.771 214.02
2 8.008 649.562 1,814.23 Sket : 651.000
3 2.413 648.832 782.03
4 - 648.177 -
5 - 649.822 1,538.10 650.000
6 (4.734) 649.493 (703.68)
7 (2.557) 648.116 (482.22)
8 (1.068) 647.881 (345.97)
649.000
9 - 647.891 (727.26)
10 2.245 647.885 (765.08)
11 4.607 647.948 (44.37)
12 4.743 647.807 (1,267.18) 648.000
13 8.670 649.771
14
15 647.000
16
17
18 646.000
19 (10.000) (5.000) - 5.000 10.000
20
Luas Penampang 00+982.000 12.60
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Frontage Nyamat 1 Periode 26 Agustus - 25 September 2016


Station 11+000.000 No. Item III.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 9.195 645.713 477.95 Sket : 647.000


2 7.713 645.602 1,177.09
3 4.060 645.056 1,309.45
4 - 645.050 1,037.24
5 646.000
(3.216) 645.267 534.12
6 (4.871) 645.206 238.38
7 (5.600) 643.916 (352.73)
8 (4.500) 643.366 (321.68) 645.000
9 (3.500) 643.366 (321.72)
10 (2.500) 643.386 (321.74)
11 (1.500) 643.426 (234.61)
12 (0.771) 643.441 (247.99) 644.000
13 - 643.466 (1,333.58)
14 4.145 643.677 (332.40)
15 5.178 643.705 (1,287.67) 643.000
16 9.195 645.713
17
18
19 642.000
20 (8.000) (6.000) (4.000) (2.000) - 2.000 4.000 6.000 8.000 10.000 12.000

Luas Penampang 11+000.000 20.10

Lokasi Frontage Nyamat 1 Periode 26 Agustus - 25 September 2016


Station 11+025.000 No. Item III.1
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Timbunan di dalam Rumija Proyek

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 6.404 645.907 980.46 Sket : 648.000


2 3.369 645.992 350.97
3 2.282 645.935 737.09
4 - 646.005 951.24
5 (2.945) 646.000 513.43
647.000
6 (4.534) 645.879 894.70
7 (7.304) 645.811 78.23
8 (7.546) 645.811 (1,491.15)
9 (2.919) 645.008 (287.50)
10 (2.027) 644.877 (169.93) 646.000
11 (1.500) 644.898 (483.70)
12 - 644.928 (483.70)
13 1.500 644.898 (322.48)
14 2.500 644.858 (322.45)
645.000
15 3.500 644.838 (7.96)
16 3.525 644.826 (303.17)
17 4.465 644.836 (622.77)
18 6.404 645.907
19 644.000
20 (10.000) (5.000) - 5.000 10.000

Luas Penampang 11+025.000 11.32


LEMBAR PERHITUNGAN VOLUME
PT. PERENTJANA DJAJA

Lokasi : Underpass
Pekerjaan : Galian
No. Item : III.1
Item Pekerjaan : Galian Biasa untuk Timbunan di dalam Rumija Proyek

LUAS PANJANG VOLUME


NO STATION LUAS (M2) KETERANGAN
RATA-RATA (M2) (M1) (M3)
UP Nyamat 1
1 0+905.810 15.33 Sertifikat 1
27.12 19.19 520.45
2 0+925.000 38.91 Sertifikat 1
33.87 15.67 530.70
3 0+940.670 28.82 Sertifikat 1
24.59 9.33 229.45
4 0+950.000 20.36 Sertifikat 1
12.82 25.00 320.56
5 0+975.000 5.28 Sertifikat 1
8.94 7.00 62.59
6 0+982.000 12.60 Sertifikat 1

SUB TOTAL - 1 612.60 M3


Frontage Nyamat 1
1 11+000.000 20.10 Sertifikat 1
15.71 25.00 392.68
2 11+025.000 11.32 Sertifikat 1
5.66 20.56 116.32
3 11+045.555 0.00 Sertifikat 1

SUB TOTAL - 2 509.00 M3

TOTAL VOLUME 1,121.59 M3

Disetujui oleh: Dibuat dan diajukan oleh:


Kontraktor Pelaksana Subkontraktor
Nindya Karya - Jaya Konstruksi, KSO PT Citra Guna Perkasa

Sabir Said, S.T.


Site Engineering Manager
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Frontage Nyamat 1 Periode 26 Juli - 25 Agustus 2016


Station 11+058.888 No. Item III.3
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 (1.087) 646.791 (351.02) Sket : 648.000


2 - 646.002 (1,594.68)
3 4.937 646.070 432.52
4 3.603 646.737 1,165.16
5 - 646.728 351.41 647.000
6 (1.087) 646.791
7
8
9
646.000
10
11
12
13
14 645.000
15 (6.000) (4.000) (2.000) - 2.000 4.000 6.000
Luas Penampang 11+058.888 3.39

Lokasi Frontage Nyamat 1 Periode 26 Juli - 25 Agustus 2016


Station 11+069.920 No. Item III.3
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 3.500 647.439 323.75 Sket : 649.000


2 2.500 647.459 323.78
3 1.500 647.499 188.60
4 0.918 647.528 297.07 648.000
5 - 647.552 381.73
6 (1.179) 647.488 137.30
7 (1.603) 647.428 166.29 647.000
8 (2.117) 647.418 (29.97)
9 (2.024) 647.388 (655.17)
10 - 647.402 (104.56)
11 646.000
0.323 647.400 (195.52)
12 0.927 647.361 (199.64)
13 1.543 646.822 (1,063.82)
14 4.832 646.773 432.44 645.000
15 3.500 647.439 (4.000) (3.000) (2.000) (1.000) - 1.000 2.000 3.000 4.000 5.000 6.000
Luas Penampang 11+069.920 2.30

Lokasi Frontage Nyamat 1 Periode 26 Juli - 25 Agustus 2016


Station 11+083.253 No. Item III.3
Pekerjaan Timbunan Tanah Item Pembayaran Borrow Material

No Jarak Elevasi Luas (F) Keterangan : F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5

1 2.078 648.306 (51.45) Sket :


2 2.237 648.279 (201.84) 650.000
3 2.857 647.496 (797.75)
4 5.321 647.359 408.54
5 4.064 647.987 402.39 649.000
6 2.822 648.063 91.14
7 2.542 648.288 150.21
8 2.078 648.306 648.000
9
10
11 647.000
12
13
14 646.000
15 1.500 2.000 2.500 3.000 3.500 4.000 4.500 5.000 5.500 6.000
Luas Penampang 11+083.253 1.24
LEMBAR PERHITUNGAN VOLUME
PT. PERENTJANA DJAJA

Lokasi : Frontage
Pekerjaan : Timbunan
No. Item : III.3
Item Pekerjaan : Borrow Material

LUAS PANJANG VOLUME


NO STATION LUAS (M2) KETERANGAN
RATA-RATA (M2) (M1) (M3)
Frontage Nyamat 1
1 11+025.000 0.00
0.42 19.99 8.37
2 11+044.990 0.84 Sertifikat 2
2.12 13.90 29.41
3 11+058.888 3.39 Sertifikat 3
2.85 11.03 31.42
4 11+069.920 2.30 Sertifikat 3
1.77 13.33 23.62
5 11+083.253 1.24 Sertifikat 3
0.62 10.18 6.31
6 11+093.430 0.00

TOTAL VOLUME 99.14 M3

Disetujui oleh: Dibuat dan diajukan oleh:


Kontraktor Pelaksana Subkontraktor
Nindya Karya - Jaya Konstruksi, KSO PT Pilar Persada Semarang

Sabir Said, S.T.


Site Engineering Manager
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Desember 2015 - 25 Januari 2016


Station 39+675.00 No. Item III.2
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Dibuang di Luar Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (30.508) 640.506 (2,220.63)
2 (23.566) 640.338 (1,791.06) Sket :
3 (17.978) 640.504 (1,742.88)
4 (12.538) 640.583 (511.86) 642.000
5 (10.930) 640.077 (828.16)
6 (8.339) 639.883 (178.63) 641.000
7 (7.784) 640.138 (844.13)
8 (5.136) 639.261 (1,226.93) 640.000
9 (1.298) 639.336 (208.06)
10 639.000
(0.646) 638.772 (206.29)
11 - 638.676 (1,753.17) 638.000
12 5.490 638.772 (456.58)
13 6.909 637.543 (1,800.66) 637.000
14 12.559 637.659 (291.49)
15 13.463 637.138 (3,087.58) 636.000
16 23.157 637.231 (403.22)
17 24.406 636.776 (3,044.36) 635.000
18 33.971 636.860 8.49
634.000
19 33.971 637.360 3,046.75
(40.000) (30.000) (20.000) (10.000) - 10.000 20.000 30.000 40.000
20 24.406 637.276 403.53
21 23.157 637.731 3,090.01
22 13.463 637.638 291.72
23 12.559 638.159 1,802.07
24 6.909 638.043 456.94
25 5.490 639.272 1,754.54
26 - 639.176 206.45
27 (0.646) 639.272 208.22
28 (1.298) 639.836 1,227.89
29 (5.136) 639.761 844.79
30 (7.784) 640.638 575.70
31 (9.580) 640.534 389.27
32 (10.805) 641.172 6,320.10
33 (30.508) 640.506
Luas Penampang 39+675.00 30.78
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Desember 2015 - 25 Januari 2016


Station 39+700.00 No. Item III.2
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Dibuang di Luar Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (31.684) 641.019 (1,153.62)
2 (28.074) 640.803 (1,769.55) Sket :
3 (22.546) 640.687 (1,796.96)
4 (16.934) 640.615 (1,799.31)
5 (11.319) 640.708 (1,714.44) 642.000
6 (5.967) 640.691 (1,911.84)
7 - 640.805 (2,258.84)
8 641.000
7.050 640.032 (422.46)
9 8.361 639.205 (2,582.84)
10 16.445 639.402 (697.39)
11 640.000
18.613 638.882 (2,522.05)
12 26.500 638.601 (631.43)
13 28.450 637.937 (1,773.00)
639.000
14 33.985 637.409 4.16
15 33.985 637.654 347.05
16 32.896 637.645 322.16 638.000
17 31.910 638.119 1,245.94
18 28.007 638.160 320.76
19 27.034 638.895 965.93 637.000
20 24.013 638.960 232.76
21 23.297 639.294 1,512.10
22 18.566 639.281 313.16 636.000
23 17.602 639.823 3,063.27
24 8.026 639.800 157.13
25 7.543 640.453 1,399.38 635.000
26 3.175 640.620 1,018.15 (40.000) (30.000) (20.000) (10.000) - 10.000 20.000 30.000 40.000
27 - 641.353 430.03
28 (1.341) 640.929 1,929.83
29 (7.363) 640.941 3,762.69
30 (19.105) 641.016 170.46
31 (19.638) 641.055 2,914.48
32 (28.731) 641.063 175.80
33 (29.281) 641.097 769.77
34 (31.684) 641.132 1.79
35 (31.684) 641.019
Luas Penampang 39+700.00 23.06
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Desember 2015 - 25 Januari 2016


Station 39+725.00 No. Item III.2
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Dibuang di Luar Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (12.986) 640.957 (697.92)
2 (10.808) 640.944 (1,592.15) Sket :
3 (5.839) 640.893 (1,870.83)
4 - 640.805 (1,762.21) 642.000
5 5.500 640.579 (914.40)
6 8.351 640.122 (1,810.10)
7 14.001 639.702 (2,169.19) 641.000
8 20.774 639.297 2,101.09
9 14.227 640.101 252.31
10 13.447 640.476 2,057.17 640.000
11 7.024 640.518 506.08
12 5.449 640.995 1,746.43
13 - 641.010 1,192.92 639.000
14 (3.722) 641.005 167.27
15 (4.244) 641.024 2,774.83
16 (12.902) 641.102 26.82 638.000
17 (12.986) 641.119 1.05
18 (12.986) 640.957
637.000
19
(20.000) (10.000) - 10.000 20.000 30.000 40.000
20 23.675 639.123 (2,557.01)
21 31.666 638.836 1.84
22 31.666 638.952 436.30
23 30.299 638.925 248.68
24 29.552 639.588 290.30
25 28.647 639.648 2,016.22
26 22.339 639.562 241.14
27 21.574 639.249 (672.89)
28 23.675 639.123
Luas Penampang 39+725.00 13.73
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Desember 2015 - 25 Januari 2016


Station 39+750.00 No. Item III.2
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Dibuang di Luar Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (13.568) 641.376 (556.58)
2 (11.832) 641.356 (1,342.19) Sket :
3 (7.647) 641.381 79.95
4 (7.897) 641.438 1,818.68 642.000
5 (13.568) 641.469 0.63
6 (13.568) 641.376

7 (0.671) 641.395 (215.19)


8 - 641.394 (414.66) 641.000
9 1.293 641.306 91.61
10 1.008 641.648 323.45
11 - 641.770 215.31
12 (0.671) 641.395
640.000
13 9.450 640.748 (3,059.36)
14 18.999 640.726 (1,410.45)
15 23.401 640.704 (1,127.96)
16 26.912 640.430 (306.18)
639.000
17 27.864 640.331 (243.65)
(20.000) (10.000) - 10.000 20.000 30.000 40.000
18 28.609 639.963 (53.38)
19 28.776 639.967 1.44
20 28.776 640.067 498.04
21 27.254 640.828 1,662.93
22 22.063 640.803 344.61
23 20.999 641.139 5,523.38
24 3.769 641.136 (1,821.88)
25 9.450 640.748
Luas Penampang 39+750.00 8.57
LEMBAR PERHITUNGAN LUAS PENAMPANG
PT. PERENTJANA DJAJA

Lokasi Jalan Utama Zona C Periode 26 Desember 2015 - 25 Januari 2016


Station 39+775.00 No. Item III.2
Pekerjaan Galian Tanah Item Pembayaran Galian Biasa untuk Dibuang di Luar Proyek

No Jarak Elevasi Luas (F) Keterangan :


F = {( X1 x Y2 ) - ( X2 x Y1 )} x 0.5
1 (20.543) 641.494 (875.05)
2 (17.812) 641.405 (1,189.87) Sket :
3 (14.102) 641.412 (2,346.51)
4 (6.785) 641.398 (2,175.72)
643.000
5 - 641.331 (2,505.68)
6 7.814 641.398 (3,748.43)
7 19.500 641.209 (1,363.29)
8 23.750 641.135 (853.80)
9 26.411 641.070 (116.46)
10 26.767 640.892 5.34
11 642.000
26.767 641.291 398.06
12 25.539 641.613 3,492.83
13 14.649 641.554 270.77
14 13.810 641.778 4,430.92
15 - 641.698 322.77
16 (1.006) 641.789 372.10
17 641.000
(2.166) 642.064 515.24
18 (3.771) 642.083 229.59
19 (4.487) 642.229 64.02
20 (4.683) 641.745 228.40
21 (5.395) 641.770 36.57
22 (5.512) 642.131 191.57
23 640.000
(6.107) 641.935 1,362.45
24 (30.000) (20.000) (10.000) - 10.000 20.000 30.000
(10.352) 641.955 208.43
25 (11.000) 641.871 2,424.20
26 (18.554) 641.898 253.56
27 (19.340) 641.758 385.98
28 (20.543) 641.762 2.75
29 (20.543) 641.494
Luas Penampang 39+775.00 20.77
LEMBAR PERHITUNGAN VOLUME
PT. PERENTJANA DJAJA

Lokasi : Jalan Utama Zona C


Pekerjaan : Galian
No. Item : III.2
Item Pekerjaan : Galian Biasa untuk Dibuang di Luar Proyek

LUAS PANJANG VOLUME


NO STATION LUAS (M2) KETERANGAN
RATA-RATA (M2) (M1) (M3)
1 39+675.000 30.78
26.92 25.00 673.09
2 39+700.000 23.06
18.40 25.00 459.98
3 39+725.000 13.73
11.15 25.00 278.85
4 39+750.000 8.57
14.67 25.00 366.81
5 39+775.000 20.77
10.39 25.00 259.63
6 39+800.000 0.00

TOTAL VOLUME 2,038.35 M3

Disetujui oleh: Dibuat dan diajukan oleh:


Kontraktor Pelaksana Subkontraktor
Nindya Karya - Jaya Konstruksi, KSO PT Dwi Tunggal Abdi Pertiwi

Sabir Said, S.T.


Site Engineering Manager
REKAPITULASI PEKERJAAN
GALIAN DAN TIMBUNAN DI DALAM RUMIJA PROYEK
PT CITRA GUNA PERKASA
(Sampai dengan 25 Oktober 2016)

VOLUME KUMULATIF VOLUME KUMULATIF


NO. URAIAN SATUAN s.d. PERIODE LALU
VOLUME PERIODE INI
s.d. SAAT INI

A Galian Biasa untuk Timbunan di dalam Rumija Proyek


1 Badan Jalan Lokasi Jalan Utama M3 7,180.17 0.00 7,180.17
2 Underpass dan Frontage M3 1,121.59 (0.00) 1,121.59

Jumlah Volume A M3 8,301.76 0.00 8,301.76


Volume Galian Padat (A x 0,9) M3 7,471.59 0.00 7,471.59

B Galian Biasa untuk Dibuang di Luar Proyek


1 Badan Jalan Lokasi Jalan Utama M3 - - -

Jumlah Volume B M3 - - -

C Total Timbunan
1 Badan Jalan Lokasi Jalan Utama M3 18,140.42 10,054.74 28,195.16
2 Underpass dan Frontage M3 - - -

Jumlah Volume C M3 18,140.42 10,054.74 28,195.16

D Borrow Material
1 Badan Jalan Lokasi Jalan Utama = C - (A x 0.9) M3 10,668.84 10,054.74 20,723.57

Jumlah Volume D M3 10,668.84 10,054.74 20,723.57


REKAPITULASI PERHITUNGAN VOLUME

Proyek : PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP II Nomor MC : 2 (DUA)


RUAS BAWEN - SOLO, SEKSI III BAWEN - SALATIGA Bulan : OKTOBER
PAKET 3.3D : SIDOREJO - TENGARAN (STA. 36+100 s.d. STA. 40+409) Tanggal : 26 SEPTEMBER s.d. 25 OKTOBER
No. Item : I.2 Tahun : 2016
Item Pembayaran : Borrow Material

No Lokasi Pekerjaan Satuan Kuantitas Keterangan

A. TOTAL TIMBUNAN
1. Jalan Utama
STA. 39+075 s.d. STA. 39+650 m3 28,195.16 Sertifikat 2

Total ( 1 ) Timbunan Jalan Utama m3 28,195.16

Total ( A ) Timbunan Tanah m3 28,195.16

B. TOTAL GALIAN YANG MEMENUHI SYARAT UNTUK TIMBUNAN


1. Jalan Utama
STA. 38+750 s.d. STA. 39+050 m3 7,180.17 Sertifikat 1

Total ( 1 ) Galian Jalan Utama (Bank) m3 7,180.17

2. Underpass dan Frontage


UP Nyamat 1 STA. 00+905.810 s.d. STA. 00+982.000 m3 612.60 Sertifikat 1
FR Nyamat 1 STA. 11+000.000 s.d. STA. 11+045.555 m3 509.00 Sertifikat 1
Total ( 2 ) Galian Underpass dan Frontage (Bank) m3 1,121.59

Total ( B ) Galian yang Memenuhi Syarat untuk Timbunan ( 1 + 2 ) m3 8,301.76

C. BORROW MATERIAL = A - (B x 0,9) m3 20,723.57

Total : Kumulatif s/d saat ini m3 20,723.57


Kuantitas Kontrak m3 63,976.61
Kuantitas s/d saat ini m3 20,723.57
s/d Periode lalu m3 10,668.84
Periode saat ini m3 10,054.73

Disetujui oleh: Dibuat dan diajukan oleh:


Kontraktor Pelaksana Subkontraktor
Nindya Karya - Jaya Konstruksi, KSO PT Citra Guna Perkasa

Sabir Said, S.T.


Site Engineering Manager

You might also like