Professional Documents
Culture Documents
Solar System Quick Guide-Tanzania
Solar System Quick Guide-Tanzania
Solar System Quick Guide-Tanzania
1. Shape in Foundation
shape in foundation of frame pole: Would choose location of mouting frame base design and actually
size base station to avoid disadvantage to the solar system and other item of the site.
- Locate the foundation by injecting tension. Close the landmark in positions outside the pit to
ensure that after the excavation was still determined to be a pole center point foundation. Close
landmark strung guaranteed 2 diagonal of the square by four shape to level headed .
2. The test construction materrial
- Cement: by visual examination at the request PC30 label design, manufacturing date (time from
production day put to construction day greater than 60 days).
- Stone: By visually check the uniformity of the rubble through color, size. Ensure air and other
impurities.
3. Prepare foundation
- Digging foundation to ensure proper geometry and depth required by the design is
600x600x800 mm (length x width x height); width of the bottom of the pit ensuring wider
dimension as designed from 10 to 20 cm, enough to transplant formwork and drainage during
construction
4. Framework
- Formwork must ensure correct geometry, ensuring tight and solid during the concrete pour.
- Measure the size of the foundation formwork, take a pictures, check to make sure.
5. Concrete work
- Hygiene pit, lined cement bags or canvas bottom pineapple, use the 5cm thick millet,
millet bottom steel wrenches
- Mix according grading regulations ensure achievement of concrete, concrete dress
carefully ensure, within the time allowed, the concrete should be void, noted avoid
distorting foundation bolts. Concreting must have steel rod, crowbars to dress hand. Fort
concrete right technique from between around
- Measure the depth before and after finish to test
- Avoid chipping concrete and concrete surfaces, smooth concrete, gaining size as
designed
- After pouring concrete to rain, shade and regular moisturizing (from 7- 14 days
maintenance depending on ambient temperature)
- Testing hardened concrete saw conduct dismantling formwork (usually between 2-4 days
depending on the ambient temperature
- Foundation bolts and flange link footed passage closed snugly with positioning plate. Not
listed, cushion inserts, ecu or other objects
- Bolts right pole connector fitting properly designed, a sufficient number of bulon and ecu
- The link bar and surface mounted panels must be exactly equal distance in the position
- Check the tightening of bolts with a wrench force.
- Use of plumb or total station to determine the vertical poles
- Installation of the details left to form a mounting frame system :
Once completed solar mounting frame, to laying the panels and wiring, the requirements and
procedures as follows :
Anti‐theft security bar
- Start making panels fitted, set to the correct slides in, pushing them into the hand, so that
the panels adjacent to each other.
- Make the 3 solar panels in serial by one group, and connecting M25 cable to solar cabinet
- Make the MC4 Connector connection wire M25, ensuring contact between the cable and
the connector must be cut, twisted shells lace to tight end, avoid water seepage inside
make contact oxidation process leading to the cord.
- The remainder of the panels cord must be tied neatly in plastic crackers
Junction box
- Wire M25 consortium 3 solar panel go to the cabinet must to go inside the cable tray
Cable tray
Solar Cabinet
- The 3 solar panels in serial by one group, then using M10 play in the match connection in
Solar Cabinets.
- Each Solar Cabinet has 3 pairs of solar combiner poles, the each combiner pair pole for
solar in, solar out to Lightning protection and circuit breaker, all complete with M25
cable to power cabinet.
Solar lightning protection
Circuit Breaker
A pair Solar combiner Pole
- Each pair Solar combiner pole for 3 solar panel consortium installed (total 09 Solar
panels) and connect to Lightning protection and circuit breaker
- Cable from a 3 panels in electric box to the corresponding pairs (line voltage positive (+)
and negative voltage wire (-), are numbered on the line in panels and top wiring in the
connection cabinet order intermediate pairs 1,2,3, ... with tape paper, then add layers on
tape in order to avoid blurred.
- Must go in HDPE pipes and sewers located within brick or concrete directly
- The underground must ensure 30cm depth from the surface by reinforcing 0/0
- Construction of the first line before connecting wires to intermediate players play on
cabinet
- Use wire tipped tape if unused
- Numbered wire pairs (+/-) from Electric box to power cabinet
- For system 18 Solar panels: 18 solar panel made to 2 array, each array have 3
consortium, made by 9 solar panel, and feed to Solar combiner pole. Have one electric
box for this system
- For system 21 Solar panels: Same 18 solar panel, and leftover 3 panels, you must wire as
image below, and need a cross-connect cable, estimate l meter, and feed to Solar
combiner pole. Have two electric box for this system
- Leftover 3 panels will use one pair solar combiner pole.
6. Solar power system with Power cabinet of ZTE wire diagram
D. PICTURE WORKS OF THE QUALITY