COMPARATIVE STATEMENT

DATE : 03-Dec-11

Hydro Testing Radiography Test


SL No. Expected Cost Expected
DETAILS in Rs
DETAILS Cost in Rs
Approximate Cost For doing Radiography Test 10 % of total
1 Approximate Cost for Doing Hydro Test of 9KM(Rs 75/mtr) 675000.00 200000.00
quantyty(Random Basis)
54,21,511 Litrs water require for doing hydro test of 9 KM pipe
2 line,Availability of water and drainage of the same after testing will be No need of any water
difficult
3 Less chances of leakage(Repair) of field joint while HT Chances of Repairing is more while doing RT
4 Inspection is 100% ,more time will take Inspection is random basis ,so we can save time.
Total expected Cost is 675000.00 Total expected Cost is 200000.00

Prepared By

K.Akbar Sabir
Sr.Engineer
Site:GMR-EMCO Raw water pipeline,warora