Professional Documents
Culture Documents
Bastard, Bertrand, Meunier - 1994 - A Transformer Model For Winding Fault Studies PDF
Bastard, Bertrand, Meunier - 1994 - A Transformer Model For Winding Fault Studies PDF
2, April 1994
A TRANSFORMER MODEL FOR WINDING FAULT STUDIES
Electrical Engineering Dpt. Protection and Control Dpt. Electrical Engineering Dpt.
ECOLE SUPERIEURE DELECTRICITE M ERLIN-C ERIN ECOLE SUPERIEURE DELECTRICITE
91190 Gif-sur-Yvette 38000 Grenoble 91 190 Cif-sur-Yvette
FRANCE FRANCE FRANCE
INTRODUCTION phase I1 0 0 0 O R 5 0
>k
0 0 0 0 0 R6,
The development and the validation of algorithms for a
digital differential transformer protection require the
preliminary determination of a power transformer model [SI. phaselll
This model must allow to simulate all the situations which will
be chosen to study the behaviour of the protection algorithms. f L1 M12 M13 M14 M15
I
In particular, it must allow the simulation of internal faults [4].
This is the aspect of the model that we shall study in this paper. M21 4, M23 M24 MZ5
Study of the algorithms implemented in a transformer M31 M32 L3 M34 M35 h'
protection leads us to simulate a large part of the power network, ILI =
and not only the transformer itself. The upstream circuit with its rimary secondary M41 M42 M43 L4 M45
lines, cables and grounding system, the power transformer itself,
current transformers, potential transformers and a part of the
downstream circuit with its grounding system and loads must be
taken into account. If the aim is not to finally develop a
complete simulation software for electrical transients, the
"
igure 1
M51 M52 M53 M54
M61 M62 M63 M64 M65
L5 h!
I
XJ-
Figure 2a figure 2b
II. TURN-TO-EARTHFAULT
La, Mab and I+, are elements of the 7x7 matrix.
If coil 3 has to be divided, as shown in figure 2a. the L3 is an element of the 6x6 matrix.
position of the fault point is defined by the following data :
2. Leakage
na = number of turns of "sub-coil" a Taking into account a leakage factor between coils a and b
nb = number of turns of "sub-coil" b is essential since the fault current will largely depend on the
leakage. The leakage factor is :
The 7x7 matrix [RI will be determined with the help of the
following relations :
Ra=%R3
"3 ; Rb=:R3 PI
oh= 1 --
f
L1 M12 M l a M l b M14 M15 M16
Letusnote: k = % .
M21 L2 M 2 a M 2 b M24 M25 M26 nb
I Lb= L3
k2 + 2kd=+ 1
1
I - I
A second equation must then be determined enabling Ma, Let us consider the turn-to-turn fault shown in figure 2b.
and Mbi to be computed.
As in part II, the matrix [RI can be easily determined with
* la case : the coil i is wound onto the same leg as a and b. the help of the following relations :
We assume that o~ and (33i ,hence E, can be computed. L1 M12 M l a M l b M l c M14 M15 M16
moreover :
[consistency)
2
Mdb+C
and : 0.I(pK) = 1 --
LaLb+c
--
Mab
o a b = l - T s 1 , (16)
a b
thus:
2
[leakage)
(Tat= 1 Mac (17)
a c
2 I 2 1
e=(?) 2
(20)
no longer in three (a,b,c) but in two (a+b,c) or (a,b+c). In this
way, by using the two coefficients (Td(b+c) and (T(a+b)/c. the 8x8
matrices generated in this case will be consistent with the 7x7
matrices generated to model a turn-to-earth fault.
The third relation out of (16), (17) and (18) will be
replaced by :
694
We have now to determine the mutual inductances of one
of the three windings a, b or c with any other winding i.
The consistency principle results in
(consistency
-
with the
6x6 matrix)
M3i and L3 are computed by BCTRAN; and Lb are computed
with the help of the equations (15) and (19) to (23).
2 (leakage
specific to
the 8x8
matrix) The various mutual inductances can then be expressed :
2
1
(proportion.
2
I t has already been shown by several engineers [6] that where v1 ,v12 and v2 are the volumes of the internal winding,
leakage inductances between two concentric coils in a power the inter-winding space and the external winding. With the
transformer could be easily approximated, using the following rotation-symmetry assumption, equation (35) leads to :
assumptions :
R+a,+a,,+a,
no saturation occurs (pmre>> pair),
current density is constant in the windings, x=R+a, x=R+a,+a,,
field 8 is parallel to the axis of the magnetic core,
field 8 is symmetric in relation to this axis. The complete calculation leads to the following relation :
Let us assume that one of the windings is supplied with a W = po .nf .f(h,R,al ,al2.a2).i?
:urrent il and the other one is short-circuited. (37)
igure 6
O(a+c)/b =
3. Special cases
TH I I A121
When calculating a leakage factor, one of the sub-windings
I I rl' may not be long enough to cover the height of the core. The
shapes of the field lines are then very distorted and the third
hypothesis of section IV.1 is not valid anymore. What we
propose in such a case is to use correction factors kh, which
increase the leakage inductance calculated with the method
described in section IV.l and applied in section IV.2. The
formulas which allow calculation of the correction factors have
been determined by Maurice DENIS-PAPIN [ 6 ] . They are based
on many experimental results relating to various transformers.
* calculation of ~(,+,p,,
used in (23) to simulate the case of
figure 2b For the two cases shown on figure 9, the correction factor is
determined as follows :
The situation to be considered is described on figure 8.
Windings a and c are fed in series with a current i, whereas
winding b is short-circuited. The maximum values of H(x) are :
01 + 0 2
697
The short circuits have been made by closing a contactor
between two taps. The test transformer was supplied at low
voltage by an autotransformer wired in series with an insulation
transformer.
Some of the results of these experiments are described
- 4 % I -U
4 812 a 2
in [7].
location = 2
1556
- 4 %
I
0.018
LEAKAGE FACTOR 161
figure 10
V. EXPERIMENTAL VERIFICATION
+ m (49)
1
6
FAULT LOCATION
1
figure 12
1. Description of the test transformer
The leakage factor increases rapidly when the fault occurs on an
A special three-phase transformer has been manufactered to outer layer. Moreover, there is a slight decrease in leakage when
validate the model described above. This transformer has the the 2 winding parts (a and b) are overlapped.
following characteristics :
* 2nd example :turn-to-turn fault
rated power : 100 kVA Figure 13 shows the variations of as defined in (2)
rated voltages : 5500 V I 410 V to describe the case of figure 2b for a fault between two turns,
coupling : Dyn half a layer apart, when the position of the first defective turn
short-circuit voltage : 3,96 % moves on one of the HV windings,.
LV winding : 67 turns wound in 2 layers The location of the fault is defined by the location of the
HV winding : 1556 turns wound in 8 layers first defective tum:
location = 2
The external coil (HV) of each phase has been fitted with 1556
taps as shown in figure 11.
1
FAULT LOCATION
igure 13
698
Figure 14 shows the location of the faults relating to
points 1, 2, 3, ... of figure 13.
I f axis of symmetry
.
,
;
111.'
.. d'>*'f
.
..
,
/I-\,
....................................................
,
'$
.
X I '
I ',LfI ,
>'
I\
I
5.
i 8
-5.
I -18.
..... ........ . ........
# U
TIHB (a.)
.r n
1.0
68
be
49
z 8
21
-S.
C .
-am -18.
# 8.81 # U #.U 8.84 8.85 886 8.17 #.I8
-I nun (a.)
-6a
8 8.01 8 #I a.83 8.84 8.85 # 86 8.87 0.80
TlMB b.)
699
REFERENCES
M. DENIS-PAPIN
La Pratique Industrielle de Transfomateurs
fiditions Albin Michel ; PARIS ; 1951