I. Project Description
The project involves the design and construction of a 5 MLD bulk water supply system for the
Abuyog Water District, consisting of the following components:
Component “A’: Water treatment plant (WTP) with a capacity of 5 million liters/day ( 5MLD),
inclusive of all its accessories, a diversion weir, intake structure, supply of raw water and dosing
pumps, piping, laboratory and admin building, power house, chlorination pumps and treated
water pumps, steel tank as reservoir with a total capacity of 500 cubic meters (cu.m.), supply of
standby generator rated at 250 KVA, guard house, site development, perimeter fencing with
gate and other items in Brgy. Balinsasayao, Abuyog, Leyte.
Component “B”; Transmission facilities capable of transmitting 5 MLD of treated water from a
500 cu.m. ground tank located in Bgy. Balinsasayao down to a defined service area of the
Abuyog Water District via a series of pumps, transmission and distribution lines and ancillaries,
and passing through the existing ground tank in Abuyog, Leyte. As agreed upon during the 2 nd
Coordination Meeting held in Abuyog WD on 21 August 2018, the WD’s desired minimum
acceptable water pressure is 7 pounds/square inch (PSI) to 10 PSI.
The project is being implemented under two separate contracts, both between WVI and AKI.
Page 1 of 10
Engineer of Abuyog requested for the inclusion in the submittals of the vicinity map
and detailed engineering design of the ground water tank, together with the bill of
materials. Detailed plans and drawings are being updated and will be presented to
WVI as soon as completed.
- Preparation and erection of steel reinforcing bars for footing, tie beams and
columns is ongoing for the Water Treatment Facility; batter board is being set up for
the Administration Building
Page 2 of 10
Erected column rebars for the Water Treatment Facility “A”
Page 3 of 10
Re-survey of Lot Boundaries by WVI Surveyor on Sept. 12, 2018
- Materials, HDPE pipes, valve and fitting requirements have been submitted to
WVI and NATION Pipe Manufacturing and Industrial Products Corporation. WVI
advised that two checks have been signed for issuance to NATION to secure the
purchase and delivery of the ordered materials
Page 4 of 10
Field Office “B” at Brgy. Barayong
Cement-plastering finish of the Interior
Page 5 of 10
Field Office “B” at Brgy. Banayong
Cement-plastering finish of the Exterior
Page 6 of 10
Bi-monthly regular Toolbox Meeting “B”
Page 7 of 10
C. Others
- One (1) unit brand new Toyota Hilux,(double cab pick-up, 2-wheel drive) was
procured and delivered at site in Abuyog on 7 September 2018; another unit (2nd
hand, A-1 condition, double cab pick-up, 2-wheel drive) for use by the Abuyog WD
was delivered on August 21, 2018
1-unit Brand new Toyota Hilux service vehicle 1-unit 2nd hand Ford Wildtrak service vehicle
Description Status
1 Confirm the Reckoning Dates for the Reckoning date for start of contract has been
- Completion of Component ”A” established as 15 August 2018 as announced
- Completion of Component “B” by WVI at the 3rd Coordination Meeting on 7
September 2018
2 Obtain Mayor’s Permit Awaiting proof of ownership and lot plan to be
provided by WVI
3 Obtain DPWH Permit Preparation of required drawings and
implementation schedule is ongoing
4 Open Domestic Letter of Credit with WVI reported signing of 2 checks to secure
NATION for the supply of Materials (HDPE delivery of ordered materials
pipes, Valves & Fittings)
5 Resolve Right-of-Way issues for Meeting with local government officials is
Transmission/Distribution mains scheduled for 15 October 2018
Page 8 of 10
V. Attachments
Page 9 of 10
Attachment B: Gantt Chart for Component “B”