Electrician

Steel Fixer
Carpenter

Plumber
Mason
Sl no. Location

1 KITCHEN & DINING BLOCK 9 25 18 6 0

2 RECREATION BLOCK - MALE 31 29 10 5 1

3 RECREATION BLOCK - FEMALE 17 16 9 3 5

4 MULTIPURPOSE SPORTS HALL 6 13 34 1 7

5 SWIMMING POOL 13 36 13 6 4

6 MOSQUE 9 16 14 5 0

7 OTHER WORKS 0 1 0 1 0
TOTAL 85 136 98 27 17

Average manpower deployment from 01/08/19 to 69 140 111 27 16


31/08/19

Schedule manpower deployment as per revised


program R1 40 48 16 20 13

Additional required man power deployment as on


date to complete the project by December.2019 as -45 -88 -82 -7 -4
per revised program R1
Sub-contractor
Operator
Painter

Helper
HVAC

Total
Remark

0 1 32 2 0 93

0 1 33 1 0 111

7 0 26 1 0 84

2 1 8 1 0 73

0 0 25 3 0 100

0 0 15 1 0 60

0 0 10 1 9 22
9 3 149 10 9 543

8 4 128 10 4 517

28 18 46 6 51 286

19 15 -103 -4 42 -257
Sub-contractor
Mason-Str

Electrician
Steel Fixer
Carpenter

Operator
Plumber

Painter
Helper
HVAC
8/1/2019 64 156 110 29 17 7 5 115 11 3 517
8/3/2019 66 153 122 25 17 8 5 121 11 3 531
8/4/2019 66 148 114 27 16 8 4 112 11 3 509
8/5/2019 60 148 114 25 14 6 3 103 11 4 488
8/6/2019 65 143 108 26 15 9 3 109 11 4 493
8/7/2019 67 144 112 26 16 9 3 112 11 3 503
8/8/2019 66 137 109 27 16 9 2 105 11 3 485
### 59 140 112 28 16 9 4 120 11 3 502
### 68 137 105 29 17 6 4 129 11 0 506
### 55 133 111 22 15 8 3 113 11 0 471
### 62 127 114 27 16 8 2 116 11 4 487
### 57 140 114 29 17 8 4 132 11 3 515
### 66 138 120 26 16 8 3 135 11 3 526
### 62 137 116 25 15 7 2 133 10 0 507
### 66 141 116 28 17 9 4 130 10 5 526
### 70 140 125 29 17 11 4 129 10 4 539
### 76 139 122 29 17 11 4 135 10 4 547
### 75 141 105 27 12 11 3 145 9 4 532
### 81 134 103 29 14 8 4 144 9 8 534
### 75 129 102 27 15 8 4 141 8 7 516
### 84 137 107 24 14 8 4 149 9 5 541
### 87 139 97 24 15 9 4 150 10 5 540
### 82 139 105 27 17 9 4 150 10 7 550
### 85 136 98 27 17 9 3 149 10 9 543
69 140 111 27 16 8 4 128 10 4 517