EPRF - II REVAMP PROJECT (ERP)

ZISHAN ENGINEERS (PVT.) LTD.

SITE ACTIVITY REPORT

SUNDAYS & HOLIDAYS

Name: Jamal Bakht Designation: Sr. Mech Supervisor

Sr. No. Time In: 9:30 Time Out: 16:30 Date: Sunday 8-Sep-19

1 Pipe welding inspection (Report # 337 Total Joints Inspected 62)


2 R. T. Films Review (Total Number of Joints 36)

3 Pipe Fit up inspection (Report # 249 Total Joints Inspected 67)

4 Punch point check of test pack # Petro-PKG-101


5 Punch listing of test pack # Petro-PKG-115
6 Structure torquing inspection of C602
EPRF - II REVAMP PROJECT (ERP)

ZISHAN ENGINEERS (PVT.) LTD.

SITE ACTIVITY REPORT

SUNDAYS & HOLIDAYS

Name: Shams Soomro Designation: Welding Inspector

Sr. No. Time In: 9:30 Time Out: 16:30 Date: Sunday