1 O'Hara Cost Estimation Method - Open Pit Mine Project
2 3 Capital Cost of Mine 4 Source:T.A. O'Hara and S.C. Suboleski (1992) Section 6.3.3.2 5 Units as indicated Exchanged to 6 INPUTS or US$(Dec.1988) A$(2015) 7 Ore mined and milled t/d (O) 5,000 8 Waste to ore ratio (W) 2 9 10 Clearing FORMULAS 11 INPUTS 12 Area to be cleared in acres 108.2924209957 6.3. 13 NOTE - Only one scenario/cost to be selected 14 Scenario 1 - 20% Slopes with light tree growth $108,457 6.3.112 15 Scenario 2 - Flat land with shrubs and no trees $20,336 16 Scenario 3 - 30% Slopes with heavy trees $135,571 17 18 Pre-production Waste Stripping 19 INPUTS 20 Tonnes of Soil Ts 100000 21 Tonnes of waste rock Tw 150000 22 23 Soil stripping - max. 7 m deep $34,593 24 Waste stripping - rock requiring blasting, loading and haulage $459,741 25 26 Open Pit Drilling Equipment 27 INPUTS 28 Drill size 102, 165, 200, 250, 270, 310, 336 and 380 mm 165 29 NOTE - Only one scenario to be selected 30 Scenario 1 - Tonnes of ore or waste per day per drill Tp for medium penetration (150 m per shift) OK 6508 6.3.64 31 Scenario 2 - For easily drillable rock 8805 32 Scenario 3 - For hard drilling rock 3828 33 34 Number of drills Nd of diameter d (including supplies) generally 2 to 4 2 35 up to 55,000 t/d capacity 36 Drilling equipment cost $1,160,995 6.3.117 37 38 Shovels and Other Loading Equipment 39 Size of shovels in cubic metres 5 6.3.67 40 Manually selected closest upper Standard Size S 5 41 Number of shovels 4 6.3.68 42 Number of shovels Ns 4 43 Loading equipment cost $9,163,873 6.3.118 44 45 Trucks and Accessory Road Maintenance Equipment 46 Truck size t in t 64 6.3.69 47 Number of trucks Nt of size t 9 6.3.70 AQUÍ PONER LA FUNCION REDONDEAR MAS 48 Haulage equipment cost $8,513,271 6.3.119 49 50 Open pit Maintenance Facilities 51 Area of open pit repair shop in m2 1628 6.3.71 52 Pit maintenance facilities cost $3,232,082 6.3.120 53 54 Open Pit Communication and Electrical Distribution 55 Communications/electrical cost $224,292 6.3.121 56 57 Open Pit Fuelling System 58 Fuelling system cost $66,355 6.3.122 59 60 TOTAL COST MINE $22,875,538 61 62 CONVERSION FACTORS 63 1 tonne = 1.1023 tons 64 1 m3 = 1.30795 yd3 65 1 mm = 0.03937 inches 25.4000508001 66 1 m2 = 10.7639 feet2 67 Inflation factor MCS index for open pit capital costs US$(Dec.1988) to US$(Dec.2015) = 1.8347 68 Exchange rate A$(1988):US$(1988) = 0.855 0.855 69 Average annual Australian mining capital cost inflation 2.36% p.a. 0.0236 A B C D E F G H I J K L M N 1 O'Hara Cost Estimation Method - Open Pit Mine Project 2 3 Operating Mining Cost 4 Source:T.A. O'Hara and S.C. Suboleski (1992) Section 6.3.4.2 5 6 INPUTS 7 Ore mined and milled t/d (O) 5,000 8 Waste to ore ratio (W) 2 9 Total of Ore and waste (t) 15000 LOS 15000 ESTAN EN TM SIEMPRE LO LLEVAMOS A TON CORTAS 10 11 Units as indicated Exchanged to 12 or US$(Dec.1988) A$(2001) 13 1704.6190887874 6.3.181 14 Drilling cost per day $2,844.0224 6.3.182 15 Blasting cost per day $2,395.4384 6.3.183 16 Loading cost per day $6,137.5182 6.3.184 17 Haulage cost per day $5,966.1668 6.3.185 18 General services cost per day 19 20 TOTAL OPERATING COST PER DAY $19,048 21 UNIT OPERATING COST PER t of ORE $3.81 22 23 24 CONVERSION FACTORS 25 1 tonne = 1.1023 tons 1.1023 26 1 m3 = 1.30795 yd3 27 1 mm = 0.03937 inches 28 1 m2 = 10.7639 feet2 29 Inflation factor MCS index for open pit operating costs US$(Dec.1988) to US$(Dec.2015) = 1.8893 30 Exchange rate A$(1988):US$(1988) = 0.855 0.855 31 Average annual Australian mining operating cost inflation 2.48% p.a. 0.0248