SUMMARY OF QUOTATION

CONSTRUCTION AND COMPLETION OF 1 BLOCK OF MAKMAL KOMPUTER –


M 2 AT SK SIMPANG KUDA, BAU, KUCHING DIVISION

Including Provisional sum to be completed in INK

1. Preliminaries RM

2. Buildings

1 Block 1 Storey Makmal Komputer – M2 RM

3. Piling (Provisional)

Brought forward from Schedule of Piling Works RM

4. Electrical Works RM

5. External works

i. Site preparation for building platform including cutting, RM


filling and levelling to required level

ii. Surface water drainage RM

iii. Turfing

iv. Shiftng of existing “HDPE” water tanks RM

Contingencies RM5,000.00

Note :

a. All walls shown as `aerated’ concrete walls in the


drawings shall be replaced with 115mm brickwalls
with 20mm cement rendering on both sides