Balance Periodic Maintenance Works
Balance Periodic Maintenance Works
Service Road
1 Length
(a) 7 mtr wide (1010+9620) LHS + (1010+10070) RHS 21,710 RM
Deduction for Overlay already
860 RM
done
Remaining Length 21710-860 20850 RM
5.5 mtr wide ( excluding
(b) (450+1400) LHS + 1400 (RHS) 3250 RM
Amarawati)
2 Qty of BC (40 m thick) (20850*7) +(3250*5.5) *0.04 6553 Cu M
Add for Bus bays & Truck
3 200 Cu M
Lay Byes
4 Total 6753 Cu M
5 Cost@10855/- 6753@10855/- = 7,33,03,815/- 7.33 Cr
Road Marking
1 Length
(a) MCW
(i) 11 mtr wide 14128 RM
(ii) 9 mtr wide 26912 RM
(b) Service Road
(i) 7 mtr wide 21710 RM
(ii) 5.5 mtr wide 3250 RM
2 Edge lines (02 Nos)
3 Centre Lines
On 11 mtr wide stretch (02
(a) Area= 14128/3*2*0.15 1413 Sq M
Nos)
(b) 9 mtr wide stretch (01 Nos) Area=26912/3*0.15 1346 Sq M
( c) 7 mtr wide Road (01 Nos) Area=21710/3*0.15 1086 Sq M
4 Cat Eyes
5 Kerb Painting
Repair of blinkers &Traffic
6 Approx 3 Cr.
signals
7 Repair of Street lights
8 ROB staircase
9 RE Wall bulging
10 Reapir of drain slabs/covers
11 Repairs of foothpaths
Cleaning of culverts/water
13
ways
14 Cleaning of ROW
Summary of cost
MCW Overlay 21.6 Cr
Milling 0.15 Cr
Service Road 7.33 Cr
Overlaylay
Road Marking 1.65 Cr
Miscellenous 3 Cr
Works
33.73 Cr