Estimates for Balance Periodic Maintenance Works

MCW (39.960 to 63.000)


1 Total Length (63000-39960) * 2 46080 RM
2 Deduct for-
(a) Overlay already done (42.140 to 44.280) + (44.600 to 44.900) 2440 RM
(b) PQC portion (Toll Plaza) 700*2 1400 RM
Stretch for VUP at Amravati
(c) 600*2 1200 RM
Enclave

3 Balance Length for OverLay 46080-2440-1400-1200 41040 RM

Structures & Approchaes (11


(a) 7064*2 14128 RM
mtr wide)

(b) MCW (9 mtr) remaining 41040-14128 26,912 RM

4 Qty of BC (50mm thick) {(14128*11) + (26912*9)} * 0.05 19,880.8 Cum

Cost of BC Over Lay @


5 21,58,06,084/- 21.6 Cr
10,855/-
Milling of Pavement (Approx
41040*0.2 8208 RM
20% of Length)
6
Area 8208*3 Mtr width 24624 Sq M
Cost 24624 @ 60/- = 14,77,440/- 0.15 Cr

Service Road
1 Length
(a) 7 mtr wide (1010+9620) LHS + (1010+10070) RHS 21,710 RM
Deduction for Overlay already
860 RM
done
Remaining Length 21710-860 20850 RM
5.5 mtr wide ( excluding
(b) (450+1400) LHS + 1400 (RHS) 3250 RM
Amarawati)
2 Qty of BC (40 m thick) (20850*7) +(3250*5.5) *0.04 6553 Cu M
Add for Bus bays & Truck
3 200 Cu M
Lay Byes
4 Total 6753 Cu M
5 Cost@10855/- 6753@10855/- = 7,33,03,815/- 7.33 Cr
Road Marking
1 Length
(a) MCW
(i) 11 mtr wide 14128 RM
(ii) 9 mtr wide 26912 RM
(b) Service Road
(i) 7 mtr wide 21710 RM
(ii) 5.5 mtr wide 3250 RM
2 Edge lines (02 Nos)

Area (14,128+26912+21710+3250)*2*0.15 Sq M 19800 Sq M

3 Centre Lines
On 11 mtr wide stretch (02
(a) Area= 14128/3*2*0.15 1413 Sq M
Nos)
(b) 9 mtr wide stretch (01 Nos) Area=26912/3*0.15 1346 Sq M
( c) 7 mtr wide Road (01 Nos) Area=21710/3*0.15 1086 Sq M

Add for Zebra crossing. Speed


(d) 100 Sq M
breakers, rumble strips

4 Total Area 23745 Sq M


5 Cost @ 694/- 23745@ 694/- 1.65 Cr
Miscellenous Works
Painting, Repairs & upkeep of
1 Truck Lay byes & bus
shellters
Shevron Signs (Replacement
2
& reapirs)

3 Repair of Grantry Sign borads

4 Cat Eyes
5 Kerb Painting
Repair of blinkers &Traffic
6 Approx 3 Cr.
signals
7 Repair of Street lights
8 ROB staircase
9 RE Wall bulging
10 Reapir of drain slabs/covers
11 Repairs of foothpaths

12 Repair of damaged drain pipes

Cleaning of culverts/water
13
ways
14 Cleaning of ROW
Summary of cost
MCW Overlay 21.6 Cr
Milling 0.15 Cr
Service Road 7.33 Cr
Overlaylay
Road Marking 1.65 Cr
Miscellenous 3 Cr
Works
33.73 Cr