JT DG Saigal Sir SSR Book PDF
JT DG Saigal Sir SSR Book PDF
OF
STANDARD SCHEDULE RATES 2010
It is a mystery for each one of us how SSR has been made, what constants
are considered, whether material rates includes overhead and profit or not. In
order to overcome this, an effort has been made to compile Market Analysis of
SSR 2010 Items. It contains market analysis of all items of different section
except Section 19 “Electrical Work”, Section 22 “Heating, Ventilation & Air
Conditioning”, Section 23 “Lift”, Section 26 “Solar Heater System”, Section 27
“Fire Hydrant”, Section 28 “Inclinator” and Section 29 “Rain Water Harvesting”.
The item numbers used are same as given in SSR 2010. However wherever a
table is made in SSR, each column of the table is given number from 0.01to 0.15
depending on number of column.
I am very thankful to all who shared data with me and worked with me for
compiling this document. I hope this data will be useful to all MES officers,
Subordinates and Contractors. This data will ensure uniformity while preparing
market analysis as well as environment will be aware of the constants, factors
and wastage considered against each item.
Narendra Saigal
Director (Contracts)
Military Engineer Services
Email:narendrasaigal@gmail.com
Standard Schedule Rate 2010
Earth Work
ITEM No. 3001.01
Surface excavation not exceeding 30 cm deep and averaging 15 cm deep and getting out in Soft/loose Soil
Particulars Size Unit SSR Qty Amount (SSR)
Labour
1 Mate 1 Day Rs. 169.00 0.01 1.69
2 Mazdoor-man, 1 Day Rs. 169.00 0.07 11.83
Rs.13.52
After rounding off: Rs.15.90 Total Amount of M and L Rs.13.52
Add 17.5 % OH and CP Rs.2.37
Total Rs.15.89
Extra over stone walling f0r hammer dressing to face stones and dressing of face beds and joints, as specified,
of block - in -course masonry Hammer dressing with max depression on face from straight edge held against
the dressed surface - Lime or sand stone n exc 20 mm.
Particulars Size Unit SSR Qty Amount (SSR)
Labour
1 Stone dresser 1 Day Rs. 225.00 2.25 506.25
Rs.506.25
After rounding off: Rs.594.80 Total Amount of M and L Rs.506.25
Add 17.5 % OH and CP Rs.88.59
Total Rs.594.84
ass with mild steel hinge pin bright polished type B-12 size 125mm
Rs.82.00
Labour
863 by Narender Saigal (Director Contracts)
Military Engineer Services, India
Standard Schedule Rate 2010
Builder's Hardware
1 Carpenter, joiner 1 Day Rs. 225.00 0.063 14.175
Rs.14.18
After rounding off: Rs.113.00 Total Amount of M and L Rs.96.18
Add 17.5 % OH and CP Rs.16.83
Total Rs.113.01