Professional Documents
Culture Documents
Biogas Audit Bangladesh 2011 - 2013: Background, Boundaries, Methodologies Detailed Results
Biogas Audit Bangladesh 2011 - 2013: Background, Boundaries, Methodologies Detailed Results
Biogas Audit Bangladesh 2011 - 2013: Background, Boundaries, Methodologies Detailed Results
BIOGAS AUDIT 1
BANGLADESH
2011 - 2013
VOLUME II
Background, Boundaries,
Methodologies
and
Detailed Results
FINAL VERSION
June 2013
Dhaka, Bangladesh
Beijing, PR China
2!
A Study conducted for the National Domestic Biogas and Manure Programme
(NDBMP)
Infrastructure Development Company Ltd. (IDCOL) / KfW – Kreditanstalt fuer
Wiederaufbau / German Development Bank
Note:
This paper reflects the opinion of the authors, not necessarily IDCOL's or
KfW's policy.
Consultants:
Prof. Dr. Li Zifu, Heinz-Peter Mang, Kalidas Neupane, Elisabeth-Maria Huba, Marc Wauthelet
Assistants:
Cheng Shikun, Nusrat Jahan, Dr. Thomas Fischer
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
!
3!
Content VOLUME II
Abbreviations and Acronyms!______________________________________________!5!
Management Summary!____________________________________________________!6!
Acknowledgements!_______________________________________________________!8!
1.! Introduction and Justification!_________________________________________!10!
2.! Audit Background, Boundaries and Methodologies!_____________________!13!
2.1 Background!_______________________________________________________________!13!
2.2 Boundaries! _______________________________________________________________!14!
2.3 Methodologies! ____________________________________________________________!15!
3. Detailed Results!_______________________________________________________!19!
3.1 Fault Tree Approach for technical assessment of Biogas Plant Systems! ______!19!
3.1.1 Introduction!____________________________________________________________________!20!
3.1.2 Resources, technology and locations!______________________________________________!22!
3.1.3 Conceptual model of a Fault Tree Approach!________________________________________!24!
3.1.4 Fault trees!_____________________________________________________________________!26!
3.1.5 Calculations of Fault Probability! __________________________________________________!32!
3.1.6 Conclusions!____________________________________________________________________!33!
! !
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
4!
FIGURES
TABLES
Table 1: Results of Biogas User Surveys 2007 to 201, internal Technical Audit 2010 and BAB 2011-
2013: Functioning of Biogas Plants (in % and [households])!.......................................................................!10!
Table 2: Categories of 171 recommendations formulated in BUS 2007 – 2011 and TA 2010!...............!11!
Table 3: Cattle and Poultry farm households audited!...................................................................................!16!
Table 4: Criteria and descriptions for failures of sub-systems of small-sized biogas systems:!..............!25!
Table 5: Overview on interviews disaggregated by gender!..........................................................................!34!
Table 6: Information and knowledge transfer from LCPOs to biogas owners and operators!..................!37!
Table 7: Organizational focus of LCPOs!.........................................................................................................!40!
Table 8: Technical focus of LCPOs!.................................................................................................................!40!
Table 9: Main income of LCPOs!......................................................................................................................!40!
Table 10: Legal character of LCPOs!...............................................................................................................!41!
Table 11: Business Nature of LCPOs!..............................................................................................................!41!
Table 12: Promotion material!............................................................................................................................!42!
Table 13: After construction services (ACS) / After Sales Services (ASS) and monitoring!.....................!42!
Table 14: Major problems addressed in After Construction Services!.........................................................!43!
Table 15: Payment of subsidies from IDCOL to LCPOs!...............................................................................!44!
Table 16: Gross profit margin from biogas plant construction!.....................................................................!46!
Table 17: Economic performance of LCPO biogas departments in FY 2012: 58% are in loss!...............!46!
Table 18: Example calculations for the construction of biogas plants!........................................................!47!
Table 19: Costs of Biogas plants!....................................................................................................................!48!
Table 20: Operational expenses per LCPO and its 10 Branch offices!.......................................................!48!
Table 21: If 510 plants per year per LCPO are constructed, an institutional support of BDT 8.100 /
plant is needed!....................................................................................................................................................!49!
Table 22: If 810 plants per year per LCPO are constructed, an institutional support of BDT 6.000/plant
is needed!.............................................................................................................................................................!49!
Table 23: SWOT analysis of NDBMP programme conducted by LCPOs!..................................................!51!
Table 24: Advantages and disadvantages of biogas technology for LCPOs and the country!................!52!
Table 25: Comparison between onsite constructed and offsite-manufactured digesters!........................!53!
Table 26: Comparison ABS, FRP and concrete digester!.............................................................................!54!
Table 27: Standards for Soft digester!..............................................................................................................!54!
Table 28: Performance comparison between brickwork and plastic digesters!..........................................!55!
Table 29: Transportation and installation of Prefabricated Bag Digesters!.................................................!55!
Table 30: Criteria list to select best appropriate prefabricated biogas plant!..............................................!56!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Management Summary 6!
The Biogas Audit Report Bangladesh 2011 - 2012 is structured into three volumes and five parts:
Volume I
(I) Summary of Findings & Recommendations - focuses on the main objective and the
results of the Technical Audit and Implementation Verification Mission for the KfW-
supported biogas activities in Bangladesh, Biogas Audit Bangladesh (BAB) for short. To
achieve the main objective: "a comprehensive operational assessment of the promoted
hardware (technology) as well as software (management, coordination, process,
performances and impacts) aspects of the biogas plants installed in the framework of
NDBMP from 2006 to 2012", the scope of work of the BAB team was oriented on 7 key
questions, which defined 7 Work Packages (WP):
WP1: How reliable is the data from regular users' surveys on plant operation rate, slurry
use?
WP2: How to optimize low cost household biogas plant performance?
WP3: How good is the biogas plant quality, how good are the design, construction quality,
appliance quality, and after-sales service quality?
WP4: How reliable is the NDBMP regular internal monitoring?
WP5: How is IDCOL retaining its trained program staff?
WP6: How will the occasional flooding in Bangladesh squeeze the potential market of
biogas and affect plant construction?
WP7: How effective is the coordination between sector institutions on program
interventions, implementing and monitoring?
The ACTION PLAN as outlined during Debriefing Sessions with IDCOL and KfW in May
and June 2013, and related TERMS OF REFERENCES are added as Chapter 8.
Volume II
(II) Introduction and Justification - collects critical findings from biogas plant analysis and
institutional assessments published by international experts since 2005; this part repeats
key observations and remarks from earlier surveys, monitoring and evaluation reports.
(III) Audit background, boundaries and methodologies - summarizes relevant frame and
background information related to the Biogas Audit Bangladesh, and gives a brief
description of audit methodologies and the selection processes, as well as audit
boundaries.
(IV) Detailed results of the audit work - gives more details beyond the findings presented in
Volume I by accomplishing the Specific Objectives as listed in the Terms of Reference:
1. Assess suitability of the design of biogas plants being disseminated in terms of their
proposed performance, durability, cost-effectiveness, user-friendliness, convenience
of operation, availability of feeding materials and its ratio of use, and expected
efficiency.
2. Appraise physical quality of the installed biogas plants in terms of existing condition of
different components in general and gas tightness of dome in particular, quality of
construction materials and appliances, quality of workmanship involved in construction
as well as operation and maintenance conditions.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
4. Appraise the level of user’s satisfaction in terms of their views on quality of the
product, social and financial benefits being enjoyed from the products, problems being
encountered and user-friendliness of the offered technology.
5. Evaluate the effectiveness of the training offered to the companies and owners, and
appraise level of professionalism of companies and their field staff.
7. Appraise the internal IDCOL management and sector coordination and document
findings along with the responsibility matrix.
In the ATTACHMENT to Volume II the reader finds the templates of the questionnaires
for households and LCPOs, and the list of persons and institutions contacted during the
audit.
Volume III
(V) Attachment package - contains cross-reference sources with visited plant lists,
databases, and a photo-documentation.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Acknowledgements 8!
The international team carrying out the Biogas Audit Bangladesh was highly motivated to
enter into the Bangladesh Biogas World where enthusiasm for technical developments
towards advancements of the biogas sector prevails among professionals; and where
constructors and owners raise explicit concerns about technology models, financing
mechanisms and knowledge transfer. With critical solidarity the BAB team analyzed in depth
the implementation work done by NDBMP in the years 2006 to 2012. The results are
presented in this Biogas Audit Report. We take this opportunity to express our thanks again
to all persons who supported our work:
• 159 biogas households, who gave us access to their kitchen, shed, garden and biogas
plant; they have been valuable interview partners, serving fresh fruits, and lending
helping hands for troubleshooting and feedstock weighting. In overall total, 1% of the
NDBMP biogas plants constructed up to September 2012 have been visited by the BAB-
team.
• 15 partner organizations in their offices across the country, who opened their
documentation and talked to us about their entrepreneurial experience with, and
expectations towards IDCOL and NDBMP; in addition they were our local facilitators,
guided us to find the biogas users’ households, and provided spare parts for repairing the
plants before testing. Although they were statistically already representing the currently
(2012) 31 active partner organizations in NDBMP, we also receive important information
from those ‘not sampled’ organizations during the NDBMP stakeholder meetings
• Responsible staff and consultants of KfW, IDCOL, NDBMP, SNV, GIZ, ADB, BBDF who
supplied us with valuable updated and background information, documents, logistics and
active interest in our work:
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
This Chapter provides an overview on critical findings from biogas plant analysis and
institutional assessments published by international experts since the first programme
feasibility study in 2005. It can therefore not be avoided that this part repeats key
observations and remarks from earlier surveys, monitoring and evaluation reports.
Biogas technology implementation started in Bangladesh during the 70ies. The first floating-
drum biogas plant based on KVIC Indian design was constructed in 1972 at the premises of
Bangladesh Agriculture University (BAU). In 1976, another family size KVIC design plant was
constructed at the premises of BCSIR. In 1981, Environment Pollution Control Department
constructed about 150 floating-drum and 110 Chinese model fixed dome plants. Further
efforts to promote biogas were undertaken by BCSIR, DANIDA, LGED, DLS and Grameen
Bank. During the years 1989 to 1991, IFRD had imparted training to local youth and enabled
them to construct 126 biogas plants. A wider dissemination of biogas technology took place
when BCSIR implemented the “Biogas Pilot Plant (1st phase) Project” July 1995 to June
2000. During this period, 4,664 fixed dome plants were put in place throughout the country.
Hence, following the successful completion of the first phase of the program, BCSIR
implemented the 2nd phase of the Biogas Pilot Plant from July 2000 to June 2004,
establishing 17,194 plants. The investment subsidy for biogas households was Taka 7,500
per plant. In the period October 1998 to June 2003, LGED also implemented a biogas project
and constructed 1,120 biogas plants. Grameen Shakti constructed biogas plants without any
subsidy; about120 plants have been constructed by this organization by December 2005. It
has been observed that out of all the previously constructed biogas plants about 47% has
been said to function well, while another 32% are reported to function partially. Moreover,
most of the biogas plants are found under-fed.
In rural Bangladesh the average cooking time per family per day is estimated to be 5 hours.
Each household consumes about 3 tons of biomass per year for cooking purposes only.
Assuming that 55% of households use biomass for cooking, calculation results in about 40
million tons of biomass required annually country wide for cooking fuel. Supply of such large
quantity of biomass creates high pressure on the forest. It also causes indoor air pollution:
smoke from incomplete burning and often humid biomass is considered to be a major source
of health hazards esp. for women and children, particularly to those belonging to poor and
vulnerable groups. The use of agriculture residues and animal waste as cooking fuel rather
than as organic fertilizer leads in addition to adverse effects on soil fertility, thus affecting
crop production, productivity of land, and food security.
Table 1: Results of Biogas User Surveys 2007 to 201, internal Technical Audit 2010 and BAB
2011-2013: Functioning of Biogas Plants (in % and [households])
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
The review of program documents finally motivated the Consultant to revise and adapt the
originally planned content of VOLUME II, Chapter 3.5: "As the NDBMP also envisions
making access to biogas for smaller households, it is proposed to promote also smaller
plants requiring a daily feeding of 30 kg of dung (3 cattle head). Such plant should be able to
produce gas for cooking during at least 3 hours." (Implementation Plan, National Domestic
Biogas and Manure Programme in Bangladesh, Final version April 2006) Therefore, in
Chapter 3.5 of VOL. II the topic 'prefabricated biogas plants' is introduced as an opportunity
to tackle various challenges of NDBMP such as implementation speed, construction quality
issues, subsidy policies, commercial feasibility and sustainable market development, as well
as disaster preparedness and flood resistance.
! !
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
2.1 Background
Biogas technology implementation started in Bangladesh during the 1970ies. The first
floating-drum biogas plant based on KVIC Indian design was constructed in 1972 at the
premises of Bangladesh Agriculture University (BAU). In 1976, another family size KVIC
design plant was constructed at the premises of BCSIR. In 1981, Environment Pollution
Control Department constructed about 150 floating-drum and 110 Chinese fixed dome
models.
Further efforts to promote biogas were undertaken by BCSIR, DANIDA, LGED, DLS and
Grameen Bank. During the years 1989 to 1991, IFRD trained young people to construct 126
biogas plants. A wider dissemination of biogas technology took place through BCSIR's
“Biogas Pilot Plant Project - 1st Phase” from July 1995 to June 2000. During this period,
4,664 fixed dome plants were installed throughout the country. In a 2nd phase from July 2000
to June 2004, BCSIR implemented 17,194 plants. The investment subsidy was Taka 7,500
per plant.
In the period October 1998 to June 2003, LGED constructed 1,120 biogas plants. Grameen
Shakti disseminated 120 biogas plants without any subsidy by December 2005. Out of all the
previously constructed biogas plants about 47% are evaluated by different studies as "well
functioning", while 32% are reported to function partially1.
Bangladesh is considered to be a country, which is highly feasible for biogas production as it
fulfills all prerequisites to harness the technology. For example, high quality construction
materials such as good quality cement, good quality bricks, iron rods and sand are easily
available. Gravel is very scarce, but replaced by ‘khoa’ 2 . Water is commonly available
through tube wells and local ponds. The average temperature, which is a governing factor for
biogas production, is appropriate.
Looking at the availability of cattle dung, 8.44 million households keep 22.29 million of
cattle/buffalo; about 952,000 households own more than 5 heads of cattle whereas another 2
million households keep 3 - 4 cattle. These figures indicate that at least 3 million household
sized biogas plants are technically feasible.
Poultry droppings are also considered as excellent feedstock for biogas; around 80,000
poultry farms are estimated to operate in Bangladesh. Usually a poultry farm keeps 200 –
1,000 poultry birds making a household size biogas plant highly feasible.
A limiting factor for the technical theoretical potential of domestic biogas plants could be
monsoon flooding, high water tables especially during rainy season, and declining number of
cattle per household. Since dairy farms and poultry farms are more or less stable regarding
rearing of livestock and poultry birds, linking biogas with such farms could resolve these
limitations.
SNV Netherlands Development Organisation has been advising the implementation of the
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
1
No criteria for “functioning well” or “partially functioning have been delivered so far.
2
Khoa: broken or crushed 1st class bricks, size from ¾ inch to ¼ inch of angular shape, produced mechanically or by hand
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
“National Domestic Biogas and Manure Programme” (NDBMP) in Bangladesh from 2006 to
2012 under the “Infrastructure Development Company” (IDCOL), and other national and local 14!
partner organizations.
The overall objective of the National Domestic Biogas and Manure Programme (NDBMP) is
to develop and disseminate domestic biogas plants in rural areas with the ultimate goal to
establish a sustainable and commercial biogas sector in Bangladesh.
The National Strategy for Economic Growth, Poverty Reduction and Social Development
prepared by the Ministry of Finance and Planning also puts emphasis on “creating a policy
environment that is capable of providing right incentives to adopt new technologies”. It also
emphasizes the integration of environmental conservation strategy into national poverty
alleviation strategies.
NDBMP contributes to achieve millennium development goals set by the Government.
Contribution of biogas in this regard will help poverty reduction through (1) savings on energy
expenditure, (2) increased agriculture production by maximum utilization of bio slurry as
fertilizer, (3) gender equality through empowering women in decision-making and
maximization of their participation in the programme, (4) improved health through provision of
clean cooking energy, (5) improving sanitation by toilet construction connection to the bio-
digester, and (6) creation of opportunities for local employment.
Under this programme a total of 37,269 plants (revised target) should be installed in the
years 2006 to 2012. Several activities are implemented to achieve this target: promotion and
subsidy administration to provide Taka 9,000 per household as investment subsidy;
construction of high quality plants should be ensured by enforcing a quality control system.
To ensure proper functioning of the plant, guarantee on plants for 5 years and maintenance
services will be provided for 3 years, and training on operation and maintenance will be
provided to each biogas plant owner family. Training material and sessions will be developed
and imparted to the staff of the partner organizations to strengthen their capabilities. Proper
management and utilization of bio-slurry will be given high emphasis.
Till April 2009, about 35,000 plants were already installed in Bangladesh by a wide range of
organizations.3 The total technical potential from the available feedstock for household sized
biogas plants is estimated at 3 million systems.
2.2 Boundaries
IDCOL and KfW defined the Biogas Audit Boundaries, and as such the pathway for adequate
planning was prepared:
• The main objective of the Implementation Verification and Technical Audit assignment
(Biogas Audit Bangladesh - BAB - in short) is to make a comprehensive operational
assessment of the promoted hardware (technology) as well as software (management,
coordination, process, performances and impacts) aspects of the biogas plants installed
in the framework of NDBMP from 2006 to end 2012.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
3
Abdul Hye Mondal, Md. Zabid Iqbal, ATM Shaifullah Mehedi: Final Report - Skills for Green Jobs in Bangladesh, Bangladesh
Institute of Development Studies, E-17 Agargaon, Dhaka-1207, December 2009
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
• The specific objectives of the evaluation field studies conducted during 2011 and 2012
were defined as follows: 15!
1. Assess suitability of the design of biogas plants being disseminated in terms of their
proposed performance, durability, cost-effectiveness, user-friendliness, convenience of
operation, availability of feeding materials and its ratio of use, and expected efficiency.
2. Appraise physical quality of the installed biogas plants in terms of existing condition of
different components in general and gas tightness of dome in particular, quality of
construction materials and appliances, quality of workmanship involved in construction as
well as operation and maintenance conditions.
3. Evaluate the effectiveness of quality control mechanism: quality standards, monitoring
of quality during construction as well as operation, maintenance and after sales service,
compliance of quality standards being practiced.
4. Appraise the level of user’s satisfaction in terms of their views on quality of the product,
social and financial benefits being enjoyed from the products, problems being
encountered and user-friendliness of the offered technology.
5. Evaluate the effectiveness of the training offered to the companies and owners, and
appraise level of professionalism of companies and their field staff.
6. Document different effluent application methodologies in relation to fertilizer efficiency
and soil improvement quality.
7. Appraise the internal IDCOL management and sector coordination and document
findings along with the responsibility matrix.
• The Scope of Work of BAB includes a detailed analysis of 10 randomly selected but
representative biogas clusters (each cluster with at least 7 biogas households, out of them
at least 50% will be assessed) distributed in the entire country, selection criteria follows
statistical science considering different sizes (6), ages (constructed 2006 –2012), access
possibilities under the given budget frame, and number of biogas plants per region,
installed under the National Domestic Biogas and Manure Programme (NDBMP) since
2006.
• As agreed in the Terms of Reference, the technical and financial audit could not work on a
statistically approved sample size, as the budget frame does not allow carrying out these
investigations in depth.
2.3 Methodologies
A blended approach of methodologies was applied during the audit:
1. To be as statistically representative as possible, the audit included on a detailed analysis
of 10 randomly selected but representative biogas clusters, each cluster with at least 7
biogas households, out of which at least 50% to be assessed.
2. BAB team visited a total of 159 biogas plants, but only 106 have been audited as they had
been pre-sampled under the NDBMP framework according to the criteria presented in
Chapter 2.3 of Volume II. The samples were distributed across the entire country; the final
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
selection following statistical science considered 6 different sizes (1.2, 1.6, 2.0, 2.4, 3.2,
4.8m3 of expected daily biogas production capacity), ages (over 7 years, built 2006 – 2012), 16!
access possibilities under the given budget frame (seasons, time, and transport limitation),
and number of biogas plants per region (including divisions with highest and lowest number
of biogas plants), installed under the National Domestic Biogas and Manure Programme
(NDBMP) since 2006.
Table 3: Cattle and Poultry farm households audited
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Chapter 3 gives details of findings beyond the Summary of Findings presented in Volume I. It
follows the outline specified by the Specific Objectives defined in the Terms of Reference:
1. Assess suitability of the design of biogas plants being disseminated in terms of their
proposed performance, durability, cost-effectiveness, user-friendliness, convenience of
operation, availability of feeding materials and its ratio of use, and expected efficiency.
2. Appraise physical quality of the installed biogas plants in terms of existing condition of
different components in general and gas tightness of dome in particular, quality of
construction materials and appliances, quality of workmanship involved in construction as
well as operation and maintenance conditions.
3. Evaluate the effectiveness of quality control mechanism: quality standards,
monitoring of quality during construction as well as operation, maintenance and after sales
service, compliance of quality standards, being practiced.
4. Appraise the level of user’s satisfaction in terms of their views on quality of the
product, social and financial benefits being enjoyed from the products, problems being
encountered and user-friendliness of the offered technology.
5. Evaluate the effectiveness of the training offered to the companies and owners, and
appraise level of professionalism of companies and their field staff.
6. Document different effluent application methodologies in relation to fertilizer efficiency
and soil improvement quality.
7. Appraise the internal IDCOL management and sector coordination and document
findings along with the responsibility matrix.
3.1 Fault Tree Approach for technical assessment of Biogas Plant Systems
This sub-chapter covers three Specific Objectives as defined in the Terms of Reference:
1. Assess suitability of the design of biogas plants being disseminated in terms of their
proposed performance, durability, cost-effectiveness, user-friendliness, convenience of
operation, availability of feeding materials and its ratio of use, and expected efficiency.
2. Appraise physical quality of the installed biogas plants in terms of existing condition of
different components in general and gas tightness of dome in particular, quality of
construction materials and appliances, quality of workmanship involved in construction as
well as operation and maintenance conditions.
and
3. Evaluate the effectiveness of quality control mechanism: quality standards, monitoring of
quality during construction as well as operation, maintenance and after sales service,
compliance of quality standards, being practiced.
BAB team visited a total of 159 biogas plants, but only 106 have been audited as they have
been sampled officially under the NDBMP framework according to the criteria presented in
Chapter 2.3 of Volume II, and 8 biogas plants have not been constructed in the framework of
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
NDBMP. Two sampled biogas plants were still in the start-up phase in the same month of
visit, three biogas plants were visited on request of neighbors to audited plants, only one 20!
sampled biogas plant owner refused the interview, but observations could be noted. This
gives the background to the reason why only an average of statistically 100 biogas plants are
subject to the analysis by a Fault Tree Approach.
For the first time a Fault Tree Approach (FTA) was applied to assess biogas plant systems,
to identify failures, and to evaluate their impacts on the operation of small-sized biogas plant
systems (BPS) from a technical perspective. FTA proved to be an effective analysis tool for
the technical evaluation of biogas systems.
Five sub-systems of BPS were defined including (1) structural components, (2) biogas
appliances, (3) piping system, (4) biogas production, and (5) effluent disposal system. Based
on the statistical analysis of 100 samples, the fault probabilities of the five sub-systems are
0.32, 0.25, 0.48, 0.88 and 0.71, respectively. The weights of the five sub-systems are
determined by the Delphi method and the fault probability of the BPS is then calculated. The
results show that the expected daily biogas amount is seldom reached, failures in the piping
system happen frequently, and that proper disposal and reuse of bio-slurry are often
neglected. Regardless of any social and economic benefits of BPS implemented under the
National Domestic Biogas and Manure Programme (NDBMP), under technical aspects the
implementation of NDBMP could be evaluated as follows: (1) The operation status of BPS is
not optimal; (2) The ideal status of well-operated and performing biogas plants hardly exists;
(3) Skilled masons and quality workmanship are prerequisites for efficient functioning of BPS;
and (4) Maintenance plays a key role for continuous efficient functioning.
The definition of the system, its components and functional analysis is introduced and
technical faults, probabilistic analysis and discussion of results are presented.
A simplified calculation is performed based on failure frequency displaying the general
operation scenario of BPS under NDBMP Bangladesh.
3.1.1 Introduction
The production of biogas through anaerobic digestion provides significant advantages over
other forms of bioenergy production, and has been evaluated to be the most energy-efficient
and environmentally beneficial technology for bioenergy production 4 . Biogas, a clean,
efficient, and renewable source of energy, is gaining popularity as a substitute for other fuels
to save energy and to protect the environment 5. Biogas for Sanitation destroys bacteria,
viruses and Helminth eggs in human and animal excreta to a certain extent; the digested nd
post-composted sludge can be used in agriculture6. The development of rural household
biogas systems is an important way of promoting agricultural adjustments, reducing Green
House Gas (GHG) emissions, increasing rural incomes, enhancing the ecology in rural areas,
optimizing rural energy consumption structures, and improving the quality of both rural life
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
4
Weiland P. Biogas production: current state and perspectives. Appl Microbiol Biotechnol 2010; 85:849-60.
5
Liu Y, Kuang Y, Huang N, Wu Z, Xu L. Popularizing household-scale biogas digesters for rural sustainable energy
development and greenhouse gas mitigation. Renew Energy. 2008, 33: 2027-2035
6
Mang HP, Li Z. Technology review of biogas sanitation - Biogas sanitation for blackwater, brown water or for excreta and
organic household waste treatment and reuse in developing countries. Deutsche Gesellschaft für Internationale
Zusammenarbeit GmbH (GIZ). 2010. Eschborn, Germany
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
and agricultural products7. Anaerobic digestion for treating organic waste reduces solid waste
volumes, but enriches plant nutrients into residues8, which can then be used as fertilizer to 21!
return nutrients to the soil ecosystem9. The performance of biogas residues or bio-slurry
compared to mineral fertilizer shows positive impacts on crop yields and soil microbial
functions10.
Successful dissemination of domestic biogas technology has occurred worldwide in countries
where governments and institutions are involved in the subsidy system, in planning, design,
construction, operation and maintenance of biogas plants 11 . Several countries in Asia,
particular China and India, have launched large-scale campaigns to popularize biogas
technology12.
As an agriculture-based country, Bangladesh faces energy and environmental challenges13,
and - at the same time, has huge potentials for utilizing biogas technologies. Over 25,000
fixed dome biogas plants operated on cow dung or poultry litter have been installed in
Bangladesh until 2008. 14 Associated with Netherlands Development Organization (SNV),
German International Cooperation Agency (GIZ), and Asian Development Bank (ADB),
Infrastructure Development Company Ltd (IDCOL) launched the National Domestic Biogas
and Manure Programme (NDBMP), which aim to construct a total of 37,269 household-
based biogas plants between 2006-201215.
NDBMP Biogas Plant Systems (BPS) is based on a household-scale biogas digester: they
are usually defined as integrated systems that include pretreatment of feedstock, biogas
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
7
Chen RJ. Livestock-biogas-fruit systems in South China. Ecol Eng 1997; 8: 19-29
Gautam R, Baral S, Heart S. Biogas as a sustainable energy source in Nepal: present status and future. Renew Sust Energy
Rev 2009; 13:248-52
Chen Y, Yang G, Sweeney S, Feng Y. Household biogas use in rural China: a study of opportunities and constraints. Renew
Sust Energy Rev 2010; 14(1): 545-9
Cheng S, Li Z, Shih J, Du X, Xing J. A field study on acceptability of 4-in-1 biogas systems in Liaoning Province, China. Energy
Procedia 2011, 5: 1382-1387
Ding W, Niu H, Chen J, Du J, Wu Y. Influence of household biogas digester use on household energy consumption in a semi-
arid rural region of northwest China. Appl Energy 2012; 97: 16-23
8
Mata-Alvarez J, Macé S, Llabrés P. Anaerobic digestion of organic solid wastes. An overview of research achievements and
perspectives. Bioresour Technol 2000; 74:3-16
9
Odlare M, Arthurson V, Pell M, Svensson K, Nehrenheim E, Abubaker J. Land application of organic waste-effects on the soil
ecosystem. Appl Energy 2011; 88:2210-8
10
Svensson K, Odlare M, Pell M. The fertilizing effect of compost and biogas residues from source separated household waste.
J Agric Sci 2004; 142:461-7.
Suthar S. Potential of domestic biogas digester slurry in vermitechnology. Bioresour Technol 2010; 101: 5419-5425.
Abubaker J, Risberg K, Pell M. Biogas residues as fertilisers – Effects on wheat growth and soil microbial activities. Appl Energy
2012; 99: 126-134.
11
Mang HP, Li Z, Mantopi M, Huba EM, Schwarz D, Schnell R, Nguyen G, Kellner C, Selke J. Biogas production in developing
countries (low-tech applications) for small-scale heat and cooking gas. 2012. Springer Publication.
Jiang X, Sommer GS, Christensen KV. A review of the biogas industry in China. Energ Policy 2011; 39: 6073-6081.
Hossain G. Improved cookstove and biogas programmes in Bangladesh. Energy Sust Develop 2003, VII (2l): 97-100
Prasertsana S, Sajjakulnukit B. Biomass and biogas energy in Thailand: Potential, opportunity and barriers. Renew Energy.
2006, 31:599-610.
Gautama R, Baral S, Heart S. Biogas as a sustainable energy source in Nepal: Present status and future challenges. Renew
Sust Energy Rev 2009, 13: 2668-2674
Rao PV, Baral SS, Dey R, Mutnuri S. Biogas generation potential by anaerobic digestion for sustainable energy development in
India. Renew Sust Energy Rev 2010, 14: 2086-2094. 13: 248-252
Surendra KC, Khanal SK, Shrestha P, Lamsal B. Current status of renewable energy in Nepal: Opportunities and challenges.
Renew Sust Energy Rev 2011; 15:4107-4117
12
Bond T, Templeton MR. History and future of domestic biogas plants in the developing world. Energy Sust Develop 2011;
15:347-354.
13
Asif M, Barua D. Salient features of the Grameen Shakti renewable energy program. Renew Sust Energy Rev 2011; 15:
5063-5067
14
W.M.H. Jaim, Shabeen Akter: Seed, Fertilizer and Innovation in Bangladesh: Industry and Policy Issues for the Future, IFPRI
Project Paper, September 2012
15
Infrastructure Development Company Ltd (IDCOL). website: http://www.idcol.org/energyProject.php
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Many researchers have focused on technical problems of BPS 17 due to the fact that
operational reliability is one of the most important issues for disseminating household-sized
biogas technology. There are many methods to model reliability, among which the Fault Tree
Approach (FTA) is a deductive, top-down method aiming at the analysis of the effects of
initiating faults and events within a complex system18. Compared to other methods, FTA has
an understandable logic background structure and is thus accepted as evaluation method of
complex and multi-level systems19. It is also a risk-estimation tool that can model interactions
between events, thus deriving the occurrence of an event based on the occurrence or non-
occurrence of other events20. Fault Tree Analysis has been applied already in numerous
fields such as water supply systems, power distribution systems, and fuel cell degradation21.
Identification and analysis of potential risks in BPS are expected to improve BPS' operational
reliability, thereby optimizing actual operation impact. However, there is not yet any report
about the application of Fault Tree Analysis (FTA) in the biogas sector. !
Bangladesh is among the countries that are committed to the dissemination of household
sized biogas plants. To evaluate the general operation scenarios of BPS under NDBMP in
Bangladesh, the Biogas Audit Bangladesh gave the opportunity for nationwide data collection.
To this end, the national territory was clustered; each of the 9 clusters contained 10 to 12
BPS. A total of 100 BPS were selected and sampled. In order to gain detailed technique data,
technique assessment of BPS aiming at operation status in reality was performed. Before
field study, necessary tools were prepared for checking the components of BPS. The
household members responsible for maintaining biogas plant and cooking were interviewed
in a bid to identify the failures.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
16
Ministry of Agriculture of the People’s Republic of China. Classification of scale for biogas engineering (NY/T 667-2003).
2003. [in Chinese]
17
Cheng S, Li Z, Shih J, Du X, Xing J. A field study on acceptability of 4-in-1 biogas systems in Liaoning Province, China.
Energy Procedia 2011, 5:1382-1387.
Ding W, Niu H, Chen J, Du J, Wu Y. Influence of household biogas digester use on household energy consumption in a semi-
arid rural region of northwest China. Appl Energy 2012; 97: 16-23.
Mwirigi JW, Makenzi PM, Ochola WO. Socio-economic constraints to adoption and sustainability of biogas technology by
farmers in Nakuru Districts, Kenya. Energy Sust Develop 2009; 13(2):106-15.
Willem G, Wang G. Microanalysis of the benefits of China’s family-size bio-digesters. Energy 2010; 35: 4457-4466
Charles N, Jo D, Henri S, David T, Henry K, Herman L. Multi criteria sustainability assessment of biogas production in Kenya.
Appl Energy. 2012; 93: 496-506.
18
Bedford T, Cooke R. Probabilistic Risk Analysis: Foundations and Methods. Cambridge: Cambridge University Press; 2001.
19
Ortmeier F, Schellhorn G. Formal Fault Tree Analysis - Practical Experiences. Electronic Notes in Theoretical Computer
Science. 2007;185:139-51.
20
Bedford T, Cooke R. Probabilistic Risk Analysis: Foundations and Methods. Cambridge: Cambridge University Press; 2001.
21
!Abdul Rahman F, Varuttamaseni A, Kintner-Meyer M, Lee JC. Application of fault tree analysis for customer reliability
assessment of a distribution power system. Reliability Engineering & System Safety. 2013;111:76-85.
Lindhe A, Norberg T, Rosén L. Approximate dynamic fault tree calculations for modelling water supply risks. Reliability
Engineering & System Safety. 2012;106:61-71.
Doménech E, Escriche I, Martorell S. Exposure Assessment based on a combination of event and fault tree analyses and
predictive modelling. Food Control. 2010;21:1338-48.
Lindhe A, Rosén L, Norberg T, Bergstedt O. Fault tree analysis for integrated and probabilistic risk analysis of drinking water
systems. Water Research. 2009;43:1641-53.
Placca L, Kouta R. Fault tree analysis for PEM fuel cell degradation process modelling. International Journal of Hydrogen
Energy. 2011;36:12393-405.
Volkanovski A, Čepin M, Mavko B. Application of the fault tree analysis for assessment of power system reliability. Reliability
Engineering & System Safety. 2009;94:1116-27.
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
23!
Biogas from BPS is utilized mostly as cooking fuel. NDBMP's fixed brick dome designs are
developed for two types of feedstock: (a) cattle dung and human excreta, and (b) poultry
droppings.
Each design is constructed in 6 standardized sizes for a variety of daily gas production
capacities: 1.2, 1.6, 2.0, 2.4, 3.2 and 4.8m3.
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
24!
Figure 2: Schematic overview on an ideal and complete biogas system for farm-households;
desulfurizer22 and double burner stoves are not foreseen in the NDBMP standard model
A typical BPS is commonly described as biogas production and utilization system composed
of five main categories: structural components (e.g. inlet tank, outlet chamber and digester),
piping system (e.g. gas pipeline and valve), biogas utilization system (e.g. biogas stove and
biogas lamp), effluent disposal system (i.e. digestate storage and reuse) and elements
related to the anaerobic digestion process (biogas production). The reliability characteristics
of these categories are different in nature.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
22
While 88% of the biogas plants systems had a methane content of more than 50% (up to 70% in one case), all measured
chicken litter using biogas plants have shown a H2S content higher than 100ppm up to 3000ppm, but also 40% of the cow dung
plants showed biogas plants a H2S content of higher than 100ppm but always under 250 ppm, therefore a desulfurizer for
poultry biogas plants is of health and burner/stove material lifetime benefit.
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
diagram called a fault tree is constructed showing the logical event relationships based on
the data collected during the field missions, technical problems are identified as a basic 25!
event and criteria for FTA are defined. These criteria and descriptions for failures in the five
subsystems are displayed in the following table.
Table 4: Criteria and descriptions for failures of sub-systems of small-sized biogas systems:
B1: Failures in Sub-System "Structural components" of the audited plants:
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
26!
B4: Failures in Sub-System "Biogas production" of the audited plants:
B5: Failures in Sub-System "Effluent disposal/ reuse system" of the audited plants:
BPS failure happens because of events occurring in one or more of the five subsystems
(structural components, biogas utilization equipment, piping system, biogas production, and
effluent disposal system). As such, any failure in a subsystem (called “first-level contributors”)
can result in the abnormal operation of BPS. Similarly, subsystem failure also results from
undesirable events in the second-level contributors until the basic events.
The top event of the elaborated fault tree is the “abnormal operation of small-sized biogas
system”. The global BPS fault tree is an “OR” gate that includes the faults of any of the five
sub-systems faults. The following Figures present fault trees for the five sub-systems.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Every type of fault is broken down to identify the different causes until the basic events that
are responsible for the undesirable event are clearly deducted. Each event is numbered in 27!
the order of B1 to B5 for first-level contributors, C1 to C14 for second-level contributors, D1
to D31 for third-level contributors and E1 to E4 for forth-level contributors, respectively.
!
Abnormal!operation!of!BPS!
A!
1! 2! 3! 4! 5!
Legend!!
! Top!event! Transfer!In!
symbol!
! Intermediate!event! OR!gate!
The potential risks for the overall operation due to malfunctioning of sub-systems were
evaluated by establishing a fault tree for BPS. Based on this fault tree, the encountered
failures were classified in into five main categories and 14 key types. The following failures
were detected in the 100 sampled plants:
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Unsuitable!efMluent!disposal! 28!
Absent!of!efMluent!disposal!
No!efMluent!from!outlet!chamber!
No!enough!feedstock!
Breakdown!of!anaerobic!digestion!process!
Thick!scum!layer!
Leakage!of!biogas!digester!
Strong!leakage!of!piping!system!
Blockage!of!piping!system!
Malfunction!of!biogas!stove!
Crack!in!structural!components!
Broken/absent!of!mixing!device!
Inconvenient!position!of!plant!components!
Unsuitable!inlet!pipe!slope!
Structure!components!
Biogas!utilization!equipments!
Piping!system!
!
Biogas!production!
!Effluent!disposal!system!
! ! !
!
Figure 4: Types of failures detected in Biogas Plant Sub-systems
Legend:! !
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
In the category 'structural components', the most serious fault is an unsuitable inlet pipe,
accounting for 50% of all in detail studied BPS. After 5-year operation time, about all mixing 29!
devices are broken or missing. Among the 100 BPS samples, 5 % outlet or inlet chambers
were cracked due to flood or ground settling. It is supposed that masons and supervisors are
not aware of the importance of the correct positioning of plant components. From the
category specific fault tree displayed above, it turns out that low-quality workmanship could
be called the main reason for failure events in this sub-system.
Legend:!
Only biogas stoves have been considered in the category 'biogas utilization equipment',
based on the fact that the visited households generally do not use biogas lamps and other
appliances. The fault frequency of biogas stoves is high (25%) due to the fact that trivial
components are not well maintained - such as air injection hole, air injection ring, and gas tap.
The operational status of a biogas stove is directly linked to its efficiency. The efficiency of
biogas stoves has been quoted as 20%-56%23, which clearly depends on the day-to-day
maintenance.
In 88% of the biogas plants, methane content of more than 50% (up to 70% in one case) was
measured. All audited poultry litter based biogas plants show H2S content higher than
100ppm up to 3000ppm, but also 40% of the cattle manure fed plants produced a H2S
content between 100 and 500 ppm. BAB team therefore recommends installing desulfurizers
for the benefit of users' health - and to extend stove construction material lifetime.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
23
Itodo IN, Agyo GE, Yusuf P. Performance evaluation of a biogas stove for ISAT/GTZ. Biogas Digest Volume II. Biogas -
Application and Product Development, Information and Advisory Service on Appropriate Technology (ISAT), Deutsche
Gesellschaft für Technische Zusammenarbeit (GTZ); 1999.
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
30!
Legend:!
The most frequent failure of the piping system are weak (37%) or strong (16%) leakages; this
is obviously due to the many connections within the piping systems, inadequate material and
neglected maintenance. Any loose connection could lead to leakage. This kind of failure
event could be easily avoided through good piping material and fittings, as well as through
committed maintenance. However, the longer a biogas plant operates, the more frequent
occurs this failure.
A potential risk of blockage of the gas piping system exists when H1 is bigger than H6 (refer
to the Schematic Overview of BPS). 60% of the sampled biogas plants are constructed in
such a way that this potential risk could be detected by measuring the relevant levels; 38%
had already experienced foam or condense water blockages in the past. This failure is
caused either by missing understanding or knowledge (= missing training) and / or low-
quality workmanship.
87% of BPS are not equipped with a water trap; where the pipeline is too long, condense
water accumulates in the pipe and causes problems for smooth biogas supply to the stove.
Regular discharge of condense water is necessary to reduce the impact of this failure.
In total, 53% of the sampled BPS show failures in the piping system - either blockage or
leakage, main gas valves (25%). rubber hose (13%) or kitchen gas taps (29%). In order to
avoid any kind of failures for this sub-system both, understanding the reason why quality
work is required for plumbing and timely maintenance, play key roles for trouble-free
operation.!
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
31!
Legend:!
Biogas production is the core purpose of any BPS; and it is a key condition for satisfactory
biogas utilization. When daily biogas production yields less than 50% of the designed
standard capacity, sub-system failures must be investigated. 30% of the households reported
insufficient biogas production. Among them, 5 biogas digesters presented leakages due to
low-quality workmanship. Tests and interviews revealed in the majority (85%) of the biogas
plants too low amount of feedstock, and in 14 % existed a thick scum layer in the digester
that prevented the biogas rise. In summary, low biogas production is related to a significant
knowledge gap on biogas technology and plant maintenance. Plant owners and their
household members need to be enabled to manage their BPS for improved biogas yields.
In the effluent disposal sub-system, the most frequent failures are “unsuitable effluent
disposal” (44%), “no effluent from outlet chamber” (17%), and “absence of effluent disposal”
(31%). If no slurry overflows from the outlet chamber, the fermentation process doesn’t
operate well or the liquid is infiltrating into the ground. This failure could also be avoided by
quality check after construction and during commissioning. Bio-slurry is - besides biogas, one
of the essential benefits of the whole BPS as it facilitates resource recovery and reuse in
agriculture. However, in reality, this benefit of BPS is often neglected.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
32!
Legend:!
From the statistical analysis above, fault probability (P) of event B1 is calculated based on
fault probability of event C1, C2, C3 and C4.
P!" ≈ 0.48
Fault probability (P) of event B2 is based on failure number of event C6, which is 0.25.
Fault probability (P) of event B3 is based on failure number of event C7 and C8, which is
0.48 as explained above.
Fault probability (P) of event B4 is 0.88, based on the number of statistical failures against
100 samples.
Fault probability (P) of event B5 is calculated based on fault probability of event C13, C14
and C15. Event C13, C14 and C15 are not independent events, therefore,
P!" = P!"# + P!"# + P!"# = 0.71
Then, the fault probability of top event A, which stands for abnormal operation of BPS, is
calculated based on fault probability of five sub-systems, namely, event B1, B2, B3, B4 and
B5.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
The calculation is based on the probability theory. The result indicates that ideal operation
and performance of BPS hardly exists in reality. Any mistake could lead to a total defect of
BPS as demonstrated in the fault tree analysis. The fault probability of the five sub-systems
could be applied as operation scenarios of BPS.
100%!
90%!
80%!
70%!
60%!
50%!
40%!
30%!
20%!
10%!
0%!
Fault!of!structure! Fault!of!biogas! Fault!of!piping! Fault!of!biogas! Fault!of!efMluent!
components! utilization! system! production! disposal!system!
equipment!
!
Figure 10: Fault probability of the five sub-systems
3.1.6 Conclusions
Technical data collected during the countrywide Biogas Audit Bangladesh were processed;
findings were categorized and analyzed under the Fault Tree Approach. The faults of BPS
are summarized and criteria for failures of BPS are defined.!
Fault Tree Approach analysis contributes in a very efficient way to the technical analysis of
BPS as it helps to identify components' faults that could result in reduced performance of a
biogas plant. Among the five sub-systems – faults in biogas production (88%) (Mainly due to
underfed biogas plants) and faults in the effluent disposal and reuse systems (71%) happen
most often, followed by failures in the sub-system "piping" (48%). !
The results show that best plant performance could be achieved only through serious training
of masons and plumbers, supervisors and manufacturers, and women and men as future
biogas plant owners and users, in order to implement perfect construction work and timely
maintenance:
1. The general operation status of BPS is not at its optimum, sizes should be reduced;
2. The ideal operation and promised performance status hardly exists in reality;
3. Skilled masons, informed owners and 'operators' (mainly women) are prerequisites to
well-performing BPS.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Appraise the level of user’s satisfaction in terms of their views on quality of the product,
social and financial benefits being enjoyed from the products, problems being encountered
and user-friendliness of the offered technology.
BAB team experienced a remarkable gender specific difference in both knowledge about
biogas technology and appreciation of benefits. In the first field missions this observation was
both limited and confirmed by the fact that in 30 interviews, the team for being strangers and
men was not allowed to talk directly to the housewife, but has to rely on "second-hand"
information provided by husbands and male relatives about female opinions on biogas
technology. This chapter therefore presents findings focusing on women.
The decision to expand BAB team by a national female junior expert resulted in a significant
increase of interviews with biogas using housewives, and thus in a wealth of insights which
men as official plant owners would not have been able to provide.
The level of knowledge of the interviewed women about biogas technology is exceedingly
poor. This lack of knowledge leads to a number of obstacles for successful program
implementation, and hinders the capitalization of biogas benefits in the households of the
BPS owners. Overall little knowledge on biogas plant management creates both, confusion in
the female user and reduced performance of the biogas plant. As a result some women
consider installing a biogas plant as an awful decision of the husband. The following list is
based on the gender-specific analysis of 106 household interviews:
• Women don’t obtain the required information about maintenance and cleaning of
biogas appliances: even in the cleanest kitchen stove plate holes were found filled
with food remainders, which create disturbance of gas transient.
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
• Women are not informed about how to control slurry intrusion in the gas pipe. They
have no idea about the utilization of the main gas valve; therefore they tend to keep 35!
the main gas valve open after cooking, and they do not close it during plant feeding
which results in slurry intrusion in the gas pipeline.
• Women are not informed about the flame color or height, which indicate the gas
pressure, efficiency and the gas consumption rate.
• Women are not taught how to detect the presence of water in the gas pipeline by
observing the flame movements.
• Knowledge about bioslurry is for a large number of women at the rank of zero. Some
of them believe that bioslurry management and distribution aren’t their
responsibilities. Although the women of many tribes in the hilly region have the
liability of agricultural practice they aren’t aware about the value of bioslurry.
• Women’s participation in training and information sharing on biogas technology, plant
and slurry management is not common.
• Most of the interviewed women are not aware about the health hazards caused by
smoke from firewood although they themselves suffer from eye irritation and
respiratory health problems.
• Women who felt inspired by biogas plants built in the neighborhood said they could
not convince the husband or the head of the family to invest in a biogas system.
• A nice stove is a common demand among the interviewed women. Some of the
women use modern looking stoves designed for LPG but not for biogas. This results
in lower performance of the biogas plant system.
• The distance between stove and the gas valve is a matter of irritation for the women;
therefore they generally do not close the main gas valve.
• Most of the interviewed women hesitate to use human excreta as raw material for
biogas production whereas interviewed men are openly thinking about using human
excreta to increase biogas yields and to replace reduced feedstock from poultry litter
or cattle dung.
• Women’s expectation on biogas yields relate to the size of the biogas plant, not to the
amount of feedstock and the regularity of feeding. Eventually women are unaware
about the amount of raw material for biogas generation that is related with the
number of cattle or poultry. Even with decreasing numbers of animals, women still
expect equal cooking hours like before.
• It is common that women are responsible to mix cow dung and water for cattle
manure based biogas plants but most of them don’t know the mixing ratio of cow
dung and water. Men are often responsible to feed poultry litter based plant.
BAB team emphasizes the need to include women's perspective into the NDBMP
program design, starting with promotional activities, training events and attractive stove
models, and by hiring female staff in NDBMP and the LCPOs. The following list -
although not exhaustive - contains recommendations collected during the interviews with
female biogas users:
• The stove design should be changed to make the kitchen more attractive; and the
distance between stove and stove valve should be reduced.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
• Create awareness about the effect of firewood smoke, which causes cancer,
coughing, bronchitis etc. 36!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
BAB interview partners confirmed this observation. The following table displays the
participation, disaggregated by gender, in training, orientation and information transfer. 37!
Table 6: Information and knowledge transfer from LCPOs to biogas owners and operators
No training at all 59
Leaflet! 12
The Construction Manual is generally used as training material for LCPO technicians,
masons and supervisors. However, LCPOs complain that the manual alone is not sufficient
for supervisor training, as the tasks of a supervisor covers not only construction issues but
also plant siting, bio-slurry use, user training in maintenance. In addition, LCPOs ask for
training in promotion, marketing and gender inclusion.
BAB team concludes that women’s participation in any training event and information session
on biogas plant operation and maintenance as well as slurry management should be more
emphasized than it is currently done by NDBMP and LCPOs. The training should include
stove and pipe cleaning procedures, and explain the relation between visible indicators -
such as flame color and movements, and plant operation.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Chapter 3.4 summarizes the findings related to bio-slurry use and disposal according to the
Specific Objective 6:
Document different effluent application methodologies in relation to fertilizer efficiency and
soil improvement quality
BAB database analysis reveals that those biogas plant owners, who use bio-slurry for
different purposes, developed very individual ways of bio-slurry application. Still 31% of
biogas plant owners have no slurry pit and their system discharge the effluent directly to
neighbouring fallow lands or water bodies; 44% have one pit - very often just a pond; and
about 25% have 2 and more storage pits for slurry.
This corresponds with the data on slurry use: 31% who discharge the effluent directly into the
environment do not see any opportunity to use the slurry as fertilizer; 50% told BAB team
that they are using 100% of the produced bio-slurry - either as fertilizer on own lands or as
commercial product (liquid and dried fertilizer; dried dung cake as fuel). About 19% of biogas
farmers store the slurry at least seasonally and for partial use.
Some plant owners told BAB team that using bio-slurry improves both taste and harvest
yields of vegetables and crops. Among those who apply bio-slurry types of use vary
remarkable, including organic fertilizer without composting (15%), with composting (36%),
mixed with other agricultural residues (9%). If bio-slurry is managed, bio-slurry is used for
fish feed (15%) - either liquid or dried; in dried form bio-slurry is sold as fertilizer for
gardening (43%), or as dung stick for kitchen fuel (12%).
LCPOs do talk to farmers about the potential benefits of bio-slurry, but they are obviously not
able to support farmers in the correct application of slurry or in marketing efforts. Therefore
the number of owners who sell slurry as fertilizer is still very limited; some sell up to 20% of
their slurry production every month at 1 to 2 TK/kg, summing up to 3000 TK/year. One
biogas plant owner usually sells bio-slurry for 10 000 TK/year.
It is, however, relevant to notice that still 50% of the biogas farmers experience problems
with bio-slurry management; either for its liquid form or for the knowledge gap about its
properties: while some farmers are afraid that their crops will be negatively affected by the
high nutrient content of bio-slurry, others guess that bioslurry contains less nutrients than
cow dung.
During the Field Missions, BAB team observed the following risks related to currently
practiced bio-slurry management among NDBMP biogas plant owners:
• Safety distances between water sources and slurry pits, or water sources and pit
latrines are often not respected thus creating risks of contamination by nitrates,
nitrites and pathogens.
• Slurry pits are generally not sealed resulting in infiltration, runoff, and leaching, or
they are permanently overflowing resulting in one point pollution and soil overloading.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
The review of program documents motivated the Consultant to revise and adapt the originally
planned content of VOLUME II, chapter 3.5: "As the NDBMP also envisions making access
to biogas for smaller households, it is proposed to promote also smaller plants requiring a
daily feeding of 30 kg of dung (3 cattle head). Such plant should be able to produce gas for
cooking during at least 3 hours" (Implementation Plan, National Domestic Biogas and
Manure Programme in Bangladesh, Final version April 2006).
Therefore, this chapter does not focus on internal IDCOL management strategies
Appraise the internal IDCOL management and sector coordination and document
findings along with the responsibility matrix.
Instead, it is dedicated to future trends and opportunities in the biogas sector development.
This includes three relevant topics:
1. NDBMP database for internal monitoring and quality control;
2. The situation of LCPOs as key stakeholders for sustainable sector development;
3. Prefabricated biogas plants as an opportunity to tackle various challenges of NDBMP such
as implementation speed, construction quality issues, subsidy policies, commercial feasibility
and sustainable market development.
BAB team was informed only in May 2013 that NDBMP stopped the use of its web based
database in December 2012 as too many differences in spelling, understanding and
interconnection with "desktop" database were detected; this underlines the BAB and TA
observations. In the ongoing reprogramming process, BAB recommendations will be
considered as well.
Until October 2012, in total 52 LCPOs had contributed to build 20157 biogas plants across
the country. BAB focused on companies with current IDCOL contracts when sampling
LCPOs for semi-structured interviews; 12 of the 31 active (2012) companies were
interviewed in their headquarter and two in branch offices between November 2011 and
September 2012. These 12 companies have constructed 68.73% of all NDBMP biogas
plants (13851 out of 20157) and are still actively contributing to the sector. Apart from the two
branch office interviews, open talks were also conducted during field visits with
representatives of LCPOs met on site.
The interviews collected data on eight different aspects relevant for biogas sector
development.
1. Partner Organization identity and profile;
2. Domestic biogas technology dissemination approaches;
3. Program framework, capacity building and monitoring;
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Parameter % of responses
1 Construction 66
2 Financing 66
3 Maintenance 58
Parameter % of responses
1 Domestic biogas 66
2 Solar Energy 66
Parameter % of response
1 Microcredit 50
2 Solar 33
3 Donor support 25
4 Biogas 17
5 Consultancy services 17
6 Health services 17
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Two organizations have dual legal status, one as NGO and Microfinance Institution, and one
as Microfinance and Private Company.
Table 11: Business Nature of LCPOs
Parameter % of responses
1 Not-For-Profit 75
One LCPO has dual business nature: sometimes Not-For-Profit and sometimes commercial.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
All LCPOs are using published material from IDCOL/ NDBMP. Apart from using this material,
their main promotional tools are door-to-door visits.
Table 12: Promotion material
Parameter % of responses
Usually the key message for promotion of biogas is "easy cooking"; in addition, LCPOs
emphasize the use of bioslurry as substitution of chemical fertilizer.
To disseminate the programme messages and to motivate farmers to invest in biogas plants,
LCPOs adopt different methodologies such as awareness programs, house-to-house visits,
focal group discussions, visits to local leaders, posters and leaflets, orientation and yard
meetings, and presentations at fairs.
98% of the biogas plants for which LCPOs signed agreements with farmers are already
constructed, and 2% are currently under construction. Usually the construction starts within
one (50%) or two (41%) weeks after signing the agreement between client and LCPO. All
LCPOs have internal quality control systems (IQS) in place: 75% of the LCPOs monitor each
and every plant during construction, 17% monitor samples only, and 8% monitor only in very
specific cases believing that their masons are following each quality instruction. Quantity of
appliances and pipes are checked in each site by masons and supervisors, however, the
quality of these materials is not controlled, as LCPOs believe in brand names and NDBMP
selection.
Table 13: After construction services (ACS) / After Sales Services (ASS) and monitoring
Parameter % of responses
1 Every year in each plant 41
2 In critical situation 33
3 Each month 25
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
50% of LCPOs address the user's complaint within a week, 41% on the next day and 8%
during the same day. Major problems addressed are listed in the following Table. 43!
Parameter % of responses
1 Less gas 58
2 Stove stops to burn during the time of cooking 33
3 Pipe leakage 17
5 Nipple broken 8
6 Gas valve problem (broken) 8
7 Slurry in pipeline 8
Before 2012, 92% of the biogas plants (13843/14987) are so far financed with loans. 25% of
the owners ask for a loan for more than 75% of the plant cost; 58% need 50 to 74%, 17%
request less than 50% of the plant cost. 58% of the LCPOs start construction work within one
week after signing the loan agreement, and others within two weeks. The main problem with
the loan management is the down payment by the plant owners; another barrier is that
owners don’t have transport and time to come to the LCPO office to sign the loan agreement,
and in many cases construction starts before the loan agreement is signed.
The period of loan repayment differs: 50% of the LCPOs mention 2 years, 25% say 1 to 2
year, and 8% give 3 years. Each of the LCPOs motivates users to perform extra income
generation activities such as sale of fertilizer, sale of gas (in case of excess), fish cultivation
and other activities to repay the loan in time.
The main problem of the loan procedure is the cash collection, as there is no collateral and
guarantee; LCPOs suggest that it would be easier, if loans to local groups could be applied.
In addition, the fact that masons and construction supervisors are responsible for cash
collection complicates the procedure. As far as possible the responsibilities for construction
and loan should be separated, as they are two different processes.
During visits and discussion it turned out clearly that the subsidy paid from IDCOL for each
biogas plant is understood by the LCPOs as institutional support or payment from IDCOL to
the LCPO for their work. The biogas plant owner benefits from this subsidy only as “not
invoiced services”, but has no control whether or not these services are provided by the
LCPO at a correct cost. This hinders the transparency of the whole subsidy system and
creates distrust between biogas clients and LCPOs. Concerning the discussion about
subsidies, please refer to the following Chapter 3.5.6 and Tables 18 – 22.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
The LCPOs fix their biogas targets considering the following parameters:
• Information from staff involved in biogas work at household level (67%)
• Looking on previous year's progress (66%)
• Through market study (33%)
• Based on IDCOL-NDBMP requirements (8%)
• Availability of masons (8%)
However, only 33% achieve their targets, while 67% cannot accomplish their plans. Reasons
for the success are identified as quality of construction, goodwill of company and dedication
of staff and organization.
Reasons for not achieving the targets are:
• Focus on construction of plants against cash only;
• Preferring other financing mechanism as they are no longer interested in loan
procedure;
• Other institution gives more subsidy (up to 17000TK) per plant in the same area;
• Benefit from loan procedure is not sufficient to cover operation costs;
• Lacking sources of funds
• Less subsidy
• The organization is not experienced in strategic planning and target setting
• High staff turnover, lack of skilled manpower
• Lack of maintenance knowledge
• Increased cost of construction material
• Poultry firms shut down due to bird flu
• Number of cattle decreased
• Construction material not available
• Management issues within the organization
92% of the LCPOs are receiving the payment of subsidies on time as soon as the loan
agreement is signed; as per agreement between the LCPO and IDCOL this payment is due
21 working days after submission of an invoice.
Table 15: Payment of subsidies from IDCOL to LCPOs
Parameter % of responses
4 Two weeks 8
33% of the LCPOs are not satisfied with the payment mechanism in place:
• Procedure takes long time for preparation;
• Cost variations in different regions are not considered.
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
25% of the LCPOs are convinced that biogas technology could be a sustainable business
even without subsidies and even at household level. 45!
In 2013, only 21 LCPOs signed a contract with IDCOL’s NDBMP in contrast to 31 in 2012
(2006/7: 54 LCPOs). This process of slimming down the number of biogas program
implementers contains both positive and negative aspects: the positive aspects indicate that
the committed LCPOs are interested to take ownership of the biogas program, as even in the
interviews some of them mentioned that biogas technology could be a good business; the
negative aspects proof the following statement of the SIXTH FIVE YEAR PLAN FY2011 –
FY201524 - although this statement relates to the formal banking sector, it describes to a
certain extend the business understanding of a number of LCPOs: “The combination of
public ownership and lack of competition contributed to not only weak performance of the
banking sector measured in terms of what is known as the CAMEL indicators, but very
importantly, the banking sector became a huge source of rent seeking and corruption.”
Already in 2005, the IDCOL-SNV Technical Feasibility Study describes: “The participation of
stakeholders varies from consultative, contributory, operational and collaborative depending
upon the nature of tasks to be performed. Biogas program is recommended to encourage
operational and collaborative partnership as far as possible. This will help in
institutionalization of partners and building true ownership feeling of the interventions by the
stakeholders.“ 25
In 2009, the revised NDBMP Implementation Plan links ‘ownership’ only to the GoB: “A
degree of government ownership is critical to the long-term survival and sustainability of the
sector.”26
The biogas sector in Bangladesh is today characterized by competition of subsidy levels, and
not by market oriented competition of companies that search to win customers by delivering
high quality products and by providing reliable services. In the view of most of the LCPOs,
the term „ownership“ refers only to the farmers who have to pay and maintain their biogas
plant, not to themselves as the real owners of the national biogas program and the drive for
implementation. Especially the smaller LCPOs do not see themselves in the ‘driver’s seat’ -
but IDCOL staff; instead, they understand their role in the program as contractor (in the worst
case as odd-job man), not as entrepreneur in a nascent business sector.
Biogas plants are constructed on the basis of a general quotation, which is prepared annually
by NDMP; the LCPO revises and adapts the quotation according to local prices. 83% of the
LCPOs define their quotation on the basis of market prices and considering their internal
expenses. 17% of the LCPOs apply directly the NDBMP quotation. 50% of the LCPOs are
satisfied with this type of quotation where as 50% have some reservations as neither
transportation costs nor contingencies are included.
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
24
SIXTH FIVE YEAR PLAN FY2011-FY2015, Accelerating Growth and Reducing Poverty Part!1, der Strategic Directions and
Policy Framework Planning Commission, Ministry of Planning ,Government of the People’s Republic of Bangladesh
25
Prakash C. Ghimire, Renewable Energy Consultant, Development Partners – Nepal: Feasibility Studzý Biogas Program
Bangladesh, 2005
26
Revised Implementation Plan 2009, IDCOL
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Parameter % of responses
1 10% -15 % 50
2 Balance 17
3 No gross profit 8
4 0-10% 8
33% of the LCPOs don’t know the break-even-point of biogas plant construction activities, as
they never analyzed it.
One LCPO told BAB team that the break-even-point should be calculated based on the cost
for masons; currently the LCPO employs 16 masons and the break-even-number of biogas
plant construction therefore would be 16 x 4 x 12 = 768 (note: this organization built 965
plant in 7 years). 25% of the LCPOs guess that they need to construct 100 biogas plants to
achieve the break-even-point. Regarding the net profit, 33% told BAB team that the profit
from each plant is about BDT 5.000; 8% talk about a net profit of 6%, where as the rest
claims that biogas business is a loss and without any economic profit at all.
Table 17: Economic performance of LCPO biogas departments in FY 2012: 58% are in loss
Parameter % of responses
1 Break-even 17
2 Loss 25
3 Not analyzed 25
None of the LCPOs runs a workshop for biogas appliances. 17% affirmed that they purchase
the appliances from NDBMP recommended manufacturers.
The topic ‘subsidy’ is raised and discussed since long; LCPOs claim that their biogas
business could never be financially viable if the subsidy would not be increased significantly.
The subsidy increase from BDT 7.000 to BDT 9.000 in 2008, resulted in an increase of
biogas plant constructions in 2009. In the last annual review meeting, IDCOL agreed to
assess the subsidy demand of LCPOs in the NDBMP framework. Together with some
LCPOs the IDCOL biogas team calculated the minimum subsidy amount that will bring a
LCPO biogas business to the breakeven point. The Consultant was asked by KfW to revise
this calculation based on the BAB findings. In the following chapter - and especially in the
Tables 18 to 22, in which the Consultant performed a detailed calculation based on data
obtained from LCPOs and IDCOL.
The following example of a financial analysis is based on the assumptions:
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
1.2 1.6 2 2.4 3.2 4.8 1.2 1.6 2 2.4 3.2 4.8
1! Materials!
1.1! Bricks Nos 850 935 1130 1250 1470 1890 Nos 770 900 1020 1130 1334 1726
1.2! Sands Cu. m. 1.6 1.8 2 2.2 2.5 3.3 Cu. m. 1.5 1.5 1.8 2 2.3 3
1.3! Aggregates Cu. m. 0.3 0.35 0.45 0.5 0.65 0.9 Cu. m. 0.3 0.34 0.42 0.48 0.62 0.88
1.7! Polythine m 1 1 1 1 1 1 m 1 1 1 1 1 1
2! Appliances!
2.1! Dome Pipe m 0.6 0.6 0.6 0.6 0.6 0.6 m 0.6 0.6 0.6 0.6 0.6 0.6
3.2! Maintenance Fee (‘000) BDT 0.7 0.7 0.7 0.7 0.7 0.7 Takka 0.7 0.7 0.7 0.7 0.7 0.7
3.4! Labours* Mandays 15.36! 18.48! 21.6! 24.72! 28.96! 39.44! Mandays 15.36! 18.48! 21.6! 24.72! 28.96! 39.44!
*!per!cum!earthwork!excavation!is!taken!as!0.8!md!/cum!!and!the!excavation!qty!is!taken!as!3.5!times!the!size!of!plant!and!2!labors!per!one!mason!
!
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
1.2 1.6 2 2.4 3.2 4.8 1.2 1.6 2 2.4 3.2 4.8
Materials BDT 14776 16820 19936 21852 26534 34992 14066 16378 18966 20826 24998 33832
Bricks Nos 6800 7480 9040 10000 11760 15120 6160 7200 8160 9040 10672 13808
Sands Cu. m. 1120 1260 1400 1540 1750 2310 1050 1050 1260 1400 1610 2100
Aggregates Cu. m. 720 840 1080 1200 1560 2160 720 816 1008 1152 1488 2112
Cement Bags 5280 6240 7200 7680 9600 12480 5280 6240 7200 7680 9120 12480
GI Wire Kg 100 100 100 100 100 150 100 100 150 150 200 200
MS rod Kg. 576 720 936 1152 1584 2592 576 792 1008 1224 1728 2952
Polythine m 180 180 180 180 180 180 180 180 180 180 180 180
Appliances BDT 3896 4026 5161 5251 5728 6896 3896 4026 5342 5342 5908 6006
Dome Pipe m 300 300 300 300 300 300 300 300 300 300 300 300
Brass Nipple Nos 110 220 220 220 330 330 110 220 220 220 330 330
Main Valve Nos 320 320 320 320 320 320 320 320 320 320 320 320
Gas Tap /Ball valve Nos 320 320 640 640 640 960 320 320 640 640 640 640
Stove Nos 750 750 1500 1500 1500 2250 750 750 1500 1500 1500 1500
Mixer Nos 750 750 750 750 750 750 750 750 750 750 750 750
Hose Pipe m 328 328 393.6 393.6 393.6 492 328 328 393.6 393.6 393.6 492
Inlet Pipe m 721.6 721.6 721.6 811.8 902 902 721.6 721.6 902 902 1082.4 1082.4
Emulsion Paint litr 220 220 220 220 440 440 220 220 220 220 440 440
Labor BDT 7008 8344 9680 11016 12688 17032 7008 8344 9680 11016 12688 17032
Mason Man-days 2400 2800 3200 3600 4000 5200 2400 2800 3200 3600 4000 5200
Labor Man-days 4608 5544 6480 7416 8688 11832 4608 5544 6480 7416 8688 11832
Total BDT 25680 29190 34777 38119 44950 58920 24970 28748 33988 37184 43594 56870
Total cost of plant BDT 25680 29190 34777 38119 44950 58920 24970 28748 33988 37184 43594 56870
Construction Material cost of plant 14776 16820 19936 21852 26534 34992 14066 16378 18966 20826 24998 33832
Cost of appliances BDT 3896 4026 5161 5251 5728 6896 3896 4026 5342 5342 5908 6006
Cost of Labor BDT 7008 8344 9680 11016 12688 17032 7008 8344 9680 11016 12688 17032
!
Table 20: Operational expenses per LCPO and its 10 Branch offices
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
2. Operating expenses
Cost of branch office 510
Item Cost of central office
plants
Office rent 3500 10000 540000 1059
Table 21: If 510 plants per year per LCPO are constructed, an institutional support of
BDT 8.100 / plant is needed
Table 22: If 810 plants per year per LCPO are constructed, an institutional support of
BDT 6.000/plant is needed
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
In the discussion of a general increase of the subsidies from BDT 9.000 to BDT 13.500 the
following aspects have to be considered:
1. Staff:
(i) Not all LCPOs maintain Branch Offices with 2 employees; in smaller LCPOs the Branch
Manager works as supervisor.
(ii) In LCPOs headquarters, the tasks of the program coordinator could be combined with
the tasks of the program manager – there is no evidence that 2 similar functions should be
subsidized as overheads.
(iii) In average, total biogas staff in successful LCPOs that achieve the quality construction
of 510 biogas plants per year, should be composed by 1 program manager, 1 accountant,
5 branch manager, 10 supervisors, and 20 masons.
3. What will happen, if the Branch Office cannot construct the minimum of 51 biogas plants
per year?
4. Construction costs should be revised, too, not only the subsidy level: A significant number
of biogas plants has no mixing device; central gas pipes are locally produced (cheaper than
calculated); digging is not completed as it has been calculated for – thus construction costs
do often not reach what has been calculated as a matrix.
5. There is a new tendency that two third of the biogas clients pay in cash, only one third
requires a long-term loan. Is this already reflected in the "selling price"? This will change if
smaller biogas plant sizes are better promoted.
6. Considering the fact that most of the biogas plants are under-fed, and referring to the
socio-economic conditions of the target group (pro-poor) the Consultant proposes that
subsidies should be increased mainly for plant sizes of 1.2, 1.6 and 2m3 in order to broaden
the ‘pro poor’ segment in IDCOL’s biogas program. Subsidies for 2.4m3 could be slightly
adjusted, but not for the plant sizes of 3.2 and 4.8m3.
7. It should be further analyzed if biogas plants built at commercial poultry farms should be
included in the subsidy scheme, especially when the biogas is sold or electricity is generated.
9. The subsidy concept as elaborated recently in 2013 focuses on the business development
of LCPOs, not on potential biogas plant owners. It could be doubted if this subsidy concept
contributes to achieve commercially viable market oriented biogas technology dissemination
in Bangladesh. In addition, it even does not integrate in the calculations any After-Sales-
Services and refurbishment costs (after 5 years) to assure the well performance of the
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
biogas plant: no performance indicators are related to the subsidy disbursement. As long as
the potential customer does not realize a benefit from the increased subsidy, the pace of 51!
plant construction will not boost.
BAB team asked LCPO representatives to give their opinion about NDBMP to support efforts
towards sustainable development of the national biogas sector. The following tables give
proof of serious interest of the partners in the long-term establishment of a commercially
viable biogas industry.
Table 23: SWOT analysis of NDBMP programme conducted by LCPOs
Strengths Weaknesses
Opportunities Threats
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Fiber glass use (prefabricated plants) Slurry may pollute ground water if not properly
Big market managed 52!
Use of latrine Health Hazards
Many biogas can be built as there are lots of Loan Repayment
farmers and lots of available feed stock Shortage of skilled and available masons
Table 24: Advantages and disadvantages of biogas technology for LCPOs and the country
In contrast to onsite brick-concrete constructed digesters, prefabricated digesters are produced off-
site from a wide range of materials that are endowed with special physical properties.
Prefabricated digesters are characterized as follows:
• Affordable in view of their service life
• Convenient and easy to maintain
• Could serve as collateral because they can be removed and sold second-hand
• Transportable on a ready-to-assemble package
• Customized sizing to meet different purposes
Prefabricated biogas digester are suitable for places where
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Maintenance Normal use will not cause damage to digester body, Should be maintained, probably repaired
and its cost or medium term maintenance; it can be used (emptied) in medium term that causes stop of
continuously. No stop of gas production, no need of gas production, interruption of use, risk for
maintenance cost. high maintenance cost.
Service life Over 25 years, if industrial manufactured, even longer Normal service life exceeding 10 years, but
if installed underground maintenance is necessary in case of cracks
5-year Maintenance free, low operation cost, normal Due to possible cracks in digester body and
operation operation serious stripping of internal surface, at least
emptying and maintenance recommended
once in five years; significant operation cost.
10-year Digester body is free of maintenance; low operation Risk of serious leakages resulting from
operation cost, normal operation cracks in digester body and serious stripping
of internal surface; continuing normal
operation after major repair; significant
operation cost.
Total Reasonable initial investment, free of regular Less initial investment, need for regular
investment maintenance, limited operation cost maintenance, high operation cost
Mass (weight) Light, specific weight ≤1.9, designable to dome Huge weight, general transport of only the
structure, easy overlapping for transport, increased material, easy damage; prefabricated
number in transport and reducing transport cost members for assembly, but increased
transport cost
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Biogas output Conforming to applicable national standard and Conforming to applicable national standard
30% over the national standard, energy-saving and
cost effective
Gas leakage No pressure drop 24h after filling gas of 10kpa Allowable 3%, 24h after filling gas of 8kpa
(air tightness)
Building cycle Easy and short-time installation, short building cycle Long building cycle of generally 8-12 days
of generally 1-2 days
ce
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Digester, storage bag, hard/soft pipe, desulfurizer, biogas blower pump, T joint, switch,
Components
bend, reducer, straight connection, slurry sucking machine, etc
3 3 3
Volume of digester 6m 8m 10m
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
Voltage: 220V; Outlet gas pressure: 0.03MPa; displacement: 0-30L/min; outlet pipe
Blower pump
diameter: 16mm; power: 25kW
Even if the frame conditions - such as high ground water table or extended flooding, long
rainy seasons, soil temperature throughout the year at least 20oC, and limited access roads
(minimum for 6t trucks) are recommending the installation of prefabricated biogas digesters,
there are more criteria to be considered before a decision about the type of prefabricated
digesters should be taken.
Table 30: Criteria list to select best appropriate prefabricated biogas plant
Criteria Details
o GWP impact is 0.032 kg CO2 equivalent per kg cement (country specific
Construction material Green
figures!)
House Gas Inventory for Life-
o GWP impact is 0.101kg CO2 equivalent per brick (country specific
Cycle-Assessment (LCA)
figures!)
o Transport of construction material and workers
Energy Inventory o Energy need during on-site installation
o Energy input during operation
o Recycling of construction material after operational lifetime
(environmental impact)
End-of-Life o Operational lifetime (esp. in situation where people are yet to be
motivated for the adoption of this technology and the necessary skill and
materials are not readily available, it is necessary to prefer plants with
longer life though it may require higher initial investment.)
o A design should be simple and understandable, not only for construction
Simple Design
but also for "operation and maintenance”.
o Work input (time and staff) needed during installation.
Utilization of easy available
o Consider to make use of easily available materials, also for repair work
material
o The feeding and digester design should be compatible with the type of
inputs to be used (cattle, pig or poultry manure, mixing with straw, feed
Suitable for the type of feedstock residues, kitchen waste, urine, water...)
to be used o Potential dry matter content which could be handled within the digester
o Stable floor connection possible,
o If toilet connection possible and acceptable, preventive measures for
short cut avoiding from inlets to outlet etc.
o Selection of a particular design and size of its various components or
Frequency of Using Inputs and
parts also depends on how frequently the user can feed the system and
Outputs
also how frequently the gas will be utilized.
o Biogas storage sizes, maximum and average pressure.
Banking business model o Prefabricated biogas plant itself could be used as loan collateral
3
Cost relations o Price per m construction and/ or effective volume
!
FINAL REPORT Biogas Audit Bangladesh 2011 - 2013, VOLUME II!
1. Household Questionnaire
2. LCPO Questionnaire
3. Contacts during BAB onsite missions
!
!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
HOUSEHOLD Questionnaire
for Verification &Audit Mission to NDBMP
Informed consent & cover page
Greetings! My name is ______________________________. I am here on behalf of the German
Development Cooperation supporting the National Domestic Biogas and Manure Program. We
are conducting a detailed analysis of biogas plants installed in the country since 2006 under the
framework of the program – especially observing biogas production and use, and the handling of
bio-slurry. In order to get more information about your biogas plant, its operation and the
challenges and benefits you are experiencing, we are conducting a survey of households in this
area.
Your household has been selected by chance from all the households with biogas plants in this
area. I would like to ask you some questions related to the installation, operation, maintenance
and other issues related to your biogas plant. We would also like to take technical measurements
of the plant components and carry out some tests to evaluate the plant’s overall condition.
The information you provide will be useful to find out the status of biogas plants not only in your
community, but also in general in other regions and will be used to plan future improvements of
the program for biogas energy in Bangladesh.
All the information you give will be dealt with as confidential; it will be used to prepare general
reports, without mentioning any specific names. There will be no way to identify that you are the
one who gave this information.
Participation in the survey is voluntary, and you can choose not to take part.
If you have any questions about the survey, you can ask the NDBMP staff or the LCPO staff who
are both here with the survey team. Do you have any questions about the survey?
Name and Signature of interviewer
Date:
Respondent agreed to be interviewed 1. YES 2. NO
Signature of Respondent
Interviewers:
Remember to obtain consent from each household. Write answers directly in the tables and
mark the boxes at each question. The listed options just provide for facilitation - don’t give
answers instead of your interview partner. Enable her/him to say " I don't know" or to give any
answer even if not listed among the options.
Check ALL answers recorded in each section, ensuring gaps or missing answers are
obtained BEFORE leaving the household.
_____________________________________________________________________
Data Entry personnel
Name
Date
Data Entry Code
! 58!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
1. HOUSEHOLD IDENTIFICATION
This section is to be completed for each household visited
101. Plant Code No (NDBMP Database)
102. Central Gas Pipe Number (LCPO register)
103. Name of the Plant Owner
104. Phone No.
105. Responsible LCPO (NDBMP Database)
106. Contact Telephone No.
107. District name
108. Village Name
109. GPS
110. Sample number
3
111. Type and Size of Plant Cattle dung Poultry manure m
112. Type of Financing Loan Cash
113. Date of construction &operation start-up
114. Construction type of house
115. Electricity supply (grid connection) Yes No
116. Total number of persons benefitting from biogas
for cooking
117. Family members of plant owner living in the house:
Female adults Male adults Girls (age 12 Boys (age 12 Girls (age Boys (age
(age >18) (age >18) – 18) – 18) <12) <12)
2. ANIMALS
Numbers Total number If open grazed, for
Adult Calf before 5 years how many
Livestock
Stall- Open- Stall- Open- hours/day? In which
fed grazed fed grazed season?
Cow/Oxen (201-
206)
Poultry (207-212)
Other animal (213
- 218) (specify)
3. INSTALLATION AND FUNCTIONING OF YOUR BIOGAS PLANT Data Entry
codification
Why did you decide to have a Biogas Plant? 301
Please describe your motivation:
How did you get to know about Biogas Technology? 302
Please describe
Who constructed your biogas plant? 303
1. Unskilled Mason
2 LCPOs’ Mason
3 Local Skilled Mason
4 Do not know
Were any standards set by the Partner Organization regarding the 304
quality of construction material and mason to construct biogas
plants?
1 No
2 Yes
3 Do not know
! 59!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
If yes, what types of quality standards were set (answers can be more 305
than one)?
1 Trained masons should be used
2 Standards on construction materials
3 Standards on pipe and appliances
4 Standards on plant design
5 Do not know
How much time was needed to complete the installation of your biogas plant?
1 From the first request: days / weeks / months 306
2 From the day of layout: days / weeks / months 307
Are you satisfied with the performance of the Partner Organization 308
during the preparation and construction of your biogas plant?
1 No
2 Yes, Partly
3 Yes, Fully
4 Please give reasons:
Is your biogas plant functioning according to your expectation and 309
knowledge?
1 No – if no, continue with 310, 311
2 Yes, partly – continue with 312
3 Yes, fully – continue with 313
If your plant is not functioning / has failed, how long is the plant 310
defunct?
1 Less than a month
2 1 to 4 months
3 4 to 12 months
4 More than a year
5 Never started
If your plant has failed, what do you think are the reasons for such 311
failure(s)?
1 Poor workmanship during construction
2 Sub-standard quality of construction materials and
appliances
3 Poor operation because of poor training (over fed,
under-fed, too much water, too less water)
4 Poor maintenance/ No maintenance service available
5 Non-availability of spare parts
6 Natural disasters
7 Slurry entered into the gas pipe
8 Water collected in pipe clogged it
9 Higher water table/flooding during rainy season
10 Do not know
11 Others (please specify)
If your biogas plant is partly functioning- what does not work 312
according to your expectations and knowledge?
1 Biogas production not as expected and required
2 Mixing device is damaged / broken
3 Inlet pipe is blogged and cannot be cleaned out
4 Slurry production is not as expected
5 Other (please specify)
If “Yes, fully functioning”: are you satisfied with the biogas plant? 313
1 No - if No, continue with 314
2 Yes, partly – continue with 315
3 Yes, fully – continue with 316
If you are NOT SATISFIED, what are the reasons? (more than one 314
answer possible)
1 Not enough gas for cooking/lighting
2 Difficult to operate
3 Often encountering technical problems
4 Additional work
! 60!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
1 No training received
2 No training but leaflet/booklet/manual provided
3 Yes, service provider gave training
3 Yes, family head (husband / wife – please mark!)
received training by service provider
4 Housewife was informed by husband about plant
operation and how to cook on biogas
5 Yes, husband / wife (please mark!) received one day
orientation training provided by service provider
6 Yes, husband / wife (please mark!) received short
term O & M training (7days or less)
7 Yes, husband / wife receivedon the spot instructions
from mason/company supervisors etc.
8 Beside technical training, agricultural aspects have
been highlighted by service provider
9 Others (specify)
Have you received any follow up services from the Partner 324
Organization?
1 No, not even when requested
2 No, not at all
3 Yes, on call
4 Yes, regularly (Please give period of “regularly”)
Is there any service center nearby? 325
1 No
2 Yes, very near (with in 5 km reach)
3 Yes, quite far (5-10 km reach)
4 Yes, very far (more than 10 km reach)
Is a toilet attached to biogas plant? 326
1 No, we do not have toilet - continue with 328
2 We have toilet but not attached to biogas plant -
continue with 328
3 Yes, Toilet is attached to biogas plant - continue with
327
If toilet is attached to the plant, who encouraged you to do so? 327
1 Own motivation
2 The Partner Organization
3 Friends and relatives
4 Others (specify)
Are there any taboos related to attaching toilets to biogas plants? 328
1 No
2 Biogas from plants with attached toilets is considered
to be un-sacred
3 People are hesitant to handle the slurry if a toilet is
attached to the biogas plant
4 Others (specify)
Are there any advantages in attaching toilets to biogas plants? 329
1 No
2 Safety in the night
3 Cleanliness and hygiene
4 Others (specify)
Do you know your investment to built the plant? 330
1 Don’t Know (continue with 333)
2 Yes Amount in TK…………………
Did you take loan to build the plant? 331
1 Don’t Know (continue with………)
2 Yes Amount of Loan in TK……………..
If yes - status of repayment 332
1. All repaid
2. Paying Continues (give running month…………..)
Was it ever necessary to repair your biogas plant? 333
! 62!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
5 Kerosene stove
6 Electrical stove or appliances (list
-for example: rice cooker-)
7 Others (specify)…..
How much other fuel did you use for cooking purpose before having a 409
biogas plant? (Give amount, unit and cost/unit)
Amount Unit TK/unit
1 Fire wood
2 Cow dung
3 Agricultural residues
4 LPG
5 Kerosene
6 Electricity
7 Other (specify)
Are you using other sources of fuel besides biogas for lighting? (Give 410
amount, unit and cost/unit)
1 NO Amount Unit TK/unit
2 Electricity
3 Kerosene
4 LPG
5 Other (specify)
How much other fuel did you use for lighting purpose before having a 411
biogas plant? (Give amount, unit and cost/unit)
Amount Unit TK/unit
1 Fire wood
2 Cow dung
3 LPG
4 Kerosene
5 Electricity
6 Other (specify)
Do you sell biogas to other households? 412
1 NO
2 Yes – please describe how, unit and price/unit
5. USE OF SLURRY
2
Total land owned by the Household at the plant site m 501
2
Surface used for agriculture and gardening at the plant site m 502
2
Land used for agriculture ..... km away from plant site m 503
Do you use biogas slurry on farm for agriculture or gardening? 504
1 No
2 Yes – completely continue with 504
3 Yes - Partially …(%), - continue with 504
4 Yes - seasonally - continue with 504
If NO, what do you do with the slurry? 505
1 Sale to others for agriculture or gardening
2 Give out to others for free
3 Make dung cakes to burn for own use
4 Make dung cakes to burn for sale
5 Drain to water courses or drains
6 Other (specify)
Why do you not use slurry? 506
1 It has lesser nutrient value than dung / manure
2 It is difficult to use because it is liquid
3 Reluctant to use the slurry from biogas plant because toilet
is attached
4 No land for slurry use
5 Others (specify)
If YES, what do you do with the slurry? 507
1 Use as organic fertilizer without composting
2 Use as organic fertilizer after composting (in shadow/ under
a roof / not protected against sun) - please mark
! 65!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
! 67!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
8. MEASUREMENT CHECKLIST
Please take the measurements as indicated in the following sketch and document them in
cm in the sketch.
In addition please measure:
ITEM Measurement Date Entry
Code
o
Temperature inside the digester C 812
o
Ambient Temperature C 813
pH value of slurry in the digester 814
Top filling over the dome Cm 815
! 68!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
Indicate measurements and tick in the following sketches where leakages are observed:
! 69!
NDBMP!Plant!Code!…………………………....!/!BAB!Interview!No.!………….………………..!
! 70!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
Questionnaire!for!Technical,!Social!and!Institutional!Audit!of!NDBMP!
Informed)consent)&)cover)page)
(Lending)&)Construction))Partner)Organizations)
Greetings! My name is ______________________________. I am here on behalf of the German
International Development Cooperation supporting the National Domestic Biogas and Manure
Program. We are conducting a detailed analysis of biogas plants installed in the country since
2006 under the framework of the program – especially observing biogas production and use, and
the handling of bio-slurry. In order to get more information about the technology dissemination
strategy and process, as well as the challenges and benefits you are experiencing, we are
conducting a survey not only of households but also on Partner Organizations.
Your organization is constructing household biogas plants in this area. I would like to ask you
some questions related to the 'marketing strategy', training offers, subsidies, installation, after-
sales-services, operation, maintenance and other issues related to these biogas plant. We would
also like to take technical measurements of biogas plants and their components and carry out
some tests to evaluate the plants' overall conditions and integration into households' economy
and work schedule.
In addition we are interested to get your opinion about the NDBMP strategic development,
coordination, past and current performance and future potential.
The information you provide will be useful to find out the status of the NDBMP and will be used to
plan future improvements of the implementation of biogas technology in Bangladesh.
All the information you give will be dealt with as confidential; it will be used to prepare general
reports, without mentioning any specific names. There will be no way to identify that you are the
one who gave this information.
Participation in the survey is voluntary, and you can choose not to take part.
If you have any questions about the survey, you can ask the NDBMP staff who are here with the
survey team. Do you have any questions about the survey?
! 71!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
! 72!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
! 73!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
! 74!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
! 75!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
4 Use of biogas
5 Slurry use
6 Maintenance of biogas plant
7 Repair of biogas plants
8 Other (please specify)
Do you have internal training sessions for your staff working in 410
domestic biogas technology?
1 No - continue with 410
2 Yes - continue with 411
If NO, why not: 411
If YES, please list topics and participants: 412
Topic staff position Man Woman
1
2
3
4
5
6
Please describe the MONITORING carried out by IDCOL-NDBMP on your 413
organization:
1.1 once per 1.2 once per 1.3 twice per
Period of contract year year
1
monitoring 1.4 every third 1.5 once per 1.6 Other
month month (please specify)
2 Content of 2.1 accounts 2.2 list of 2.3 Other
monitoring constructed (please specify)
plants
5. Technology Implementation Procedure
Number of construction agreements till today 501
Number of plants constructed till today 502
Number of plants currently under construction 503
After signing a construction agreement: what is the average 504
time required until start of construction of biogas plants
(days / weeks / months)
Do you monitor biogas plants and their quality by means of an Internal 505
Quality Control system?
1 No - continue with 509
2 Yes - continue with 510
If NO, why not? (more than one answer is possible) 506
1 Confident in quality of construction
2 No trained staff in organization to establish and carry out IQC
3 If any other reason, please specify
If YES, in which moment between signing the construction agreement 507
and handing over the biogas plant do you apply IQC?
1 In every biogas plant in any moment
2 Only sometimes in some plants
3 In critical situations (please specify)
4 Other moment (please specify)
Do you check the quality of construction material delivered to the site? 508
1 NO
2 YES
If no, why not? 509
If Yes, how often? 510
! 76!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
! 77!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
3 Appliance manufacturers
4 Others (please specify)
Do you provide periodically AFTER Construction SERVICES (ACS) to the 522
biogas households?
1 No
2 Yes
If No, Why you don't do ACS? 523
1 No trained staff
2 Not in business priority
3 Not well paid
4 If any other reason (please specify):
If Yes, in which sequences do you carry out control visits? 524
1 Every year in each plant
2 Every year only in randomly selected plants
3 In critical situation
4 Other (please specify)
How fast do you respond to customer complaints? 525
1 Same day
2 Next day
3 With in a Week
4 Depends on current work load in the moment of complaints
5 Other (please specify)
According to your experience: what are the major problems addressed in 526
customers' complaints since you are in the biogas business? (please
list)
6. Loan Implementation Procedure
Number of signed loan agreements till today 601
Number of plants constructed under loan agreement till 602
today
Number of plants with loan agreement currently under 603
construction
After signing the loan agreement: average time required until 604
start of construction of biogas plants (days / weeks / months)
What do you identify as main obstacles for signing loan agreements with 605
interested households? (please list)
What is the range of loan amount requested by households? 606
1 Full amount of biogas system costs including material and labor
2 51 to 75% of biogas system costs including material and labor
3 30 to 50% of biogas system costs including material and labor
4 11 to 29% of biogas system costs including material and labor
5 1 to 10% of biogas system costs including material and labor
6 Only labor cost
7 Only material cost
8 Only cost for biogas appliances
9 Other (please specify)
What are the criteria for your organization to fix the loan interest and the 607
re-payment rate? (please elaborate or give relevant documents to the
interviewer)
According to your experience: How long is the average re-payment time? 608
Do you motivate / support households to create income generating 609
activities (home / farm based enterprises) related to their biogas system?
1 NO
2 YES
! 78!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
! 79!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
! 80!
DATA!SHEET!Nr:!…………………………!/!………………………..!/!..........................!/!.......................!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(PO!code)!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!(district!Code)!!!!!!!!!!!!!!!!!Date!!!!!!!!!!!!!!!!!!!!!Interview!Nr.!!
! 81!
Contacts(during(BAB(onsite(missions((
Organisation
Name Position Address District Country Cell number Phone e-mail website
Name Type
Development Road-90, House 88 02882 88 09 666
David Kunze Director KfW Dhaka Bangladesh david.kunze@kfw.de
Bank 10/c, Gulsan-2 2713 777 333
Biogas Grameen Grameen Bank 01199-
M A Gofran NGO Dhaka Bangladesh gofran@dhaka.net www.gshakti.org
Consultant Shakti Bhaban, Mirpur-2 269968
Network
Netherland
WIM J.van Leader DR. Kuyperstraat 31(0) 6 283 33 (0)
SNV Development Netherlands wvannes@snvworld.org www.snvworld.org
Nes Renewable 5 935 35 703440 244
Organisation
Energy
Rahman
Redwanoor Palasbari West
Managing Renewab 01712-
Rahman Enterprise Para ,Asuliya, Dhaka Bangladesh redwanoor@yahoo.com
director le Energy 586110
Bulbul Savar
CO.
Settlement RDEC-LGED
Roshan Raj UN- 01755 88-02- roshan.shrestha@uppr
Improveme International Building, Level-8, Dhaka Bangladesh
Shrestha HABITAT 501157 8156435 bd.org
nt Advisor Agargaon
Community RDEC-LGED
Roshan B. UN- 01741- 88-02- roshan.shakya@upprbd
Banking International Building, Level-8, Dhaka Bangladesh
Shakya HABITAT 340164 8156435 .org
advisor Agargaon
Md. Borhan
Managing 58/A Mohakhali 01911- borhan.mojumdar@yah
Uddin RINDA Enterprise Dhaka Bangladesh
director Bazar 925690 oo.com
Mojumdar
Abu Taher 58/A Mohakhali 01727- borhan.mojumdar@yah
Chairman RINDA Enterprise Dhaka Bangladesh
Nannu Bazar 601407 oo.com
Islami
Commercial
Amecon
Md.Hasrulla Complex, 01915- azmot@ameconelctroni
Director Renewab Factory Dhaka Bangladesh
h 2/1,Block-kha 461353 cs.com
le Energy
section-02,
Mirpur
Martin Training 9002544,
Marketing 1/C-1/A, Pallabi, 01819- mmmawts@caritasmc.o
Ronald MAWTS Centre & Dhaka Bangladesh 9002493, www.mawts.org
Manager Mirpur-12 525317 rg
Pramanic Factory 8013810
E2,House:15 880-02- dipal@dipalbarua.com,
Dipal C. Enterprise & 01713- www.greenenergyb
Chairman BGEF Road 36, Dhaka Bangladesh 9861140, dipal@greenenergybd.c
Barua NGO 500500 d.com
Gulshan-2 8818915, om
Head of
E2,House:15 880-02-
Research & Enterprise & 01726- info@greenenergybd.co www.greenenergyb
Naim Din BGEF Road 36, Dhaka Bangladesh 9861140,
Developme NGO 177634 m d.com
Gulshan-2 8818915,
nt
RISDA- House-46, Lane- 01552350687
Hemayet Executive 88-02-
Banglade NGO 3, Block-A, Dhaka Bangladesh , info@risda.org.bd, www.risda.org.bd
Hossain Director 9008133-4
sh section-^, Mirpur 01972350687
Contacts(during(BAB(onsite(missions((
Organisation
Name Position Address District Country Cell number Phone e-mail website
Name Type
Md. 15-18, Lane-6,
Shamsul Project Shubash Block-D, 01730- 88-02-
NGO Dhaka Bangladesh shubashati@gmail.com
Arefin Manager ati Kalapani-Bat 300082 9013431
Laskar Tala, Mirpur-12
Eng.
Executive RDF Tower, 01920- 88-448-
Md.Abul RDF NGO Barguna Bangladesh trmmbd@yahoo.co, www.rdfbd.org
Engineer Police Line Sarak 214438 62706
Bashar
Dr.
Principal
Mohammaa Research Dr. Quadrat -I- 01556- 88-
Scientific BCSIR Dhaka Bangladesh roufmd@yahoo.com www.bcsir.gov.bd
d Abdur organisation Khuda Road 318036 028622908
Officer
Rouf
Senior
Md. Saiful Research Dr. Quadrat -I- 01816- saiful_chem@yahoo.co
Scientific BCSIR Dhaka Bangladesh www.bcsir.gov.bd
Islam organisation Khuda Road 477161 m
Officer
ATM WIN House-2,
Private 88-02-
Mahbubul Chairman sources Road#1/A, Dhaka Bangladesh www.ttbcbd.com
Company 8833463
Alam Limited Gulsan-1
Mohammad Area GHASHF 438, Mehedibag 01819- ghashful@ghashful- www.ghashful-
NGO Dhaka Bangladesh
Salim Manager UL Road 511132 bd.org bd.org
Energy Development 86- www.energyforall.i
Xia Zuzhang xiazuzhang@gmail.com
for All Bank 13888783919 nfo
Salvista Hub. 8802-
Eng.M.K. Headof Chicks @ Private 01712-
House:8, Road: Dhaka Bangladesh L228142531- info@cknfeeds.com www.cknfeeds.com
Nazrul Islam Operation Feeds Company 837095
14, Dhanmondi 33
Salvista Hub. 8802-
Ekhlasul Managing Chicks @ Private 01711-
House:8, Road: Dhaka Bangladesh L228142531- info@cknfeeds.com www.cknfeeds.com
Haque director Feeds Company 262394
14, Dhanmondi 33
Salvista Hub. 8802-
Shahed Chicks @ Private 01713-
Advisor House:8, Road: Dhaka Bangladesh L228142531- info@cknfeeds.com www.cknfeeds.com
Israil Khan Feeds Company 278184
14, Dhanmondi 33
Md. Salvista Hub. 8802-
Business Chicks @ Private 01713-
Ashfaqul House:8, Road: Dhaka Bangladesh L228142531- info@cknfeeds.com www.cknfeeds.com
Manager Feeds Company 278190
Islam 14, Dhanmondi 33
Dhaka Trade
Centre, 99, Kazi
Md. Tobarok Saori
Managing Telecom Nazrul Islam 01740-
Hossain Telecom Dhaka Bangladesh tobarok@saoritel.com www.saoritel.com
director Company Avenue 5th 909497
Bagmar Ltd.
floor, Kawran
Bazar
Mayor of
Advocate
Tongi 01711- mayor@tongimunicipalit www.tongimunicipa
Md. Azmat Mayor GO 19, Tongi Bhoran Gazipur Bangladesh
Municipal 525733 y.com lity.com
Ullah Khan
ity
( 83(
Contacts(during(BAB(onsite(missions((
Organisation
Name Position Address District Country Cell number Phone e-mail website
Name Type
Inclusive
House: 474,
Insurance
Syed H Secratory Road:31, New 01914-
RADOL Through Dhaka Bangladesh 02 871 5323 radol_06@hotmail.com www.radol.org
Loton General DOHS, 005956
NGO-Insurer
Mohakhali
Partnership
Commitm D/4, Zakir
Chief
Monir Alam ent Consultancy hossain Road. 01714- monir.chowdhury07@g
Executive Dhaka Bangladesh 02-9103551
Chowdhuri Consulta Office Block-E, 082977 mail.com
Officer
nts Mohammadpur
28, Metropolitan
Housing Society,
Md. Shafiqul Program 01914- 88-02-
NUSRA NGO Babor road, Dhaka Bangladesh nusrabd@yahoo.com www.nusrabd.org
Islam Coordinatot 157737 9136990
Block-F,
Mohammadpur
BRAC-Centre for 01199-
Prabir Manager, BRAC- Development 810144
NGO Dhaka Bangladesh 9205583 bcdm@bdmail.net
Kumar Saha Operation CDM Management, 01711-
Rajendropur 075960
Md. Ghulam Gonosha
Executive Mirzanagar via 01713-
Mustafa stho NGO Dhaka Bangladesh 9673512 geducation@dhaka.net www.gkbd.org
Director Savar Cantt 033862
Dulal Kendro
Senior
Manzur Gonosha
Director, Mirzanagar via 01711-
Kadir stho NGO Dhaka Bangladesh 9673512 gkhealth@dhaka.net www.gkbd.org
Health Savar Cantt 429860
Ahmed Kendro
Program
House:8, Road :
Ferdous Project Poly Private 01713- www.polyconcrete.
1, Block:F, Dhaka Bangladesh ferdous@pcc.no
Sheikh Director Concrete Company 238386 com.bd
Banani
info@risda.org.bd,
House- 46(1st
RISDA- risdabangladesh@yaho
Hemayet Executive floor), Lane-3,
Banglade NGO Dhaka Bangladesh 15522350687 9008133-4 o.com, www.risda.org.bd
Hossain Director Block -A, Section-
sh hemayet168@yahoo.co
6, Mirpur .
m
info@risda.org.bd,
House- 46(1st
Md. RISDA- risdabangladesh@yaho
floor), Lane-3,
Shamsur Chairman Banglade NGO Dhaka Bangladesh 1711480207 9008133-4 o.com, www.risda.org.bd
Block -A, Section-
Rahman sh srahman09@yahoo.co
6, Mirpur .
m
Salvista Hub.
Shah Sufi Brand Chicks @ Private
House:8, Road: Dhaka Bangladesh 1713278187 8142531-33 info@cknfeeds.com www.cknfeeds.com
Ahmed Executive Feeds Company
14, Dhanmondi
( 84(
Contacts(during(BAB(onsite(missions((
Organisation
Name Position Address District Country Cell number Phone e-mail website
Name Type
Head of
Salvista Hub.
Engr. M.K. Operation, Chicks @ Private 1713278179,
House:8, Road: Dhaka Bangladesh 8142531-33 info@cknfeeds.com www.cknfeeds.com
Nazrul Islam New Feeds Company 01712837095
14, Dhanmondi
Project
Executive mmalik@idcol.org,
Mahmood Panthopath,
Director IDCOL GO Dhaka Bangladesh 8116663 mahmood.malik13@gm www.idcol.org
Malik Kawran Bazar
and CEO ail.com
S.M. Director
Panthopath,
Formanul Legal IDCOL GO Dhaka Bangladesh 9103881 fislam@idcol.org www.idcol.org
Kawran Bazar
Islam Affairs
9114385,
Senior
Nazmul Panthopath, 01912 8111235,
Programme IDCOL GO Dhaka Bangladesh faisal@idcol.org www.idcol.org
Islam Faisal Kawran Bazar 056989 9143157 Ext-
Manager
33
Sr.
Mohammad
Investment Panthopath, 9102171-
Wahidur IDCOL GO Dhaka Bangladesh 1556338657 mwahidr@hotmail.com www.idcol.org
Officer Kawran Bazar 8(Ext-4)
Rahman
(Technical)
Netherland
Rajeev Senior munankami@snvworld.
SNV Development Dhaka Bangladesh
Munankami Advisor org
Organisation
House # 23,
Independ
Independen Ranavola
M. ent Consultancy
t Avenue, Sector # Dhaka Bangladesh 1716981532 8953462 mhassan@cite
Hassanullah Consulta farm
Consultant 10, Uttara Model
ncy
Town
Seed
Sha 45/ka,
Md. Rafiqul Executive Bangla 01730- 8837132, seedbangla@gmail.co
NGO (Hossain market), Dhaka Bangladesh
Islam Director Foundati 063950 8851333 m
North Badda
on
Biogas
Technolo 140, Crescent
Md. btcsl@yahoo.com,
gy Consultancy Road, Green 01715-
Shamsul Chairman Dhaka Bangladesh 9613962 shamsul34@yahoo.co
Consultin farm Road, 967790
Haque m
g Dhanmondi
Services
Former BARI/
Director BSTI/
01713
General/ Plant dmislam@agni.com,
Dr. M S 002180,
Chairman/ Growth GO Dhaka Bangladesh dmislam1946@yahoo.c
Islam 01726
President/ Regulator om
444595
Technical Associati
Advisor on
( 85(
Contacts(during(BAB(onsite(missions((
Organisation
Name Position Address District Country Cell number Phone e-mail website
Name Type
Biogas
Technolo 140, Crescent
btcsl@yahoo.com,
Md. Naimul Managing gy Consultancy Road, Green 01715
Dhaka Bangladesh 9613962 n_haque_ifrd@yahoo.c
Haque director Consultin farm Road, 293667
om
g Dhanmondi
Services
Dilder
Senior Road-90, House www.giz.de/bangla
Ahmed GIZ German GO Dhaka Bangladesh 9666701000 dilder.taufiq@giz`.de
Advisor 10/c, Gulsan-2 desh
Toufiq
Dr. Eng M.
Senior Road-90, House www.giz.de/bangla
Khalequzza GIZ German GO Dhaka Bangladesh 9666701000 khaleq.zaman@giz.de
Advisor 10/c, Gulsan-2 desh
man
Dr. Eng.
Senior Road-90, House 01711 www.giz.de/bangla
Khursheed- GIZ German GO Dhaka Bangladesh 9666701000 khaleq.zaman@giz.de
Advisor 10/c, Gulsan-2 522832 desh
UL-Islam
Institute
of
Professor 9661920-73/
Statistical University of University of 01731
Dr. Md. Amir Director Dhaka Bangladesh 8281, 8293
Research Dhaka Dhaka 267718
Hossain (O)
and
Training
Institute
of
House- 357,
Manage
Road 27, New info.imcb@gmail.com,
M Zakir ment Consultancy 01819
President DOHS, Dhaka Bangladesh 8834046 youngconsultant@gmail
Hossain Consulta firm 162727
Mohakhali, .com
nt
Dhaka 1213
Banglade
sh
(
( 86(