Professional Documents
Culture Documents
Fundamental FTTH Planning and Design: Part 1: Technology
Fundamental FTTH Planning and Design: Part 1: Technology
Fundamental FTTH Planning and Design: Part 1: Technology
Fundamental FTTH
Planning and Design: Part 1
Placement of network elements in the field can have a major effect on
deployment costs. Here are some principles to follow.
By David Stallworth ■ OFS
C
hoosing the right fiber-to-the-
home design strategy is very
important, but the best strategy
Learn about the challenges
in the world may not achieve the de- of FTTH deployment at the
sired results if network elements are not
placed economically in the field. Years Broadband Properties Summit,
ago, OFS initiated a Fundamental Plan-
ning research project to address this is-
April 26–28 in Dallas.
sue. The project was later expanded to
include the locations of central offices
(COs) and nodes. This massive effort led locations studied. We studied virtually locations and outside-plant network
to the development of ideal configura- every possible configuration, evaluating configurations. Some of the conclu-
tions for outside-plant networks and op- multiple feeder routes; different routing sions became obvious once they were
timal locations for COs and nodes. techniques, such as parallel routes, per- discovered, and others were revelations
In the study, we developed an ideal pendicular routes and circular routes; that have been further refined over the
solution based on an ideal service area – and different cable sizes or route capaci- years. By understanding what an ideal
network should look like, a planner can
configure a real network to conform to
the ideal as much as possible.
By understanding what an ideal network should The study showed that the most eco-
nomical location for a CO or node is ex-
look like, a planner can configure a real network actly in the middle of the area it serves
to conform to the ideal as much as possible. (see Figure 3). This position not only
yielded the lowest cost for all custom-
ers in the serving area but also provided
the lowest optical loss to all customers.
a square with streets arranged in square ties. As the studies progressed, patterns
began to emerge that were both intuitive Most designers consider this an intuitive
blocks (see Figure 1).
and informative. finding.
The initial study consisted of mov-
For a square area with uniform den-
ing the CO or node around the area to
The node goes in the middle sity throughout, the ideal node location
study the effects of its position on total
From this study, we reached several is in the middle of the area it serves. Let’s
network costs (see Figure 2; the CO is
general conclusions that have proven call this the geographic economical lo-
the red point). Most of the variation over time to define the most economi- cation (GEL). However, because not all
was in outside-plant cost, as other costs cal method for planning CO or node areas have this characteristic, we should
(switches, terminations and so forth)
remained constant. The CO or node
was placed in various positions in the About the Author
ideal area, and various configurations David Stallworth is the design and product manager at OFS, a manufacturer of opti-
of feeder routes were studied along with cal fiber and connectivity solutions. You can reach him at 770-798-2423 or by e-mail
the associated support structures. at dstallworth@ofsoptics.com.
Figure 2 shows just a few of the
Figure 3: This is the most cost-effective location for the central office. Figure 4: We then made the study area less ideal by varying its density.
ideal with the actual. For example, on the coast of South Caro-
lina, where I live, we do not have many eastern routes – the
Atlantic Ocean is in the way! Valleys are usually oblong and not
square, yielding only two possible routes. However, the prin-
ciples of the ideal world still apply, and planners should make
every effort to come as close as possible to the ideal.
Figure 5: Density affects the proper placement of the CO or node.
There is a very good reason to stay as close as possible to the
ideal: As shown in Figure 6, cost rises exponentially as
the location moves away from the ideal point.
In building a network, the first step is to locate the
GEL point and then adjust it for density. After establish-
ing the DEL, the designer can examine the area to locate
appropriate land or rights-of-way. This requires good en-
gineering judgment. Access to a road network is needed
for placing cables. In addition, the location should be
blended in with the surrounding structures and should
be as “green” as practical.
Figure 7: Splitter cabinet location (cabinet is red dot) Figure 8: Smaller cabinet locations (cabinets are red dots)
d
ndeMulti-Housing
Expa2011
Program
v Agenda Developed by Industry Leaders! v
v Three-Day Program, 50 Speakers v
v View the full program now! v
April 26 – 28, 2011
InterContinental
Hotel – Dallas
Addison, Texas
The Leading Conference on Broadband Technologies and Services
To Exhibit or Sponsor, contact: Irene Prescott at irene@broadbandproperties.com, or call 505-867-2668.
For other inquiries, call 877-588-1649, or visit www.bbpmag.com.