Work Method Statement: Delhi Metro Rail Corporation
Work Method Statement: Delhi Metro Rail Corporation
Casting of Column
1
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
CONTENTS
Sr.
Content Page no.
No.
1. Objective 3
2. Scope of work 3
3. Field of application 3
4. Reference documents 3
5. Staff responsibilities 3
6. Workmanship 6
8. Preliminary Activities 7
11. Deshuttering 12
12. Curing 12
14. Safety 13
2
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
1. OBJECTIVE:
The objective of this method statement is to frame a procedure for the construction of COLUMN
foundation at DMRC, contract Package.
2. SCOPE OF WORK:
Method for casting of columns as per the approved Good for Construction drawings & relevant
technical specifications.
The scope of work includes the following;
Starter Concrete
Staging for column
Reinforcement tying for column.
Shuttering of column.
Concreting of column.
De shuttering of column.
Curing of column.
3. FIELD OF APPLICATION:
All Columns
4. REFERENCE DOCUMENTS:
Contract Specifications
IRS: Concrete Bridge Codes
IS: 1786:1985 - High Strength Deformed Steel Bars and Wires for Concrete Reinforcement—
Specification
IS: 2502-1963: Code of practice for bending and fixing of bars for concrete reinforcement.
IS SP:34 -1987 – Hand book on concrete reinforcement and detailing
IS:10262- 2009 – Concrete Mix Proportioning – Guidelines
CWP for Production and Transportation of concrete.
SHE conditions of contract
SHE manual of contract
Project EHS plan
5. STAFF RESPONSIBILITIES:
5.10 ENGINEERS:
Reporting to the respective in-charge.
Achieving targets as per the planned.
Targeting for zero accidents.
Quality check at all the stages of activities.
5
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
6. WORKMANSHIP:
6.1
6.1.1 Column will be constructed in size & shape as shown in the GFC drawing.
6.1.2 Concrete will be of specified grade with using Ordinary Portland Cement.
6.3 Reinforcement
7.1 Equipment’s
6
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
7.2 Materials
7.2.2 Water
8. PRELIMINARY ACTIVITIES:
Sequence of work:
7
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
9.0 Survey point will be marked for X, Y & Z (RLs) axes and corners of the Column as per the
drawings for starter casting of column.
9.1 The column will be checked for variation from the theoretical co-ordinates and submitted to
DMRC for verification. Permissible deviation in plan location for column shall not me more than
10 mm as per the technical specifications.
9.2 Steel shutter/Ply Shutter/ Doka/Cup-Lock will be used as formwork on the sides of the
Column based on the conditions at site. Standard Formwork release oil (Reebol-Fosroc) shall be
applied on the formwork material.
9.3 Cutting & bending of reinforcement as per the approved BBS will be carried out in the
reinforcement yard & the same will be transported by Trailer/Truck to the required location.
9.4 The vertical reinforcement for the Column will be placed in position as shown in the Column
GFC drawings. It shall be ensured that the vertical bars of column reinforcement shall be erected
and tied with proper supporting arrangement to avoid tilting of the reinforcement.
9.5 Concrete will be transported by Transit mixer and it will be poured using mobile placer boom
however for the stand by arrangement bucket/pump will be used. The height of fall of concrete
should be less than 1.5 m Vibration will be carried out using suitable vibrators & top surface will
be wooden trowel finished. The maximum thickness of each layer of concrete will be 300 mm
and concreting will be done in dry conditions.
9.6 The de-shuttering will be carried out after 16 to 24 hrs. Of concreting and curing will be done
for 14 days or application of curing compound at surface of column.
a. The work shall be commenced after obtaining statutory permits from the Traffic police
department and Greater Haryana Municipality Corporation and other Government bodies.
b. Requisite Permissions shall be kept by site safety department before start the activity and
shall be available at place of work.
8
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
a. Construction team shall be trained / detailed about the approved Construction Work
Procedure (CWP) by Construction manager and Stage In-charge.
b. Awareness through Safety pep talks regarding vehicular movement inside working zone and
road traffic shall be undertaken.
10.3 Reinforcement
A. Material
a. Bar Bending Schedule shall be prepared as per the Good for construction drawings.
b. Reinforcement steel shall be fabricated through automatically operated machines and
mandrels confirming to IS1786:2008.
c. Cut and bent reinforcement shall be stacked on sleepers and protected to prevent rusting by
covering with tarpaulin sheets.
a. Reinforcing steel shall conform to the dimensions and shapes given in the Bar Bending
Schedules.
b. Reinforcement steel shall be fabricated through automatically operated steel service centre.
c. Cut and bent reinforcement shall be stacked on sleepers and protected to prevent rusting by
covering with tarpaulin sheets.
D. Transportation of Reinforcement:
9
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
a. Cut and bent reinforcement shall be transported to place of work on trucks /trailers.
Marking of column as per coordinates shall be done as per the GFC drawing at site and co-
ordinates furnished by designer.
a) The height of the starter shall be decided based on the height of the Column above Starter.
b) Reinforcement ring and links shall be tied with main vertical reinforcement as per GFC
drawing.
c) Formwork :
Starter formwork shall be fixed with supporting arrangement either of frame or System
formwork.
Every corner of shutter shall be tightened and made leak proof with the help of rubber
sheets / foam.
The starter shutter shall be checked for its axis coordinates.
Concrete of M-40 grade shall be placed to the required height and thoroughly vibrated
to have a homogenous layer.
The starter shutter shall be removed after the concrete has gained sufficient initial
strength, say about 12 hours.
d) Construction joint shall be prepared by cleaning with an air-water jet and by wire booming on
the concrete which is still soft enough that laitance can be removed, but hard enough to
prevent aggregate from loosening. If the concrete for some reason is set before the
construction joint preparation, then in such situation the joint shall be prepared using a wet
sand blast or ultra-high pressure water jet.
e) All types of construction joint shall be tooled and made free from any loose mortars /
concrete.
10.6 Column
a. Rebar tying.
i. Temporary Staging shall be done using formwork or with the help of 40 mm dia. Ledger
pipes around the Column to facilitate tying of re-bar according to site.
10
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
ii. Working platforms at proper intervals shall be formed to facilitate the workers for tying the
reinforcement.
iii. Vertical ladders shall be used to climb up to the staging.
iv. Reinforcement shall be tied together for full height and at every intersection (with
rings/links/ stirrups) with GI Binding wire according to our code.
v. Rings/ links/stirrups shall be tied in place as specified in drawing.
vi. The drain pipe shall be held in place with a link or ring tied to the reinforcement at 1 m
interval.
vii. The drain pipes shall be joined using couplers.
viii. Earthing rod shall be placed as shown in the GFC drawing.
ix. Cover blocks shall be provided at suitable intervals to have a clear cover 50 mm according
to GFC Drawing.
x. Lap length shall be as given in the GFC drawing and shall be staggered.
i. Shutter shall be free from any foreign materials and dried before applying release agent.
ii. Surface shall be coated with mould releasing agent using brush to prevent adhesion of
concrete to the formwork before fixing of shutters. It shall be applied as per the
manufacturer’s specifications. Care shall be taken that the material so applied does not
leave any blisters, voids, blow holes and detoriation of application.
iii. Working platform shall be made along with the frame for placing further shutters.
iv. Top working platform which is part of the Column shutter shall be erected.
c. Checking of coordinates
i. Coordinates for Column center shall be checked as per Survey CWP.
i. PVC tremie pipe of 150 mm diameter shall be placed alongside the drainage pipe for placing
concrete. 1.5 mts pipes shall be joined together by threading to make the total length of the
tremie pipe. The length of the pipe shall be adjusted as the concrete progresses by removing
each length of pipe.
e. Access ladder
i. Staging with ladder shall be placed on one side of the column shutter and connected to the
working platforms of the column shutter.
i. M-40 grade of concrete from the batching plant shall be placed in the column.
ii. Concrete shall be placed with the help of Boom placers/concrete pumps/concrete buckets in
layers.
11
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
iii. The elephant hose of the boom placer shall be lowered into the concrete delivery pipe to have
control on the free fall of concrete.
iv. The height of free fall of concrete shall be restricted to 1.5M and the layer thickness shall not
exceed 300mm.
v. The concrete layers shall be vibrated with the help of suitable vibrators.
vi. Shutter vibrator may also be used depending on the shape and size of the structure.
vii. Care shall be taken not to vibrate for a long time, since this may lead to the segregation of
concrete. No concrete shall be allowed inside the drain pipe at the time of concreting.
viii. Placing of concrete shall be as per the concrete pour plan.
ix. Top level shall be leveled and finished smoothly.
x. Construction joint shall be prepared by cleaning by an air-water jet on the concrete which is still
soft enough that laitance can be removed, but hard enough to prevent aggregate from
loosening. If the concrete for some reason is set before the construction joint preparation, then
in such situation the joint shall be prepared using a wet sand blast or ultra-high pressure water
jet.
11 De shuttering:
12 Curing:
14 SAFETY:
All safety precautions will be taken care as per approved site safety plan. All works shall be carried
out within the barricaded area. Adequate traffic marshals and safety personnel’s will be deployed
during the course of work.
12
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
13
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
Contractor :
14
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
Contractor :
15
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
Contractor :
16
DELHI METRO
RAIL CASTING OF COLUMN
CORPORATION
Contractor :
17