NAME: Jobenson B. Camiguing YR. & SEC.

: BSCE V - P

SITE VISIT REPORT

DATE: 09-17-19

NAME OF PROJECT: Construction of Bogo Bridge


PROJECT LOCATION: Brgy. Bogo, Maasin City, Southern Leyte
CONTRACTOR: Lady of Assumption Enterprises
PROJECT COST: P 24,906,420.94
PROJECT DURATION: 460 C.D.
I. ACTIVITIES
 Concrete Pouring -Volume: 107.8 cu.m
-(11x22x0.4) + capping
II. WEATHER CONDITION
LEGEND:

SUNNY 08:00 09:00 10:00 11:00 12:00


AM AM AM AM NOON
CLOUDY
SHOWERY
HEAVY

III. MATERIALS
Material Unit Quantity Remarks
Concrete (1:2:3) bags and cu.m 1 mixer
Cement bags 50 bags/mixer Concrete pouring of
Sand cu.m 2.5 cu.m/mixer concrete deck
Gravel cu.m 5 cu.m/mixer

IV. MANPOWER
Designation No. of No. of Remarks
Person Hours
nel
Project In-Charge 1 8 For monitoring
For managing and operating the Pump
Pump Crete Operator 3 8
Crete machine
Mixer Driver 3 8 For concrete delivery in the site
Laborer 11 12 For concrete pouring

V. EQUIPMENT
Equipment/Machine SPEC Quantity No. of Hours Remarks
Pump Crete 1 8 Concrete pouring
Concrete Vibrator 1 8 Concrete pouring
Concrete Mixer 3 8 Concrete delivery

VI. PROBLEMS ENCONTERED/SOL’N:


Just from the start of the activity of pouring the concrete into the formed bridge
deck, a clogging of concrete in the tube of the Pump Crete machine occurred that
causes a delay in work for half of the day. To resolve the problem, they needed to
reinstall back the tube by getting the clogged concrete in it.

VII. DOCUMENTATION
Prepared by:
Jobenson Camiguing
STUDENT ENGINEER

Approved by:
Engr. Luzanne Bakunawa
CE INSTRUCTOR