Revised 2005

PC-1 FORM

GOVERNMENT OF PAKISTAN
PLANNING COMMISSION

PROFORMA FOR DEVELOPMENT PROJECTS

(PRODUCTION SECTORS)

? Agriculture Production

? Agriculture Extension

? Industries, Commerce
And Minerals
Revised 2005

GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1 FORM
(PRODUCTION SECTORS)

1. Name of the project

2. Location

3. Authorities responsible for:


i. Sponsoring
ii. Execution
iii. Operation and maintenance
iv. Concerned federal ministry

4. Plan provision

5. Project objectives and its relationship with sector objectives

6. Description, justification, technical parameters and technology transfer


aspects (enclose feasibility study for projects costing Rs 300 million and
above)

7. Capital cost estimates

8. Annual operating and maintenance cost after completion of the


Project

9. Demand and supply analysis

10. Financial plan and mode of financing

11. Project benefits and analysis


i) Financial
ii) Economic
iii) Social benefits with indicators
iv) Employment generation (direct and indirect)
v) Environmental impact
vi) Impact of delays on project cost and viability

12. a) Implementation schedule


1
b) Result Based Monitoring (RBM) Indicators.

13. Management structure and manpower requirements including


specialized skills during construction and operational phases

14. Additional projects/decisions required to maximize socio-economic


benefits from the proposed project

15. Certified that the project proposal has been prepared on the basis of
Instructions provided by the Planning Commission for the preparation
of PC-I for production sector projects

Prepared by ______________________
Name, Designation & Phone #

Checked by _______________________
Name, Designation & Phone #

Approved by _______________________
Name, Designation & Phone #