PROGRESS Of WORK
PERCENTAG
No. PEKERJAAN Unit Volume E TO TOTAL PREVIOUS THIS WEEK TO DATE
CONTRACT
VALUE (%) VOLUME % Wf ( % ) VOLUME % Wf ( % ) VOLUME % Wf ( % )
II Infrastruktur
1 Instalasi Listrik External Unit 1.00 1.671% 0.50 50.0% 0.8% 0.50 50.0% 0.8% 1.00 100.0% 1.7%
2 Instalasi Pipa Air External Unit 1.00 2.234% 0.50 50.0% 1.1% 0.50 50.0% 1.1% 1.00 100.0% 2.2%
3 Drainase Unit 1.00 6.990% 0.93 93.5% 6.5% 0.07 6.5% 0.5% 1.00 100.0% 7.0%
II Infrastruktur
1 Instalasi Listrik External Unit 1.00 5,500,000 5,500,000 1.671% 0.00 - 0.0% 0.0% 0.00 5,500,000 100.0% 1.7% 0.00 5,500,000 100.0% 1.7%
2 Instalasi Pipa Air External Unit 1.00 7,350,000 7,350,000 2.234% 0.00 - 0.0% 0.0% 0.00 7,350,000 100.0% 2.2% 0.00 7,350,000 100.0% 2.2%
3 Drainase Unit 1.00 23,000,000 23,000,000 6.990% 0.00 - 0.0% 0.0% 0.00 23,000,000 100.0% 7.0% 0.00 23,000,000 100.0% 7.0%