RESUME PROGRESS MINGGUAN

PEMBANGUNAN 1 UNIT TEMPAT IBADAH UMAT KRISTIANI Minggu ke : 19 ( Sembilan Belas )


DI TANJUNG MAKMUR ESTATE, KABUPATEN KUTAI BARAT - KALIMANTAN TIMUR Periode : 26 Oktober - 1 November 2018
Kontrak No. 039/EPSSK/CONT/2018

PROGRESS Of WORK
PERCENTAG
No. PEKERJAAN Unit Volume E TO TOTAL PREVIOUS THIS WEEK TO DATE
CONTRACT
VALUE (%) VOLUME % Wf ( % ) VOLUME % Wf ( % ) VOLUME % Wf ( % )

I Pembangunan Rumah & Bangunan Lainnya


1 Tempat Ibadah Umat Kristiani Unit 1.00 89.105% 0.89 88.7% 79.0% 0.11 11.3% 10.1% 1.00 100.0% 89.1%

II Infrastruktur
1 Instalasi Listrik External Unit 1.00 1.671% 0.50 50.0% 0.8% 0.50 50.0% 0.8% 1.00 100.0% 1.7%
2 Instalasi Pipa Air External Unit 1.00 2.234% 0.50 50.0% 1.1% 0.50 50.0% 1.1% 1.00 100.0% 2.2%
3 Drainase Unit 1.00 6.990% 0.93 93.5% 6.5% 0.07 6.5% 0.5% 1.00 100.0% 7.0%

100.0% 87.5% 12.5% 100.0%

CV. MITRA ABADI PT. PP. LONDON SUMATRA INDONESIA Tbk,


DI BUAT OLEH DI PERIKSA DAN DIVERIFIKASI OLEH:

SIROJUDDIN ROJIB BAKRI LAMARIUS SITOMPUL


DIREKTUR CIVIL ENGINEER MANAGER TME
RESUME PROGRESS MINGGUAN
PEMBANGUNAN 1 UNIT TEMPAT IBADAH UMAT KRISTIANI Payment ke : 1 ( Pertama )
DI TANJUNG MAKMUR ESTATE, KABUPATEN KUTAI BARAT - KALIMANTAN TIMUR Periode : 14 - 20 September 2018
Kontrak No. 039/EPSSK/CONT/2018

Harga Jumlah PERCENTAGE PROGRESS Of WORK


TO TOTAL
No. PEKERJAAN Unit Volume Satuan Harga CONTRACT PREVIOUS THIS WEEK TO DATE
VALUE (%)
( Rp ) ( Rp ) VOLUME VALUE % Wf ( % ) VOLUME VALUE % Wf ( % ) VOLUME VALUE % Wf ( % )

I Pembangunan Rumah & Bangunan Lainnya


1 Tempat Ibadah Umat Kristiani Unit 1.00 293,199,661 293,199,661 89.105% 0.00 - 0.0% 0.0% 0.50 293,199,661 100.0% 89.1% 0.50 293,199,661 100.0% 89.1%

II Infrastruktur
1 Instalasi Listrik External Unit 1.00 5,500,000 5,500,000 1.671% 0.00 - 0.0% 0.0% 0.00 5,500,000 100.0% 1.7% 0.00 5,500,000 100.0% 1.7%
2 Instalasi Pipa Air External Unit 1.00 7,350,000 7,350,000 2.234% 0.00 - 0.0% 0.0% 0.00 7,350,000 100.0% 2.2% 0.00 7,350,000 100.0% 2.2%
3 Drainase Unit 1.00 23,000,000 23,000,000 6.990% 0.00 - 0.0% 0.0% 0.00 23,000,000 100.0% 7.0% 0.00 23,000,000 100.0% 7.0%

Total 329,049,661 100.0% - 0.0% 329,049,661 100.0% 329,049,661 100.0%

CV. MITRA ABADI PT. PP. LONDON SUMATRA INDONESIA Tbk,


DI BUAT OLEH DI PERIKSA DAN DIVERIFIKASI OLEH:

SIROJUDDIN ROJIB BAKRI LAMARIUS SITOMPUL


DIREKTUR CIVIL ENGINEER MANAGER TME