CNC Turning: Technical Description
CNC Turning: Technical Description
CNC Turning
international
© WorldSkills International
TD06 v2.0 - WSC2009
WorldSkills International, by a resolution of the Technical Committee and in accordance with the
Constitution, the Standing Orders and the Competition Rules, has adopted the following minimum
requirements for this skill for the WorldSkills Competition.
1. INTRODUCTION ........................................................................................................2
2. COMPETENCY AND SCOPE OF WORK ..................................................................2
3. THE TEST PROJECT.................................................................................................3
4. SKILL MANAGEMENT AND COMMUNICATION......................................................5
5. ASSESSMENT ...........................................................................................................6
6. SKILL-SPECIFIC SAFETY REQUIREMENTS ...........................................................7
7. MATERIALS & EQUIPMENT .....................................................................................7
8. MARKETING THE SKILL TO VISITORS AND MEDIA..............................................9
Effective 09.12.08
Liam Corcoran
Technical Committee Chair
Programming of the CNC lathe takes place through well-known machine control unit and/or a
Computer-Aided Machining (CAM) software. Machinists can use either the machine control unit
and/or the CAM software to produce the final product according to the given drawing specification.
Such parts are used everywhere in metal Industries, such as Automotive, Tool and Die, Aviation,
and even in the Aerospace industries.
1.2.1 Every Expert and Competitor must know this Technical Description.
1.2.2 In the event of any conflict within the different languages of the Technical Descriptions, the English
version takes precedence.
1.3.1 As this Technical Description contains only skill-specific information it must be used in association
with the following:
• WSI - Competition Rules
• WSI - Competition Manual
• WSI - Online resources as indicated in this document
• Host Country - Health and Safety regulations
The modules are comprised of programming, set-up and actual machining work.
The Test Projects must be designed in metric and to the standards described. Only Test Projects
that follow the guidelines will be allowed for the voting.
Each Expert shall bring a machined sample part of his/her design. This is needed for the CMM
(coordinate measuring machine) as the programming part. It is also supportive in the voting for the
Test Project to have a “real” machined part available.
• Only Test Project proposals, which meet the following criteria, will be allowed for the voting poll:
Project features according to this document
• Project can be machined according to specifications of provided machine
• Drawing in ISO-A and ISO-E
• Drawing free of errors
• Machined sample part existing and conform to drawing. (The programming of the Coordinate
Measuring machine may cause problems if dimensions of sample deviate more than ±0.2mm)
• Marking sheets complete and free of errors.
Project selection will be conducted by the Experts from drawings and sample parts that they have
brought to the competition in one of the three official languages. The drawings must correspond to
the determined marking criteria and to the desired project features as described in this document
Then all Experts have 15 minutes to study the different proposals, followed by the secret vote. The
project with the most votes will be chosen. Faulty drawings or designs will not be eligible for voting.
In the event of a tie, the other projects are eliminated and a new vote between the tied projects
takes place. If by any chance, there is still a tie between 2 or more projects, the Chief Expert’s vote
is worth 2 votes, which will then settle the vote.
3.4.1 The marking scheme proposal is developed by the person(s) developing the Test Project. The
detailed and final marking scheme is developed and agreed by all Experts at the Competition.
3.4.2 Marking schemes should be entered into the CIS prior to the Competition.
Project selection will be conducted by the Experts from drawings and sample parts that they have
brought to the Competition in one of the three official languages.
The drawings must correspond to the determined marking criteria and to the desired project
features as described in this document
The Host Country is to provide the technical specifications of the provided equipment to the
technical delegates of the participating countries at least eight (8) months before the WorldSkills
Competition.
Free training on machine and software must be provided at least four (4) months prior to the
Competition. Travel, lodging and food expenses for this training are to be carried by the Competitor
or his/her sponsor.
The Host Country is obligated to schedule this training at least four (4) months before the
Competition, and notify the participants at least six (6) months before the Competition.
Participating in the provided training is the choice of the Competitors and/or their sponsor.
The Sponsors must supply specialists and service staff for the software and the CNC machines in
adequate numbers to ensure that the competition runs smoothly. These specialists will be available
at all times before and during the competition, as well as during the marking of the test projects.
5. ASSESSMENT
This section describes how the Experts will assess the Test Project / modules. It also specifies the
assessment specifications and procedures and requirements for marking.
B) Surface finish
• Maximal 5 marking aspects
• Measure specified locations (marked on print)
C) Main dimensions
• Must be 10 marking aspects.
• Each dimension equals 5 points
D) Secondary dimensions
• Maximal 15 marking aspects
• Each dimension equals 1.0, 1.5, 2.0, 2.5, 3.0 or 3.5 points
E) Use of Material :
• + 5 Points - if NO additional Material is used
• + 0 points - if ONE additional material is used
• Competitors may ONLY receive ONE extra material per test part.
The Infrastructure List specifies the items & quantities requested by the Experts for the next
Competition. The Host Country will progressively update the Infrastructure List specifying the actual
quantity, type, brand/model of the items. Host Country supplied items are shown in a separate
column.
At each Competition, the Experts must review and update the Infrastructure List in preparation for
the next Competition. Experts must advise the Secretary General of any increases in space and/or
equipment.
At each Competition, the Technical Observer must audit the Infrastructure List that was used at
that Competition.
The Infrastructure List does not include items that Competitors and/or Experts are required to bring
and items that Competitors are not allowed to bring – they are specified below.
Please note that the following is an example of the layout, and is not definitive.
Approx. Space for 20 competitors = 750m²
Space requirements : For 2 competitors, 1 Machine, 2 Workbenches 5m x 7m= 35m²
Depot for Shopmaster: 6m x 9m = 54m²
Expert Room: 9m x 9m = 81m²
Space for Inspection equipment: 9m x 15m = 135m²
Walking and working space between machines : Approx. 15m² per competitor workstation
Add in some space for columns as well as competitors toolcarts.
Based on 20 competitors this would mean approx. 750 m² for the competition.
8.2 Sustainability
• Recycling
• Use of ‘green’ materials
• Use of completed Test Projects after Competition