Variation Order: Design

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 67

design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 001/BR/X/2002
DATE : 23-Oct-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 01/ X / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
1 Java Villa 103 ( 1 Room )
a Bingkirai timber blind c/ finishing lasur as described in drawing to 0.00 2,475,000.00
Walk in closet and Toilet window ( W1& W ex. ) : 3 Unit
b Timber Blind 1.00 x 3.00 M c/ finishing lasur as describe in drawing 0.00 6,600,000.00
to existing window Bedroom : 4 unit

2 Java Villa 120 ( 1 Room )


a Bingkirai timber blind c/ finishing lasur as described in drawing to 0.00 2,475,000.00
Walk in closet and Toilet window ( W1& W ex. ) : 3 Unit
b Timber Blind 1.00 x 3.00 M c/ finishing lasur as describe in drawing 0.00 6,600,000.00
to existing window Bedroom : 4 unit

2 Resort Standard ( 14 Room )


a Bingkirai timber blind c/ finishing lasur as described in drawing to 0.00 11,550,000.00
Entry ( W ex. ) : 1 Unit
b Timber Blind 1.00 x 3.00 M c/ finishing lasur as describe in drawing 0.00 92,400,000.00
to existing window Bedroom : 4 unit

2 Resort Villa ( 3 Room )


a Bingkirai timber blind c/ finishing lasur as described in drawing to 0.00 1,476,180.00
Window ( W1 ) : 1 Unit
b Timber Blind 1.00 x 3.00 M c/ finishing lasur as describe in drawing 0.00 19,800,000.00
to existing window Bedroom : 4 unit

TOTAL: 0.00 143,376,180.00


PRICE INCREASE/ DECREASE: -143,376,180.00
LAST CONTRACT SUM : Rp. 2,300,000,000.00 Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum 2,156,623,820.00
Variance to original contract:Rp. -143,376,180.00
Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 002/BR/X/2002
DATE : 31-Oct-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 03; 04; 05/ X / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
1 Java Villa 103 (1 Unit) 11,240,354.29 0.00
Relocate 1 M entry wall and new terracce (attachment BQ)

2 Resort Standard 109 & 110 (2 Unit) 21,197,052.05 0.00


Relocate wall and add pond to landscape (attachment BQ)
a Water circulation pump ex DAB submersible and natural filter (sand 0.00 1,500,000.00
& coral) for Pond to Room 109
b NYY cable outlet installation to Standard Outlet Pump 0.00 147,500.00
c Power outlet to Pump 0.00 72,500.00

3 Resort Villa 114 & 115 (2 Unit) 190,819,864.28 133,567,334.02


Change bathroom plan (attachment BQ)
a Timber Wardrobe as detail (2 unit) 0.00 9,185,000.00
b Modification wardrobe existing as indication in drawing (3 unit) 6,888,750.00 0.00
c Change exhaust fan to AC (2 unit) 14,600,000.00 750,000.00

TOTAL: 244,746,020.62 145,222,334.02


PRICE INCREASE/ DECREASE: 99,523,686.60
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 002-A/BR/X/2002
DATE : 31-Oct-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 03; 04; 05/ X / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
1 Java Villa 103 (1 Unit) 11,240,354.29 0.00
Relocate 1 M entry wall and new terracce (attachment BQ)

TOTAL: 11,240,354.29 0.00


PRICE INCREASE/ DECREASE: 11,240,354.29
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 004-A2/BR/XI/2002
DATE : 9-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 09/ XI / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Door and Window work

1 Change Refinish existing window Wex to melton glass 35,632,000.00 4,611,000.00

2 Change clear glass to melton glass to new window 15,159,150.00 3,444,420.00

TOTAL: 50,791,150.00 8,055,420.00


PRICE INCREASE/ DECREASE: 42,735,730.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 002-B/BR/X/2002
DATE : 31-Oct-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 03; 04; 05/ X / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

2 Resort Standard 109 & 110 (2 Unit) 21,197,052.05 0.00


Relocate wall and add pond to landscape (attachment BQ)

Deduction work :
a Water circulation pump ex DAB submersible and natural filter (sand 0.00 1,500,000.00
& coral) for Pond to Room 109 (1 unit)
b NYY cable outlet installation to Standard Outlet Pump (1 unit) 0.00 147,500.00
c Power outlet to Pump (1 unit) 0.00 72,500.00

TOTAL: 21,197,052.05 1,720,000.00


PRICE INCREASE/ DECREASE: 19,477,052.05
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 002-C/BR/X/2002
DATE : 31-Oct-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 03; 04; 05/ X / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

3 Resort Villa 114 & 115 (2 Unit) 190,819,864.28 133,567,334.02


Change bathroom plan (attachment BQ)

Deduction work :
a Timber Wardrobe as detail (2 unit) 0.00 9,185,000.00
b Modification wardrobe existing as indication in drawing (3 unit) 6,888,750.00 0.00

TOTAL: 197,708,614.28 142,752,334.02


PRICE INCREASE/ DECREASE: 54,956,280.26
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 003/BR/X/2002
DATE : 1-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 06/ X / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
1 Java Villa 120 (1 Unit) 8,964,490.76 0.00
Relocate 1 M entry wall and new terracce (attachment BQ)

TOTAL: 8,964,490.76 0.00


PRICE INCREASE/ DECREASE: 8,964,490.76
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 004/BR/XI/2002
DATE : 9-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 09/ XI / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Door and Window work 80,526,350.00 15,180,420.00


(Change existing glass with melton glass, see attachment for BQ)

II Masonry work 6,894,580.00 0.00


(Sound proof RS 111 & 112, see attachment for BQ)

III Sanitary Ware 7,125,000.00 0.00


(Shower spray ex TOTO, see attachment for BQ)

TOTAL: 94,545,930.00 15,180,420.00


PRICE INCREASE/ DECREASE: 79,365,510.00
LAST CONTRACT SUM : Rp. 0.00 Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum 79,365,510.00
Variance to original contract:Rp. -2,220,634,490.00
Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 004-A1/BR/XI/2002
DATE : 9-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 09/ XI / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Door and Window work

1 Change modified existing window glass with fix glass 8 mm, 29,735,200.00 7,125,000.00
to Bedroom, see attachment for BQ

TOTAL: 29,735,200.00 7,125,000.00


PRICE INCREASE/ DECREASE: 22,610,200.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 004-B/BR/XI/2002
DATE : 9-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 09/ XI / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Masonry work 6,894,580.00 0.00


(Sound proof RS 111 & 112, see attachment for BQ)

TOTAL: 6,894,580.00 0.00


PRICE INCREASE/ DECREASE: 6,894,580.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 004-C/BR/XI/2002
DATE : 9-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 09/ XI / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Sanitary Ware 7,125,000.00 0.00


(Shower spray ex TOTO, see attachment for BQ)

TOTAL: 7,125,000.00 0.00


PRICE INCREASE/ DECREASE: 7,125,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 005/BR/XI/2002
DATE : 9-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Terrace Partition (12 Unit, @ Rp. 7.737.055,00) 92,844,660.00 0.00


(see attachment for BQ)

TOTAL: 92,844,660.00 0.00


PRICE INCREASE/ DECREASE: 92,844,660.00
LAST CONTRACT SUM : Rp. 79,365,510.00 Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum 172,210,170.00
Variance to original contract:Rp. -2,127,789,830.00
Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 006/BR/XI/2002
DATE : 9-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Landscape

1 Hardscape to RS 101 (see attachment for BQ) 39,411,308.80 0.00

2 Hardscape to RS 105 (see attachment for BQ) 24,314,715.75 0.00

TOTAL: 63,726,024.55 0.00


PRICE INCREASE/ DECREASE: 63,726,024.55
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 007/BR/XI/2002
DATE : 13-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: 19/ XI / BRAK / 2002 Request for Variation Ref.:
COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
IX Finished work (Java Villa; Resort Standard; Resort Villa)

1 Change Marmo marble to polished marble to Walk in Closet 70,071,736.35 76,678,150.00


(see attachment for BQ)

2 Progreess on site Marmo marble, 2 cm thick façade as indicated in 19,530,500.00 0.00


drawing to Walk in Closet and Toilet on Resort Standard phase 1 &
phase 2; 58.3 m2 @ Rp. 335,000.00

TOTAL: 89,602,236.35 76,678,150.00


PRICE INCREASE/ DECREASE: 12,924,086.35
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum #VALUE!
Variance to original contract:Rp. #VALUE!
Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 008/BR/XI/2002
DATE : 19-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Pump Room Java Villa 103

1 Under ground pump room 5,200,533.87 0.00

TOTAL: 5,200,533.87 0.00


PRICE INCREASE/ DECREASE: 5,200,533.87
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 009/BR/XI/2002
DATE : 19-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Pump Room Java Villa 120

1 Upper ground to Under ground pump room 4,222,333.87 1,860,691.71

TOTAL: 4,222,333.87 1,860,691.71


PRICE INCREASE/ DECREASE: 2,361,642.16
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 010/BR/XI/2002
DATE : 19-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Plunge Pool 103

1 Add stair 792,508.75 0.00

II Plunge Pool 120

1 Add stair 450,000.00 0.00

TOTAL: 1,242,508.75 0.00


PRICE INCREASE/ DECREASE: 1,242,508.75
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 011/BR/XI/2002
DATE : 27-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Masonry work

1 Add plastered to existing wall upper wastafel 101 862,331.63 0.00

TOTAL: 862,331.63 0.00


PRICE INCREASE/ DECREASE: 862,331.63
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 012/BR/XI/2002
DATE : 27-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Masonry work

1 Modified jaro-jaro window to small window and sand blasting glass 743,723.75 0.00

TOTAL: 743,723.75 0.00


PRICE INCREASE/ DECREASE: 743,723.75
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 013/BR/XI/2002
DATE : 27-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Gazebo 103 11,936,367.70 0.00

TOTAL: 11,936,367.70 0.00


PRICE INCREASE/ DECREASE: 11,936,367.70
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 014/BR/XII/2002
DATE : 2-Nov-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Floor Work

- Change terrazzo floor existing to polished marble 30x30 cm to 9,603,688.28 0.00


Room 103

- V. Floor work. Terrazzo tile as existing to Bedroom and terracce 0.00 2,624,196.00
(V.O. NO. 002-A/BR/X/2002; 20 Nov 2002)

TOTAL: 9,603,688.28 2,624,196.00


PRICE INCREASE/ DECREASE: 6,979,492.28
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 015/BR/XII/2002
DATE : 18-Dec-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Bathtub 103

- Change design bathtub 103 with new design 3,026,154.98 1,486,996.60

TOTAL: 3,026,154.98 1,486,996.60


PRICE INCREASE/ DECREASE: 1,539,158.38
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 015-A/BR/XII/2002
DATE : 29-Dec-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Bathtub 103; 120; 114 & 115

- Change design bathtub 103 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 120 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 114 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 115 with new design 3,026,154.98 1,486,996.60

TOTAL: 12,104,619.91 5,947,986.40


PRICE INCREASE/ DECREASE: 6,156,633.51
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 016/BR/XII/2002
DATE : 18-Dec-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Bathtub 101

- Change design bathtub 101 with new design 2,392,855.00 1,486,996.60

TOTAL: 2,392,855.00 1,486,996.60


PRICE INCREASE/ DECREASE: 905,858.40
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 017/BR/XiI/2002
DATE : 17-Dec-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Masonry work

1 Modified jaro-jaro window to small window and sand blasting glass 5,820,361.25 0.00
@ Rp. 529,123.75 x 11 Unit (Room 102,104,105,106,107,109,
110,116,117,118 & 119)

TOTAL: 5,820,361.25 0.00


PRICE INCREASE/ DECREASE: 5,820,361.25
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 018/BR/XiI/2002
DATE : 17-Dec-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Finished work

1 Polished marble 30x30 cm to above bathtub wall (window/1 side) 6,260,949.66 0.00
@ Rp. 447,210.69 x 14 Unit (Room 101,102,104,105,106,107,
109,110,111,112,116,117,118 & 119)

TOTAL: 6,260,949.66 0.00


PRICE INCREASE/ DECREASE: 6,260,949.66
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 018-A/BR/I/2003
DATE : 7-Jan-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Finished work

1 Polished marble 30x30 cm to above bathtub wall (window side) 2,518,708.50 0.00
Java Villa 103 & 120 (2 Unit)

2 Polished marble 30x30 cm to above bathtub wall (window side) 7,640,082.45 0.00
Resort Standard 101,102,104,105,106,107,109,110,111,112,116,
117,118,119 (14 Unit)

3 Polished marble 30x30 cm with frame palimanan stone 15x30 cm 1,989,779.72 0.00
to above bathtub wall (back waterfall) Resort Villa 114 & 115
(2 Unit)

TOTAL: 12,148,570.67 0.00


PRICE INCREASE/ DECREASE: 12,148,570.67
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 019/BR/XII/2002
DATE : 29-Dec-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Bathtub

1 - Change design Bathtub with new design (14 Unit) 27,462,470.00 20,817,944.00
(Room 102,104,105,106,107,109,110,111,112,113,116,117,118
dan 119)

TOTAL: 27,462,470.00 20,817,944.00


PRICE INCREASE/ DECREASE: 6,644,526.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 020/BR/XII/2002
DATE : 29-Dec-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Finished work

1 Palimanan 15x30 cm frame to door entrance 103 440,250.00 0.00

2 Palimanan 15x30 cm frame to door entrance 120 440,250.00 0.00

3 Peable wash cover to base timber column existing Room 103 501,559.08 0.00

4 Peable wash cover to base timber column existing Room 120 756,449.76 0.00

TOTAL: 2,138,508.84 0.00


PRICE INCREASE/ DECREASE: 2,138,508.84
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 021/BR/XII/2002
DATE : 29-Dec-02
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Fix & Furniture work

1 Mini Bar with marble top table and burning facing c/ finishing lasur 5,500,000.00 5,500,000.00
as described in drawing to Room 103

2 Mini Bar with marble top table and burning facing c/ finishing lasur 5,500,000.00 5,500,000.00
as described in drawing to Room 120

TOTAL: 11,000,000.00 11,000,000.00


PRICE INCREASE/ DECREASE: 0.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 022/BR/I/2003
DATE : 3-Jan-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Door & Window work

1 Modified existing glass window become fix window c/w repair and 0.00 6,750,000.00
maintain with additional timber wedge, glued, sealant as necessary
to avoid any leakage Room 101; 102; 103; 104; 105; 107; 109;
110; 111; 112; 113; 114; 115; 116; 117; 118; 119 & 120.
( @ Rp. 375.000 x 18 Unit)

TOTAL: 0.00 6,750,000.00


PRICE INCREASE/ DECREASE: -6,750,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 023/BR/I/2003
DATE : 3-Jan-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I Outdoor Shower Java Villa 120

1 II. 11. Compacted sand bed 10 cm to concrete slab floor 0.00 7,187.40
2 II. 17. Polyethelane sheet damp proof membrane bed 0.5 mm 0.00 10,395.00
3 III. 7. Concrete K 175, 8 cm thick w/ rebars 0.00 50,351.00
4 III. 22. Waterproofing coating 0.00 61,875.00
5 V. 3. Polished marble slab 2 cm thick 0.00 184,705.29

TOTAL: 0.00 314,513.69


PRICE INCREASE/ DECREASE: -314,513.69
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 024/BR/I/2003
DATE : 18-Jan-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Penambahan dinding pagar dan roster pada dinding pagar 103 1,160,417.43 0.00

2 Perubahan posisi saklar two gang Java Villa 103 150,000.00 0.00

3 Peable wash jalan entry 113 690,671.52 0.00

4 Chusion tenun ikat pada kursi make up (19 unit) 0.00 1,710,000.00

TOTAL: 2,001,088.95 1,710,000.00


PRICE INCREASE/ DECREASE: 291,088.95
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 025/BR/I/2003
DATE : 29-Jan-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Resapan termasuk bak kontrol, buis beton, ijuk, batu bata, galian 4,000,000.00 0.00
dan buang tanah pada Resort Standar (14 Room)

2 Pasang tumbled marble mock up 101 (1 unit) 137,768.75 0.00

3 Pebble wash pada depan bathtub Resort Standard & Resort Villa 2,569,462.50 0.00
(15 unit)

4 Pasang roster pada dinding Room 120 925,000.00 0.00

5 Peninggian posisi palmet jendela existing Bedroom pada Java 2,850,000.00 0.00
Villa, Resort Standard dan Reosrt Villa

6 Make up/Beauty mirror 0.00 0.00

TOTAL: 10,482,231.25 0.00


PRICE INCREASE/ DECREASE: 10,482,231.25
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 026/BR/I/2003
DATE : 29-Jan-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Perubahan Wardrobe pada Room 101,102,103,104,105,106,107, 22,256,000.00 0.00


109,110,111,112,116,117,118,119 & 120

2 Bongkar small table pada Room 101,102,103,104,105,106,107, 2,794,648.96 0.00


109,110,111,112,116,117,118,119 & 120

3 Perubahan arah bukaan pintu kaca tempered pada Room 101, 3,164,139.00 0.00
102,103,104,105,106,107,109,110,111,112,114, 115, 116,117,
118,119 & 120

TOTAL: 28,214,787.96 0.00


PRICE INCREASE/ DECREASE: 28,214,787.96
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 027/BR/II/2003
DATE : 27-Feb-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Saklar kartu legrand Mozaic 45, 744 45 termasuk pemasangan 450,000.00 0.00
pada Java Villa, Resort Standard dan Resort Villa (22 unit)

2 Instalasi kabel NYY pada lampu wardrobe 113 (2 titik) 230,000.00 0.00

3 Lampu small E14 c/w fitting, lampu dan microswitch pada wardrobe 144,000.00 0.00

4 Pindah saklar existing belakang wardrobe 113 (1 titik) 75,000.00 0.00

5 Make up/Beauty mirror (Room 114 & 115) 0.00 4,200,000.00

6 Instalasi kabel NYY pada lampu atas pintu entry Java Villa, 0.00 0.00
Resort Standard dan Resort Villa (1 titik/Room; 22 Unit)

7 Timber box lamp c/ lamp E14/25W, fitting and other accessories to 0.00 0.00
Java Villa, Resort Standard and Resort Villa (1point/Room; 22 unit)

NOTE:
1. Waktu pelaksanaan 2 minggu setelah disetujuinya VO ini.

TOTAL: 899,000.00 4,200,000.00


PRICE INCREASE/ DECREASE: -3,301,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 028/BR/I/2003
DATE : 29-Jan-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Sand blasting logo di pintu dan partisi kaca pada Java Villa, 5,400,000.00 0.00
Resort Standard dan Resort Villa

TOTAL: 5,400,000.00 0.00


PRICE INCREASE/ DECREASE: 5,400,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 028/BR/iI/2003
DATE : 5-Feb-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Gazebo Room 103 14,254,508.70 0.00

2 Timber deck pump Room 103 4,056,253.92 0.00

3 Timber pergola Room 103 6,662,275.00 0.00

TOTAL: 24,973,037.62 0.00


PRICE INCREASE/ DECREASE: 24,973,037.62
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 029/BR/I/2003
DATE : 1-Feb-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Marmer sudut bathtub 1 piece cream dan dark brown pada 1,000,000.00 0.00
Mock up Java Villa 120 (1 Unit) @ Rp. 1.000.000,00

TOTAL: 1,000,000.00 0.00


PRICE INCREASE/ DECREASE: 1,000,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 030/BR/III/2003
DATE : 4-Mar-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Perubahan design Bathroom Phase 3 (Room 121; 122 & 123) 257,462,000.00 210,441,000.00
(lihat lampiran)

TOTAL: 257,462,000.00 210,441,000.00


PRICE INCREASE/ DECREASE: 47,021,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 031/BR/III/2003
DATE : 4-Mar-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Perubahan posisi Refrigerator pada Nieche Resort Standard 3,826,900.00 0.00


@ Rp. 273.350 x 14 unit

2 Peninggian Vanity table pada Java Villa; Resort Standard dan 1,463,000.00 0.00
Resort Villa @ Rp. 77.000 x 19 unit

TOTAL: 5,289,900.00 0.00


PRICE INCREASE/ DECREASE: 5,289,900.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 032/BR/IV/2003
DATE : 22-Apr-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Change plywood trusses (gewel) to wall trusses to Room 121, 122 11,000,000.00 0.00
& 123 (Phase 3)

TOTAL: 11,000,000.00 0.00


PRICE INCREASE/ DECREASE: 11,000,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 033/BR/IV/2003
DATE : 22-Apr-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Gate and wall fence work Room 101 - 102 area 48,887,175.40 0.00

TOTAL: 48,887,175.40 0.00


PRICE INCREASE/ DECREASE: 48,887,175.40
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 034/BR/IV/2003
DATE : 22-Apr-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Change window to sliding door and add pebble wash stepping 9,000,000.00 0.00
Room 120

TOTAL: 9,000,000.00 0.00


PRICE INCREASE/ DECREASE: 9,000,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 035/BR/IV/2003
DATE : 25-Apr-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Add clear glass 10 mm w/ film and removed roof glass existing to 8,049,000.00 0.00
Resort Standard (101, 102, 104, 105, 106, 107, 111, 112, 116,
117, 118 & 119) @ Rp. 670.750 x 12 Unit

TOTAL: 8,049,000.00 0.00


PRICE INCREASE/ DECREASE: 8,049,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 036/BR/IV/2003
DATE : 25-Apr-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Change design laminated glass 5 + 5 mm with clear glass 10 mm w/ 9,548,040.00 18,825,000.00


film sand blasting to Glass roof 121, 122 & 123

TOTAL: 9,548,040.00 18,825,000.00


PRICE INCREASE/ DECREASE: -9,276,960.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


VARIATION ORDER V.O. NO. : 037/BR/VI/2003
DATE : 4-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

1 Floor work to Entry and Landscape area 101 & 102 14,500,000.00 0.00

TOTAL: 14,500,000.00 0.00


PRICE INCREASE/ DECREASE: 14,500,000.00
LAST CONTRACT SUM : Rp. Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum
Variance to original contract:Rp.

Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id
design

VARIATION PRICE REQUEST


RESUME VARIATION ORDER Ph. 1,2 & 3 V.O. NO. : -
DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I VARIATION ORDER (Already approv)

1 All Villa (001/BR/X/2002; 18 Nov 2002)


- All Timber Blind 0.00 143,376,180.00

2 Java Villa 103 (002-A/BR/X/2002; 20 Nov 2002)


- Relocate entry wall 1 M and new Terracce 11,240,354.29 0.00

3 Resort Standard 109 & 110 (2 Unit) (002-B/BR/X/2002;


20 Nov 2002)
- Relocate wall and add pond to landscape 21,197,052.05 0.00

- Water circulation pump ex DAB and natural filter (1 Unit) 0.00 1,500,000.00

- NYY cable installation to Standard Outlet (1 Unit) 0.00 147,500.00

- Power Outlet to Pump (1 Unit) 0.00 72,500.00

4 Resort Villa 114 & 115 (2 Unit) (002-C/BR/X/2002; 20 Nov 2002)


- Change bathroom plan 190,819,864.28 133,567,334.02

- Timber wardrobe as detail (2 Unit) 0.00 9,185,000.00

- Modification wardrobe existing as indication (3 Unit) 6,888,750.00 0.00

5 Java Villa 120 (1 Unit) (003/BR/X/2002; 18 Nov 2002)


- Relocate entry wall 1 M and new Terracce 8,964,490.76 0.00

6 Door & Window work (004-A1/BR/XI/2002; 20 Nov 2002)


- Change modified existing window glass with fix glass 8 mm to 1,858,450.00 375,000.00
Bedroom Java Villa and Resort Standard (make 1 Unit mock up to
Room 106)

7 Door & Window work (004-A2/BR/XI/2002; 20 Nov 2002)


- Change clear glass to melton glass to new window 15,159,150.00 3,444,420.00
(Room 103, 109, 110, 113, 120)

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 48 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1,2 & 3 V.O. NO. : -
DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
8 Masonry work (004-B/BR/XI/2002; 20 Nov 2002)
- Sound proof wall Resort Standard 111 & 112 6,894,580.00 0.00

9 Sanitary ware (004-C/BR/XI/2002; 20 Nov 2002)


- Shower spray ex TOTO to All Toilet Bathroom 7,125,000.00 0.00

10 Plunge Pool (010/BR/XI/2002; 20 Nov 2002)


- Add stair to 103 792,508.75 0.00
- Add stair to 120 450,000.00 0.00

11 Pump Room 120 (009/BR/XI/2002; 25 Nov 2002)


- Under ground pump room 4,222,333.87 1,860,691.71

12 Finished work (Java Villa; Resort Standard; Resort Villa)


(007/BR/XI/2002; 25 Nov 2002)
- Change Marmo marble to polished marble to Walk in Closet 70,071,736.35 76,678,150.00

- Progreess on site Marmo marble, 2 cm thick façade as indicated in 19,530,500.00 0.00


drawing to Walk in Closet and Toilet on Resort Standard phase 1
& phase 2; 58.3 M2 @ Rp. 335,000.00

13 Door & Window work (005/BR/XI/2002; 25 Nov 2002)


- Terrace Partition (12 Unit, @ Rp. 7.737.055,00)(make 1 unit 7,737,055.00 0.00
mock up to Room 104)

14 Pump Room 103 (008/BR/XI/2002; 26 Nov 2002)


- Under ground pump room 4,400,533.87 0.00

15 Masonry work (012/BR/XI/2002; 27 Nov 2002)


- Modified jaro-jaro window to small window and sand blasting 743,723.75 0.00
glass (Room 101)

16 Floor work (014/BR/XII/2002; 4 Des 2002)


- Change terrazzo floor existing to polished marble 30x30 cm to 9,468,088.28 0.00
Room 103

- Terrazzo tile as existing to Bedroom and terracce 0.00 2,624,196.00


(V.O. NO. 002-A/BR/X/2002; 20 Nov 2002)

17 Masonry work (017/BR/XII/2002; 24 Des 2002)


- Modified jaro-jaro window to small window and sand blasting 5,820,361.25 0.00
glass @ Rp. 529.123,75 x 11 Unit (Room 102, 104, 105, 106, 107,
109, 110, 116, 117, 118 & 119)

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 49 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1,2 & 3 V.O. NO. : -
DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
18 Finished work (020/BR/XII/2002; 30 Des 2002)
- Palimanan 15x30 cm frame to door entrance 103 440,250.00 0.00

- Palimanan 15x30 cm frame to door entrance 120 440,250.00 0.00

- Peable wash cover to base timber column existing Room 103 501,559.08 0.00

- Peable wash cover to base timber column existing Room 120 756,449.76 0.00

19 Door Window work (022/BR/I/2003; 8 Jan 2003)


- Modified existing glass window become fix window c/w repair and 0.00 6,750,000.00
maintain with additional timber wedge, glued, sealant as necessary
to avoid any leakage Room 101,102,103,104,105,107,109,110,
111,112,113,114,115,116,117,118,119 & 120
(@ Rp. 375.000 x 18 unit)

20 Finished work (018-A/BR/I/2003; 8 Jan 2003)


- Polished marble 30x30 cm to above bathtub wall (window side) 2,518,708.50 0.00
Java Villa 103 & 120 (2 unit)

- Polished marble 30x30 cm to above bathtub wall (window side) 7,640,082.45 0.00
Resort Standard 101, 102, 104, 105, 106, 107, 109, 110, 111, 112,
116, 117, 118, 119 (14 unit)

- Polished marble 30x30 cm wit frame palimanan stone 15x30 cm to 1,989,779.72 0.00
above bathtub wall (back waterfall) Resort Villa 114 & 115 (2 unit)

21 (024/BR/I/2003; 18 Jan 2003)


- Penambahan dinding pagar dan roster pada dinding pagar 103 1,160,417.43 0.00

- Perubahan posisi saklar two gang Java Villa 103 150,000.00 0.00

- Peable wash jalan entry 113 690,671.52 0.00

- Chusion tenun ikat pada kursi make up (19 unit) 0.00 1,710,000.00

22 (025/BR/I/2003; 11 Feb 2003)


- Resapan termasuk bak kontrol, buis beton, ijuk, batu bata, galian 4,000,000.00 0.00
dan buang tanah pada Resort Standard

- Pasang tumbled marble mock up 101 (1 unit) 137,768.75 0.00

- Peable wash pada depan bathtub Resort Standard & Resort Villa 2,569,462.50 0.00

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 50 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1,2 & 3 V.O. NO. : -
DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
- Pasang roster pada dinding 120 (1 unit) 925,000.00 0.00

- Peninggian posisi palmet jendela existing Bedroom pada Java 2,850,000.00 0.00
Villa, Resort Standard dan Resort Villa

- Make up/Beauty mirror 0.00 0.00

24 (015-A/BR/XII/2002; 11 Feb 2003)

- Change design bathtub 103 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 120 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 114 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 115 with new design 3,026,154.98 1,486,996.60

26 (019/BR/XII/2002; 11 Feb 2003)

- Change design Bathtub with new design (13 Unit) 25,500,865.00 19,330,948.00
(Room 102,104,105,106,107,109,110,111,112,116,117,118
dan 119)

27 (028/BR/I/2003; 11 Feb 2003)

- Sand blasting logo di pintu dan partisi kaca pada Java Villa, 5,400,000.00 0.00
Resort Standard dan Resort Villa

28 (029/BR/I/2003; 11 Feb 2003)

- Marmer sudut bathtub 1 piece cream dan dark brown pada 1,000,000.00 0.00
Mock up Java Villa 120 (1 Unit) @ Rp. 1.000.000,00

29 (030/BR/III/2003; 5 Mar 2003)


- Perubahan design Bathroom Phase 3 (Room 121; 122 & 123) 257,462,000.00 210,441,000.00

30 (016/BR/XII/2002; 5 Mar 2003)


- Change design bathtub 101 with new design 2,392,855.00 1,486,996.60

31 (027/BR/III/2003; 5 Mar 2003)

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 51 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1,2 & 3 V.O. NO. : -
DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
- Saklar kartu legrand mozaic 45.744 45 termasuk pemasangan pada 450,000.00 0.00
Java Villa 103 (1 unit)

- Instalasi kabel NYY pada lampu wardrobe 113 (2 titik) 230,000.00 0.00

- Lampu small E14 c/w fitting, lampu dan microswitch pada wardrobe 144,000.00 0.00

- Pindah saklar existing belakang wardrobe 113 75,000.00 0.00

- Make up beauty mirror (Room 114 & 115) 0.00 4,200,000.00

32 (032/BR/IV/2003; 22 Apr 2003)


- Change plywood trusses (gewel) to wall trusses to Room 121, 122 11,000,000.00 0.00
& 123 (Phase 3)

33 (033/BR/IV/2003; 24 Apr 2003)


- Gate and wall fence work Room 101 - 102 area 41,991,675.00 0.00

34 (037/BR/IV/2003; 4 May 2003)


- Add clear glass 10 mm w/ film and removed roof glass existing to 8,049,000.00 0.00
Resort Standard (12 unit)

35 (036/BR/IV/2003; 4 May 2003)


- Change design laminated glass 5+5 mm w/ clear glass 10 mm w/ film 9,548,040.00 18,825,000.00
sand blasting to glass roof 121, 122 & 123

36 (026/BR/I/2003)
- Perubahan wardrobe pada Room 101,102,103,104,105,106, 22,256,000.00 0.00
107,109,110,111,112,116,117,118,119 & 120

- Bongkar small table pada Room 101,102,103,104,105,106, 2,794,648.96 0.00


107,109,110,111,112,116,117,118,119 & 120

- Perubahan arah bukaan pintu kaca tempered pada Room 101,102, 3,164,139.00 0.00
103,104,105,106,107,109,110,111,112,116,117,118,119 & 120

37 (037/BR/VI/2003)
- Floor work to entry and landscape area 101 & 102 14,500,000.00 0.00

TOTAL: 838,217,775.08 641,522,902.73


PRICE INCREASE/ DECREASE: 196,694,872.35
LAST CONTRACT SUM : Rp. 2,300,000,000.00 Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum 2,496,694,872.35

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 52 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1,2 & 3 V.O. NO. : -
DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
Variance to original contract:Rp. 196,694,872.35
Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 53 - 67
design

VARIATION PRICE REQUEST


RESUME VARIATION ORDER Ph. 1 & 2 V.O. NO. : -
DATE : 13-Mar-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I VARIATION ORDER (Already approv)

1 All Villa (001/BR/X/2002; 18 Nov 2002)


- All Timber Blind 0.00 143,376,180.00

2 Java Villa 103 (002-A/BR/X/2002; 20 Nov 2002)


- Relocate entry wall 1 M and new Terracce 11,240,354.29 0.00

3 Resort Standard 109 & 110 (2 Unit) (002-B/BR/X/2002;


20 Nov 2002)
- Relocate wall and add pond to landscape 21,197,052.05 0.00

- Water circulation pump ex DAB and natural filter (1 Unit) 0.00 1,500,000.00

- NYY cable installation to Standard Outlet (1 Unit) 0.00 147,500.00

- Power Outlet to Pump (1 Unit) 0.00 72,500.00

4 Resort Villa 114 & 115 (2 Unit) (002-C/BR/X/2002; 20 Nov 2002)


- Change bathroom plan 190,819,864.28 133,567,334.02

- Timber wardrobe as detail (2 Unit) 0.00 9,185,000.00

- Modification wardrobe existing as indication (3 Unit) 6,888,750.00 0.00

5 Java Villa 120 (1 Unit) (003/BR/X/2002; 18 Nov 2002)


- Relocate entry wall 1 M and new Terracce 8,964,490.76 0.00

6 Door & Window work (004-A1/BR/XI/2002; 20 Nov 2002)


- Change modified existing window glass with fix glass 8 mm to 1,858,450.00 375,000.00
Bedroom Java Villa and Resort Standard (make 1 Unit mock up to
Room 106)

7 Door & Window work (004-A2/BR/XI/2002; 20 Nov 2002)


- Change clear glass to melton glass to new window 15,159,150.00 3,444,420.00
(Room 103, 109, 110, 113, 120)

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 54 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1 & 2 V.O. NO. : -
DATE : 13-Mar-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
8 Masonry work (004-B/BR/XI/2002; 20 Nov 2002)
- Sound proof wall Resort Standard 111 & 112 6,894,580.00 0.00

9 Sanitary ware (004-C/BR/XI/2002; 20 Nov 2002)


- Shower spray ex TOTO to All Toilet Bathroom 7,125,000.00 0.00

10 Plunge Pool (010/BR/XI/2002; 20 Nov 2002)


- Add stair to 103 792,508.75 0.00
- Add stair to 120 450,000.00 0.00

11 Pump Room 120 (009/BR/XI/2002; 25 Nov 2002)


- Under ground pump room 4,222,333.87 1,860,691.71

12 Finished work (Java Villa; Resort Standard; Resort Villa)


(007/BR/XI/2002; 25 Nov 2002)
- Change Marmo marble to polished marble to Walk in Closet 70,071,736.35 76,678,150.00

- Progreess on site Marmo marble, 2 cm thick façade as indicated in 19,530,500.00 0.00


drawing to Walk in Closet and Toilet on Resort Standard phase 1
& phase 2; 58.3 M2 @ Rp. 335,000.00

13 Door & Window work (005/BR/XI/2002; 25 Nov 2002)


- Terrace Partition (12 Unit, @ Rp. 7.737.055,00)(make 1 unit 7,737,055.00 0.00
mock up to Room 104)

14 Pump Room 103 (008/BR/XI/2002; 26 Nov 2002)


- Under ground pump room 4,400,533.87 0.00

15 Masonry work (012/BR/XI/2002; 27 Nov 2002)


- Modified jaro-jaro window to small window and sand blasting 743,723.75 0.00
glass (Room 101)

16 Floor work (014/BR/XII/2002; 4 Des 2002)


- Change terrazzo floor existing to polished marble 30x30 cm to 9,468,088.28 0.00
Room 103

- Terrazzo tile as existing to Bedroom and terracce 0.00 2,624,196.00


(V.O. NO. 002-A/BR/X/2002; 20 Nov 2002)

17 Masonry work (017/BR/XII/2002; 24 Des 2002)


- Modified jaro-jaro window to small window and sand blasting 5,820,361.25 0.00
glass @ Rp. 529.123,75 x 11 Unit (Room 102, 104, 105, 106, 107,
109, 110, 116, 117, 118 & 119)

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 55 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1 & 2 V.O. NO. : -
DATE : 13-Mar-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
18 Finished work (020/BR/XII/2002; 30 Des 2002)
- Palimanan 15x30 cm frame to door entrance 103 440,250.00 0.00

- Palimanan 15x30 cm frame to door entrance 120 440,250.00 0.00

- Peable wash cover to base timber column existing Room 103 501,559.08 0.00

- Peable wash cover to base timber column existing Room 120 756,449.76 0.00

19 Door Window work (022/BR/I/2003; 8 Jan 2003)


- Modified existing glass window become fix window c/w repair and 0.00 6,750,000.00
maintain with additional timber wedge, glued, sealant as necessary
to avoid any leakage Room 101,102,103,104,105,107,109,110,
111,112,113,114,115,116,117,118,119 & 120
(@ Rp. 375.000 x 18 unit)

20 Finished work (018-A/BR/I/2003; 8 Jan 2003)


- Polished marble 30x30 cm to above bathtub wall (window side) 2,518,708.50 0.00
Java Villa 103 & 120 (2 unit)

- Polished marble 30x30 cm to above bathtub wall (window side) 7,640,082.45 0.00
Resort Standard 101, 102, 104, 105, 106, 107, 109, 110, 111, 112,
116, 117, 118, 119 (14 unit)

- Polished marble 30x30 cm wit frame palimanan stone 15x30 cm to 1,989,779.72 0.00
above bathtub wall (back waterfall) Resort Villa 114 & 115 (2 unit)

21 (024/BR/I/2003; 18 Jan 2003)


- Penambahan dinding pagar dan roster pada dinding pagar 103 1,160,417.43 0.00

- Perubahan posisi saklar two gang Java Villa 103 150,000.00 0.00

- Peable wash jalan entry 113 690,671.52 0.00

- Chusion tenun ikat pada kursi make up (19 unit) 0.00 1,710,000.00

22 (025/BR/I/2003; 11 Feb 2003)


- Resapan termasuk bak kontrol, buis beton, ijuk, batu bata, galian 4,000,000.00 0.00
dan buang tanah pada Resort Standard

- Pasang tumbled marble mock up 101 (1 unit) 137,768.75 0.00

- Peable wash pada depan bathtub Resort Standard & Resort Villa 2,569,462.50 0.00

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 56 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1 & 2 V.O. NO. : -
DATE : 13-Mar-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
- Pasang roster pada dinding 120 (1 unit) 925,000.00 0.00

- Peninggian posisi palmet jendela existing Bedroom pada Java 2,850,000.00 0.00
Villa, Resort Standard dan Resort Villa

- Make up/Beauty mirror 0.00 0.00

24 (015-A/BR/XII/2002; 11 Feb 2003)

- Change design bathtub 103 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 120 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 114 with new design 3,026,154.98 1,486,996.60

- Change design bathtub 115 with new design 3,026,154.98 1,486,996.60

26 (019/BR/XII/2002; 11 Feb 2003)

- Change design Bathtub with new design (13 Unit) 25,500,865.00 19,330,948.00
(Room 102,104,105,106,107,109,110,111,112,116,117,118
dan 119)

27 (028/BR/I/2003; 11 Feb 2003)

- Sand blasting logo di pintu dan partisi kaca pada Java Villa, 5,400,000.00 0.00
Resort Standard dan Resort Villa

28 (029/BR/I/2003; 11 Feb 2003)

- Marmer sudut bathtub 1 piece cream dan dark brown pada 1,000,000.00 0.00
Mock up Java Villa 120 (1 Unit) @ Rp. 1.000.000,00

TOTAL: 464,160,417.12 406,569,906.13


PRICE INCREASE/ DECREASE: 57,590,510.99
LAST CONTRACT SUM : Rp. 2,300,000,000.00 Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum 2,357,590,510.99
Variance to original contract:Rp. 57,590,510.99
Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 57 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1 & 2 V.O. NO. : -
DATE : 13-Mar-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 58 - 67
design

VARIATION PRICE REQUEST


RESUME VARIATION ORDER Ph. 3 V.O. NO. : -
DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I VARIATION ORDER (Already approv)

1 (030/BR/III/2003; 5 Mar 2003)


- Perubahan design Bathroom Phase 3 (Room 121; 122 & 123) 257,462,000.00 210,441,000.00

2 (016/BR/XII/2002; 5 Mar 2003)


- Change design bathtub 101 with new design 2,392,855.00 1,486,996.60

3 (027/BR/III/2003; 5 Mar 2003)


- Saklar kartu legrand mozaic 45.744 45 termasuk pemasangan pada 450,000.00 0.00
Java Villa 103 (1 unit)

- Instalasi kabel NYY pada lampu wardrobe 113 (2 titik) 230,000.00 0.00

- Lampu small E14 c/w fitting, lampu dan microswitch pada wardrobe 144,000.00 0.00

- Pindah saklar existing belakang wardrobe 113 75,000.00 0.00

- Make up beauty mirror (Room 114 & 115) 0.00 4,200,000.00

4 (032/BR/IV/2003; 22 Apr 2003)


- Change plywood trusses (gewel) to wall trusses to Room 121, 122 11,000,000.00 0.00
& 123 (Phase 3)

5 (033/BR/IV/2003; 24 Apr 2003)


- Gate and wall fence work Room 101 - 102 area 41,991,675.00 0.00

6 (037/BR/IV/2003; 4 May 2003)


- Add clear glass 10 mm w/ film and removed roof glass existing to 8,049,000.00 0.00
Resort Standard (12 unit)

7 (036/BR/IV/2003; 4 May 2003)


- Change design laminated glass 5+5 mm w/ clear glass 10 mm w/ film 9,548,040.00 18,825,000.00
sand blasting to glass roof 121, 122 & 123

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 59 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 3 V.O. NO. : -
DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

8 (026/BR/I/2003)
- Perubahan wardrobe pada Room 101,102,103,104,105,106, 22,256,000.00 0.00
107,109,110,111,112,116,117,118,119 & 120

- Bongkar small table pada Room 101,102,103,104,105,106, 2,794,648.96 0.00


107,109,110,111,112,116,117,118,119 & 120

- Perubahan arah bukaan pintu kaca tempered pada Room 101,102, 3,164,139.00 0.00
103,104,105,106,107,109,110,111,112,116,117,118,119 & 120

9 (037/BR/VI/2003)
- Floor work to entry and landscape area 101 & 102 14,500,000.00 0.00

TOTAL: 374,057,357.96 234,952,996.60


PRICE INCREASE/ DECREASE: 139,104,361.36
LAST CONTRACT SUM : Rp. 2,300,000,000.00 Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum 2,439,104,361.36
Variance to original contract:Rp. 139,104,361.36
Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 60 - 67
No. Uraian Room Harga Satuan Jumlah

A Kontrak

1 Preliminaries 1.00 74,000,000.00 74,000,000.00

2 Java Villa 103 1.00 214,123,269.38 214,123,269.38

3 Java Villa 120 1.00 204,079,926.75 204,079,926.75

4 Resort Standard 12.00 99,691,424.31 1,196,297,091.72

5 Resort Villa 6.00 66,783,666.99 400,702,001.94

6 Resort Standard (109; 110) 2.00 105,399,121.14 210,798,242.28

7 Total 2,300,000,000.00

22.00
B Phase III

1 - Resort Villa 121, 122, 123 3.00 66,783,666.99 200,351,000.97

2 - Preliminaries 0.14 74,000,000.00 10,090,909.09

3 Total 210,441,910.06

C Phase I & II 19.00

1 Preliminaries 0.86 74,000,000.00 63,909,090.91

2 Java Villa 103 1.00 214,123,269.38 214,123,269.38

3 Java Villa 120 1.00 204,079,926.75 204,079,926.75

4 Resort Standard 12.00 99,691,424.31 1,196,297,091.72

5 Resort Villa (113) 1.00 66,783,666.99 66,783,666.99

6 Resort Standard (109; 110) 2.00 105,399,121.14 210,798,242.28

7 Resort Villa (114+115) 2.00 95,409,932.14 190,819,864.28

8 Total 19.00 2,146,811,152.31

D Variation Order

1 VO Kurang -406,569,906.13

2 VO Tambah 464,160,417.12
3 Total 57,590,510.99

E Summary

1 Kontrak sekarang (C8 + D3) 2,204,401,663.30

2 Pembayaran
- Uang muka 397,272,727.27 0.8636363636
- Termyn 1 354,198,042.00 0.1363636364
- Termyn 2 591,577,334.00 62,727,272.73
- Termyn VO 1 127,221,158.00

3 Total 1,470,269,261.27

4 Retensi 5% 110,220,083.16

5 Pembayaran Kontrak & VO (1 - 3 - 4) 623,912,318.86


REKAPITULASI KONTRAK
RENOVATION BATHROOM ALAM KULKUL BOUTIQUE RESORT PROJECT

KONTRAK PHASE 1 DAN 2 (19 ROOM) PHASE 3 (3 ROOM)


No. Uraian
Room Harga Satuan Jumlah Room Harga Satuan Jumlah Room Harga Satuan Jumlah

1 Preliminaries 1.00 74,000,000.00 74,000,000.00 0.86 74,000,000.00 63,909,090.91 0.14 74,000,000.00 10,090,909.09

2 Java Villa 103 1.00 214,123,269.38 214,123,269.38 1.00 214,123,269.38 214,123,269.38 0.00 214,123,269.38 0.00

3 Java Villa 120 1.00 204,079,926.75 204,079,926.75 1.00 204,079,926.75 204,079,926.75 0.00 204,079,926.75 0.00

4 Resort Standard 12.00 99,691,424.31 1,196,297,091.72 12.00 99,691,424.31 1,196,297,091.72 0.00 99,691,424.31 0.00

5 Resort Villa 6.00 66,783,666.99 400,702,001.94 3.00 66,783,666.99 200,351,000.97 3.00 66,783,666.99 200,351,000.97

6 Resort Standard (109; 110) 2.00 105,399,121.14 210,798,242.28 2.00 105,399,121.14 210,798,242.28 0.00 105,399,121.14 0.00

TOTAL ### ### ###

7 VARIATION ORDER (17 Feb 2003) 0.00 57,590,510.99 139,104,361.36


22.00
TOTAL ### ### ###
B Phase III

1 - Resort Villa 121, 122, 123 3.00 66,783,666.99 200,351,000.97

2 - Preliminaries 0.14 74,000,000.00 10,090,909.09

3 Total 210,441,910.06

C Phase I & II 19.00

1 Preliminaries 0.86 74,000,000.00 63,909,090.91

2 Java Villa 103 1.00 214,123,269.38 214,123,269.38

3 Java Villa 120 1.00 204,079,926.75 204,079,926.75

4 Resort Standard 12.00 99,691,424.31 1,196,297,091.72

5 Resort Villa (113) 1.00 66,783,666.99 66,783,666.99

6 Resort Standard (109; 110) 2.00 105,399,121.14 210,798,242.28

7 Resort Villa (114+115) 2.00 95,409,932.14 190,819,864.28

8 Total 19.00 2,146,811,152.31

2,357,253,062.37
2,414,843,573.36
D Variation Order
1 VO Kurang -406,569,906.13

2 VO Tambah 464,160,417.12

3 Total 57,590,510.99

E Summary

1 Kontrak sekarang (C7 + D3) 2,204,401,663.30

2 Pembayaran
- Uang muka 397,272,727.27 0.864
- Termyn 1 354,198,042.00 0.136
- Termyn 2 591,577,334.00 ###
- Termyn VO 1 127,221,158.00

3 Total 1,470,269,261.27

4 Retensi 5% 110,220,083.16

5 Pembayaran Kontrak & VO (1 - 3 - 4) 623,912,318.86


design

VARIATION PRICE REQUEST


RESUME VARIATION ORDER Ph. 1,2 & 3 V.O. NO. : -
NON BATHROOM DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION

I VARIATION ORDER (Already approv)

1 Java Villa 103 (002-A/BR/X/2002; 20 Nov 2002)


- Relocate entry wall 1 M and new Terracce 11,240,354.29 0.00

2 Resort Villa 114 & 115 (2 Unit) (002-C/BR/X/2002; 20 Nov 2002)


- Timber wardrobe as detail (2 Unit) 0.00 9,185,000.00

- Modification wardrobe existing as indication (3 Unit) 6,888,750.00 0.00

3 Java Villa 120 (1 Unit) (003/BR/X/2002; 18 Nov 2002)


- Relocate entry wall 1 M and new Terracce 8,964,490.76 0.00

4 Door & Window work (004-A1/BR/XI/2002; 20 Nov 2002)


- Change modified existing window glass with fix glass 8 mm to 1,858,450.00 375,000.00
Bedroom Java Villa and Resort Standard (make 1 Unit mock up to
Room 106)

5 Masonry work (004-B/BR/XI/2002; 20 Nov 2002)


- Sound proof wall Resort Standard 111 & 112 6,894,580.00 0.00

6 Door & Window work (005/BR/XI/2002; 25 Nov 2002)


- Terrace Partition (12 Unit, @ Rp. 7.737.055,00)(make 1 unit 7,737,055.00 0.00
mock up to Room 104)

7 Floor work (014/BR/XII/2002; 4 Des 2002)


- Change terrazzo floor existing to polished marble 30x30 cm to 9,468,088.28 0.00
Room 103

- Terrazzo tile as existing to Bedroom and terracce 0.00 2,624,196.00


(V.O. NO. 002-A/BR/X/2002; 20 Nov 2002)

8 Finished work (020/BR/XII/2002; 30 Des 2002)

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 66 - 67
VARIATION PRICE REQUEST
RESUME VARIATION ORDER Ph. 1,2 & 3 V.O. NO. : -
NON BATHROOM DATE : 9-Jun-03
To: PT. WIETASHA PUTRINDO WISATA
Attention: Mr. ARU SHANTIRAN
Contract / SPK: BATHROOM RENOVATION / No. 001 / VR - AKBR / IX / 02

Site Instruction Ref.: Request for Variation Ref.:


COST ADJUSTMENT (Rp.)
NO. DESCRIPTION ADDITION DEDUCTION
- Palimanan 15x30 cm frame to door entrance 103 440,250.00 0.00

- Palimanan 15x30 cm frame to door entrance 120 440,250.00 0.00

- Peable wash cover to base timber column existing Room 103 501,559.08 0.00

- Peable wash cover to base timber column existing Room 120 756,449.76 0.00

9 (032/BR/IV/2003; 22 Apr 2003)


- Change plywood trusses (gewel) to wall trusses to Room 121, 122 11,000,000.00 0.00
& 123 (Phase 3)

10 (033/BR/IV/2003; 24 Apr 2003)


- Gate and wall fence work Room 101 - 102 area 41,991,675.00 0.00

11 (037/BR/VI/2003)
- Floor work to entry and landscape area 101 & 102 14,500,000.00 0.00

TOTAL: 122,681,952.17 12,184,196.00


PRICE INCREASE/ DECREASE: 110,497,756.17
LAST CONTRACT SUM : Rp. 2,300,000,000.00 Original Contract sum (w/o PPN 10%) 2,300,000,000.00
Current contract sum 2,410,497,756.17
Variance to original contract:Rp. 110,497,756.17
Quotation by: (Contractor) Prepared/ Checked by: (Supervisor) Approved by: (Owner / Representative)

Signed: Signed: Signed:


Name: Name: Name:
Date: Date: Date:

Jl. Tunggul Ametung III/9 Denpasar - Bali, Phone/Fax. No. 62 361 413194, e_mail : cdesign@indo.net.id Page 67 - 67

You might also like