Site: Central Piedra Buena (Bahia Blanca - Argentina) Eng.: Mr. Joerg Fellmerk Dates: 13.09.2014 - 29.09.2014 Unit 30

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Site : Central Piedra Buena (Bahia Blanca – Argentina)

Eng. : Mr. Joerg Fellmerk


Dates: 13.09.2014 - 29.09.2014
Unit 30

The current document is a brief summary day by day of the Alstom service on Brou1 and Brou2 of unit 30 on
CPB Plant in Bahia Blanca.
Sempell will release a complete report of the service.

13.09.2014 Sa. To 15.09.2014 Mo. Travel to site and Visa

16.09.2014 Tu. Preparations for valve disassembly. CPB was removing isolation on Brou1 and Brou2
Valves.

17.09.2014 We. CPB released the area in order to Alstom start the valves dismantling. The Brou2 (MP)
valve disassembly started.

Pagina 1 de 6
18.09.2014 Td. Dismantling of Brou1 and Brou2 (LP-and HP).

Brou2 seatring welding.

Pagina 2 de 6
Brou2 taper key

Brou1 disassembly process

19.09.2014 Fr. Inspection and cleaning of both Valves.

Brou2 Stem Cracks (Pos 20)

Pagina 3 de 6
Brou1 Cage status (pos10)

Brou1 stem and cone (pos 82, 20)

20.09.2014 Sa. Cleaning and reconditioning inside parts on both Valves.

Brou1 body seatring damages

21.09.2014 Su. Day off

22.09.2014 Mo. CPB reparation jobs planning.

Pagina 4 de 6
23.09.2014 Tu. CPB perform Machining on stem and cone of both valves.

24.09.2014 We. CPB Preparation jobs for grinding on Brou1 (HP) and Brou2 welding (MP).
Sempell sent the welding procedure and recommendations.

Brou2 seatring welding cleaning and heat treatment previus to weld.

25.09.2014 Td. CPB perform the Brou2 (MP) Welding according with Babcock manual. The valve was
controlled heated to 250 o C before the welding start. The welding was TIG (Union CrMo910 2,5m). After
welding was finished a heat treatment was applied rising up the temperature to 650 oC during 2 (two) hours.
On Brou1 (HP) a pneumatic tool was mounted to the valve body and the body seat was machined from
16:00hrs to 7:00 next day.

Brou1seatring machining.

Pagina 5 de 6
26.09.2014 Fri. Brou 1 (HP) Body seat checking and valve assembly. Brou1 ready to actuator assembly
by CPB. On Brou2 CPB is performing post welding heat treatment.

Brou2 bodyseat new welding

27.09.2014 Sa. Brou 2 (MP) Body seat checking and valve assembly. Brou2 ready to actuator assembly
by CPB.

28.09.2014 Su. To 29.09.2014 Mo. Returning to Germany

Pagina 6 de 6