Site: Central Piedra Buena (Bahia Blanca - Argentina) Eng.: Mr. Joerg Fellmerk Dates: 13.09.2014 - 29.09.2014 Unit 30
Site: Central Piedra Buena (Bahia Blanca - Argentina) Eng.: Mr. Joerg Fellmerk Dates: 13.09.2014 - 29.09.2014 Unit 30
Site: Central Piedra Buena (Bahia Blanca - Argentina) Eng.: Mr. Joerg Fellmerk Dates: 13.09.2014 - 29.09.2014 Unit 30
The current document is a brief summary day by day of the Alstom service on Brou1 and Brou2 of unit 30 on
CPB Plant in Bahia Blanca.
Sempell will release a complete report of the service.
16.09.2014 Tu. Preparations for valve disassembly. CPB was removing isolation on Brou1 and Brou2
Valves.
17.09.2014 We. CPB released the area in order to Alstom start the valves dismantling. The Brou2 (MP)
valve disassembly started.
Pagina 1 de 6
18.09.2014 Td. Dismantling of Brou1 and Brou2 (LP-and HP).
Pagina 2 de 6
Brou2 taper key
Pagina 3 de 6
Brou1 Cage status (pos10)
Pagina 4 de 6
23.09.2014 Tu. CPB perform Machining on stem and cone of both valves.
24.09.2014 We. CPB Preparation jobs for grinding on Brou1 (HP) and Brou2 welding (MP).
Sempell sent the welding procedure and recommendations.
25.09.2014 Td. CPB perform the Brou2 (MP) Welding according with Babcock manual. The valve was
controlled heated to 250 o C before the welding start. The welding was TIG (Union CrMo910 2,5m). After
welding was finished a heat treatment was applied rising up the temperature to 650 oC during 2 (two) hours.
On Brou1 (HP) a pneumatic tool was mounted to the valve body and the body seat was machined from
16:00hrs to 7:00 next day.
Brou1seatring machining.
Pagina 5 de 6
26.09.2014 Fri. Brou 1 (HP) Body seat checking and valve assembly. Brou1 ready to actuator assembly
by CPB. On Brou2 CPB is performing post welding heat treatment.
27.09.2014 Sa. Brou 2 (MP) Body seat checking and valve assembly. Brou2 ready to actuator assembly
by CPB.
Pagina 6 de 6