KNPC Letter - Wo-40

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 177

Ref. No.

:KCC/KNPC/CB-CPD-2066/W-40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Mr. Meshal A Al- Abbasi


Team Leader- Project Control & Quality Assurance –PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Approval of RFQ for separate Dedicated Nitrogen Header at


MAA Refinery

Dear Sir,

With reference to above mentioned subject, please find the attached RFQ of
CB/CPD/2066/W-40/MAA (Separate Dedicated Nitrogen Header at MAA Refinery).

This is submitted for your kind review and approval.

Assuring you of our best attention and cooperation at all times.

Thanks and Best Regards,

Abdulla Kadib
Contractor’s Representative
Encl: - 1. As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W-40/L-275 Date: 02nd August 2017

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Mr. Anwar N Hayat


TPL Specialist , Project Management- PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Time Extension.

Dear Sir,

With reference to above mentioned subject, please be informed that KCCEC did not
receive the legible and complete drawings for the scope of work. However KCCEC
submitted the RFQ on 10-07-2017 through KCCEC letter reference no. KCC/KNPC/CB-
CPD-2066/L-245 for the approval. Till date there is no response from KNPC due to
which, we are unable to submit the proposal in time.

Therefore, you are kindly requested to provide time extension for 03 weeks after
getting approval of RFQ.

This is for your kind information and necessary action.

Assuring you of our best attention and cooperation at all times.


Thanks and Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W-40/L-275 Date: 06th August 2017

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Mr. Anwar N Hayat


TPL Specialist , Project Management- PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Submission of Work Proposal – 40, Rev-00.

Dear Sir,

With reference to the above mentioned subject, KCCEC would like to inform that
duration mentioned in the Work Requistion is 04 months. But as per the site condition
Scaffolding is required approximately 3.5 km, therefore it’s not possible to erect the
scaffolding laying of pipe ,testing and commissioning.

So KCCEC considered 12 months duration to complete the work order.

Assuring you of our best attention and cooperation at all times.

Thanks and Best Regards,


Abdulla Kadib
Contractor’s Representative

Encl: 1. Work Proposal – 40, Rev-00..

Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Mr. Anwar N Hayat


TPL Specialist, Project Management- PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Submission of Work Proposal – 40, Rev-01.

Dear Sir,

With reference to the above mentioned subject and KNPC letter reference no.
KNPC/KCC/CB-CPD-2066-F-17-0431 dated 31st Oct-2017, please find attached revised
Work Proposal of CB/CPD/2066/W-40/MAA/Rev-00 along with quotation for separate
deicated nitrogen header at MAA refinery.
This is for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,
Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- 1. Work Proposal Rev – 03.


2. Quotations.
3. Compliance Statement

Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Mr. Anwar N Hayat
TPL Specialist, Project Management- PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Second Kick of Meeting.

Dear Sir,

With reference to the above-mentioned subject, KCCEC would like to inform that the Work
order # 40 (Separate Dedicated Nitrogen Header at MAA Refinery) has awarded on 02nd Jan-
2018 through letter ref no. KNPC/KCC/CB-CPD-2066-F-17-0508.

The first kick of meeting happened on 15th Jan2018 and it was concluded without work order
commencement date and the focal point from KNPC, during the meeting Engeering Dept
informed that they will arrange for another meeting in order to finalize certain issues.
KCCEC has called for the second Kick of Meeting on 28th Jan-2018 during this meeting also
unable to finalize the contract custodian by the Engeering Dept.So we are kindly requested
you to advice us the Custodian for Work Order # 40.
This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Mr. Anwar N Hayat


TPL Specialist, Project Management- PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Delay in submission of Work Propsal

Dear Sir,

With reference to the above mentioned subject, KCCEC has received the work
requestion on 2/7/2017 and submitted the RFQ for KNPC approval through
KCCEC letter ref.no.KCC/KNPC/CB-CPD-2066/W40/L-245 dated 10/7/2017
and received the approval for RFQ through KNPC letter ref.no. KNPC/KCC/
CB-CPD-2066-F-17-0296 dated on 9/8/2017. Based on the approval KCCEC
has floated enquiries to the vendors for the supply of

a) CS Pipes & Fittings


b) Instrument Signal Cable
c) Supply & Installation of Control Calve
d) Supply & Installation of Electroic pressure transmission

After the joint site visit by the vendors along with KCCEC and KNPC vendors
provided the quotation for CS Pipes & Fittings on 25/8/2017, 27/8/2017 &
30/8/2017/ Pressure transmitter on 10/9/2017, 28/9/2017 & 29/8/2017 &
28/8/2017/ Control Valves on 7/9/2017, 29/8/2017.

Please find the attached quotation for your reference.The drawings received
along with the work requistions are not clear.The same has been informed to
the end user but clear copy of drawings received almost one month later from
the end user it was affecting the scaffolding calculation. Moreover, KCCEC has
to prepare breakup for scaffolding

for a length of 3.8 km, it is spread all over the MAA refinery due to which there
is a delay in proposal submission.

After review of these quotations received from vendors KCCEC was able to
submit the work proposal on 12/9/2017.

This is for your kind information.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative
Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Mr. Anwar N Hayat
TPL Specialist, Project Management- PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Isometric Drawing.

Dear Sir,
With reference to the above mentioned subject, please be informed that
KNPC engineering dept has informed that they will provide the Isometric
drawings and sleeper foundation drawings. Once the work order has been
awarded to KCCEC but till date KNPC not provided any drawings. It’s
affecting our site activities, so you are kindly requested to provide the
necessary drawings in order to start our activity.

Further, please be informed that KCCEC is not performing any enquiry


related works line preparation of drawings & calculations.

Hence, once again you are kindly requested to provide necessary drawings
as soon as possible.

This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/L-001 Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Approval of Organization Chart and CV’s.


Dear Sir,

With reference to the above mentioned work order, please find attached organization chart
and

personnel CV’s for your kind review and approval.

S.No Name Designation Site

1 Mr.Nestor Belmonte Work order Co-ordinator MAA

2 Mr.Bibin QC Supervisor MAA

3 Mr.Ibrahim Kandil Coating Supervisor MAA

4 Mr.Salamon Arokiyadoss Mechanical Supervisor MAA

5 Mr.Tausif Raza Khan Scaffolding Supervisor MAA

6 Mr.Ray Bhupendra Kumar Rigging & Mechanical Supervisor MAA

7 Mr.Soji Alex E & I Supervisor MAA

Your kind cooperation and support in this regards is highly appreciated.

Best Regards,

Abdulla Kadib
Contractor’s Representative
Encl: As mentioned above.

Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Pressure Transmitter Drawing Approval.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith
the drawings for Pressure Transmitter.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)
Ref.: Contract no. CB/CPD/2066.
Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Placing Purchase Orders.

Dear Sir,

With reference to the above mentioned subject, please find attached


herewith the
following:-

1. Purchase order ref no: C-2016350/W-40/001 dated 04th Jan-2018 for


supply of pipes, fittings & valves.
2. Purchase order ref no: C-2016350/W40/002 dated 01st Feb-2018 for
supply of control valve.
3. Purchase order ref no: C-2016350/W40/003 dated 09th Jan-2018 for
supply of pressure transmittal.
4. Purchase order ref no: C-2016350/W40/004 dated 04th Jan-2018 for
supply of control cables.

This is submitted for your kind information and record.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Shoring Plan for Shelter # 01.

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref
no.KNPC/
PTFBP/KCCEC/2066/WO1-L-0140 dated 29th Jan-2018, please find
attached
Shoring plan for shelter # 1.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Painting & blasting Procedure

Dear Sir,

With reference to the above mentioned subject, please find attached Painting &
blasting Procedure ref no.2066-KCCEC/QA.QC-PR-PI-O Rev (0)

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Welding Procedure Specification.

Dear Sir,

With reference to the above mentioned subject, please find attached the following
and previous approvals for the same.

1. WPS ref no. WPS/KCCEC-004 Rev-A dated 04th March-2013 with supporting
PQR.
2. WPS ref no. WPS/KCCEC-004 Rev-A dated 04th Feb-2013 with supporting
PQR.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Approval documents for control valve

Dear Sir,

With reference to the above mentioned subject, please find attached the following
documents for control valve:

1. Specifications Data Sheet


2. Calculation Sheet
3. Inspection & Test Plan
4. Outline drawing (General arrangement drawing)

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,
Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Data Sheet for Control cable

Dear Sir,

With reference to the above mentioned subject, please find attached data sheet for
control cables.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative
Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Isometric Drawing and Layout area.

Dear Sir,

With reference to the above mentioned subject, please be informed that the work
order has been awarded to KCCEC on 02nd January’18 and Kick of Meeting
conducted on 15th Jan-2018.

During the meeting KCCEC has requested for the Laydown area for storing the
pipe
materials but till date KNPC not allotted any area. So, KCCEC unable to make Pre-
construction activities.
Further, please be informed that KNPC Engineering dept informed that once the
work order
has placed Isometric drawings will be provided to start the fabrication work, but
drawings
are not yet provided.

Therefore, in order to expedite the site activities, you are kindly requested to take
necessary

action in this regard.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co.
Projects Department
Kuwait.

Kind Attn.: Mr. Anwar N Hayat


TPL Specialist , Project Management- PD I

CC: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Isometric drawing and laydown Area

Dear Sir,
With reference to KCCEC letter no.KCC/KNPC/CB-CPD/W-40/L-007 dated
21/02/2018, KCCEC would like to follow up the request for Isometric drawing and
laydown area.

Work order has been awarded to KCCEC on 2/01/2018 and Kick off meeting was
conducted on 15/01/2018. During the meeting KCCEC has requested for the laydown
area for storing the pipe materials and to carry out necessary fabrication activities but
till date KNPC has not allotted any area. Hence, KCCEC is unable to carry out any
pre-construction activities

Further, please be informed that KNPC Engineering Dept. informed that once the work
order has placed Isometric drawings will be provided to start the fabrication works,
but drawings are not yet provided.

Therefore, in order to expedite the site activities, you are kindly rtequested to take
necessary action in this regard.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request of Laydown Area

Dear Sir,
With reference to the above mentioned subject and further to our discussion,
please be informed that

1. The duration of the work will be 2nd Jan to June 2018.


2. The name of the contractor will be M/s. Kuwait Controls Company
Engineering Contracting.
3. The size of the area required will be (40m x 70m) 2800m2
4. The purpose of the utilization area will be workshop & for fabrication
storage area.
5. The work ordercommencement date will be on 15th April 2018

This is submitted for yor kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material test certificate for Piping materials & valves

Dear Sir,

With reference to the above mentioned subject and our PO ref.no.C-


2016350/ W-40/001 dated 4/1/2018, please find attached material test
certificates for the following items as per PO:

1. Item No.36
2. Item No.37
3. Item No.40
4. Item No.41

This is submitted for yor kind information.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)


Ref.: Contract no. CB/CPD/2066.
Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material test certificate for Piping materials

Dear Sir,

With reference to the above mentioned subject and our PO ref.no.C-


2016350/ W-40/001 dated 4/1/2018, please find attached material test
certificates for the following items as per PO:

1. Items from 5 to 12
2. Items from 14 to 20
3. Items from 22 to 34

This is submitted for your review & approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificate.

Dear Sir,

With reference to the above mentioned subject and our PO ref no. C-
2016350/WO-
040/001, please find attached Material Test Certificate for the following items
as per
PO :

1. Items from 05 to 35.


2. Items Nos. 38 , 39 & 42.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificate.

Dear Sir,

With reference to the above mentioned subject, please find attached Piping
Test
Certificates for Items (1) to (4) as per our PO ref no. C-2016350/W-40/001.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Blasters & Painters List.

Dear Sir,

With reference to the above mentioned subject, please find attached list
along with
valid cards of Blasters and Painters who will be utilized for the above
mentioned
order.

This is submitted for your kind information and record.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Storage Yard.

Dear Sir,

With reference to the above mentioned subject, we kindly request you to


provide us
with storage yard with approximately 20mtr x 30 mtr which required to store
our
materials like (Scafolding, pipes…etc).

This is submitted for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain,
Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)-2388592/81097/23881823-vipin

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Work Permit Executor.

Dear Sir,

With reference to the above mentioned subject, please nominate the following persons
for Work Permit Executor:-

Sno Name Position Civil Id Employee No


1 Mr.Tawsif Khan Scaffolding Supervisor 288121805687 19669
2 Mr.Tom Charuvil Scaffolding Supervisor 2872053015969 26584
3 Mr.MohammedAli Mechanical Supervisor 292020302994 19174
4 Mr.Jaswail Piping Supervisor 272020121749 11158
5 Mr.Misra Piping Supervisor 280021510084 11140

This is for your kind information and necessary action as they are required to start
site
activities.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificate.

Dear Sir,
With reference to the above mentioned subject and KCCEC letter
ref.no.KCC/KNPC/CB/CPD-2066/W-40/L-08, L-09, L-010 regarding
approval for material test certificate, please be informed that the supplier due
to long delay in approval it will lead to change in materials heat numbers &
again we have to go back for the same approval cycle which will delay
supplying the materials.

This is for your kind information and necessary action .

Assuring you of our best cooperation and services at all times, we


remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Test Certificate for Cables.

Dear Sir,

With reference to the above mentioned subject and PO ref.no.C-2016350/W-


40/004 dated 04th Jan-2018, please find attached Test Certificate for Cable.

This is submitted for your kind approval, so that we can dispatch the
materials.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Inspection Test Plan for Piping.

Dear Sir,

With reference to the above mentioned subject, please find attached ITP ref no-
2066-KCCEC/WO-40-ITP-01 Rev-0 for piping works.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Piping Fabrication and Erection Procedure.

Dear Sir,

With reference to the above mentioned subject, please find attached Piping
fabrication and Erection Procedure ref no-2066-KCCEC/WO-40-PR-01 Rev-0.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Commencement date and Start site activities.

Dear Sir,

With reference to the above mentioned subject and our meeting held on 24th April-
18, we still waiting KNPC reply for the raised points during meeting, which is
very important to be settled prior to commencement date especially issuning work
Permit.

This is for your kind action and feedback.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Welders List.

Dear Sir,

With reference to the above-mentioned subject, please find attached Welders List
along with valid identifications cards.

This is submitted for your kind information and record.

The same welders will be used for the above-mentioned Work Order.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Commencement date and site activities.

Dear Sir,

With reference to the above mentioned subject and our meeting held on 02nd
April-18, we still waiting KNPC reply for the raised points during meeting
especially issuing Work Permit as we have submitted our manpower list via our
letter ref no.KCC-KNPC-CB-CPD/WO40-L-13 dated 16th April-18 to nominate
them for executor training which will enable us to start site activities.

Kindly send us your feedback, as it is first required step to start any activities.

This is for your kind action and feedback.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Duty Time at Ramdan and Summer Season.

Dear Sir,

With reference to the above mentioned subject, we would like to inform you that our
Duty
Time will be as following:-

1. From 16/05/2018 till 31/05/2018 (Ramdan Month).


Work start on 06:00 AM & close on 12:00 PM.
2. From 01/06/2018 till 14/06/2018 (Ramdan Month).
Work start on 04:00 AM and close on 10:00 AM.
3. From 15/06/2018 till 30/08/2018.
Work start on 03:00Am and close on 11:00 AM.

This is submitted for your information and action regarding issuing Work Permit.

Assuring you of our best cooperation and services at all times, we remain.
Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co.
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificates

Dear Sir,

With reference to the above mentioned subject and further to our letters ref:
 KCC/KNPC/CB-CPD-2066/W40/L-008 dated 8/03/18
 KCC/KNPC/CB-CPD-2066/W40/L-009 dated 15/03/18
 KCC/KNPC/CB-CPD-2066/W40/L-010 dated 28/03/18
 KCC/KNPC/CB-CPD-2066/W40/L-015 dated 24/04/18

and inspite of our repeated reminders regarding the approval for Material test
certificate
submitted on 24/04/18.

Kindly be informed that the material supplier due to extended delay in obtaining
the approval shall dispose the materials leading to change in material heat numbers.
Also, KCCEC has been informed that 9th May 2018 is the start date of the work
order.Therefore, we once again request to kindly expedite the approval formalities
so as to enable us proceed with procurement of materials.

This is submitted for your information and necessary action

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L-021 Date: 08th May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


(01)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for IT Access Card and System.

Dear Sir,

With reference to the above mentioned subject, KCCEC would like to request an
access card
and a dedicated system in IOB in order to have a smooth flow of opening a permit for
Work
Order # 40.

This is submitted for your information and necessary action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L-022 Date: 09th May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


(13)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Commencement Date.

Dear Sir,

With reference to the above mentioned subject and KNPC letter reference no.MAA-
MNZ1E-
18-041 dated 25th April-2018 and received by KCCEC on 08th May-2018.

KCCEC would like to advise as following: -

1) We conducted three kick of meeting at MAA as following:-

1.1) On 15th Jan-2018 and 28th Jan-2018 at MAA admin with engineering &
services.
1.2) On 02nd April-2018 at IOB with End User Maintainence Zone -1
(Copy attached of mail and agenda)

2) Our area on concern were same as following:-

2.1 ) Issuing work permit


KCCEC standby with PD, the executor is PD. From our past experience with
maintainence for Work orders [ 124 & 101], KCCEC will be executor and
training to be arranged along with IT access card.

2.2) Approved welders, blasters and painters.


We have approved staff by PD with valid identification cards and the same
will be used by maintenance and KCCEC doesn’t require to go again for
any qualifications same happen before for above mentioned order.We
request KNPC to arrange for above mentioned points piror to commencement
date as the same not considered in our time estimation.

3) Please be advised that delays occurred are not due to late submission of various
documents by KCCEC.In fact, KCCEC is awaiting response from KNPC for the
documents submitted.

Letter Ref.no. User Delay in reply


KCC/KNPC/CB-CPD-2066-L-001 Dt- Request for Approval of organization chart 95 days
06/02/2018 & CVs
KCC/KNPC/CB-CPD-2066-L-002 Dt- Request for Pressure Transmitter Drawing 85 days
14/02/2018 Approval
KCC/KNPC/CB-CPD-2066-L-003 Dt- Painting and Blasting Procedure 85 days
14/02/2018
KCC/KNPC/CB-CPD-2066-L-005 Dt- Welding Procedure Specification 86 days
15/02/2018
KCC/KNPC/CB-CPD-2066-L-006 Dt- Data Sheet for Control cable 80 days
20/02/2018
KCC/KNPC/CB-CPD-2066-L-008 Dt- Material Test Certifcate for Piping Materials 63 days
08-03-2018 & Valves
KCC/KNPC/CB-CPD-2066-L-009 Dt- Material Test Certifcate 55 days
15-03-2018
KCC/KNPC/CB-CPD-2066-L-010 Dt- Material Test Certifcate 43 days
28-03-2018
KCC/KNPC/CB-CPD-2066-L-014 Dt- Test Certificates for cables 17 days
24-04-2018
KCC/KNPC/CB-CPD-2066-L-015 Dt- Material test certificate 17 days
24-04-2018

Also find attached complaints received from suppliers and manfacturers due to
delay in approval process.

From the above, KCCEC have no any delay and we request KNPC to change
commencement date to 15/5/18 subject to issuing work permits and the above
raised points shall be milestones in our bar chart.

Abdulla Kadib
Contractor’s Representative

Cc.: TPL Specialist , Project Management- PD I

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 16th May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


(03)
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Inspection test plan for Painting works

Dear Sir,

With reference to the above mentioned subject, please find attached inspection test
plan for painting works.

This is submitted for your review and approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 16th May-
2018

M/s. Kuwait National Petroleum Co. No of Pages:


(0)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Commencement Date

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref.no.MAA-
MNZIE-18-046 dated 10/5/18 we would like to reply as following:

1. Test certificate approval received by mail from KNPC on 15/5/18

2. Only End user who is Maintenance Zone-I responsible for all submission
approvals.

3. For Commencement date, please refer to our letter ref.no.KCC/KNPC/CB-CPD-


2066/W40/L-022 dated 14/5/18 in which we request KNPC to change the
commencement date to 15/5/18 subject to mentioned milestones.

This is submitted for your information and action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 21ST May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


(03)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Issuing Work Permit.

Dear Sir,

With reference to the above mentioned subject, please be informed that on 21st May-
2018, we received work permit at 10:00 AM (Copy attached) with Four hours delay
due to non availability of issuer.

Kindly do the needful to avoid the same in future as it has time and cost impact.
.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl: As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 21ST May-
2018

M/s. Kuwait National Petroleum Co. No of Pages:


(01)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Issuing Work Permit.

Dear Sir,

With reference to the above mentioned subject and our letter ref no.:
KCC/KNPC/CB-CPD-2066/W40/L-25 dated 22nd May-2018, please be informed
that today 22nd May-2018, we didn’t receive work permit due to non availability of
issuer.

Idle manpower and equipment mentioned in the daily report will be claimed as per
annexure IE & IF.

Please take quick action to give us permit in regular basis.


Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 22nd May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


(0)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for pressure transmitter drawing approval

Dear Sir,

With reference to the above mentioned subject and our letter ref no.:
KCC/KNPC/CB-CPD-2066/W40/L-002 dated 14/02/2018, we kindly remind you
that we still waiting your approval.
This is submitted for your information and action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 24th May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


(03)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Commencement Date

Dear Sir,
With reference to the above mentioned subject and our letter ref.no.
KCC/KNPC/CB-CPD-2066/W40/L-022 dated 14/5/18(copy attached), we still
awaiting KNPC reply regarding changing commencement date to 15/05/2018.

This is submitted for your action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 24th May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


(0)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Official Correspondence

Dear Sir,

With reference to the above mentioned subject, we kindly request KNPC to send us
all received mails via official letters, which will enable us to send KNPC our official
reply.

This is submitted for your information and action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 24th May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


(03)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)


Ref.: Contract no. CB/CPD/2066.
Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Supporting Educational Documents

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref.no.MAA-
MNZ1E-18-047 dated 13/05/18, please find the attached diploma copy for
Mr.Ibrahim Kandil.

This is submitted for your information and action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 27h May-
2018

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Tie in Procedure.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the Tie
in Procedure ref no. 2066/KCCEC/WO-40-PR-04 Rev-0.

This is submitted for your review and approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 27h May-
2018

M/s. Kuwait National Petroleum Co. No of Pages:


(09)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Hydro Testing Procedure.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
Hydro Test Procedure ref no. 2066/KCCEC/WO-40-PR-03 Rev-0.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 27h May-
2018

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Welder List.

Dear Sir,

With reference to the above mentioned subject and KNPC Internal Memo ref no.
MAA-IC(I)- MO-18-0786 dated 22nd May-2018, please find attached the following:-

1. Daily Welding Inspection Report.


2. Radiographin Test Report.

In which, it show continuity proof for the welder Dharmendra kumar ID.
No.284041608175

This is submitted for your review and approval.

Assuring you of our best cooperation and services at all times, we remain.
Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 27h May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificate.

Dear Sir,

With reference to the above mentioned subject, please find attached mail from
supplier in which they inform us that all items are sold out due to delay in approval
process by KNPC.

The same informed to KNPC via our letters ref no. KCC/KNPC/CB-CPD-
2066/W40/L-15
dated 24th April-2018 and letter no. KCC/KNPC/CB-CPD-2066/W40/L-22 dated
04th
May-2018 (Copy Attached).

The Supplier will send to us new MTC’s for KNPC approval and KCCEC reserve its
right
for the Time impact.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Cc.: Project Task Force (A) Leader – PD I

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L-
th
Date:27 May-2018

M/s. Kuwait National Petroleum Co. No of


Pages:
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Welding procedure Specification.

Dear Sir,
With reference to the above mentioned subject and KNPC internal memo ref no.
MAA-IC (I)-MO-18-0753 dated 17th May-2018, we kindly request KNPC to approve
the submitted WPS ref no.
1. WPS/KCCEC-001- Rev-01
2. WPS/KCCEC-004 – Rev-0A

Which is earlier approved via MAA- I & C (Copy of Previous approval attached).

Generating new WPS & PQR will have time and cost impact.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L-
th
Date:27 May-2018

M/s. Kuwait National Petroleum Co. No of


Pages:
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Issuing work permit

Dear Sir,
With reference to the above mentioned subject and KNPC letter ref.no.
KCC/KNPC/CB-CPD-2066/W40/L-025 dated 21/05/18 and KCC/KNPC/CB-CPD-
2066/W40/L-026 dated 29/05/18 we didn’t receive work permit as issuer request e-
permit.

WE kindly request you to arrange with operation to give us manual permit to avoid
idle manpower, please also expedite for IT accesss card and system as requested
early via our letter ref.no. KCC/KNPC/CB-CPD-2066/W40/L-021 dated 8/05/18 to
avoid such delay in future.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 31st May-


2018

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificate.

Dear Sir,

With reference to the above mentioned subject, please find attached material test
certificate for Items # 13 and 25 as per attached summary.

This is submitted for your review and approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Abdulla Kadib
Contractor’s Representative

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 03-06-2018

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Technical submittal for control valve

Dear Sir,

With reference to the above mentioned subject, please find attached technical
submittal Ref.no.503-80002128-TRNS-001 for control valve.

This is submitted for your review and approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Submission of Baseline Schedule

Dear Sir,

With reference to the above mentioned subject, please find attached Baseline
schedule for this work order.

This is submitted for your review and information.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for approval of Radiographic testing procedure

Dear Sir,

With reference to the above mentioned subject, please find attached radiographic
testing
Procedure

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for approval of Dye Penetrant Testing procedure

Dear Sir,

With reference to the above mentioned subject, please find attached Dye Penetrant
testing
Procedure

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Inspection Test plan for Piping

Dear Sir,

With reference to the above mentioned subject and KNPC letter


ref.no.MAA_MNZIE-18-062 dated 4/06/18, please find attached revised ITP
ref.no.2066-KCCEC/WO_40-ITP-01 for piping after incorporating KNPC
comments.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,
Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material test Certificate

Dear Sir,

With reference to the above mentioned subject, please find attached material test
certificates for items # 1 &3 as per purchase order.

This is submitted for your kind review and approval.


Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Inspection Test plan for Painting Works

Dear Sir,
With reference to the above mentioned subject and KNPC letter
ref.no.MAA_MNZIE-18-061 dated 4/06/18, please find attached revised ITP
ref.no.2066-KCCEC/QA-QC-PR-PI-00 for painting works after incorporating
KNPC comments.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Blasters & Painters List

Dear Sir,
With reference to the above mentioned subject and further to KCCEC letter ref.no.
KCC/KNPC/CB-CPD-2066/W40/L-011 dated 3/4/18 and as per our discussion we
still waiting KNPC confirmation to utilize our approved blasters and painters.

Please expedite your reply as the subject hampering our time schedule.

This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:(04)


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Request for Pressure Transmitter Drawing Approval

Dear Sir,

With reference to the above mentioned subject and KCCEC letter ref.no.
KCC/KNPC/CB-CPD-2066/W40/L-002 dated 14/02/18 and KCC/KNPC/CB-CPD-
2066/W40/L-027 dated 23/05/18 we still waiting for KNPC approval.

This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:(


)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Hydro Testing Procedure

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref.no.MAA-
MNZIE-18-071 dated 11/06/18, please find attached revised hydrotesting procedure
ref.no.2006-KCCEC/WO-40-PR-03 Rev1 incorporating KNPC comments.

This is for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:(


)
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Approval Material Test Certificate

Dear Sir,

With reference to the above mentioned subject and KCCEC letter ref.no.
KCC/KNPC/CB-
CPD-2066/W40/L 18-036 dated 31/05/18 & KCC/KNPC/CB- CPD-2066/W40/L
18-041
dated 11/6/18 , please find attached urgent reminders received from suppliers for
your approval.

Please expedite your reply, else the heat numbers will not be available and we will
face
the same problem which we faced during the previous material approval.

This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. No of Pages:(
)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Welding Procedure Specification

Dear Sir,
With reference to the above mentioned subject and KNPC letter ref.no. MAA-
MNZIE-18-
076 dated 19/06/18, we would like to confirm you the following:

1. Nitrogen header is work order under standby project.

2. WPS & PQR chosen based on material specification.

3. WPS & PQR approved before from MAA I & C for work order 124.

4. Cost and time impact will be reflected on the work order and submitted for
KNPC
approval.

In order to meet our time schedule, we instructed our staff to co-ordinate with I &
C to start
generating new WPS.
This is for your kind information
Assuring you of our best cooperation and services at all times, we remain,
Best Regards,

Sharad Shringare
Project Manager
CC: TPL Specialist- Project Management – PD I

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. No of Pages:(
)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016-2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Tie-in Procedure

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref.no. MAA-
MNZIE-18-
078 dated 19/6/18, please find revised Tie-in procedure incorporating KNPC
comments.

This is for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:(30


)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificate

Dear Sir,

With reference to the above mentioned subject, please find attached the material test
certificate for Items Nos. (2 & 4) as per attached purchase order.

This is for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,
Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. No of Pages:(
)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Approval of CV’s

Dear Sir,
With reference to the above mentioned subject, please find attached herewith the
CV’s of
below mentioned personnel for your kind review and approval.
S.No Name Position Nationality Total Remarks
experiance

01 Jai Govind Jaiswal Piping Indian 18 Attached KNPC


Supervisor previous approval

02 Tom C.vareghese Scaffolding Indian 15


Supervisor

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Mohammed Mansour
Asst. CEO
Encl: CV’s

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. No of Pages:(


)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

CC: TPL Specialist- Project Management – PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Speed KNPC approvals

Dear Sir,
With reference to the above mentioned subject, we kindly request you to speed the
issue of
KNPC approvals for the submitted letters as following:

S.No Letter No. Subject Submission Delay till


Date date(days)

01 002 Approval for Pressure Transmitter 14/02/18 137

02 14 Test certificates for Cables 24/4/18 69

03 33 Request for Welder Approval 28/5/18 35

04 37 Technical submittal for Control valves 04/06/18 30

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Mohammed Mansour
Asst. CEO
Encl: Copy of above mentioned letters

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 22nd July’18

M/s. Kuwait National Petroleum Co. No of Pages:(


)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Technical Proposal for Control Valve.

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref
no……………………
dated………, please find attached revised document incorporating KNPC
comments.

The data sheet attached with recommendation mail regarding flow direction.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 22nd July’18

M/s. Kuwait National Petroleum Co. No of Pages:(


)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)


Ref.: Contract no. CB/CPD/2066.
Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Technical Proposal for Control Valve.

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref
no……………………
dated………, please find attached revised document incorporating KNPC
comments.

The data sheet attached with recommendation mail regarding flow direction.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date:


M/s. Kuwait National Petroleum Co. No of Pages:(01
)
Projects Department
Kuwait.

Kind Attn.: Mr.Anwar N Hayat


TPL Specialist- Project Management – PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Blasters & Painters.

Dear Sir,

With reference to the above mentioned subject, we would like to inform you that
we
Submitted to KNPC list of approved Blasters & Painters along with valid cards
informing
them that the same shall be mobilized for above mentioned Work order.

KNPC replying us that they should have cards issued by MAA Inspection and
corrission
Department and not allowing us to utilize them.

We kindly request you to send to End User to allow us to use the qualified Painter
and
Blaster, else it could have time and cost impact to qualify the qualified persons.

This is submitted for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Mohammed Mansour
Asst. CEO

Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Mr.Anwar N Hayat
TPL Specialist- Project Management – PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Welding Procedure Specification.

Dear Sir,
We refer to the submitted Welding procedure specification (WPS) which
previously
approved by KNPC (MAA inspection & corrosion department) for the same
material
specification in workorder 124 (Copy attached).

The End user is insisting to generate a new WPS specific for above mentioned
workorder
as per attached KNPC letter ref. No. MAA-MNZ1E-18-076 dated 19/6/2018.

We have obtained three quotations as per attached comparison sheet for generating
new
WPS with cost impact of KD 770/- & it will take 2 weeks from the date of KNPC
approval.

This is submitted for your review and approval.

Assuring you of our best cooperation and services at all times, we remain,
Best Regards,
Mohammed Mansour
Asst. CEO

Encl: a) Comparsion Sheet & 3 Quotations


b) WBS |& Sample3 of previous approval
c) End user KNPC letter ref.no. MAA-MNZ1E-18-076

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 22nd July’18

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Technical Proposal for Control Valve.

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref no. MAA-
MNZ1E-18
084 dated 02nd July’18, please find attached revised document incorporating
KNPC
comments, please also find attached recommendation mail regarding flow
direction.
This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Mohammed Mansour
Asst. CEO

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Mr.Anwar N Hayat
TPL Specialist- Project Management – PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Welding Procedure Specification.

Dear Sir,
With reference to the above mentioned subject and KNPC letter ref no.
KNPC/KCC/CB-
CPD-2066-F-18-0215 dated 18th July’18, we would like to inform you the
following:-

1. We confirm that as per contract clause no.3.1.e of scope of work it is contractor


responsibility to develop WPS.
2. KCCEC developed WPS ref no. WPS/KCCEC-001 Rev (1) and WPS ref no.
WPS/KCCEC-004 Rev (A) and submitted for end user approval.
3. End user insisting to develop new WPS for Work Order #40.
4. We request KNPC PDI to write to end user to allow us using above mentioned
WPS, else approve the submitted quotation to generate new WPS.

This is for your kind review and necessary action.


Best Regards,

Mohammed Mansour
Asst. CEO

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 22nd July’18

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: ITP for Painting Works.

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref no. MAA-
MNZ1E-18-
096 dated 12th July’18, please find attached Revised Inspection Test Plan ref no.
KCCEC
QA/QC-ITP-00 incorporating KNPC comments.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Mohammed Mansour
Asst. CEO

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 22nd July’18

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for approval Pressure Trasnmitter drawing.

Dear Sir,

With reference to the above mentioned subject, please be informed that on


14thFeb’18, we
submitted pressure transmitter drawings for approval via our letter ref
.:KCC/KNPC/CB-
CPD-2066-W40-L-002 and inspite of several reminders (copy attached) till date we
still
waiting your approval.

Kindly expedite your reply as it is hammering the time schedule and will cause
serious
delay for the work order.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Mohammed Mansour
Asst. CEO
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for approval of Mechanical Engineer

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
CV of
Mechanical Engineer for the subject work order.

S.No Name Designation Nationality

1 Mr.Mohammed Ali.N Mechanical Engineer Indian

This is for your kind review and approval.

Your kind cooperation and support in this regards is highly appreciated.

Best Regards,

D Kannan
Project Engineer
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for approval of Mandoop

Dear Sir,

With reference to the above mentioned subject, please be informed that the below
mentioned
personnels are our mandoop.

S.No Name Designation Civil ID Nationality

1 Mr.Mohamed Basiouny Mandoop 273091004405 Egyptian

2 Mr. Mahmoud Khair Mandoop 285111805743 Egyptian

Your kind cooperation and support in this regards is highly appreciated.

Sharad J.Shringare
Project Manager
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for approval Pressure Trasnmitter drawing.

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref.no.MAA-
MNZIE-18-
105 dated 29/7/18, please find attached revised drawing incorporating KNPC
comments.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,
Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Report No. 02.

Dear Sir,

With reference to the above-mentioned subject, please find attached the Monthly
Report for
the month of 01st July’2018 to 31st July’2018.

This is submitted for your kind information.

Assuring you our best cooperation and services at all times, we remain,

Best regards,
Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificate.

Dear Sir,

With reference to the above-mentioned subject, please find attached revised Material
Test
Certificates for Item#01 as per purchase order.

This is submitted for your kind review and approval.


Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Dye Penetrant Testing Procedure.

Dear Sir,
With reference to the above mentioned subject and KNPC letter ref no. MAA-
MNZ3-18-095
dated 12th July’2018, please find attached Dye Penetrant test procedure ref no. QCP-
KIL-06
Rev-01 incorporating KNPC comments.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad J Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Radiographic Test Procedure.

Dear Sir,

With reference to the above-mentioned subject and KNPC letter ref no. MAA-
MNZ1E-18-
094 dated 12th July’2018, please find attached revised Radigraphic Test Procedure ref
no.
QCP-KIL-20 Rev-01 incorporating KNPC comments.

This is submitted for your kind review and approval.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)


Ref.: Contract no. CB/CPD/2066.
Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: “Eid Al-Adha Holiday”.

Dear Sir,

Please be informed that KCCEC-MAA site shall be observing Eid Al Adha holiday
from
Monday 20th August’2018 till Thursday 23rd August’2018.

However, site activities shall be carried out on 18th, 19th and 25th August’2018.

We take this opportunity to wish all a very ‘‘HAPPY EID AL ADHA’’.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Technical Proposal for control valve.

Dear Sir,

With reference to the above-mentioned subject and KCCEC letter ref.no.


KCC/KNPC/CB-CPD-2066/W40/L-056 dated 22nd July’2018, kindly update the
status of revised documents submitted for your kind review and approval.

Also, find attached reminders received from the supplier.

This is for your kind information and urgent action.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Subj.: Request for Scaffolding Supervisor approval

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
CV of
Mr.Samir Abdoh Adli Mohammad for the post of Scaffolding Supervisor.

Sno Name Desigination Nationality


01 Mr. Samir Abdoh Adli Scaffolding Egyptian
Mohammad Supervisor

This is submitted for your kind review and approval.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Subj.: Request for Instrumentation Supervisor approval.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
CV of
Mr.J Subbaraman for the post of Instrumentation Supervisor.

Sno Name Desigination Nationality


01 Mr. J Subbaraman Instrumentation Supervisor Indian

This is submitted for your kind review and approval.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co.


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Subj.: Request for Airless Spray Painter approval.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
followings
CV’s for the post of Airless Spray Painter:-

Sno Name Desigination Nationality


01 Mr. Yoonus Airless Spray Painter Indian
Pulpadan
02 Mr.Phoolena Singh Airless Spray Painter Indian
03 Mr.Mansoor Airless Spray Painter Indian
Ahamad

This is for your kind review and approval.

Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co.
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Sand Blaster & Airless Spray Painter approval.

Dear Sir,
With reference to the above mentioned subject, please find attached herewith the
followings
CV’s for the post of Sand Blaster & Airless Spray Painter :-

I. Sand Blaster
Sno Name Desigination Nationality
01 Mr. Taj Muhammed Sand Blaster Pakistan
Khan
02 Mr.Fazal Akbar Sand Blaster Pakistan
03 Mr.Ismail Sand Blaster Pakistan
II. Painter
Sno Name Desigination Nationality
01 Mr. Yoonus Airless Spray Painter Indian
Pulpadan
02 Mr.Phoolena Singh Airless Spray Painter Indian
03 Mr.Mansoor Airless Spray Painter Indian
Ahamad
Please note that completion date of work order is 14/04/2019.
This is for your kind review and approval.
Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co.
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Duty Time

Dear Sir,

With reference to the above mentioned subject, please be advised of change in


working hours.
The working hours with effect from 8th September’2018 shall be as follows:

Work Start : 6:00 AM


Work Finish : 2:00 PM

This is for your information and action regarding issuing Work Permit.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: (05)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Inspection Test Plan for Painting Works.


Dear Sir,

With reference to the above mentioned subject and KNPC letter ref no. MAA-
MNZ1E-18-096
dated 12th July’2018, please find attached herewith revised ITP ref no.
KCCEC/QA/QC-ITP
PW-03 Rev-03 incorporating comments.

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: (05)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WR.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Inspection Report.

Dear Sir,

With reference to the above mentioned subject and our PO order ref no. C-
2016350/W40/001
dated 04th Jan-2018, please find attached Materials Inspection Report.

Please note that all materials against above mentioned purchase order are available in
Kuwait at
supplier warehouse at MAB and ready for your inspection.

This is for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.:
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Sand Blaster & Airless Spray Painter approval.

Dear Sir,
With reference to the above mentioned subject, please find attached herewith the
followings
CV’s for the post of Sand Blaster & Airless Spray Painter:-
I. Sand Blaster
Sno Name Desigination Nationality
01 Mr. Taj Muhammed Khan Sand Blaster Pakistan
02 Mr. Fazal Akbar Sand Blaster Pakistan
03 Mr. Ismail Sand Blaster Pakistan
II. Painter
Sno Name Desigination Nationality
01 Mr. Yoonus Pulpadan Airless Spray Painter Indian
02 Mr. Phoolena Singh Airless Spray Painter Indian
03 Mr. Mansoor Ahamad Airless Spray Painter Indian
04 Mr. Doctor Khan Airless Spray Painter Pakistan

This is for your kind review and approval.


Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J.Shringare
Project Manager

Encl: As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: (12)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Report No.03

Dear Sir,

With reference to the above-mentioned subject, please find attached herewith the
Monthly Report
for the month of 01st Aug-2018 to 31st Aug 2018.

This is for your kind information & necessary records.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager

Encl: - As mentioned above


.
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Supply of Piping Material.

Dear Sir,

With reference to the above-mentioned subject, please be informed that all piping
materials are
available at supplier warehouse at Mina Abdulla and ready for inspection.

Kindly arrange for inspection to enable us sending the material for painting and
welding.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,

Sharad J.Shringare
Project Manager
.

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Material Test Certificate

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref no. MAA-
MNZ1E-18-139
dated 10/6/18, please refer to our letter ref.no. KCC/KNPC/CB-CPD-2066/W40/L-69
dated
10/9/18 (copy attached).

This is for your information and necessary action.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,
Sharad J. Shringare
Project Manager

Encl: - As mentioned above


.

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for approval of Pressure Transmitter

Dear Sir,

With reference to the above mentioned subject and KCCEC letter ref.no.
KCC/KNPC/CB-CPD-2066/W-40/L-60 dated 02/8/18, we kindly request KNPC to
expedite the approval for Pressure Transmitter.

This is for your kind information and necessary action.


Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J.Shringare
Project Manager

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Welding Procedure Specifications.

Dear Sir,
With reference to the above mentioned subject and further to our previous
correspondences and
as per KNPC request to generate new WPS, please find attached the following:-

1. WPS no. { WPS-KCCEC-MAA-002} Rev-00 dated 12th Sep’2018 and supporting


PQR.
2. WPS no. { WPS-KCCEC-MAA-003} Rev-00 dated 12th Sep’2018 and supporting
PQR.

This is submitted for your kind review and approval.

Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J.Shringare
Project Manager

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 04 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Welding Electrodes

Dear Sir,

With reference to above mentioned subject, please find attached inspection certificates
for
welding electrodes (ER7052 & E7018).

This is for your kind review and approval.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J. Shringare
Project Manager

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: (01)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)


Ref.: Contract no. CB/CPD/2066.
Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Blasters and Painters Approval

Dear Sir,

With reference to above mentioned subject, please be informed that KCCEC


manpower are ready for oral interview and practical exam at Mina Abdulla yard.

Kindly expedite and confirm us your availability to avoid more delay.

This is for your kind information and necessary action.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J. Shringare
Project Manager

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Test Certificate for Control Valve.

Dear Sir,

With reference to above mentioned subject and KNPC approval letter ref no. MAA-
MNZ1E-18-135 dated 09th Sept’2018, please find attached Test Certificate for control
valve.

This is submitted for your kind approval and dispatch clearance.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J. Shringare
Project Manager

Encl:- As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Pressure Transmitter Drawings.

Dear Sir,

With reference to above mentioned subject and KCCEC letter ref.no. KCC/KNPC/CB-
CPD-2066/W40/L-60 dated 2/8/18 and KCC/KNPC/CB-CPD-2066/W40/L-75 dated
26/9/18, we kindly request KNPC to expedite the approval for pressure transmitter
drawings, so as to enable us proceed with manufacturing formalities.

This is for your kind information and necessary action.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J. Shringare
Project Manager

Encl:- As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Test Certificate for Control Valve

Dear Sir,

With reference to above mentioned subject and KCCEC letter ref.no. KCC/KNPC/CB-
CPD-2066/W40/L-80 dated 1/10/18, we are still awaiting KNPC approval of control
valve test certificate and dispatch clearance to deliver the control valve.

This is for your kind information and urgent action.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Sharad J. Shringare
Project Manager
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: (12)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Report No.04

Dear Sir,

With reference to the above-mentioned subject, please find attached herewith the
Monthly Report
for the month of 01st September-2018 to 30th September-2018.

This is for your kind information & necessary records.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager
Encl: - As mentioned above
.

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Cc: Team Leader – Project Control PD I

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Delay in Approval process.


Dear Sir,
With reference to above mentioned subject, we would like to inform you that we are
facing a serious delay in approvals for materials, procedures and drawings which cause
time impact.

As example, we have submitted revised drawings for pressure transmitter on 02 nd Aug


’2018 via our letter ref no. KCC/KNPC/CB-CPD-2066/W40/L-60 and inspite of
several verbal and official reminders (copy attached of our letter ref no.
KCC/KNPC/CB-CPD-2066/W40/L-81) no response has been received from KNPC
yet.
Please note that the supplier is calling KCCEC daily and they are going to revise there
quotation due to delays occurred by KNPC and expiry of quotation validity.

We kindly request KNPC to expedite there reply to avoid further delays.

This is for your kind information and urgent action.

Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J. Shringare
Project Manager
Encl: - As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: MTC for Structural Support Materials.


Dear Sir,
With reference to above mentioned subject, please find attached herewith the MTC for
Structural materials for piping supports.

This is for your kind review and approval.


Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J. Shringare
Project Manager

Encl: - As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Additional Piping Materials.

Dear Sir,
With reference to above mentioned subject and as per site condition, please find
attached comparision sheet between ordered materials as per purchase order and the
additional materials required and as per site conditions.

This is submitted for KNPC requesting to issue the materials to KCCEC from KNPC
warehouses, else to advise us to proceed with procuring.

Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J. Shringare
Project Manager

Encl: - As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 05 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Request for Mobile Gatepass

Dear Sir,
With reference to above mentioned subject, we kindly request you to issue gatepass for
Intrinsically safe mobile Ex-Handy 07 as following:

Sno Name Civil ID No. Desigination Mobile No. IMEI No


01 Mr. Mohamed 285092803135 Engineer 69022912 012894000111320
Kamel
02 Mr. Nestor 282062205413 Engineer 65017487 012894000111916

Please also find attached copy of Civil ID and gatepass.


This is for your information and necessary action.
Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J. Shringare
Project Manager

Encl: - As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Request for Drawings.
Dear Sir,
With reference to above mentioned subject, please provide the following drawing listed
below
for Instrumentation works.

Sno Description Dwg ref no.


1 Instrument Junction Box Wiring Diagram UCR (Dwg. No. 1-71-3.75-4001)
2 Panel Strip with Adjacent Connections (Dwg. No. 1-71-3.75-4001-1/2)
3 Panel Strip with Adjacent Connections (Dwg. No. 1-71-3.75-4001-2/2)
4 UCR Marshalling Termination Drawings (Dwg. No. 2.57-3.75-5001-1/194)
5 Index Sheet - (Dwg. No. 2.57-3.75-5001-2/194)
6 Marshalling Termination – UTC – 005 - (Dwg. No. 2.57-3.75-5001-24/194)
7 Instrument I/O List with Alarms – Cover Sheet (Dwg. No. 2.70-3.70-4001-1/14)
8 Nitrogen Gas Unit For 71-PY-0508 & 71-PT-0508 (Dwg. No. 2.70-3.70-2001-14/14)
9 Instrument Loop Wiring Diagrams – Cover Sheet (Dwg. No. 2.71-3.79-4005-1/23)
10 Instrument Segment/Loop Diagram – Index Sheet (Dwg. No. 2.71-3.79-4005-2/23)
11 Nitrogen Gas Unit – Instrument Loop Wiring Diagram (Dwg. No. 2.71-3.79-2005-23/23)
12 Layout of Inst. Wiring & Air Piping Utility Facilities (Dwg. No. 2102.70-3.75-302-A-2/3)
13 Layout of Inst. Wiring & Air Piping Utility Facilities (Dwg. No. 2102.70-3.75-302-B-3/3)
14 Hook Up Drawing
15 Cable Schedule
This is for your information and necessary action.
Assuring you our best cooperation and services at all times, we remain,
Best regards,

Sharad J. Shringare
Project Manager

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Approval of Rigging Supervisor.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the CV
of
Mr.Shahid Jamal Khan for the postion of Rigging Supervisor for the subject work
order.

SNo Name Position Nationality


01 Mr.Shahid Jamal Khan Rigging Supervisor Indian
This is for your kind review and approval.
Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly HSE Statistics Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the Monthly
HSE
statistics report for the month of October’ 2018.

This is submitted for your kind information and official records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 1+3)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Environment Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the Monthly
Environment report for the month of March 2019.

This is submitted for your kind information and official records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 16 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Revised Welding Procedure.

Dear Sir,

With reference to the above mentioned subject and KNPC letter ref no. MAA-MNZ1E-
18-179 dated
30/10/2018, please find attached revised welding procedure incorporating KNPC comments as
following:

1) WPS ref.no WPS-KCCEC-MAA-002 Rev (2) with supporting PQR ref No. PQR-KCCEC-
MAA-002
Rev (1)
2) WPS ref.no WPS-KCCEC-MAA-003 Rev(2) with supporting PQR ref No. PQR-KCCEC-
MAA-003
Rev (1)

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Approval of Cables

Dear Sir,

With reference to the above mentioned subject and further to our KCCEC letters submitted
vide
ref.no. KCC/KNPC/CB-CPD-2066/W-40/L-06 dated 20th Feb 2018 &
KCC/KNPC/CB-CPD-
2066/W-40/L-14 dated 24th April 2018.(as attached for your ready reference)
KCCEC would like to follow up the status of approval for Control Cables and request
to expedite
replies as soon as possible.

This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 17 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Request for Tie-In Schedule

Dear Sir,

With reference to the above mentioned subject, please find below list of tie in that will be
conducted
in respected units and let us know when can we perform the tie-in as per line no.

Attached also, are the reference drawing for each tie in.

Tie-In Report
Shutdown
S/N Description Nos Size Line no. will do the tie - in
Required
Tie - In Unit
1 1 6" Yes NG-71-45002-L1-6"
71
Tie - In Unit
2 1 2" Yes NG-71-45001-L1-2"
98
Tie - In Unit
3 2 1" Yes NG-58-45209-HR9-1"
58
NG-25-45105-A1A1-1"
NG-25-45112-A1A1-1"
Tie - In Unit
4 6 3/4" & 1" Yes NG-25-45202-A1A1-1"
25
NG-25-45205-A1A1-1"
NG-25-45208-A1A1-1"

Shutdown
S/N Description Nos Size Line no. will do the tie - in
Required
NG-05-45114-L1-1"
Tie - In NG-05-45112-A7-1"
5 4 1" Yes
Unit 05 NG-05-45115-L1-1"
NG-05-45113-L1-1"
NG-26-45105-A1A1-1"
Tie - In 3/4" &
6 Yes NG-26-45112-A1A1-1"
Unit 26 1"
NG-26-45202-A1A1-1"
NG-26-45205-A1A1-1"
NG-26-45208-A1A1-1"

This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 03 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)


Ref.: Contract no. CB/CPD/2066.
Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly HSE Statistics Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the Monthly
HSE
statistics report for the month of Nov’ 2018.

This is submitted for your kind information and necessary records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: (02 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Environment Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the Monthly
Environment report for the month of Nov’ 2018.

This is submitted for your kind information and necessary records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 06 )
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Baseline Schedule
Dear Sir,
With reference to the above mentioned subject and KNPC letter ref.no.MAA-MNZ1E-18-
190 dated 27th Nov’2018, we would like to inform you that initial stage we face delay in
approvals which didn’t enable us to start either welding nor painting.
Main reasons were but not limited to the following:
1. Approval of painting procedures, KCCEC submitted the procedure on 14/2/2018
and obtained approval from KNPC on 2/7/2018.
2. Approval of painters and blasters, KCCEC submitted list of previous approved
blasters and painter on 3/4/2018 with valid cards from PD, KNPC didn’t responded
us and once approaching I & C they request us to requalify the blasters and painters
via I & C division. KCCEC submitted CV’s on 10/9/18 and KNPC qualified the
blasters and painters on 28/10/2018.
3. Approval of welding procedure, KCCEC submitted WPS on 15/02/18 and KNPPC
rejected on 19/06/18, however it was earlier approved by I & C. KNPC forced us to
generate new WPS and KCCEC informed that there will be time & cost impact.
KCCEC submitted the new WPS on 26/9/18 and we received KNPC approval by
mail on 29/11/18.
4. Approval of MTC for piping material, KCCEC submitted material test certificate
to KNPC on 8/03/18 and KNPC obtained approval from KNPC on
4/7/18.Inspection of piping materials, KCCEC wrote to KNPC on 10/09/18 that
materials is available in Kuwait and arrange for inspection. KNPC inspected the
materials on 24/9/18.
In view of the above, there was delay beyond our limit and kindly find attached revised
schedule with completion date till……….
Sharad J. Shringare
Project Manager

Encl: As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: (06 )
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Revised Work Schedule
Dear Sir,

With reference to the above-mentioned subject and KNPC letter ref.no.MAA-MNZ1E-


18-190 dated 27th Nov’2018, we would like to inform you that at the initial stage of this
work order, M/s KCCEC had considerable delays in approvals which compelled us to
start neither welding nor painting though we placed purchase orders before
commencement date of work order.

Main reasons were but not limited to the following:

1. Approval of painting procedures, KCCEC submitted the procedure on 14/2/2018


and obtained approval from KNPC on 2/7/2018.

2. Approval of painters and blasters, KCCEC submitted list of previous approved


blasters and painter on 3/4/2018 with valid cards from PD, KNPC didn’t
responded us and once approaching I & C they request us to requalify the blasters
and painters via I & C division. KCCEC submitted CV’s on 10/9/18 and KNPC
qualified the blasters and painters on 28/10/2018.
3. Approval of welding procedure, KCCEC submitted WPS on 15/02/18 and
KNPPC rejected on 19/06/18, however it was earlier approved by I & C. KNPC
forced us to generate new WPS and KCCEC informed that there will be time &
cost impact. KCCEC submitted the new WPS on 26/9/18 and we received KNPC
approval by mail on 29/11/18.

4. Approval of MTC for piping material, KCCEC submitted material test certificate
to KNPC on 8/03/18 and KNPC obtained approval from KNPC on
4/7/18.Inspection of piping materials, KCCEC wrote to KNPC on 10/09/18 that
materials is available in Kuwait and arrange for inspection. KNPC inspected the
materials on 24/9/18.

In view of the above, there was delay not attributed towards KCCEC and beyond our
limit. Therefore, please find attached revised schedule with completion date till 31-
Aug-2019 submitted for your review and acceptance.
Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co.
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Additional Piping Materials

Dear Sir,

With reference to the above-mentioned subject and KNPC letter ref.no.MAA-MNZ1E-18-


196 dated 3rd Dec’2018, we would like to thank you for your approval, however we still
awaiting KNPC decision whether KNPC will supply the materials (free issue materials
from KNPC warehouses) or KCCEC has to procure it.

This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 11 )

Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Delays in Work Execution.

Dear Sir,
th reference to the above-mentioned subject, please note that since the initiation of this
work order, KCCEC is facing serious delays in obtaining approvals of WPS, painters and
blasters etc. from KNPC.
KCCEC had submitted the following for approvals (copies as attached): -
1. Piping Materials.
2. ITP for Piping.
3. IF Drawings.

However, KNPC Inspection Engineer stopped our work since 17th Dec’2018 as per
attached mail requesting us to provide additional requirements thus deviating from approved
drawings and ITP causing idle resources and incurring delays
This is for your kind information and necessary action.
Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager
Encl: - As mentioned above

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages. ( )

Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Non Issuing and Delay Issuing Work Permit.

Dear Sir,
With reference to the above-mentioned subject, please be informed the following:-

1. Since 19th Dec’2018, issuer is not issuing us hot work permit at Unit#71 for piping
works and supports.
2. Daily we are receiving scaffolding work permit with minimum 02 hours delay due to
E- permit.

The same has been reported to KNPC and we would like to highlight that we continue to
face same problem as before, please ref to our letter ref no. KCC/KNPC/CB-CPD-
2066/W40-L-26 dated 23rd May-2018.

Therefore, we once again request your kind intervention into this matter to avoid delays
and idle manpower.
Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages. ( )

Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department
(2016- 2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Tie in Details.

Dear Sir,

With reference to the above-mentioned subject, please find attached Tie in Report
submitted for your kind review and information:

1. Tie-in will occurred in 06 Units.


2. Number of Tie-ins are 20 Nos.
3. Additional materials required of same shall be provided by KNPC.
4. Operation shall decide weather required shutdown or not.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: - As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 23rd Dec’2018


M/s. Kuwait National Petroleum Co. Nos of Pages.: (20)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Monthly Report No.06

Dear Sir,

With reference to the above-mentioned subject, please find attached herewith the
Monthly Report
for the month of 01st November-2018 to 30th November-2018.

This is for your kind information & necessary records.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager

Encl: - As mentioned above


.

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Delay in issuing Work Permit.

Dear Sir,

With reference to the above-mentioned subject, please be informed that we are facing
delay in
obtaining E-permit as follows:-

Date Issuing Time Delay in Hours


26th Dec’2018 08:00 02 Hrs
27th Dec’2018 08:02 02 Hrs

This is affecting our prouductivity and delay the work activities.

This is for your kind information & necessary action.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,

Sharad Shringare
Project Manager

Encl: - As mentioned above


.

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date: 30th Dec’2018


M/s. Kuwait National Petroleum Co. Nos of Pages.: (20)
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Report No.07

Dear Sir,

With reference to the above-mentioned subject, please find attached herewith the
Monthly Report
for the month of 01st December-2018 to 31st December-2018.

This is for your kind information & necessary records.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,

Sharad J Shringare
Project Manager

Encl: - As mentioned above


.
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 04 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly HSE Statistics Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the Monthly
HSE
statistics report for the month of December’ 2018.

This is for your kind information and necessary records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: - As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: (
02 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Environment Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
Monthly
Environment report for the month of December’ 2018.

This is for your kind information and necessary records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl:- As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co.
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Issuing Work Permit

Dear Sir,

With reference to the above mentioned subject and our previous correspondences
regarding same
subject and our letter ref.no. KCC/KNPC/CB-CPD-2066/W40/L- 103 dated 30th
Dec’2018, please
be informed that on 5th Jan’2019 we did not receive work permit for piping works due
to E-permit.

KCCEC highlighted of facing serious delay and idle resources incurring additional cost
due to
non-issuance of work permit.
Therefore, we once again request your kind intervention into this matter.

This is for your kind information and necessary action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Mohamed Abdullah
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co.
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Approval of Scaffolding Supervsior.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith CV of
Mr.Pabitra
Paikary for the post of Scaffolding Supervisor.

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co.
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Delay in Execution.

Dear Sir,

With reference to the above-mentioned subject and KNPC letter ref no. KNPC/KCC/CB-CPD-
2066-F-19-0027 dated 24th Jan’2019, we would like to inform you that there is no delay, but
serious delay in execution due to but not limits to the following reasons which beyond KCCEC
limits: -

1) Approval of Painting Procedure: -


KCCEC submitted painting procedure on 14th Feb’2018 via our letter ref no. KCC/KNPC/CB-
CPD-2066/W40/L-003. KNPC approve it on 02nd July’2018 via KNPC letter ref no. MAA-
MNZ1E-18-083 after almost 05 months delay.

2) Approval of Blasters & Painters: -


KCCEC submitted list of approved blaster and painters on 03rd April’2018 via KCCEC letter
ref no. KCC/KNPC/CB-CPD-2066/W40/L-011 & no response from KNPC, in order to
expedite KCCEC approach MAA I & C department and they request us to approve the persons
from there department. KCEC submitted CV’s of blasters and painters on 10th Sept’2018 via
our letter ref no. KCC/KNPC/CB-CPD-2066/W40/L- 070 and KNPC quality them on 28th
Oct’2018, but till date they didn’t send us any official approval.

From the above KCCEC were not able to proceed for painting till 28th Oct’2018 which impact
the schedule with almost 07 months.
3) Approval of Welding Procedure: -
KCCEC submitted WPS on 15th Feb’2018 via our letter ref no. KCC/KNPC/CB-CPD-
2066/W40/L-005. KNPC rejected it on 29th May’2018 via KNPC letter ref no, MAA-MNZ1E-
18-056 (i.e. after delay 04

Months|), however the same WPS was earlier approved by MAA I & C department in work
order no. 124 Fourth Standby (CB-CSPD-2005/W124).
KNPC forces us to generate new WPS and we wrote to inform KNPC that the same will have
impact, please refer to our letters to PD ref no. KCC/KNPC/CB-CPD-2066-L-659 dated 15th
July’2018 and KCC/KNPC/CB-CPD-2066-L-664 dated 23rd July’2018.
KCCEC to expedite generated new WPS and submitted to KNPC on 27th Sept’2018 via our
letter ref no. KCC/KNPC/CB-CPD-2066/WO1-L-076 and KNPC approve it on 03rd dec’2018
via KNPC letter ref no. MAA-MNZ1E-18-198 (i.e. with delay 02 months).
From above KCCEC were not able to proceed for welding till 03rd Dec’2018, which impact
the schedule with almost 08 months.
4) Approval of MTC & Piping Materials Inspection: -
KCCEC submitted MTC for piping materials on 08th March’2018 via our letter ref no.
KCC/KNPC/CB-CPD-2066/WO1-L-008 and KNPC delay the reply till heat no’s changes and
materials no longer available with supplier.
We request KNPC to expedite approval on 07th May’2018 via our letter ref no.
KCC/KNPC/CB-CPD-2066/WO1-L-020.
Finally, after several submission KNPC approved materials on 16th July’2018 via KNPC letter
ref no, MAA-MNZ1E-18-099 which delay material delivery almost 03 months.
5) Delay in approval process:
We wrote to PD on 24th Oct’2018 via our letter ref no. KCC/KNPC/CB-CPD-2066/W40/L-
085 that we are facing delay in approval process for materials, process and drawings which
cause impact on the schedule.
6) Non-Issuing/Delay issuing Work Permit: -
We are facing delay in issuing work permits and few days reach to non-issuing the permit due
to E-permit, please ref to our letters ref no. KCC/KNPC/CB-CPD-2066/WO1-L-007,
KCC/KNPC/CB-CPD-2066/WO1-L-003, KCC/KNPC/CB-CPD-2066/WO1-L-0101.
We hope that we clear the picture for KNPC and KCCEC did & still doing efforts to complete
the work order.
Assuring you of our best cooperation and services at all times, we remain.
Best Regards,

Mohamed Abdullah
Contractor’s Representative
Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( 04 )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly HSE Statistics Report.

Dear Sir,
With reference to the above mentioned subject, please find attached herewith the Monthly
HSE
statistics report for the month of January’2019.

This is for your kind information and necessary records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Mohamed Abdullah
Contractor’s Representative

Encl: - As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: “National & Liberation Day Holiday”.

Dear Sir,

With reference to the above-mentioned subject, please be informed that KCCEC- MAA site
shall be observing Liberation Day holiday on Monday 25th Feb’2019 & Tuesday 26th
Feb’2019.

However, site activities shall be carried out on Saturday 23rd Feb’2019 & Sunday 24th
Feb’2019.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Mohamed Abdullah
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Work Permit Executor

Dear Sir,

With reference to the above-mentioned subject, please f

Mr.Jaigovind Jaiswal for DCO approval of work permit executor.


Assuring you our best cooperation and services at all times, we remain,

Best regards,

Mohamed Abdullah
Contractor’s Representative

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: (
)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly HSE Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
Monthly
HSE Report for the month of February’ 2019.

This is for your kind information and necessary records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Mohamed Abdullah
Contractor’s Representative

Encl:- As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: (
)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Tie in Details.

Dear Sir,

With reference to above mentioned subject and KNPC letter ref no. MAA-MNZ1-19-0202
dated 17th Feb’2019, please find attached file with marked Isometric Plus P & ID for all
Tie in
for Units nos. (5,25 & 26)

This is for your kind review and necessary action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Mohamed Abdullah
Contractor’s Representative

Encl: As mentioned above


Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: (
)
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016-
2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Tie in Details.

Dear Sir,

With reference to above mentioned subject and KNPC letter ref no. MAA-MNZ1-19-0256
dated 21st Feb’2019, we would like to highlight that there is still continuous delay in
issuing
work permit by issuer reach to 03 hours delay. Attached sample copy of work permits on
th
27
Feb’2019 in which permits received at 09:05 Am and on 03rd March’2019 in which
permits
received at 08:10 Am.

This is really hammering our schedule and budget due to idle resources. We had extend
our
working hours by 03 hours till 05:00 PM, however it will not be useful as we are loosing
morning 03 hours due to delay issuing work permit and we will not able to support KNPC
and
mitigate the plan.

We would like to suggest KNPC do the following :

I. Option I :- Allowing manual permits instead of E- Permit.

II. Option II : As per new work pemit system, KNPC to deo the needful to pemit us for 06
days
instead of daily permits.

This is for your kind review and necessary action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Mohamed Abdullah
Contractor’s Representative

Encl: As mentioned above

.
Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:
M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Report February’2019

Dear Sir,
With reference to the above-mentioned subject, please find attached herewith the Monthly
Report
for the month of February’2019.

This is for your kind information & necessary records.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,

Mohamed Abdullah
Contractor’s Representative

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Additional Required Materials.

Dear Sir,

With reference to the above-mentioned subject and KNPC letter ref no. MAA-MNZ1E-19-
0282 dated 06th March’2019, please find attached comparision sheet in which M/s COMETCO
is recommended as they are lowest price with total amount 4056.285 KD and delivery period
04 weeks.

Please , also note that prices mentioned do not cover any third party inspection.

This is submitted for your kind review and approval.

Assuring you our best cooperation and services at all times, we remain,

Best Regards,

Mohamed Abdullah
Contractor’s Representative

Encl: As mentioned above

Ref. No.:KCC/KNPC/CB-CPD-2066/W40/L- Date:


M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )
Projects Department
Kuwait.
Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)
WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery
Sub.: Request for time Extension
Dear Sir,

With reference to the above-mentioned subject, we would like to inform you that there has been delays
in execution of work. Main reasons were but not limited to the following:
1. Approval of painting procedures, KCCEC submitted the procedure on 14/2/2018 and obtained
approval from KNPC on 2/7/2018.
2. Approval of painters and blasters, KCCEC submitted list of previous approved blasters and painter
on 3/4/2018 with valid cards from PD, KNPC didn’t responded us and once approaching I & C
they request us to requalify the blasters and painters via I & C division. KCCEC submitted CV’s
on 10/9/18 and KNPC qualified the blasters and painters on 28/10/2018.
3. Approval of welding procedure, KCCEC submitted WPS on 15/02/18 and KNPPC rejected on
19/06/18, however it was earlier approved by I & C. KNPC forced us to generate new WPS and
KCCEC informed that there will be time & cost impact. KCCEC submitted the new WPS on
26/9/18 and we received KNPC approval by mail on 29/11/18.
4. Approval of MTC for piping material, KCCEC submitted material test certificate to KNPC on
8/03/18 and KNPC obtained approval from KNPC on 4/7/18.Inspection of piping materials,
KCCEC wrote to KNPC on 10/09/18 that materials is available in Kuwait and arrange for
inspection. KNPC inspected the materials on 24/9/18.
5. Please find below the delays occurred in getting the minimum approvals for commencement
of
execution works.

Letter Ref.no. User Delay in reply


KCC/KNPC/CB-CPD-2066-L-001 Dt- Request for Approval of organization chart 95 days
06/02/2018 & CVs
KCC/KNPC/CB-CPD-2066-L-002 Dt- Request for Pressure Transmitter Drawing 85 days
14/02/2018 Approval
KCC/KNPC/CB-CPD-2066-L-003 Dt- Painting and Blasting Procedure 85 days
14/02/2018
KCC/KNPC/CB-CPD-2066-L-005 Dt- Welding Procedure Specification 86 days
15/02/2018

Letter Ref.no. User Delay in reply


KCC/KNPC/CB-CPD-2066-L-006Dt 20/02/2018 Data Sheet for Control cable 80 days
KCC/KNPC/CB-CPD-2066-L-008 Dt-08-03-2018 Material Test Certifcate for Piping 63 days
Materials & Valves
KCC/KNPC/CB-CPD-2066-L-009 Dt-15-03-2018 Material Test Certifcate 55 days
KCC/KNPC/CB-CPD-2066-L-010 Dt-28-03-2018 Material Test Certifcate 43 days
KCC/KNPC/CB-CPD-2066-L-014 Dt-24-04-2018 Test Certificates for cables 17 days
KCC/KNPC/CB-CPD-2066-L-015 Dt-24-04-2018 Material test certificate 17 days

Inspite of delays incurred, KCCEC is existing all its efforts to complete the work order and seeking
time extension till 31-Aug-19 and you are kindly requested for approve the same.
Assuring you our best cooperation and services at all times, we remain,
Best Regards,

Sharad J Shringare
Project Manager
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: (1+3 )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Environment Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
Monthly Environment Report.for the month of March 2019.

This is submitted for your kind information and necessary records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: (1+3 )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Environment Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
Monthly Environment Report.for the month of March 2019.

This is submitted for your kind information and necessary records.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Sharad J. Shringare
Project Manager

Encl: As mentioned above


Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for the approval.

Dear Sir,

With reference to the above mentioned subject, please find attached CV of the
following staff for approval:

Sno Name Desigination Nationality


1 Rakesh Kumar Mishra Piping Supervisor Indian
2 Sayed Tajuddin Civil Supervisor Indian

This is for your kind review and approval.

Assuring you of our best attention and cooperation at all times

Thanks & Best Regards,

Amr Abdou
Contractor’s Representative

Encl: As above
Sub.: Fire Watcher

Dear Sir,

With reference to the above mentioned subject, you are kindlyrequested to nominate
the personnel’s mentioned in the enclosed list of 19 nos. employees for Fire Watcher.

This is for your information and necessary action.

Assuring you of our best cooperation and services at all times, we remain.

Best Regards,

Amr Abdou
Contractor’s Representative

Encl: As above
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub: Working Hours during Ramadan.

Dear Sir,

With reference to the above mentioned subject, please be informed that KCCEC working hours
during Ramadan will be as follows:

- Site Working Hours : 05:00 AM to 11:00 AM

This is for your kind information and action.

Assuring you of our best cooperation and services at all times, we remain,

Best Regards,

Amr Abdou
Contractor’s Representative
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Contractors Monthly Enviornmnt Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the Contractors
Monthly Enviornmnt Report.for the month of May 2019.

This is for your kind information and record.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Amr Abdou
Contractor’s Representative

Encl: As above
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Approval of Piping Material.

Dear Sir,

With reference to the above mentioned subject and PO for additional Piping Material ref. no.
C-2016350-W-40-015 dated 30th May 2019, please find attached material data sheets for all
items except items (31, 32, 33, 34 & 35)

This is for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Amr Abdou
Contractor’s Representative

Encl: As above
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly HSE Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
Monthly HSE Report for the month of June 2019.

This is for your kind information and records.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Amr Abdou
Contractor’s Representative

Encl: As above
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Environmental Report.

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
Monthly Environmental Report for the month of June 2019.

This is for your kind information and official records.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Amr Abdou
Contractor’s Representative

Encl.: As Above
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Request for Approval for Piping Material.

Dear Sir,

With reference to the above mentioned subject, and KNPC letter ref. no. MAA-MNZ1-
19-0684 & MAA-MN21-19-0685 dated 27/6/2019, please find attached the following:

1) Revised MTC for Item # 29.


2) For Item #31, as per drawing & MTC the trim (ASTM A 182 –F6a) & Disc
(ASTM A216-WCB+13CR)

This is submitted for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Amr Abdou
Contractor’s Representative

Encl.: As Above
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub.: Monthly Report No.14

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the
Monthly Report No.14 for the month of July 2019.

This is for your kind information and official records.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Amr Abdou
Contractor’s Representative

Encl.: As Above
Ref. No.: KCC/KNPC/CB-CPD-2066/W40/L- Date:

M/s. Kuwait National Petroleum Co. Nos of Pages.: ( )


Projects Department
Kuwait.

Kind Attn.: Team Leader Maintenance Zone – I (MAA)

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO.: CB/CPD/2066/W-40/MAA
Separate Dedicated Nitrogen Header at MAA Refinery

Sub: Monthly HSE Statistics Report

Dear Sir,

With reference to the above mentioned subject, please find attached herewith the Monthly
HSE statistics report for the month of July 2019.

This is submitted for your kind review and official records.

Assuring you our best cooperation and services at all times, we remain,

Best regards,

Amr Abdou
Contractor’s Representative

Encl: As above
Ref. No.:KCC/KNPC/CB-CPD-2066/L- Date

M/s. Kuwait National Petroleum Co.


Projects Department, Kuwait.

Kind Attn.: Mr. Anwar N Hayat


Team Leader- Project Control PD-1

Ref.: Contract no. CB/CPD/2066.


Standby Contract for Project Services for Project Department (2016- 2021)

WO# CB/CPD/2066/W-040/MAA - Separate dedicated Nitrogen Header at MAA


refinery

Sub.: Time Extension

Dear Sir,
We refer to your fax message ref. KNPC/KCC/CB-CPD-2066-F-19-0191 dated 30 Jul’2019 for the above
subject work order.

Kindly be informed that we faced some issues at site that were beyond the control of KCCEC. These issues
were brought to the attention of KNPC vide our letter ref.

1.KCC/KNPC/CB-CPD-2066-L-022 dated 09/05/2018

2.KCC/KNPC/CB-CPD2066-L-85 dated 24/10/2018,

3.KCC/KNPC/CB-CPD2066-L-97 dated 09/12/2018,

4. KCC/KNPC/CB-CPD2066-L-99 dated 20/12/2019,

5.KCC/KNPC/CB-CPD2066-L-103 dated 30/12/2019,

6.KCC/KNPC/CB-CPD2066-L-111 dated 04/2/2019,

7.KCC/KNPC/CB-CPD2066-L-120 dated 09/04/2019

Issues can be summrised as following:

1. Delay in Approval of blasters, and painters: Prior to finalization of commencement date it was agreed
to utilize the earlier approved staff as the time required to qualify staff was not considered in the
proposal. However, Later KCCEC had to requalify the staff which had major time impact of 7
Months on schedule.
2. Delay in the approval process: late approvals for submitted documents such as Drawings for pressure
transmitter, & other materials WPS, Basting and painting procedures, ITP for piping, etc. which had
an impact of 8 months.
3. Delay in approval of WPS: As earlier approved WPS in other work orders were not accepted by
KNPC, KCCEC was compelled to generate new WPS which had considerable time impact of 8
months. KNPC was notified of this time impact well in advance which also had an impact on idle
manpower & resource time for mobilized welders.
4. Nonissuing/Delay in the issuance of work permits for daily works which were highlighted in letters /
progress meetings/Weekly meetings losing productive hours on daily basis.
5. Delay in approval of MTC & Piping Material which had an impact of 3 months.

We are continuing to face site hindrances such as the existing excavated road of length 30 mtrs. Etc. which
is obstructing our work front. Furthermore Shutdown dates for the units have not been provided so as to
ascertain the hydro test and tie-in works.
%

In view of the above, we enclose herewith the revised schedule for the available work front which is under
discussion with the End-user and is subject to confirmation of Shutdown dates.

This is for your kind review and approval.

Assuring you of our best cooperation and services at all times, we remain,

Best regards,

Amr Abdou
Contractor’s Representative

Enel: Mentioned as Above

You might also like