ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

ASSOCIATED WORKS OF NEW OPERATOR SHELTERS A


ASSOCIATE 164 19-Feb-18 15-Sep-18

MILESTONES
MILESTONE 0

MOBILIZATION & GENERAL


MOBILIZATIO 0

PROCUREMENT
PROCUREM 0

INSTRUMENTATION ITEMS ( FOC CABLES , PANELS )


INSTRUMENTA 0

MECHANICAL ITEMS
I 0

CIVIL ITEMS 0

ELECTRICAL IT
ITEMS 0

SPECIALISED V
VENDORS & SUBCONTRACTORS 0

CONSTRUCTION
CONSTRUCT 164 19-Feb-18 15-Sep-18

SHELTERS 164 19-Feb-18 15-Sep-18

SHELTER NO 01 (TYPEA) 51 19-Feb-18 18-Apr-18 18-Apr-18, SHELTE

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 51 19-Feb-18 18-Apr-18 18-Apr-18, E & I WO

A1-260 Route Survey & permit Authorization 2 19-Feb-18 20-Feb-18

A1-270 Cable Trench excavation 24 21-Feb-18 20-Mar-18

Actual Work Critical Remaining W... Page 1 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

A1-290 Soft Sand Bedding 6 21-Mar-18 27-Mar-18

A1-300 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 28-Mar-18 03-Apr-18

A1-280 Installation of cable trays & conduits 10 01-Apr-18 11-Apr-18

A1-310 Caution Tape , Backfilling & Providing route marker 7 04-Apr-18 11-Apr-18

A1-250 Installation of feeder Module ( Fuji) 5 07-Apr-18 11-Apr-18

A1-320 Cable Termination & Testing 6 12-Apr-18 18-Apr-18

SHELTER NO 03 (TYPEA) 46 19-Apr-18 23-Jun-18 23-Jun-18,

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 46 19-Apr-18 23-Jun-18 23-Jun-18,

A3-630 Route Survey & permit Authorization 2 19-Apr-18 21-Apr-18

A3-640 Cable Trench excavation 20 22-Apr-18 14-May-18

A3-660 Soft Sand Bedding 6 14-May-18 22-May-18

A3-670 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 14-May-18 22-May-18

A3-620 Installation of feeder Module ( Togami) 5 18-May-18 26-May-18

A3-680 Caution Tape , Backfilling & Providing route marker 7 23-May-18 04-Jun-18

A3-650 Installation of cable trays & conduits 10 26-May-18 12-Jun-18

Actual Work Critical Remaining W... Page 2 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

A3-690 Cable Termination & Testing 5 17-Jun-18 23-Jun-18

SHELTER NO 06 (TYPEA) 36 19-Feb-18 01-Apr-18 01-Apr-18, SHELTER

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 36 19-Feb-18 01-Apr-18 01-Apr-18, E & I WOR

A6-310 Route Survey & permit Authorization 2 19-Feb-18 20-Feb-18

A6-320 Cable Trench excavation 20 21-Feb-18 15-Mar-18

A6-340 Soft Sand Bedding 6 10-Mar-18 15-Mar-18

A6-350 Laying of Cables( Power.Fire Alarm, Industronic) 6 10-Mar-18 15-Mar-18

A6-330 Installation of cable trays & conduits 10 13-Mar-18 24-Mar-18

A6-360 Caution Tape , Backfilling & Providing route marker 7 17-Mar-18 24-Mar-18

A6-300 Installation of feeder Module ( Togami) 5 19-Mar-18 24-Mar-18

A6-370 Cable Termination & Testing 5 27-Mar-18 01-Apr-18

SHELTER NO 07 (TYPEA) 29 26-Mar-18 28-Apr-18 28-Apr-18, SHELT

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

Actual Work Critical Remaining W... Page 3 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

INSTALLATION OF SHELTER 0

E & I WORKS 29 26-Mar-18 28-Apr-18 28-Apr-18, E & I W

A7-320 Route Survey & permit Authorization 2 26-Mar-18 27-Mar-18

A7-330 Cable Trench excavation 22 28-Mar-18 22-Apr-18

A7-340 Installation of cable trays & conduits 10 09-Apr-18 21-Apr-18

A7-310 Installation of feeder Module ( Togami) 5 15-Apr-18 21-Apr-18

A7-350 Soft Sand Bedding 6 16-Apr-18 22-Apr-18

A7-360 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 16-Apr-18 22-Apr-18

A7-370 Caution Tape , Backfilling & Providing route marker 7 18-Apr-18 25-Apr-18

A7-380 Cable Termination & Testing 5 23-Apr-18 28-Apr-18

TOOL ROOM N
NO.3 0

SHELTER NO 08 (TYPEA) 30 19-Feb-18 25-Mar-18 25-Mar-18, SHELTER N

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 30 19-Feb-18 25-Mar-18 25-Mar-18, E & I WOR

A8-290 Route Survey & permit Authorization 2 19-Feb-18 20-Feb-18

A8-300 Cable Trench excavation 15 21-Feb-18 10-Mar-18

A8-320 Soft Sand Bedding 6 04-Mar-18 10-Mar-18

Actual Work Critical Remaining W... Page 4 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

A8-310 Installation of cable trays & conduits 10 08-Mar-18 20-Mar-18

A8-330 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 11-Mar-18 17-Mar-18

A8-280 Installation of feeder Module ( Al Ahleia) 5 14-Mar-18 20-Mar-18

A8-340 Caution Tape , Backfilling & Providing route marker 7 18-Mar-18 25-Mar-18

A8-350 Cable Termination & Testing 5 20-Mar-18 25-Mar-18

SHELTER NO 14 (TYPEA) 26 02-Apr-18 01-May-18 01-May-18, SHEL

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 26 02-Apr-18 01-May-18 01-May-18, E & I

A14-320 Route Survey & permit Authorization 2 02-Apr-18 03-Apr-18

A14-330 Cable Trench excavation 15 04-Apr-18 21-Apr-18

A14-340 Installation of cable trays & conduits 10 14-Apr-18 25-Apr-18

A14-360 Laying of Cables( Power.Fire Alarm,Gaitronics) 7 14-Apr-18 21-Apr-18

A14-350 Soft Sand Bedding 6 15-Apr-18 21-Apr-18

A14-310 Installation of feeder Module ( Reyrolle belmos) 5 19-Apr-18 25-Apr-18

A14-370 Caution Tape , Backfilling & Providing route marker 8 22-Apr-18 30-Apr-18

A14-380 Cable Termination & Testing 6 25-Apr-18 01-May-18

Actual Work Critical Remaining W... Page 5 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

SHELTER NO 02 (TYPEB) 28 02-May-18 12-Jun-18 12-Jun-18, S

FOUNDATION F
FOR SHELTER 0

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 28 02-May-18 12-Jun-18 12-Jun-18, E

B2-330 Route Survey & permit Authorization 1 02-May-18 02-May-18

B2-340 Cable Trench excavation 20 03-May-18 30-May-18

B2-350 Installation of cable trays & conduits 10 14-May-18 29-May-18

B2-320 Installation of feeder Module ( Togami) 5 21-May-18 29-May-18

B2-360 Soft Sand Bedding 6 21-May-18 30-May-18

B2-370 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 21-May-18 30-May-18

B2-380 Caution Tape , Backfilling & Providing route marker 8 24-May-18 07-Jun-18

B2-390 Cable Termination & Testing 6 02-Jun-18 12-Jun-18

SHELTER NO 04 (TYPEB) 37 23-Jun-18 05-Aug-18 05-A

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

Actual Work Critical Remaining W... Page 6 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

E & I WORKS 37 23-Jun-18 05-Aug-18 05-A

B4-320 Route Survey & permit Authorization 2 23-Jun-18 25-Jun-18

B4-330 Cable Trench excavation 20 25-Jun-18 18-Jul-18

B4-350 Soft Sand Bedding 6 11-Jul-18 18-Jul-18

B4-340 Installation of cable trays & conduits 10 15-Jul-18 26-Jul-18

B4-360 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 17-Jul-18 24-Jul-18

B4-310 Installation of feeder Module ( Togami) 5 21-Jul-18 26-Jul-18

B4-370 Caution Tape , Backfilling & Providing route marker 7 24-Jul-18 01-Aug-18

B4-380 Cable Termination & Testing 6 29-Jul-18 05-Aug-18

SHELTER NO 10 (TYPEB) 35 13-Jun-18 26-Jul-18 26-Jul

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 35 13-Jun-18 26-Jul-18 26-Jul

B10-310 Route Survey & permit Authorization 2 13-Jun-18 18-Jun-18

B10-320 Cable Trench excavation 20 18-Jun-18 11-Jul-18

B10-340 Soft Sand Bedding 6 04-Jul-18 11-Jul-18

B10-350 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 04-Jul-18 11-Jul-18

Actual Work Critical Remaining W... Page 7 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

B10-330 Installation of cable trays & conduits 10 08-Jul-18 19-Jul-18

B10-360 Caution Tape , Backfilling & Providing route marker 7 11-Jul-18 19-Jul-18

B10-300 Installation of feeder Module ( ABB) 5 14-Jul-18 19-Jul-18

B10-370 Cable Termination & Testing 6 19-Jul-18 26-Jul-18

SHELTER NO 11 (TYPEB) 37 23-Apr-18 13-Jun-18 13-Jun-18, S

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 37 23-Apr-18 13-Jun-18 13-Jun-18, E

B11-290 Route Survey & permit Authorization 2 23-Apr-18 24-Apr-18

B11-300 Cable Trench excavation 22 25-Apr-18 22-May-18

B11-310 Installation of cable trays & conduits 10 18-May-18 04-Jun-18

B11-320 Soft Sand Bedding 6 21-May-18 30-May-18

B11-330 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 21-May-18 30-May-18

B11-280 Installation of feeder Module ( ABB) 5 26-May-18 04-Jun-18

B11-340 Caution Tape , Backfilling & Providing route marker 7 31-May-18 12-Jun-18

B11-350 Cable Termination & Testing 6 04-Jun-18 13-Jun-18

SHELTER NO 13 (TYPEB) 30 12-Jun-18 19-Jul-18 19-Jul-1

FOUNDATION F
FOR SHELTER 0

Actual Work Critical Remaining W... Page 8 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 30 12-Jun-18 19-Jul-18 19-Jul-1

B13-290 Route Survey & permit Authorization 2 12-Jun-18 17-Jun-18

B13-300 Cable Trench excavation 20 17-Jun-18 10-Jul-18

B13-310 Installation of cable trays & conduits 10 01-Jul-18 12-Jul-18

B13-320 Soft Sand Bedding 7 02-Jul-18 10-Jul-18

B13-330 Laying of Cables( Power.Fire Alarm,Gaitronics) 7 02-Jul-18 10-Jul-18

B13-340 Caution Tape , Backfilling & Providing route marker 7 04-Jul-18 12-Jul-18

B13-280 Installation of feeder Module ( Togami) 5 07-Jul-18 12-Jul-18

B13-350 Cable Termination & Testing 6 12-Jul-18 19-Jul-18

SHELTER NO 15 (TYPEB) 25 05-Aug-18 09-Sep-18 0

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 25 05-Aug-18 09-Sep-18 0

B15-320 Route Survey & permit Authorization 2 05-Aug-18 07-Aug-18

B15-330 Cable Trench excavation 20 07-Aug-18 05-Sep-18

Actual Work Critical Remaining W... Page 9 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

B15-340 Installation of cable trays & conduits 8 25-Aug-18 03-Sep-18

B15-310 Installation of feeder Module ( ABB) 5 28-Aug-18 03-Sep-18

B15-350 Soft Sand Bedding 6 29-Aug-18 05-Sep-18

B15-360 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 29-Aug-18 05-Sep-18

B15-370 Caution Tape , Backfilling & Providing route marker 7 01-Sep-18 09-Sep-18

B15-380 Cable Termination & Testing 5 03-Sep-18 09-Sep-18

SHELTER NO 16 (TYPEB) 25 19-Jul-18 18-Aug-18 18-

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 25 19-Jul-18 18-Aug-18 18-

B16-290 Route Survey & permit Authorization 2 19-Jul-18 22-Jul-18

B16-300 Cable Trench excavation 20 22-Jul-18 14-Aug-18

B16-310 Installation of cable trays & conduits 10 31-Jul-18 12-Aug-18

B16-280 Installation of feeder Module ( Al Ahleia) 5 06-Aug-18 12-Aug-18

B16-320 Soft Sand Bedding 6 07-Aug-18 14-Aug-18

B16-330 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 07-Aug-18 14-Aug-18

B16-340 Caution Tape , Backfilling & Providing route marker 7 09-Aug-18 18-Aug-18

B16-350 Cable Termination & Testing 5 12-Aug-18 18-Aug-18

Actual Work Critical Remaining W... Page 10 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

SHELTER NO 05 (TYPEC) 59 05-Jun-18 18-Aug-18 18-

REROUTING O
OF UG FACILITIES UNDER SHELTER 0

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 59 05-Jun-18 18-Aug-18 18-

C5-320 Route Survey & permit Authorization 2 05-Jun-18 08-Jun-18

C5-330 Cable Trench excavation 20 09-Jun-18 05-Jul-18

C5-350 Soft Sand Bedding 6 05-Jul-18 12-Jul-18

C5-360 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 12-Jul-18 19-Jul-18

C5-370 Caution Tape , Backfilling & Providing route marker 7 19-Jul-18 28-Jul-18

C5-310 Installation of feeder Module ( Togami) 5 28-Jul-18 02-Aug-18

C5-340 Installation of cable trays & conduits 8 02-Aug-18 12-Aug-18

C5-380 Cable Termination & Testing 5 12-Aug-18 18-Aug-18

SHELTER NO 09 (TYPEC) 38 26-Jul-18 15-Sep-18

FOUNDATION F
FOR SHELTER 0

CONSTRUCTION OF UG FACILITIES
CONSTRUCTIO 0

INSTALLATION OF SHELTER 0

E & I WORKS 38 26-Jul-18 15-Sep-18

Actual Work Critical Remaining W... Page 11 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone
ASSOCIATED WORKS OF NEW OPERATOR SHELTERS AT MAA REFINERY

Activity ID Activity Name BL Project Start Finish J A S O N D J F M A M J J A S


Duration

C9-290 Route Survey & permit Authorization 2 26-Jul-18 29-Jul-18

C9-300 Cable Trench excavation 15 29-Jul-18 15-Aug-18

C9-320 Soft Sand Bedding 5 15-Aug-18 27-Aug-18

C9-330 Laying of Cables( Power.Fire Alarm,Gaitronics) 6 27-Aug-18 03-Sep-18

C9-310 Installation of cable trays & conduits 8 30-Aug-18 09-Sep-18

C9-280 Installation of feeder Module ( Al-Ahliea) 5 03-Sep-18 09-Sep-18

C9-340 Caution Tape , Backfilling & Providing route marker 5 03-Sep-18 09-Sep-18

C9-350 Cable Termination & Testing 5 09-Sep-18 15-Sep-18

COMPLETION & HANDOVER


COMPLETIO 0

Actual Work Critical Remaining W... Page 12 of 12 Date Revision Checked Approved
31-Jan-18 Updated Schedule
Remaining Work Milestone