Impacted Start: 29.06.2019 PAHARPUR_MIL JV, LOT 2900 Date: 19.07.

2019
Impacted Finish: 13.11.2019 Concrete Bedding 21URA
ID Task Name Baseline Baseline Baseline Duration Start Finish Finish Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19
Duration Start Finish Variance 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
1 COOLING WATER SYSTEM 127 days 20 Jun '19 31 Oct '19 136 days 24 Jun '19 13 Nov '19 13 days 4 days
2 Concrete Bedding 21 URA 127 days 20 Jun '19 31 Oct '19 136 days 24 Jun '19 13 Nov '19 13 days 4 days
3 Mobilization 6 days 20 Jun '19 25 Jun '19 5 days 24 Jun '19 28 Jun '19 3 days 4 days
4 Layer no. 1 - Concrete Bedding 48 days 26 Jun '19 12 Aug '19 82 days 29 Jun '19 25 Sep '19 37 days 3 days
5 Segment No. 1 in Chess board Pattern 3 days 26 Jun '19 28 Jun '19 8 days 29 Jun '19 06 Jul '19 8 days 3 days

9 Segment No. 2 in Chess board Pattern 2 days 28 Jun '19 29 Jun '19 6 days 04 Jul '19 09 Jul '19 10 days 6 days

12 Segment No. 3 in Chess board Pattern 2 days 29 Jun '19 30 Jun '19 12 days 04 Jul '19 15 Jul '19 15 days 5 days

15 Segment No. 4 in Chess board Pattern 2 days 30 Jun '19 01 Jul '19 11 days 09 Jul '19 19 Jul '19 18 days 9 days

18 Segment No. 5 in Chess board Pattern 2 days 01 Jul '19 02 Jul '19 11 days 13 Jul '19 23 Jul '19 21 days 12 days

21 Segment No. 6 in Chess board Pattern 2 days 02 Jul '19 03 Jul '19 4 days 22 Jul '19 25 Jul '19 22 days 20 days

24 Segment No. 7 in Chess board Pattern 2 days 03 Jul '19 04 Jul '19 6 days 22 Jul '19 27 Jul '19 23 days 19 days

27 Segment No. 8 in Chess board Pattern 2 days 04 Jul '19 05 Jul '19 4 days 27 Jul '19 30 Jul '19 25 days 23 days

30 Segment No. 9 in Chess board Pattern 2 days 05 Jul '19 06 Jul '19 3 days 30 Jul '19 01 Aug '19 26 days 25 days

33 Segment No.10 in Chess board Pattern 2 days 06 Jul '19 07 Jul '19 3 days 01 Aug '19 03 Aug '19 27 days 26 days

36 Segment No. 11 in Chess board Pattern 3 days 07 Jul '19 09 Jul '19 11 days 03 Aug '19 20 Aug '19 35 days 27 days

39 Segment No. 12 in Chess board Pattern 0 days? NA NA 2 days 20 Aug '19 21 Aug '19 0 days

42 Segment No. 13 in Chess board Pattern 2 days 09 Jul '19 10 Jul '19 2 days 21 Aug '19 22 Aug '19 36 days 36 days

45 Segment No. 14 in Chess board Pattern 2 days 10 Jul '19 11 Jul '19 5 days 22 Aug '19 26 Aug '19 39 days 36 days

48 Segment No. 15 in Chess board Pattern 2 days 11 Jul '19 12 Jul '19 6 days 22 Aug '19 27 Aug '19 39 days 35 days

51 Segment No. 16 in Chess board Pattern 2 days 12 Jul '19 13 Jul '19 2 days 27 Aug '19 28 Aug '19 39 days 39 days

54 Segment No. 17 in Chess board Pattern 2 days 13 Jul '19 14 Jul '19 2 days 28 Aug '19 29 Aug '19 39 days 39 days

57 Segment No. 18 in Chess board Pattern 2 days 14 Jul '19 15 Jul '19 2 days 29 Aug '19 30 Aug '19 39 days 39 days

60 Segment No. 19 in Chess board Pattern 2 days 15 Jul '19 16 Jul '19 2 days 30 Aug '19 31 Aug '19 39 days 39 days

63 Segment No. 20 in Chess board Pattern 2 days 16 Jul '19 17 Jul '19 2 days 31 Aug '19 01 Sep '19 39 days 39 days

66 Segment No. 21 in Chess board Pattern 2 days 17 Jul '19 18 Jul '19 2 days 01 Sep '19 02 Sep '19 39 days 39 days

69 Segment No. 22 in Chess board Pattern 2 days 18 Jul '19 19 Jul '19 2 days 02 Sep '19 03 Sep '19 39 days 39 days

72 Segment No. 23 in Chess board Pattern 2 days 19 Jul '19 20 Jul '19 2 days 03 Sep '19 04 Sep '19 39 days 39 days

75 Segment No. 24 in Chess board Pattern 2 days 20 Jul '19 21 Jul '19 2 days 04 Sep '19 05 Sep '19 39 days 39 days

78 Segment No. 25 in Chess board Pattern 2 days 21 Jul '19 22 Jul '19 2 days 05 Sep '19 06 Sep '19 39 days 39 days

81 Segment No. 26 in Chess board Pattern 2 days 23 Jul '19 24 Jul '19 2 days 06 Sep '19 07 Sep '19 38 days 38 days

84 Segment No. 27 in Chess board Pattern 2 days 24 Jul '19 25 Jul '19 2 days 07 Sep '19 08 Sep '19 38 days 38 days

87 Segment No. 28 in Chess board Pattern 2 days 25 Jul '19 26 Jul '19 2 days 08 Sep '19 09 Sep '19 38 days 38 days

90 Segment No. 29 in Chess board Pattern 2 days 26 Jul '19 27 Jul '19 2 days 09 Sep '19 10 Sep '19 38 days 38 days

93 Segment No. 30 in Chess board Pattern 2 days 27 Jul '19 28 Jul '19 2 days 10 Sep '19 11 Sep '19 38 days 38 days

96 Segment No. 31 in Chess board Pattern 2 days 28 Jul '19 29 Jul '19 2 days 11 Sep '19 12 Sep '19 38 days 38 days

99 Segment No. 32 in Chess board Pattern 2 days 29 Jul '19 30 Jul '19 2 days 12 Sep '19 13 Sep '19 38 days 38 days

102 Segment No. 33 in Chess board Pattern 2 days 30 Jul '19 31 Jul '19 2 days 13 Sep '19 14 Sep '19 38 days 38 days

105 Segment No. 34 in Chess board Pattern 2 days 31 Jul '19 01 Aug '19 2 days 14 Sep '19 15 Sep '19 38 days 38 days

108 Segment No. 35 in Chess board Pattern 2 days 01 Aug '19 02 Aug '19 2 days 15 Sep '19 16 Sep '19 38 days 38 days

111 Segment No. 36 in Chess board Pattern 2 days 03 Aug '19 04 Aug '19 2 days 16 Sep '19 17 Sep '19 37 days 37 days

114 Segment No. 37 in Chess board Pattern 2 days 04 Aug '19 05 Aug '19 2 days 17 Sep '19 18 Sep '19 37 days 37 days

117 Segment No. 38 in Chess board Pattern 2 days 05 Aug '19 06 Aug '19 2 days 18 Sep '19 19 Sep '19 37 days 37 days

120 Segment No. 39 in Chess board Pattern 2 days 06 Aug '19 07 Aug '19 2 days 19 Sep '19 20 Sep '19 37 days 37 days

123 Segment No. 40 in Chess board Pattern 2 days 07 Aug '19 08 Aug '19 2 days 20 Sep '19 21 Sep '19 37 days 37 days

126 Segment No. 41 in Chess board Pattern 2 days 08 Aug '19 09 Aug '19 2 days 21 Sep '19 22 Sep '19 37 days 37 days

129 Segment No. 42 in Chess board Pattern 2 days 09 Aug '19 10 Aug '19 2 days 22 Sep '19 23 Sep '19 37 days 37 days

132 Segment No. 43 in Chess board Pattern 2 days 10 Aug '19 11 Aug '19 2 days 23 Sep '19 24 Sep '19 37 days 37 days

135 Segment No. 44 in Chess board Pattern 2 days 11 Aug '19 12 Aug '19 2 days 24 Sep '19 25 Sep '19 37 days 37 days

138 Layer no. 2 - Concrete Bedding 50 days 13 Aug '19 08 Oct '19 42 days 25 Sep '19 05 Nov '19 28 days 36 days
139 Segment No. 45 in Chess board Pattern 3 days 13 Aug '19 22 Aug '19 2 days 25 Sep '19 26 Sep '19 35 days 36 days

142 Segment No. 46 in Chess board Pattern 3 days 22 Aug '19 24 Aug '19 3 days 26 Sep '19 28 Sep '19 35 days 35 days

145 Segment No. 47 in Chess board Pattern 2 days 24 Aug '19 25 Aug '19 4 days 26 Sep '19 29 Sep '19 35 days 33 days

148 Segment No. 48 in Chess board Pattern 2 days 25 Aug '19 26 Aug '19 3 days 29 Sep '19 01 Oct '19 36 days 35 days

151 Segment No. 49 in Chess board Pattern 2 days 26 Aug '19 27 Aug '19 4 days 29 Sep '19 02 Oct '19 36 days 34 days

154 Segment No. 50 in Chess board Pattern 2 days 27 Aug '19 28 Aug '19 2 days 02 Oct '19 03 Oct '19 36 days 36 days

157 Segment No. 51 in Chess board Pattern 2 days 28 Aug '19 29 Aug '19 2 days 03 Oct '19 04 Oct '19 36 days 36 days

160 Segment No. 52 in Chess board Pattern 2 days 29 Aug '19 30 Aug '19 2 days 04 Oct '19 05 Oct '19 36 days 36 days

163 Segment No. 53 in Chess board Pattern 3 days 30 Aug '19 01 Sep '19 2 days 05 Oct '19 06 Oct '19 35 days 36 days

166 Segment No. 54 in Chess board Pattern 2 days 01 Sep '19 02 Sep '19 2 days 06 Oct '19 07 Oct '19 35 days 35 days

169 Segment No. 55 in Chess board Pattern 2 days 02 Sep '19 03 Sep '19 3 days 07 Oct '19 09 Oct '19 36 days 35 days

172 Segment No. 56 in Chess board Pattern 2 days 03 Sep '19 04 Sep '19 4 days 07 Oct '19 10 Oct '19 36 days 34 days

175 Segment No. 57 in Chess board Pattern 2 days 04 Sep '19 05 Sep '19 2 days 10 Oct '19 11 Oct '19 36 days 36 days

178 Segment No. 58 in Chess board Pattern 2 days 06 Sep '19 07 Sep '19 2 days 11 Oct '19 12 Oct '19 35 days 35 days

181 Segment No. 59 in Chess board Pattern 2 days 07 Sep '19 08 Sep '19 2 days 12 Oct '19 13 Oct '19 35 days 35 days

184 Segment No. 60 in Chess board Pattern 2 days 08 Sep '19 09 Sep '19 2 days 13 Oct '19 14 Oct '19 35 days 35 days

187 Segment No. 61 in Chess board Pattern 2 days 09 Sep '19 10 Sep '19 2 days 14 Oct '19 15 Oct '19 35 days 35 days

190 Segment No. 62 in Chess board Pattern 2 days 10 Sep '19 11 Sep '19 2 days 15 Oct '19 16 Oct '19 35 days 35 days

193 Segment No. 63 in Chess board Pattern 2 days 11 Sep '19 12 Sep '19 2 days 16 Oct '19 17 Oct '19 35 days 35 days

196 Segment No. 64 in Chess board Pattern 2 days 13 Sep '19 14 Sep '19 2 days 17 Oct '19 18 Oct '19 34 days 34 days

199 Segment No. 65 in Chess board Pattern 2 days 14 Sep '19 15 Sep '19 2 days 18 Oct '19 19 Oct '19 34 days 34 days

202 Segment No. 66 in Chess board Pattern 2 days 15 Sep '19 16 Sep '19 2 days 19 Oct '19 20 Oct '19 34 days 34 days

205 Segment No. 67 in Chess board Pattern 3 days 17 Sep '19 19 Sep '19 2 days 20 Oct '19 21 Oct '19 32 days 33 days

208 Segment No. 68 in Chess board Pattern 2 days 19 Sep '19 20 Sep '19 2 days 21 Oct '19 22 Oct '19 32 days 32 days

Page 1
Impacted Start: 29.06.2019 PAHARPUR_MIL JV, LOT 2900 Date: 19.07.2019
Impacted Finish: 13.11.2019 Concrete Bedding 21URA
ID Task Name Baseline Baseline Baseline Duration Start Finish Finish Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19
Duration Start Finish Variance 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
211 Segment No. 69 in Chess board Pattern 2 days 20 Sep '19 21 Sep '19 2 days 22 Oct '19 23 Oct '19 32 days 32 days

214 Segment No. 70 in Chess board Pattern 2 days 22 Sep '19 23 Sep '19 2 days 23 Oct '19 24 Oct '19 31 days 31 days

217 Segment No. 71 in Chess board Pattern 2 days 23 Sep '19 24 Sep '19 2 days 24 Oct '19 25 Oct '19 31 days 31 days

220 Segment No. 72 in Chess board Pattern 2 days 24 Sep '19 25 Sep '19 2 days 25 Oct '19 26 Oct '19 31 days 31 days

223 Segment No. 73 in Chess board Pattern 2 days 25 Sep '19 26 Sep '19 3 days 26 Oct '19 28 Oct '19 32 days 31 days

226 Segment No. 74 in Chess board Pattern 2 days 27 Sep '19 28 Sep '19 4 days 26 Oct '19 29 Oct '19 31 days 29 days

229 Segment No. 75 in Chess board Pattern 2 days 28 Sep '19 29 Sep '19 2 days 29 Oct '19 30 Oct '19 31 days 31 days

232 Segment No. 76 in Chess board Pattern 2 days 29 Sep '19 30 Sep '19 2 days 30 Oct '19 31 Oct '19 31 days 31 days

235 Segment No. 77 in Chess board Pattern 2 days 01 Oct '19 02 Oct '19 2 days 31 Oct '19 01 Nov '19 30 days 30 days

238 Segment No. 78 in Chess board Pattern 2 days 02 Oct '19 03 Oct '19 2 days 01 Nov '19 02 Nov '19 30 days 30 days

241 Segment No. 79 in Chess board Pattern 2 days 04 Oct '19 05 Oct '19 2 days 02 Nov '19 03 Nov '19 29 days 29 days

244 Segment No. 80 in Chess board Pattern 2 days 06 Oct '19 07 Oct '19 2 days 03 Nov '19 04 Nov '19 28 days 28 days

247 Segment No. 81 in Chess board Pattern 2 days 07 Oct '19 08 Oct '19 2 days 04 Nov '19 05 Nov '19 28 days 28 days

250 Layer no. 3 - Concrete Bedding 23 days 09 Oct '19 31 Oct '19 27 days 18 Oct '19 13 Nov '19 13 days 9 days
260 Segment No. 85 in Chess board Pattern 0 days? NA NA 2 days 18 Oct '19 19 Oct '19 0 days

263 Segment No. 86 in Chess board Pattern 2 days 12 Oct '19 13 Oct '19 2 days 19 Oct '19 20 Oct '19 7 days 7 days

266 Segment No. 87 in Chess board Pattern 2 days 12 Oct '19 13 Oct '19 2 days 20 Oct '19 21 Oct '19 8 days 8 days

269 Segment No. 88 in Chess board Pattern 2 days 13 Oct '19 14 Oct '19 2 days 21 Oct '19 22 Oct '19 8 days 8 days

272 Segment No. 89 in Chess board Pattern 2 days 15 Oct '19 16 Oct '19 2 days 22 Oct '19 23 Oct '19 7 days 7 days

275 Segment No. 90 in Chess board Pattern 2 days 15 Oct '19 16 Oct '19 2 days 23 Oct '19 24 Oct '19 8 days 8 days

278 Segment No. 91 in Chess board Pattern 2 days 16 Oct '19 17 Oct '19 2 days 24 Oct '19 25 Oct '19 8 days 8 days

281 Segment No. 92 in Chess board Pattern 2 days 17 Oct '19 18 Oct '19 2 days 25 Oct '19 26 Oct '19 8 days 8 days

284 Segment No. 93 in Chess board Pattern 2 days 18 Oct '19 19 Oct '19 2 days 26 Oct '19 27 Oct '19 8 days 8 days

287 Segment No. 94 in Chess board Pattern 2 days 19 Oct '19 20 Oct '19 3 days 27 Oct '19 29 Oct '19 9 days 8 days

293 Segment No. 96 in Chess board Pattern 2 days 20 Oct '19 21 Oct '19 2 days 29 Oct '19 30 Oct '19 9 days 9 days

296 Segment No. 97 in Chess board Pattern 2 days 21 Oct '19 22 Oct '19 2 days 30 Oct '19 31 Oct '19 9 days 9 days

299 Segment No. 98 in Chess board Pattern 2 days 22 Oct '19 23 Oct '19 2 days 31 Oct '19 01 Nov '19 9 days 9 days

302 Segment No. 99 in Chess board Pattern 2 days 24 Oct '19 25 Oct '19 2 days 01 Nov '19 02 Nov '19 8 days 8 days

305 Segment No. 100 in Chess board Pattern 2 days 24 Oct '19 25 Oct '19 2 days 02 Nov '19 03 Nov '19 9 days 9 days

308 Segment No. 101 in Chess board Pattern 2 days 25 Oct '19 26 Oct '19 2 days 03 Nov '19 04 Nov '19 9 days 9 days

311 Segment No. 102 in Chess board Pattern 2 days 26 Oct '19 27 Oct '19 2 days 04 Nov '19 05 Nov '19 9 days 9 days

251 Segment No. 82 in Chess board Pattern 2 days 09 Oct '19 10 Oct '19 2 days 05 Nov '19 06 Nov '19 27 days 27 days

314 Segment No. 103 in Chess board Pattern 2 days 27 Oct '19 28 Oct '19 2 days 05 Nov '19 06 Nov '19 9 days 9 days

254 Segment No. 83 in Chess board Pattern 2 days 10 Oct '19 11 Oct '19 3 days 06 Nov '19 08 Nov '19 28 days 27 days

317 Segment No. 104 in Chess board Pattern 2 days 27 Oct '19 28 Oct '19 2 days 06 Nov '19 07 Nov '19 10 days 10 days

320 Segment No. 105 in Chess board Pattern 2 days 28 Oct '19 29 Oct '19 2 days 07 Nov '19 08 Nov '19 10 days 10 days

257 Segment No. 84 in Chess board Pattern 2 days 11 Oct '19 12 Oct '19 2 days 08 Nov '19 09 Nov '19 28 days 28 days

323 Segment No. 106 in Chess board Pattern 2 days 28 Oct '19 29 Oct '19 2 days 08 Nov '19 09 Nov '19 11 days 11 days

326 Segment No. 107 in Chess board Pattern 2 days 29 Oct '19 30 Oct '19 2 days 09 Nov '19 10 Nov '19 11 days 11 days

329 Segment No. 108 in Chess board Pattern 2 days 30 Oct '19 31 Oct '19 2 days 10 Nov '19 11 Nov '19 11 days 11 days

332 Segment No. 109 in Chess board Pattern 2 days 30 Oct '19 31 Oct '19 3 days 11 Nov '19 13 Nov '19 13 days 12 days