Professional Documents
Culture Documents
SITE VISIT REPORT - Alexa Tower Project
SITE VISIT REPORT - Alexa Tower Project
SITE VISIT REPORT - Alexa Tower Project
Faculty of Engineering
Department of Architectural Engineering
Spring Semester 2018-2019
EA222- Building Technology Level (4)
1
SUBJECT: Building Technology 4
DAY: Monday DATE: 11/3/2019
SITE VISIT TO: Alexa Tower Project
SPECIFIED IN: Curtain wall structure
ADDRESS: Safeya Saghloul Street Al Raml Station
Introduction:
Alexa tower Mall , Is a mall made by “ Majid Al Futtaim
Company “ which is responsible for Carrefour
construction. Alexa Tower consists of 10 floors , the 1st 4
floors are trading floors , 2 floors for car parking and 6
managerial floors.
2
Curtain Wall
Glass curtain walls consist
of two basic components:
the glass and the frame.
How these two elements
are manipulated,
including the proportion,
properties, and
anchorage of each, constitutes the essential
distinction among individual curtain wall systems.
It’s constructed by
using mullions and
transoms that are
placed into the
slabs and
reinforced and held
by brackets placed
through the slabs.
I-Beam Structure
3
Flat Slap Structure
Flat Slabs are used by engineers in many
building due to its advantages over other
reinforced concrete floor system in
different cases. The most important
advantages of flat slabs are:
4
Aluminum Cladding
Aluminum cladding is one of the most used
types of cladding for building exteriors.
Aluminum is often chosen as the optimal
material for building cladding for
economical, functional and aesthetical
reasons. The cladding
comes in wide range White Aluminum Cladding
of different cladding
panels that virtually
enable every building shape and form.
White Aluminum Cladding IS THE MAIN
ALUMINUM TYPE WICH USED IN BUILDING
Granite Finishing
Granit Cladding or finishing gives
aesthetical shape
To the building and often used in
economical
Building it can come in different
colors and shapes
But in this building it’s black in colors Galaxy Granite
mixed
with
Stones particles and illumination.
5
Space Maintainer
Space Maintainer is used to
maintain the space
between the reinforced
bars and the slabs and also
to form the cover of the
ceiling after pouring the concrete which carry the weight.
shuttering formwork
These are used in columns
construction, wood panels are
placed near to each other’s and
installed together firmly thus when
pouring concrete, the wooden
panels don’t break down due to
the strength of the concrete
pump.