RENCANA ANGGARAN BIAYA (RAB)

Proyek : Struktur Pakuhaji


Lokasi : kota cimahi

Harga Satuan Jumlah Harga


No No ID Volume Satuan Bahan Upah Alat Subtotal Total
Rp Rp Rp Rp Rp

Sloof
1 B1015 Bekisting Kolom/m2 2xpakai dgn Papan 2/20 17.00 m2 66,573.75 34,500.00 - 101,073.75 1,718,253.75
2 A1053 Pembesian Polos/kg 17.00 btg 68,537.50 13,346.50 400.00 82,284.00 1,398,828.00
3 B1014 Cin-cin / Ring 6mm' 15.60 btg 29,150.00 10,215.00 400.00 39,765.00 620,334.00
14 A1028 Beton Ready Mix K.225/m3 1.47 m3 813,700.00 172,600.00 45,687.50 1,031,987.50 1,517,021.63

Kolom
1 A1028 Beton Ready Mix K.225/m3 1.26 m3 813,700.00 172,600.00 45,687.50 1,031,987.50 1,300,304.25
2 A1053 besi polos batang 17.50 btg 68,537.50 13,346.50 400.00 82,284.00 1,439,970.00
3 B1014 Cin-cin / Ring 6mm' 15.17 btg 29,150.00 10,215.00 400.00 39,765.00 603,235.05
4 A1070 bagisting kayu 17.50 m 26,023.50 23,700.00 - 49,723.50 870,161.25
Balok
5 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 15.33 m2 26,023.50 23,700.00 - 49,723.50 762,427.00
6 A1053 besi polos 15.33 btg 68,537.50 13,346.50 400.00 82,284.00 1,261,413.72
7 A1028 Beton Ready Mix K.225/m3 1.04 m3 813,700.00 172,600.00 45,687.50 1,031,987.50 1,068,107.06
8 B1014 Cin-cin / Ring 6mm' 12.26 29,150.00 10,215.00 400.00 39,765.00 487,518.90

Total 11,329,320.86