Professional Documents
Culture Documents
Automatically Contrilled Load Shedding
Automatically Contrilled Load Shedding
211
Ahstract-Automatlc Load Shedding (ALS) Is categorized generation. A sudden loss of generation in the system will
as one of the protection systems applied to a power network. result in a reduction in the frequency at a rate of change
The aim of this work Is to understand how the system works by which depends on the size of the resultant overload and the
creating a software simulation of tbe above-mentioned system.
inertia constant of the system.
Pre-requirement to this Is the need to understand the electrical
The relationship that defines the variation of frequency
system response to the presence of disturbances and
interruptions on over loads. A case study on University
with time, following a sudden variation in load andlor
Teknologl Petron.s Gas District Cooling (UTP GDC) generation, can be obtained, starting from the (1) for the
Cogeneration Power Plant has also been carried out. The plant oscillation of a simple generator:
has Implemented load shedding sc heme as one of their power
reliability strategy. The plant has 4 stages of load shed and a
single frequency set point to trigger the under-frequency relay. (1)
Simulation results were obtained using PSCADfEMTDC to
prove the effediveness of the system.
MVA MVA
Automatic Load Shedding may be one of the low cost o generator torque angle
=
generation plants to maintain system security and P;, net power accelerated or decelerated (MW)
=
caused by system faults, it is generally recognized that a units. It should be emphasized that the constant H in (5) is
drop in frequency is a more reliable indication of loss of expressed to an MVA base equal to the total generation
capacity of the system.
The accelerating power, PA. in (4) is responsible for the
N. PeTUmal and Aliza Che Amran are with Ele\:lrical & Electronic
frequency variation. It can be calculated from:
Engineering Department, Universili Teknologi Pelronas, Bandar Seri
Iskandar, 31750 Tronoh, Perak, Malaysia (e-mail: �=�-� �
perumal@petrOnas.com.my).
A. Simple Machine Model A steam turbine is designed such that, when operating at
nominal mechanical speed and nominal system frequency,
A single machine has been used in the power-system excessive vibrations and stresses in its components: (e.g.
model to illustrate a load-shedding system. This is resonance of turbine blades), are avoided. However, when
equivalent to asswning that the generator units are running below normal speed at a reduced system frequency,
electrically connected with negligible oscillations between cumulative damage could be produced by - excessive
them, and has uniform frequency ignoring the effect of the vibration. It is recommended, therefore, that the time limits
regulating equipment. The load is represented as a constant given in Table 1 should not be exceeded. However, during
power, which implies that there is no reduGtion in load as a transient operation and with load lle)ow nominal, reduction
result of the voltage and frequency drops due to a of frequency down to 93% of rated frequency can be
contingency situation. This model provides a pessimistic permitted without causing damage either to the turbine or to
simulation of the system since the reduction of the load due the turbo generator auxiliary lubrication and cooling
to the frequency drops and the effect of the speed regulators systems.
are neglected. In using this model, the inertia constant of the
system is calculated using (5).
TABLE I
TYPICAL TIMES
. FOR THE OPERATION OF TURBINES (FULL
The rate of change of the frequency is calculated from
LOAD)
(4) with the following assumptions:
i) The mechanical power entering the generators does not
vary and is equal in magnitude to the pre-fault value.
ii) The magnitude of the load does not vary with time,
voltage or frequency. It is only reduced by
disconnecting part of the load as a result of the 99_0 Continuously
automatic load-shedding system.
97.3 90
VI. A CASE STUDY ON LOAD SHEDDING SYSTEM fa" GTG-A LV /nI�e For GTG·8 LV In�e
2 x 5,25MVA x 90% = MCC2 = 2,OMVA VTP GDC Power Plant has proposed a 4-stage (level) of
9.4SMVA load shedding that will be implemented as a LAST option
UTP[ =2,725MVA
TNB Generat;on for power reliability and stability.. The load shedding
UTI'2 = 2,725 MVA
scheme used consists of a single frequenc y set point with
No power import under normal
operation (power supplied by Others are negligible, multiple time delay. Within a period of 0.15 seconds, the
both GTG units will be fully under-frequency relays will send out signals to trip loads in
L Loads = 9.45 MY A
used to ener&ize GDC 11 kV and
order to increase the frequency level hence prevent system
MIS 11kv busbars)
collapse or instability.
The total non-essential loads are tmknown since the
When only one generator is operating, together with the project is still under construction. For this study , a certain
TNB supply, to supply a load Of a load of 9,45 MVA, the figure will be assumed. As for CB-GS05 or CB-GS07,
TNB feeder experiences a trip-off, the excess load usually only one of the transmission ties will be open
amounting to 9,45 - 5.25 = 4.2 MVA will lead to under therefore the loads on either INB l 1kV supply or on one of
frequency instability. Hence, load shedding is required. .the generating units at GD� side will be less depend on the
Assuming non-essential loads amounting to 4.2 MVA situation.
can be shed at VTPI and VTP2, the frequency setting for
the frequency relays FI and F2 at MIS switchgear is
determined as follows: VIII. LOCATION OF UNDER FREQUENCY RELAYS
TABLE 3
UNDER-FREQUENCY RELAYS CONNECTION TO THE CONTROL
PANEL
215
CF4lin C for a Iimfted period. 111 this case, the fault is betwccn
between Distribution Controlling System or 0.25s to 0.35s which is for a duration of 0. 1 0s. No circuit
GS06 -KJOJ Distribution Cooling System Plant (DCS
breakers involved. The fault is applied to a line with no
Pla!1l) Isolation Signa!
loads connected in parallel with it.
Untitl�,:;_d''". ____��___
___-'---'-'---"''-'-_�_''
nQ name
� .. _ +2 �Fault. Curnnt
!1
.fO.2i=----a-----EI--....J
�
Fig. 3. Under-frequency relays connection
·1.6
'3,4
VIII. THE PSCAD/EMTDC SIMULATION
·5.2
-162 _Frequent�
J�f' =:-
' .�ij1,
+59.6
+57.2
'+54.8
.+52.4
-1-50';;
0 :----
. -
. .fO :-
¢
. l ---::
0.'-=Z-_- O L3
. -_-0.L.4---O ' .5
IX. CONCLUSIONS
In this paper a systematic study of under frequency
automatic load shedding system employed in electrical
power system is presented. Dynamic studies were carried
out usingPSCAD/EMTDC software. Using a defined under
frequency automatic load shedding criteria, the frequency
values and the loads to be shed can clearly be defined. This
system has been used in indus try as an effective way of
implementing automatic load shedding.
x. REFERENCES