ACTIVITIES Start Date Duration End Date

1. Painting of Angle Bars 19-Jul-18 2 20-Jul-18


2. Fabrication of Steel Truss 23-Jul-18 8 30-Jul-18
3. Installation of Steel Truss 31-Jul-18 3 2-Aug-18
4. Painting of C-Purlins 31-Jul-18 2 1-Aug-18
5. Installation of C-Purlins 3-Aug-18 3 5-Aug-18