TUGAS EKONOMI TRANSPORTASI

ASSIGNMENT 05
NAMA : JERIVO PANDEIROTH

NIM : 15021101017

Calculate the current tIme value for (using GDP per capita, not province minimum salary) :

 North Sulawesi
 Manado
 Minahasa Raya (M. Induk, Minut, Minsel, Mitra)
 Bitung
 Tomohon
Calculate the time value saving for every vehicle type when the trip time saving = 25 minutes. The
number of passenger and their economic time value were given on the following table,

K ( factor koreksi Sulawesi Utara dan sekitarnya) = 0.992063492

Solution

1. North Sulawesi
Given : GDP/PDRB atas dasar harga
konstan 2010 ( tahun 2016)……………………………….Rp. 74.771 (Miliar Rupiah)
1 Month..…………………………………………………………..20 working days
1 working day……………………………………………………. 8 hours

𝐼𝐷𝑅 74.771
Average Time Value = = 𝐼𝐷𝑅 467 ≈ 𝐼𝐷𝑅 470, −/ℎ𝑜𝑢𝑟
20 𝑑𝑎𝑦𝑠 𝑋 8 ℎ𝑜𝑢𝑟𝑠

Travel time = (25/60)=0,42 hour

Time value was calculated as shown in the following table

Vehicle Average # % Passenger With Travel Time Average Time Time Value
type of Passenger Economic Value (hour) Value (1 hour)
LV 5 60% 0.42 470 588
HV 2 80% 0.42 470 313
MC 1.5 80% 0.42 470 235
Time value saving for a day and a year (North Sulawesi)

Vehicle Average # % Passenger With Average Time Travel Time Daily traffic Time
type of Passenger Economic Value Value (1 hour) (hour) Volume Value
LV 5 60% 470 0.42 10254 6,024,225
HV 2 80% 470 0.42 365 114,367
MC 1.5 80% 470 0.42 4989 1,172,415
Time value saving for a day 7,311,007
Time value for a year = Time value (1 day) * 300 = 2,193,302,000

2. Manado
Given : GDP/PDRB atas dasar harga
konstan 2010 ( tahun 2016)……………………………….Rp. 21.194 (Miliar Rupiah)
1 Month..…………………………………………………………..20 working days
1 working day……………………………………………………. 8 hours

𝐼𝐷𝑅 21.194
Average Time Value = = 𝐼𝐷𝑅 132 ≈ 𝐼𝐷𝑅 135, −/ℎ𝑜𝑢𝑟
20 𝑑𝑎𝑦𝑠 𝑋 8 ℎ𝑜𝑢𝑟𝑠

Travel time = (25/60) = 0,42 hour

Time value was calculated as shown in the following table

Vehicle Average # % Passenger With Travel Time Average Time Time Value
type of Passenger Economic Value (hour) Value (1 hour)
LV 5 60% 0.42 135 169
HV 2 80% 0.42 135 90
MC 1.5 80% 0.42 135 68

Time value saving for a day and a year (Manado)


Vehicle Average # % Passenger With Average Time Travel Time Daily traffic Time
type of Passenger Economic Value Value (1 hour) (hour) Volume Value
LV 5 60% 135 0.42 10254 1,730,363
HV 2 80% 135 0.42 365 32,850
MC 1.5 80% 135 0.42 4989 336,758
Time value saving for a day 2,099,970
Time value for a year = Time value (1 day) * 300 = 629,991,000
3. Minahasa
Given : GDP/PDRB atas dasar harga
konstan 2010 ( tahun 2016)……………………………….Rp. 9.917 (Miliar Rupiah)
1 Month..…………………………………………………………..20 working days
1 working day……………………………………………………. 8 hours

𝐼𝐷𝑅 9.917
Average Time Value = = 𝐼𝐷𝑅 62 ≈ 𝐼𝐷𝑅 65, −/ℎ𝑜𝑢𝑟
20 𝑑𝑎𝑦𝑠 𝑋 8 ℎ𝑜𝑢𝑟𝑠

Travel time = (25/60) = 0,42 hour

Time value was calculated as shown in the following table

Vehicle Average # % Passenger With Travel Time Average Time Time Value
type of Passenger Economic Value (hour) Value (1 hour)
LV 5 60% 0.42 65 81
HV 2 80% 0.42 65 43
MC 1.5 80% 0.42 65 33

Time value saving for a day and a year (Minahasa)


Vehicle Average # % Passenger With Average Time Travel Time Daily traffic Time
type of Passenger Economic Value Value (1 hour) (hour) Volume Value
LV 5 60% 65 0.42 10254 833,138
HV 2 80% 65 0.42 365 15,817
MC 1.5 80% 65 0.42 4989 162,143
Time value saving for a day 1,011,097
Time value for a year = Time value (1 day) * 300 = 303,329,000
4. Minahasa Utara
Given : GDP/PDRB atas dasar harga
konstan 2010 ( tahun 2016)……………………………….Rp. 7.782 (Miliar Rupiah)
1 Month..…………………………………………………………..20 working days
1 working day……………………………………………………. 8 hours

𝐼𝐷𝑅 7.782
Average Time Value = = 𝐼𝐷𝑅 49 ≈ 𝐼𝐷𝑅 50, −/ℎ𝑜𝑢𝑟
20 𝑑𝑎𝑦𝑠 𝑋 8 ℎ𝑜𝑢𝑟𝑠

Travel time = (25/60) = 0,42 hour

Time value was calculated as shown in the following table

Vehicle Average # % Passenger With Travel Time Average Time Time Value
type of Passenger Economic Value (hour) Value (1 hour)
LV 5 60% 0.42 50 63
HV 2 80% 0.42 50 33
MC 1.5 80% 0.42 50 25

Time value saving for a day and a year (Minahasa Utara)

Vehicle Average # % Passenger With Average Time Travel Time Daily traffic Time
type of Passenger Economic Value Value (1 hour) (hour) Volume Value
LV 5 60% 50 0.42 10254 640,875
HV 2 80% 50 0.42 365 12,167
MC 1.5 80% 50 0.42 4989 124,725
Time value saving for a day 777,767
Time value for a year = Time value (1 day) * 300 = 233,330,000
5. Minahasa Selatan
Given : GDP/PDRB atas dasar harga
konstan 2010 ( tahun 2016)……………………………….Rp. 5.110 (Miliar Rupiah)
1 Month..…………………………………………………………..20 working days
1 working day……………………………………………………. 8 hours

𝐼𝐷𝑅 5.110
Average Time Value = = 𝐼𝐷𝑅 32 ≈ 𝐼𝐷𝑅 35, −/ℎ𝑜𝑢𝑟
20 𝑑𝑎𝑦𝑠 𝑋 8 ℎ𝑜𝑢𝑟𝑠

Travel time = (25/60) = 0,42 hour

Time value was calculated as shown in the following table

Vehicle Average # % Passenger With Travel Time Average Time Time Value
type of Passenger Economic Value (hour) Value (1 hour)
LV 5 60% 0.42 35 44
HV 2 80% 0.42 35 23
MC 1.5 80% 0.42 35 18

Time value saving for a day and a year (Minahasa Selatan)

Vehicle Average # % Passenger With Average Time Travel Time Daily traffic Time
type of Passenger Economic Value Value (1 hour) (hour) Volume Value
LV 5 60% 35 0.42 10254 448,613
HV 2 80% 35 0.42 365 8,517
MC 1.5 80% 35 0.42 4989 87,308
Time value saving for a day 544,437
Time value for a year = Time value (1 day) * 300 = 163,331,000
6. Minahasa Tenggara
Given : GDP/PDRB atas dasar harga
konstan 2010 ( tahun 2016)……………………………….Rp. 3.045 (Miliar Rupiah)
1 Month..…………………………………………………………..20 working days
1 working day……………………………………………………. 8 hours

𝐼𝐷𝑅 3.045
Average Time Value = = 𝐼𝐷𝑅 19 ≈ 𝐼𝐷𝑅 20, −/ℎ𝑜𝑢𝑟
20 𝑑𝑎𝑦𝑠 𝑋 8 ℎ𝑜𝑢𝑟𝑠

Travel time = (25/60) = 0,42 hour

Time value was calculated as shown in the following table

Vehicle Average # % Passenger With Travel Time Average Time Time Value
type of Passenger Economic Value (hour) Value (1 hour)
LV 5 60% 0.42 20 25
HV 2 80% 0.42 20 13
MC 1.5 80% 0.42 20 10

Time value saving for a day and a year (Minahasa Tenggara)

Vehicle Average # % Passenger With Average Time Travel Time Daily traffic Time
type of Passenger Economic Value Value (1 hour) (hour) Volume Value
LV 5 60% 20 0.42 10254 256,350
HV 2 80% 20 0.42 365 4,867
MC 1.5 80% 20 0.42 4989 49,890
Time value saving for a day 311,107
Time value for a year = Time value (1 day) * 300 = 93,332,000
7. Bitung
Given : GDP/PDRB atas dasar harga
konstan 2010 ( tahun 2016)……………………………….Rp. 9.538 (Miliar Rupiah)
1 Month..…………………………………………………………..20 working days
1 working day……………………………………………………. 8 hours

𝐼𝐷𝑅 9.538
Average Time Value = = 𝐼𝐷𝑅 60 ≈ 𝐼𝐷𝑅 60, −/ℎ𝑜𝑢𝑟
20 𝑑𝑎𝑦𝑠 𝑋 8 ℎ𝑜𝑢𝑟𝑠

Travel time = (25/60) = 0,42 hour

Time value was calculated as shown in the following table

Vehicle Average # % Passenger With Travel Time Average Time Time Value
type of Passenger Economic Value (hour) Value (1 hour)
LV 5 60% 0.42 60 75
HV 2 80% 0.42 60 40
MC 1.5 80% 0.42 60 30

Time value saving for a day and a year (Bitung)

Vehicle Average # % Passenger With Average Time Travel Time Daily traffic Time
type of Passenger Economic Value Value (1 hour) (hour) Volume Value
LV 5 60% 60 0.42 10254 769,050
HV 2 80% 60 0.42 365 14,600
MC 1.5 80% 60 0.42 4989 149,670
Time value saving for a day 933,320
Time value for a year = Time value (1 day) * 300 = 279,996,000
8. Tomohon
Given : GDP/PDRB atas dasar harga
konstan 2010 ( tahun 2016)……………………………….Rp. 2.567 (Miliar Rupiah)
1 Month..…………………………………………………………..20 working days
1 working day……………………………………………………. 8 hours

𝐼𝐷𝑅 2.567
Average Time Value = = 𝐼𝐷𝑅 16 ≈ 𝐼𝐷𝑅 20, −/ℎ𝑜𝑢𝑟
20 𝑑𝑎𝑦𝑠 𝑋 8 ℎ𝑜𝑢𝑟𝑠

Travel time = (25/60) = 0,42 hour

Time value was calculated as shown in the following table


Vehicle Average # % Passenger With Travel Time Average Time Time Value
type of Passenger Economic Value (hour) Value (1 hour)
LV 5 60% 0.42 20 25
HV 2 80% 0.42 20 13
MC 1.5 80% 0.42 20 10

Time value saving for a day and a year (Tomohon)

Vehicle Average # % Passenger With Average Time Travel Time Daily traffic Time
type of Passenger Economic Value Value (1 hour) (hour) Volume Value
LV 5 60% 20 0.42 10254 256,350
HV 2 80% 20 0.42 365 4,867
MC 1.5 80% 20 0.42 4989 49,890
Time value saving for a day 311,107
Time value for a year = Time value (1 day) * 300 = 93,332,000