PROJECT SCHEDULE

6th Floor SW and Column


Concreting August 27, 2019 August 31, 2019
Formwork August 26, 2019 August 30, 2019
Rebar August 23, 2019 August 27, 2019
6th Floor Slab and Beam
Concreting August 22, 2019 August 26, 2019
Rebar August 21, 2019 August 24, 2019
Formwork August 17, 2019 August 21, 2019
5th Floor SW and Column
Concreting August 13, 2019 August 17, 2019
Formwork August 12, 2019 August 16, 2019
Rebar August 9, 2019 August 13, 2019
5th Floor Slab and Beam
Concreting August 8, 2019 August 12, 2019
Rebar August 7, 2019 August 10, 2019
Formwork August 3, 2019 August 7, 2019
4th Floor SW and Column
Concreting July 30, 2019 August 2, 2019
Formwork July 29, 2019 August 1, 2019
Rebar July 27, 2019 July 30, 2019
4th Floor Slab and Beam
Concreting July 26, 2019 July 29, 2019
Rebar July 25, 2019 July 27, 2019
Formwork July 22, 2019 July 24, 2019
Zone 1 Zone 2