The document outlines a project schedule showing the planned dates for rebar installation, formwork construction, and concrete pouring for the slabs, beams, columns, and shear walls on the 4th, 5th, and 6th floors of a building. Work will proceed floor by floor starting with the 4th floor between July 22 and August 2, then the 5th floor from August 3 to August 17, and finally the 6th floor from August 17 to August 31.
The document outlines a project schedule showing the planned dates for rebar installation, formwork construction, and concrete pouring for the slabs, beams, columns, and shear walls on the 4th, 5th, and 6th floors of a building. Work will proceed floor by floor starting with the 4th floor between July 22 and August 2, then the 5th floor from August 3 to August 17, and finally the 6th floor from August 17 to August 31.
The document outlines a project schedule showing the planned dates for rebar installation, formwork construction, and concrete pouring for the slabs, beams, columns, and shear walls on the 4th, 5th, and 6th floors of a building. Work will proceed floor by floor starting with the 4th floor between July 22 and August 2, then the 5th floor from August 3 to August 17, and finally the 6th floor from August 17 to August 31.
Concreting August 27, 2019 August 31, 2019 Formwork August 26, 2019 August 30, 2019 Rebar August 23, 2019 August 27, 2019 6th Floor Slab and Beam Concreting August 22, 2019 August 26, 2019 Rebar August 21, 2019 August 24, 2019 Formwork August 17, 2019 August 21, 2019 5th Floor SW and Column Concreting August 13, 2019 August 17, 2019 Formwork August 12, 2019 August 16, 2019 Rebar August 9, 2019 August 13, 2019 5th Floor Slab and Beam Concreting August 8, 2019 August 12, 2019 Rebar August 7, 2019 August 10, 2019 Formwork August 3, 2019 August 7, 2019 4th Floor SW and Column Concreting July 30, 2019 August 2, 2019 Formwork July 29, 2019 August 1, 2019 Rebar July 27, 2019 July 30, 2019 4th Floor Slab and Beam Concreting July 26, 2019 July 29, 2019 Rebar July 25, 2019 July 27, 2019 Formwork July 22, 2019 July 24, 2019 Zone 1 Zone 2