Anchors Design 1 (3 Rows) A
Anchors Design 1 (3 Rows) A
Single Basement
Provide 3.00
Anchor
Anchors Row-2
18.24 m 4.00 m
Row-2
Anchors Row-3
Row-3 4.24 m
Excavation Level
3.0 m
0.91 0.30
Notes:
1 Performance and Proof Load Tests must be performed as per FHWA recommendations
before putting the anchors into services
2 Above design is temporary system and time period of temporary system is commonly stated to be 18 to 36 months which can be
shorter or longer based on actual project conditions
3 Design of Bearing Plate and reaction beam are the responsility of the Contractor
4 The Contractor to be engaged must have sufficient knowledge and experience of execution of the design.
Geotechnical Engineering Circular No.4 'Ground Anchors and Anchored Systems', (June
Design Approach 1999), U.S. Department of Transportation, Federal Highway Administration
Input Data
No of Anchors to be used = 3
H1 = 3m H2 = 4m H3 = 4.00 m H4 = 4.24 m
H5 = 0m H6 = 0m
Design Calculations
Step-1 2/3H1
4Su 10.41
K A 1 m
gH
= 0 TH2
2.829
0 . 15 g H 2 Pe Ps
Pe
H H
H 1 n 1
3 3
= 54.339 KN/m2
ps K A qs = 0.000 KN/m2
TH 3 S A
DL 3 = 415.08 KN Bond Length Required = BL3 = 13.84
Cos
Larger of (UBL)
11.3 m
4.0 m
9.7 m
ii) 4.5m
4.0 m
(UBL)
6.80 m
24 m
0.2H = 3.048 m
11.3 m
4.0 m
(UBL)
15.24 m
9.7 m
4.0 m
UBL1 = 13 m (UBL)
6.80 m
4.24 m
0.2H = 3.048 m
UBL2 = 9.8 m
45 o
Strand Design
= 110.149 KN
Factor of safety = 2
2
13 2 H
M1 H 1 Pe 1 Ps
54 2
= N/A KN-m
Mid-Span Moment =
M ms Rx
Pe .x 3 Px
2 2
s H 2 H 1 x.H 2
4 H H 1 2 H 2
= N/A KN-m
2
13 2 H
M1 H 1 Pe 1 Ps
54
= 117.7 KN-M/M
2
1
M2 H 2,3,4 2 Pe Ps
10
= 97.87 KN-M/M
Max. Moment = 117.735 KN-M/M = 26.4572 Kip-ft/ft
127.03 Kip-ft
*Nominal Capacity of 2ft dia Pile (with 10-#8 bars evenly distributed around parameter)
Mu/ФMn = 50% OK
red Systems', (June
tration
m
3.048 m
3.048 m
Embedment Length Calculations using WANG-REES (1986) Method (Clays)
Su = 150 kPa
Wedge Wedge
Rankine Minimum
Scr Resistance Resistance Group Flow Resistance WANG-REES Total Passive Factor of
Toe Depth Continuous (Eq.B-9) Sigle Pile Effect (Eq-B- Eq-B-12 Force (W-R) Safety
(Eq. B-13) Resistance
(Eq-B-8) 10)
Lahore
Project:
jimiansahib@yahoo.com
Input Data qs
H1
Depth of Excavation = H = 20.26 m
qs = H2 U BL
Surcharge Load 9.58 KN/m2
◦ H3
Co-efficient of friction = Ф= 34 H
No of Anchors to be used = 4
H5 = 4.66 m
◦
Inclination of Anchor = θ= 20 Hn+1= H5 = 4.66 m
Design Calculations
Step-1 2/3H1
Pressure Calculations
TH1
f'
K A tan 2 45
2
TH2
= 0.283
TH3
Pressure due to Soil
TH4
0 . 65 K A g H 2
Pe
H H
H 1 n 1
3 3 2/3Hn+1
= 75.82 KN/m2
Pe Ps
Pressure due to Surcharge
ps K Aqs
= 2.708 KN/m2
Horizontal Anchor Loads
2 H H
TH1 H1 2 Pe H1 2 Ps = 272.8 KN/m
3 2 2
H H H H
TH 2 2 3 Pe 2 3 Ps = 345.5 KN/m
2 2 2 2
H H H H
TH 3 3 4 Pe 3 4 Ps = 369.1 KN/m
2 2 2 2
H 23 H H
TH 4 4 H5 Pe 4 5 Ps = 360.2 KN/m
2 48 2 2
Anchor Design
TH 3 S A
DL 3 = 479.2 KN Bond Length Required= BL3 = 9.584 m
Cos
TH 4 S A
DL 4 = 467.6 KN Bond Length Required= BL4 = 9.352 m
Cos
Tu LN tan f
L= BL = 7.084 m
> 479.2 OK
Failure Plane
Design of Unbonded Length
Larger of H2
ii) 4.5m H3
x is larger of
Strand Design
= 110.1 KN
Factor of safety = 2
2
13 2 H
M1 H 1 Pe 1 Ps
54 2
= 86.47 KN-M/M
1
M2 H 2,3,4 2 Pe Ps
10
= 173.5 KN-M/M
= 38.98 Kip-ft/ft
### Kip-ft
*Nominal Capacity of 2ft dia Pile (with 10-#8 bars evenly distributed around parameter)
Mu/ФMn = 83% OK
Ref: Table 12
Sand & Gravel Loose (4-10) 145 Sand & GravelLoose (4-10)
Medium Dense (11-30) 220 Sand & GravelMedium Dense (11-30)
Dense (31-50) 290 Sand & GravelDense (31-50)
Sand Loose (4-10) 100 SandLoose (4-10)
Medium Dense (11-30) 145 SandMedium Dense (11-30)
Dense (31-50) 190 SandDense (31-50)
Sand & Silt Loose (4-10) 70 Sand & SiltLoose (4-10)
Medium Dense (11-30) 100 Sand & SiltMedium Dense (11-30)
Dense (31-50) 130 Sand & SiltDense (31-50)
Silty-Clay Stiff (10-20) 30 Silty-ClayStiff (10-20)
Hard (21-40) 60 Silty-ClayHard (21-40)
m Dense (11-30)
ense (11-30)
Embedment Length Calculations using WANG-REES Method
(m) (KN/m) (KN/m) (KN/m) (KN/m) (KN/m) (KN/m) (KN/m) (KN) (KN) (KN)
0.5 48.37 0.25957 18.62 12.99 42.74 318.36 44.73 42.74 10.68 16.80 42.23
1 148.73 0.75957 93.98 45.78 100.54 636.72 89.46 89.46 43.73 34.50 42.23
1.5 301.11 1.25957 221.35 88.81 168.57 955.08 134.18 134.18 99.64 53.09 42.23
2 505.48 1.75957 400.72 142.08 246.85 1273.44 178.91 178.91 177.92 72.57 42.23
2.5 761.86 2.25957 632.09 205.58 335.35 1591.80 223.64 223.64 278.56 92.95 42.23
3 1070.24 2.75957 915.46 279.32 434.10 1910.16 268.37 268.37 401.56 114.22 42.23
3.5 1430.63 3.25957 1250.84 363.29 543.07 2228.53 313.10 313.10 546.92 136.39 42.23
4 1843.01 3.75957 1638.22 457.49 662.29 2546.89 357.82 357.82 714.65 159.45 42.23
4.5 2307.40 4.25957 2077.61 561.94 791.73 2865.25 402.55 402.55 904.75 183.40 42.23
5 2823.80 4.75957 2568.99 676.61 931.42 3183.61 447.28 447.28 1117.21 208.24 42.23
5.5 3392.19 5.25957 3112.39 801.52 1081.33 3501.97 492.01 492.01 1352.03 233.98 42.23
6 4012.59 5.75957 3707.78 936.67 1241.49 3820.33 536.74 536.74 1609.22 260.62 42.23
6.5 4685.00 6.25957 4355.18 1082.05 1411.88 4138.69 581.47 581.47 1888.77 288.15 42.23
7 5409.40 6.75957 5054.58 1237.67 1592.50 4457.05 626.19 626.19 2190.68 316.57 42.23
7.5 6185.81 7.25957 5805.98 1403.52 1783.36 4775.41 670.92 670.92 2514.96 345.88 42.23
8 7014.23 7.75957 6609.39 1579.61 1984.45 5093.77 715.65 715.65 2861.60 376.09 42.23
8.5 7894.64 8.25957 7464.80 1765.93 2195.78 5412.13 760.38 760.38 3230.61 407.19 42.23
9 8827.06 8.75957 8372.21 1962.49 2417.34 5730.49 805.11 805.11 3621.98 439.19 42.23
9.5 9811.48 9.25957 9331.62 2169.29 2649.14 6048.86 849.83 849.83 4035.72 472.08 42.23
10 10847.91 9.75957 10343.04 2386.31 2891.18 6367.22 894.56 894.56 4471.81 505.86 42.23
Factor of
Safety
0.00
0.18
0.57
1.05
1.55
2.06
2.57
3.06
3.54
4.01
4.46
4.89
5.31
5.72
6.11
6.48
6.84
7.19
7.52
7.85
8.16
REPUBLIC ENGINEERING CORPORATION
Description: 2ft dia piles with Two rows of anchors Designed by: Engr. Imran
jimiansahib@yahoo.com
Input Data qs
qs = H1 U BL
Surcharge Load 0 KN/m2
BL
Soil unit weight = γsoil = 20.73 KN/m3
◦ H2
Co-efficient of friction = Ф= 34 H
No of Anchors to be used = 1
H1 = 2.1 m H2 = 4.1 m H3 = 0m H4 = 0m
H5 = 0m H6 = 0m
◦
Inclination of Anchor = θ= 15 Hn+1= H2 = 4.1 m
Design Calculations
Step-1 2/3H1
= 0.283
TH3
Pressure due to Soil
2/3Hn+1
0 . 65 K A g H2
Pe Ps
Pe
H H
H 1 n 1
3 3
= 45.03 KN/m2
ps K Aqs
= 0 KN/m2
Horizontal Anchor Loads
23H 2 10HH1 H2
TH 1 Pe H1 Ps
54 H H1 2 = 205 KN/m
2 H H
TH1 H1 2 Pe H1 2 Ps = N/A KN/m
3 2 2
H 23 H H
TH 2 2 H 3 Pe 2 3 Ps = N/A KN/m
2 48 2 2
2 H H
TH1 H1 2 Pe H1 2 Ps = N/A KN/m
3 2 2
H H H H
TH 2 2 3 Pe 2 3 Ps = N/A KN/m
2 2 2 2
H 23 H H
TH3 3 H4 Pe 3 4 Ps = N/A KN/m
2 48 2 2
2 H H
TH1 H1 2 Pe H1 2 Ps = N/A KN/m
3 2 2
H H H H
TH 2 2 3 Pe 2 3 Ps = N/A KN/m
2 2 2 2
H H H H
TH 3 3 4 Pe 3 4 Ps = N/A KN/m
2 2 2 2
H 23 H H
TH 4 4 H5 Pe 4 5 Ps = N/A
2 48 2 2
For Penta Anchored
2 H H
TH1 H1 2 Pe H1 2 Ps = N/A KN/m
3 2 2
H H H H
TH 2 2 3 Pe 2 3 Ps = N/A KN/m
2 2 2 2
H H H H
TH 3 3 4 Pe 3 4 Ps = N/A KN/m
2 2 2 2
H H H H
TH 4 4 5 Pe 4 5 Ps = N/A KN/m
2 2 2 2
H 23 H H
TH 5 5 H6 Pe 5 6 Ps = N/A KN/m
2 48 2 2
Anchor Design
TH 3 S A
DL 3 = N/A KN Bond Length Required= BL3 = N/A m
Cos
TH 3 S A
DL 3
Cos
TH 4 S A
DL 4 = N/A KN Bond Length Required= BL4 = N/A m
Cos
TH 5 S A
DL 5
Cos = N/A KN Bond Length Required= BL5 = N/A m
Tu LN tan f
L= BL = 6.474 m
> 258.9 OK
Failure Plane
Design of Unbonded Length
H1
Larger of
ii) 4.5m
H 5 H 6 cos 45 f 2
2
UBL4 = H 5 H 6 cos 45 f 2 or 4.5 m
2
= N/A
f
UBL5 = H 6 cos 45 2 or 4.5 m
2
= N/A
Strand Design
= 110.1 KN
Factor of safety = 2
2
13 2 H
M 1 H 1 Pe 1 Ps
54 2
= 47.8 KN-m
= 3.813 m
2
R HPe H Ps T1
3
= 69.64 KN/m
Mid-Span Moment
= M ms Rx
Pe .x 3 Px
4 H H 1 2 H 2
2 2
s H 2 H 1 x.H 2
= 177 KN-m
2
13 2 H
M1 H 1 Pe 1 Ps
54 2
= N/A KN-M/M
1
M2 H 2,3,4 2 Pe Ps
10
= N/A KN-M/M
Max. Moment = 177 KN-M/M
= 39.78 Kip-ft/ft
### Kip-ft
*Nominal Capacity of 2ft dia Pile (with 10-#8 bars evenly distributed around parameter)
Mu/ФMn = 85% OK