Professional Documents
Culture Documents
Feeder Automation Within The Scope of Substation Automation: ABSTRACT - This Paper Presents The
Feeder Automation Within The Scope of Substation Automation: ABSTRACT - This Paper Presents The
ABSTRACT--This paper presents the automatic feeder line switches. It does not
commonly used approaches to feeder involve long distance communications at all
automation (FA) and introduces a practical and, therefore, can only implement very
approach to implementing feeder automation limited functions of feeder automation. The
that is virtually a simple extension of the distributed solution tackles the problem by
substation automation by covering the feeders. organizing the automated feeder line switches
FA is usually implemented either based on a into groups or teams [2]. The neighboring
centralized approach or a distributed approach. teams communicate locally to detect and
Normally a distributed approach is simple and isolate faulted feeder sections and quickly
flexible. It can be implemented in a small restore the service to the healthy sections. The
scale but can only provide limited FA whole process is completed based on
functions. Instead, a centralized approach is predefined local logics. It does not require the
capable of providing complete FA functions knowledge of feeder network topology and
but requires large scale implementation. The therefore its operation does not rely on the
approach presented in this paper is of the centralized master station in the control center.
advantages of both the distributed solutions This approach significantly improves the FA
and the centralized solutions. It can achieve all functionalities but is still subject to some
FA objectives without requiring additional limitations. The centralized solution is actually
communication and hardware facilities a full scale distribution automation system. It
compared to the automated distributed requires the full knowledge of the distribution
solutions, e.g., the IntelliTeam approach [2 ]. network and relies on the communication with
the control center. This approach can
Index Terms — Feeder Automation, implement all feeder automation functions but
Distributed Solutions, Distribution requires big initial investment and normal
Automation. operation cost.
608
3.3 Centralized Solution through normally opened tie-switches that
The centralized solution of feeder may belong to other substations. Under certain
automation is really part of the full operation conditions, some of the feeder
distribution automation [1]. This approach sections of one feeder may be fed by other
requires the full knowledge of the distribution feeders due to network reconfiguration for
network, including the network topology and maintenance, fault restoration or load
operation parameters. The FA functions are transferring. This makes the SA based feeder
centrally implemented and all automatic automation a challenging task in practical
switches are controlled by the control center. implementations. This problem can be well
This approach fully relies on the resolved by installing a dual feeder terminal
communication facilities between the unit (FTU) on a tie-switch linking two feeders
individual switches and the control center. The that belong to two different substations. The
disadvantage of this approach is its dual FTU will allow both substations to
requirement of large scale implementation. monitor and control the tie-switch. It can also
allow both sides to download the basic
4. FA: an Extension of SA information about the operation condition of
The proposed solution of feeder the feeder, such as the available capacity for
automation by this paper is a semi-centralized picking up more loads. This information can
approach which is virtually an extension of the be read and used by the other side to carry out
substation automation (SA) by covering the load transferring or service restoration.
connected feeders. Normally, a substation is
automated prior to its feeders. It is in nature The FA unit in each SA master station is
that the feeder automation can be responsible for monitoring and controlling its
implemented within the scope of SA by own feeder switches, while the tie-switches
extending the communication network to are monitored and controlled by both sides.
cover the automated feeder switches. Each The FA unit is also modeled with the network
substation will be responsible for monitoring topology of all feeders in its scope. Simple
and controlling the feeders within its scope, as operational logics are proposed to deal with
shown in Fig. 1. the typical operation scenarios:
Sub A Sub B
FB A FB B
(A)
N.O.
However, in a real distribution system a feeder Tie-Switch T
may be connected to several other feeders
609
The tie-switch capacities are calculated at both
sides by the corresponding FA modules in the
two substations and are downloaded to the
dual FTU for other side to read.
FB A FB B
(A)
SW C
N.O.
F
SW D SW E tie-switch T
It can be seen from the figures that the FDIR Sub A Sub B
SW D SW E tie-switch T
detects the fault location and issues
tripping commands to the adjacent
switches of the faulted section to isolate
the fault (Fig.2. (B)).
3. FA unit issues a control command to
reclose the feeder breaker to restore the
service for the healthy upstream sections
(Fig. 2 (C)).
4. FA unit checks the capacity of the
tie-switch connected to another substation
feeder and issues a control command to
close the switch if its capacity is sufficient
to pick up the load (Fig.2. (B)).
610
It can be seen from Fig. 3 that the FDIR
function is carried out by the FA units in both
substations. The detailed procedures are
described as follows:
1. the fault occurs at location F and feeder
breaker B trips right away.
2. Because the fault is occurred at the study
feeder side of tie-switch T that is out of
the scope of substation B, the FA unit in
substation B opens tie-switch T to isolate
the fault (Fig. 3 (B)).
3. FA unit in substation B recloses the feeder
breaker FB to restore the service for
feeder B (Fig. 3 (C)).
4. At the same time, the FA unit in
substation A receives the fault report from
switches E and tie-switch T, from which it
identifies the faulted section and isolate
the fault by opening switches E and D
(Fig. 3 (B)).
5. It then closes tie-switch T and C to restore
the service for the remaining healthy
sections, as shown in Fig. 3(C).
Scenario 3: Assume a few feeder sections of It can be seen from Fig. 4 that the FDIR
the study feeder in substation A are transferred function is carried out by the FA unit in the
to another feeder and a fault occurs in one of study feeder substation with the following
the remaining sections, as shown in Fig. 4: procedures:
1. The fault occurs at location F and feeder
breaker A trips right away.
2. FA unit in substation A detects the fault
location and issues control commands to
open switches B and C to isolate the fault
(Fig. 4. (B)).
3. FA unit in substation A closes the feeder
breaker A to restore service to the
upstream feeder sections (Fig. 4. (C)).
4. FA unit in substation A checks the
capacity of feeder B based on the data
from tie-switch T and figure out the
capacity of switch D. If available, it closes
switch D to restore service to the healthy
downstream sections, as shown in Fig.
4(C).
611
The proposed approach can also effectively “Advanced feeder Automation Is Here”, IEEE
solve the problems of other FA objectives in a Power&Energy Magazine, Sept./Oct. 2005
similar way as to solving FDIR problems. [3]. J. Y. Fan, L. Zhang, J. D. McDonald,
"Distribution Network Reconfiguration:
5. Conclusion Single Loop Optimization," IEEE/PES Trans.
This paper presented a basic analysis of On Power Systems, Vol. 11, No. 3, August
the existing FA solutions, including the 1996, pp 1643-1647.
semi-automatic approach, distributed [4]. W. H. Kersting, “Distribution System
approach and centralized approach, and Modeling and Analysis”, CRC Press, 2002.
introduced a practical approach that is of the ISBN: TK3001.K423 2001.
advantages of both distributed and centralized
solutions without involving additional
software complexity and hardware demands Jiyuan (Ji-Yuan) Fan (SM’95) received Ph.D.
compared to the distributed solution. This degree in ECE from Clarkson University,
approach can be easily implemented as an Potsdam, New York in 1989. He worked with
extension of the substation automation Advance Control Systems for more than 12
function. years. He is currently with Beijing Sifang
Automation in Beijing, China.
6. References
[1]. Gary Ockwell, “Implementation of Xiaoling Zhang received MS. degree in ECE
Network Reconfiguration for Taiwan Power from Wuhan University, China in 2003. She
Company”, IEEE PES general meeting worked with Shanghai TEPIA Technology Co.,
proceeding, 2003, #0-7803-7989-6/03. Ltd. in 2003-2004. She joined Beijing Sifang
[2]. D. M. Staszesky, D. Craig, C. Befus, Automation in 2004.
612