SUBSEA INSTALLATION OF

VASHISHTA & S1 DEVELOPMENT


PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 1 0f 18

Procedure for Re-instatement of cofferdam

Oil and Natural Gas Corporation Ltd.

SUBSEA INSTALLATION OF VASHISHTA & S1 DEVELOPMENT


PROJECT

Procedure for Re-instatement of cofferdam

for

Provision of Services for Construction of Cofferdam and Beach


Pull Support Activities

0 18.01.2017 Issued for review BB KS GV KA


PREPARED BY CHECKED BY APPROVED BY PROJ. MANAGER
REV. DATE DESCRIPTION
(Initials) (Initials) (Initials) (Initials)
DOCUMENT REVISIONS
Sections changed in last revision are identified by a line in the right margin
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 2 0f 18

Procedure for Re-instatement of cofferdam

TABLE OF CONTENTS

1. INTRODUCTION .......................................................................................................................... 3
2. SUB-CONTRACTOR’S SCOPE OF WORK ................................................................................ 4
2.1 Purpose of this document ............................................................................................................. 5
2.2 Definitions .................................................................................................................................... 5
2.3 Abbreviation ................................................................................................................................. 5
2.4 References ................................................................................................................................... 6
3. QHSES ........................................................................................................................................ 7
3.1 QHSE considerations ................................................................................................................... 7
3.2 QA / QC considerations ................................................................................................................ 7
3.3 Document Responsibilities ........................................................................................................... 7
4. EQUIPMENT SPREAD ................................................................................................................ 7
5. TECHNICAL INFO ....................................................................................................................... 8
6. SCOPE OF PROCEDURE ........................................................................................................... 8
7. TASK PLAN ................................................................................................................................. 9
APPENDIX A ......................................................................................................................................... 18
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 3 0f 18

Procedure for Re-instatement of cofferdam

1. INTRODUCTION

Oil & Natural Gas Corporation Limited (ONGC), here-in after called as 'Company', is currently involved
with the exploration in several deep-sea fields off the east coast of India. As a part of the overall
development plan, ONGC intends to develop the Vashishta and S1 fields.

The Vashishta field shall comprise two wells (VA-DA and VA-DB) and is located in water depths of 500 to
700 meters. The S1 field shall comprise two wells (S1-A and S-AC) and is located in water depths of
approximately 250 to 420 meters.

ONGC have decided to tie back S2-AB to the existing G1 subsea facilities. Accordingly, S2-AB and all
associated equipment items are not part of this Contract.

The in-line tees located on the pipeline at the S2-AB location will be retained for future tie-ins.

ONGC proposes to produce Vashishta and S1 fields concurrently through in-field flow lines using daisy
chain architecture.

Twin subsea pipelines to the onshore terminal at Odalarevu will be installed.

The onshore processing terminal at Odalarevu is located about 90 km to the South- East of Rajahmundry.
This onshore processing terminal at Odalarevu receives hydrocarbons from the GS-15 field and
processing facilities are under construction to receive and process hydrocarbons from the G-1 and GS-15
fields located in the KG basin. The processing facility for gas from Vashishta and S-1 fields will be set up
adjacent to the existing terminal.
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 4 0f 18

Procedure for Re-instatement of cofferdam

2. SUB-CONTRACTOR’S SCOPE OF WORK

The main scope of work is listed below:


 Construction of access road to LFP.
 Exposure of existing lines near the holdback anchor pile locations.
 Construction of Cofferdam including access area.
 Pre-trenching from tie-in points to LFP.
 Pre-trenching from LFP to 150m seawards.
 Installation of Holdback anchor system.
 Set-up and de-rig of Beach pull equipment.
 Support operations during Beach Pull.
 Backfilling from tie-in points to LFP.
 Backfilling LFP to 150m seawards.
 Re-instatement of the beach pull site.
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 5 0f 18

Procedure for Re-instatement of cofferdam

2.1 Purpose of this document

The purpose of this document is to describe in detail the re-instatement works on the cofferdam upon
completion of beach pull operations.

The works required will be presented in the format of step by step task plans and drawings which shall be
used by construction personnel to perform the work.

2.2 Definitions

Name Description
COMPANY/ONGC Oil and Natural Gas Corporation Ltd.
CONTRACTOR JRMSA-BMD-LTHE Consortium
SUB-CONTRACTOR Narmada Offshore Constructions Pvt Ltd
“WORK” shall mean all activities all activities
necessary or incidental to be carried out, including
WORK all services to be rendered by the SUB-
CONTRACTOR in accordance with the SUB-
CONTRACT.

2.3 Abbreviation

NAME DESCRIPTION
COMPANY Oil & Natural Gas Corporation Limited (ONGC)
CONTRACTOR McDermott
GP General Purpose
HAT High Astronomical Tide
HSEQS Health, Safety, Environment Quality Surveyor
KP Kilometre Point
LAT Lowest Astronomical Tide
MDR McDermott
MPI Magnetic Particle Inspection
MSL Mean Sea Level
MT Metric Ton
N/A Not Applicable
SWL Safe working Load
TBA To be advised
WT Wall Thickness
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 6 0f 18

Procedure for Re-instatement of cofferdam

2.4 References

 R3137-IN-A-PRC-65255.026-1_Cofferdam strut & waler-Layout1


 R3137-IN-A-PRC-65255.216-1_Access road layout sht-1-Layout
 R3137-IN-A-PRC-65255.213-1_sheet pile alignment frame sht-3 (GU-15N)-sht-3
 R3137-IN-A-PRC-65255.212-1_sheet pile alignment frame sht-2 (GU-15N)-sht-.2
 R3137-IN-A-PRC-65255.211-1_sheet pile alignment frame sht-1 (GU-15N)-sht-.1
 R3137-IN-A-PRC-65255.162-0_Trenching plan @LFP to tie in point-Layout1
 R3137-IN-A-PRC-65255.161-1_Trenching plan @cofferdam-Layout1
 R3137-IN-A-PRC-65255.101-0_Cable Spooler for Beach Pull Reel Lifting Arrangement
 R3137-IN-A-PRC-65255.092-0_Beach Pull Cable Reel Lifting Arrangement
 R3137-IN-A-PRC-65255.071-0_Beachpull Cable Reel
 R3137-IN-A-PRC-65255.062-0_JRM Cable Spooler-Sectional View
 R3137-IN-A-PRC-65255.062-0_JRM Cable Spooler-Sectional View
 R3137-IN-A-PRC-65255.062-0_JRM Cable Spooler-Sectional View
 R3137-IN-A-PRC-65255.062-0_JRM Cable Spooler-Sectional View
 R3137-IN-A-PRC-65255.029-0_lucker winch arrangment-Layout1
 R3137-IN-A-PRC-65255.027-0_Taper sheet pile-1
 R3137-IN-A-PRC-65255.021-1_Beach Pull Equipment layout sht-1-Layout1
 R3137-IN-A-PRC-65255.014-1_Cofferdam section view sht2-Layout1
 R3137-IN-A-PRC-65255.013-1_Cofferdam section view sht1-Layout1
 R3137-IN-A-PRC-65255.013-1_Cofferdam section view sht2-Layout1
 R3137-IN-A-PRC-65255.013-1_Cofferdam section view sht3-Layout1
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 7 0f 18

Procedure for Re-instatement of cofferdam

3. QHSES

3.1 QHSE considerations

All activities / operations described in this document will be executed in accordance with the
CONTRACTOR’s HSE Plan and SUN-CONTRACTOR’S Emergency Response Plan and in accordance
with the COMPANY’s HSE requirements for CONTRACTORs.

Prior to commencing the works, Task Risk Assessment (TRA) will be performed on individual tasks. The
purpose of the TRA is to identify possible hazards for a specific activity and to identify any mitigating
actions required to perform the task safely. The TRA result will also be presented on worksheets collated
in the Risk Assessment Register. TRA will be performed as part of procedure review or also conducted
prior to commencement of work. A TRA toolbox talk shall be conducted with the workforce prior to
undertaking any work activities.

3.2 QA / QC considerations

All activities and operations shall be performed and completed in accordance with approved procedures,
Drawings, and specifications.

The Field Engineer and the work site supervisors are responsible for monitoring the progress of the work
and recording pertinent information as dictated in the task plan.

3.3 Document Responsibilities

Field Engineer is responsible for preparing and updating this document.

Construction manager is responsible for checking this document and ensuring it complies with the overall
project requirements.

Project Manager is responsible for approving this document.

4. EQUIPMENT SPREAD

ITEM CAPACITY
Crawler Crane - 1 Nos 100 Ton
Crawler Crane - 1 Nos 75 Ton
Crawler Crane - 2 Nos 50 Ton
Vibro hammer - 1 Nos 415
Excavator - 1 Nos Ex450
Excavator - 1 Nos Ex350
Hydra - 1 Nos 14 Ton
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 8 0f 18

Procedure for Re-instatement of cofferdam

Trucks - 4 Nos 5 units capable


Cutting sets 3 Sets
Grinding machines 2 Nos
Walk Way between access bund and Sheet Piles 2 Nos

5. TECHNICAL INFO

ITEM # ITEM DESCRIPTION DETAIL


1 Length of Cofferdam 150m
2 Width of Cofferdam 14m
3 Length of Each Strut 13.4 Mtrs
4 Total Struts installed 16 Nos
5 Length of Longitudinal Walers on South Side 87.5 Mtrs
6 Length of Longitudinal Walers on North Side 87.5 Mtrs
7 Length of Wing Wall Waler 38 Mtrs
7.376 Mtrs
8 Length of Diagonal Struts – Each Side
14.447 Mtrs

The expected Max. lift weight including rigging and contingency is 5 Tons.

6. SCOPE OF PROCEDURE

Initial Status
 Pipeline and Beach-Pull Operations are completed.
 Ready for Re-instatement
Preparation Works

 All material and equipment are prepared for the operation.


 TRA session conducted with all the crew involved in the operations is in place.
 Tool box talk carried out and to be attended by all the crew and other involves parties
 Shifting of equipment’s and tools and tackles to Retraction area / Access Bund.
Task Summary
 Backfill the Trench between Sheet Piles.
 Cut the strut joint at both sides of strut.
 Shift the struts to stack yard.
 Cut the waler and sheet pile joints.
 Lift and shift the Walers to stack yard.
 Cut the Diagonals at weld joints.
 Lift and shift the diagonals.
 Cut the wing wall waler and sheet pile joint.
 Lift and shift the wing wall Walers.
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 9 0f 18

Procedure for Re-instatement of cofferdam

 Retrieve the Sheet pile with vibro hammer.


 Shift the sheet piles to stack yard.
 Extraction of hold back anchor piles at lucker winch location.
 Extraction of hold back piles at north bund.
 Removal of stones with excavator and dump at stack yard with the help of trucks.
 Removal of fencing and temporary sheds.
 Removal of light poles.
 Removal of access road.
Weather limitations

 No Work if Swell height is more than 1.9 Mtrs.


 No Work in High Tides at Night shift.

7. TASK PLAN

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT

Back Filling of Trench between Sheet Piles

Conduct Tool Box talk and TRA with all the parties in the
1 Site HSE
job.
Position the sand bags and / or carry out the necessary
works near LFP Tie-In point to facilitate Tie-in of Onshore
and Offshore Pipelines.
2 Onshore Contractor
All the necessary works required for maintaining the
trench to facilitate Tie-in shall be performed.
R3137-IN-A-
PRC-
Prior to start of work measure the top of pipe elevation 65255.161_2_
3 FE/SS
and submit to contractor for review Trenching plan
Make sure access on north/south safe to use for both @ cofferdam-
4 Layout 1
excavation and trucks.

Position the Excavator Ex350 at Sand Storage Area for


5 EX350 / SS
loading of sand on to trucks.
Position Excavator Ex450 on North bund for backfilling of
6 EX450 / SS
sand to the trench.
Start transferring of sand from sand storage area to North
7 Ex350 / Trucks / SS
bund using Excavator Ex350 and 8 No’s of trucks.
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 10 0f 18

Procedure for Re-instatement of cofferdam

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Backfill the cofferdam trench using EX450 on north bund,
8 and have to monitor the filling not to dump stones while Ex450/SS
transferring the sand by excavator.
Trench depth shall be taken continuously to monitor the
9 FE
sea bed depths
Continue backfilling works up to CH 120 till the required
depths are achieved.
EX350 / Ex450 /
10
Refer Attached Table in Appendix A for sea bed depths Trucks / FE
required after backfilling. Top of pipe should be buried
min 2.0M
R3137-IN-A-
Upon completion of backfilling in the trench up to CH 120 PRC-
and acceptance by MDR, the gap between sheet piles 65255.161_2_
rock berm shall be filled with sand based on availability Trenching plan
of sand @ cofferdam-
Layout 1
EX350 / Ex450 /
11
Trucks / SS

The remaining CH 120 to CH 150 trench backfilled after


12 Info
MDR’s permission.
Removal of Struts, Walers and Diagonals

13 Conduct TRA and Tool Box. Site HSE

Inspect all the Cutting / Lifting gears required for cutting, Site HSE / FE / SS
14
removal and shifting. / WS / RF R3137-IN-A-
PRC-
Position all the cutting gears required for cutting of Weld
15 SS / RF 65255.204_0_
Joints.
cofferdam
Erect barriers in lifting Area / Along Access path till construction
16 SS / RF
designated destination as required. sequence sht-
4-layout 4
Position the 45T crane on north bund and Rig-up the lift
rigging on both sides of the strut. Hook - Up the Tag lines
17 as needed. 45T / RF

Note: Each sling is rated 10 Ton WLL.


SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 11 0f 18

Procedure for Re-instatement of cofferdam

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Clear the area for readiness of lifting.

With the instruction from rigger foreman, start cutting of


weld joints on both sides of the strut at onshore side.

18 45T / Cutter / RF

Upon cutting, lift the Waler slowly i.e. in controlled


manner.
Locate the strut on north bund.
19 45 T / RF
Shift the struts to stockyard using Hydra.
Repeat the steps 14-19 for removal of all the struts up
last.

Qty to be removed – 17 No’s

20 45 T / Cutter / RF
R3137-IN-A-
PRC-
65255.204_0_
cofferdam
construction
sequence sht-
4-layout 4

Upon completion of removal of struts up to CH 100,


Position the 45T crane on north bund and Rig-up the lift
21 rigging on both sides of the Waler. Hook - Up the Tag 45T / RF
lines as needed.
Note: Each sling is rated 10 Ton WLL.
Clear the area for readiness of lifting.

With the instruction from rigger foreman, start cutting of


22 all the weld joints between waler to sheet pile, and 45T / Cutter / RF
between two Walers.
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 12 0f 18

Procedure for Re-instatement of cofferdam

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT

Upon cutting, lift the Waler slowly i.e. in controlled


manner.
Locate the Waler on north bund.
23 45T RF
Shift the waler to stockyard using Hydra.
Repeat the steps 21-23 for removal of Walers up to CH
100.
24 45T / Cutter / RF
Qty to be removed – 4 No’s (2 No’s on each bund.)
Remaining struts, walers and diagonals will be removed
25
after MDR’s instruction
Upon completion of removal of struts, Position the 45T
crane on north bund and Rig-up the lift rigging on both
26 sides of the diagonal. Hook - Up the Tag lines as needed. 45T / RF

Note: Each sling is rated 10 Ton WLL. R3137-IN-A-


Clear the area for readiness of lifting. PRC-
65255.204_0_
With the instruction from rigger foreman, start cutting of cofferdam
all the weld joints between diagonal to wing wall Waler. construction
sequence sht-
4-layout4

27 45T / Cutter / RF

Upon cutting, lift the Waler slowly i.e. in controlled


manner.
Locate the diagonal on north bund.
28 45T / RF
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 13 0f 18

Procedure for Re-instatement of cofferdam

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Shift the diagonals to stockyard using Hydra.
Repeat the steps 26-27 for removal of all the diagonals.
29 45T / Cutter / RF
Qty to be removed – 4 No’s (2 No’s on each bund.)
Upon completion of removal of diagonals, Position the
100T crane at the end of north bund and Rig-up the lift
30 rigging on both sides of the longitudinal waler. Hook - Up 45T / RF
the Tag lines as needed.
Note: Each sling is rated 10 Ton WLL.
Clear the area for readiness of lifting.

With the instruction from rigger foreman, start cutting of


all the weld joints between diagonal to wing wall Waler.

31 45T / Cutter / RF

Upon cutting, lift the Wing Waler slowly i.e. in controlled


manner.
Locate the waler on north bund.
32 45T / Cutter / RF
Cut the Waler in to pieces for easy handing and shift the
same to stockyard using Hydra.
Retraction of sheet piles
1 Perform Tool Box Talk and TRA. Project HSE
Perform Visual Inspection of High Pressure hoses,
Elastomers, and other components of the system. R3137-IN-A-
Necessary checks shall be performed on all the safety PRC-
2 features of the system including safety check valve etc. SS / RF 65255.201_0_
Cofferdam
Function test the Vibro Hammer 416 prior to the start of construction
Operations. sequence sht-
Visual Inspection of all the tools and lifting gears used for 1-Layout
3 extractor of sheet piles. Site HSE / FE / RF
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 14 0f 18

Procedure for Re-instatement of cofferdam

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Inspection shall take place on all the lifting gears prior to
start of each shift.
Upon completion of Inspection, shift the Power Pack and
Vibro hammer with 45 Ton Crane to the end of cofferdam.
4 SS / 45T / RF
Locate 100ton crane on end of south bund for start of
sheet pile extraction.
Position the guide frame on sheet piles and place
6 walkway on top of guide frame for easy access to the SS / 45T / RF
sheet pile.
Hook-up the vibro hammer to sheet pile and start
7 SS / 100T / RF
extracting for 1 Mtr. from the existing level.
Upon extraction to 1 Mtr., deploy the riggers to connect
the choker sling to sheet pile and hook it to the auxiliary
hook on the crane.

8 SS / 100T / RF

R3137-IN-A-
PRC-
65255.201_0_
Cofferdam
construction
Upon extraction of sheet pile to the seabed level, recover sequence sht-
9 the sheet pile from grove using auxiliary hook on the 100T SS / 100T / RF 1-Layout
crane.
Relocate the guide frame and walk way as needed and
continue extraction of sheet piles till the corner pile is
10 SS / 100T / RF
reached.

11 Shift the sheet piles from access bund to the stock yard. SS / Hydra / RF

Upon extraction up to corner pile, repeat the steps from


Steps 7 to 11.
12 SS / 100T / RF
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 15 0f 18

Procedure for Re-instatement of cofferdam

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Removal of stones
After the completion of works which are commence
based upon MDR’s instruction i.e. Back filling of CH 120
to CH 150 , removal of struts, walers and diagonals from Info
CH 100 to CH 150 and extraction of sheet piles CH 100
to CH 150 completed, removal of stones should be start.
Conduct Tool Box talk with the excavator operators, shift
supervisors and all the personnel involved in the
operations.
FE / Excavator /
1
Truck
Care shall be taken during the entire operations to
prevent damage to the newly installed pipeline /
umbilical’s.
Position the excavator EX450 at the end of cofferdam
for commencement of rock removal.
R3137-IN-A-
PRC-
65255.201_0_
FE / Excavator / Cofferdam
2
Truck construction
sequence sht-
1-Layout

Locate the truck at the end of cofferdam in reverse


direction (heading towards onshore).
Slowly start removing the rock from sea bed and load
onto the trucks designated by replacing the trucks as and
when needed. FE / Excavator /
3
Truck
FE / SS shall be present on access bund during the entire
operational duration.
Upon reaching to the KP0.75, relocate the Excavator
Ex450 on south bund start removal of rocks.
FE / Excavator / R3137-IN-A-
4
During the entire operations, care shall be taken that no Truck PRC-
excessive loading / free rocks above designed truck 65255.201_0_
levels. Cofferdam
Excavator Ex350 shall be located on at KP0.75 for FE / Excavator / construction
5
removal of rocks on south bund. Truck sequence sht-
The rocks recovered shall be dumped at the designated 1-Layout 1
6 area owned by Narmada. Info
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 16 0f 18

Procedure for Re-instatement of cofferdam

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Upon completion of rock removals and demobilization of
Narmada’s temporary equipment, the site shall be
restored back to the original condition and handed over
to MDR.
Hold back piles removal at lucker winch location
1 Perform Tool Box Talk and TRA. Project HSE
Perform Visual Inspection of High Pressure hoses,
Elastomers, and other components of the system.
Necessary checks shall be performed on all the safety
features of the system including safety check valve etc.
2 SS / RF
Function test the Vibro Hammer 416 prior to the start of
Operations.

Visual Inspection of all the tools and lifting gears used for
extractor of sheet piles.
3 Site HSE / FE / RF R3137-IN-A-
Inspection shall take place on all the lifting gears prior to PRC-NDT-
start of each shift. 65255.031-
0_Hold back
Upon completion of Inspection, shift the Power Pack and anchor for
Vibro hammer with 45 Ton Crane to the anchor pile beach pull-
location. Layout1
4 SS / 45T / RF
Locate 100ton crane on front of the anchor pile for start
of anchor pile extraction.
Hook-up the vibro hammer to anchor pile and start
5 SS / 100T / RF
extracting for 1 Mtr. from the existing level.
Upon extraction to 1 Mtr., deploy the riggers to connect
the choker sling to anchor pile and hook it to the another
6 SS / 100T / 50T/RF
crane hook(50T)

Upon extraction of anchor pile to the ground level,


7 SS / 100T / 50T/RF
recover the anchor pile by using 50T crane
Relocate the crane as needed and continue extraction of
8 anchor piles till the anchor piles are extracted. SS / 100T / 50T/RF R3137-IN-A-
PRC-NDT-
65255.031-
Shift the anchor piles from anchor piles location to the
9 SS / Hydra / RF 0_Hold back
stock yard.
anchor for
Upon extraction,one anchor pile, repeat the steps from beach pull-
10 Steps 5 to 9. . SS / 100T / 50T/RF Layout1
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 17 0f 18

Procedure for Re-instatement of cofferdam

RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Anchor piles extraction at north bund north side
1 Perform Tool Box Talk and TRA. Project HSE
Perform Visual Inspection of High Pressure hoses,
Elastomers, and other components of the system.
Necessary checks shall be performed on all the safety
2 features of the system including safety check valve etc. SS / FE

Function test the Vibro Hammer 416 prior to the start of


Operations.
Visual Inspection of all the tools and lifting gears used for
extractor of sheet piles.
3 Site HSE / FE / RF
Inspection shall take place on all the lifting gears prior to
start of each shift.
Upon completion of Inspection, shift the Power Pack and
Vibro hammer with 45 Ton Crane to the anchor pile
4 location. SS / 45T / RF
Locate 100ton crane on front of the anchor pile for start
of anchor pile extraction.
Hook-up the vibro hammer to anchor pile and start
5 SS / 100T / RF
extracting for 1 Mtr. from the existing level.
Upon extraction to 1 Mtr., deploy the riggers to connect
6 the choker sling to anchor pile and hook it to the another SS / 100T / 50T/RF
crane hook(50T)
Upon extraction of anchor pile to the ground level,
7 SS / 100T / 50T/RF
recover the anchor pile by using 50T crane
Relocate the crane as needed and continue extraction of
8 SS / 100T / 50T/RF
anchor piles till the anchor piles are extracted.
Shift the anchor piles from anchor piles location to the
9 SS / Hydra / RF
stock yard.
Upon extraction,one anchor pile,repeat the steps from
10 SS / 100T / 50T/RF
steps 5 to 9.
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT

Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 18 0f 18

Procedure for Re-instatement of cofferdam

APPENDIX A BACKFILLING DEPTHS

CHAINAGE SEA BED LEVEL BEFORE TRENCHING

CH -12 2800
CH -9 2800
CH -6 2800
CH -3 2800
CH 0 2800
CH 3 2800
CH 8 2800
CH 13 2800
CH 18 1700
CH 23 1300
CH 28 1000
CH 33 700
CH 38 100
CH 43 -300
CH 48 -400
CH 53 -500
CH 58 -580
CH 63 -630
CH 69 -750
CH 75 -840
CH 81 -850
CH 87 -870
CH 93 -900
CH 99 -930
CH 105 -1005
CH 110 -1040
CH 115 -1180
CH 120 -1240
CH 125 -1382
CH 130 -1580
CH 135 -1612
CH 140 -1750
CH 145 -1920
CH 150 -2010