Procedure For Reinstatement Final
Procedure For Reinstatement Final
Procedure For Reinstatement Final
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 1 0f 18
for
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 2 0f 18
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................................... 3
2. SUB-CONTRACTOR’S SCOPE OF WORK ................................................................................ 4
2.1 Purpose of this document ............................................................................................................. 5
2.2 Definitions .................................................................................................................................... 5
2.3 Abbreviation ................................................................................................................................. 5
2.4 References ................................................................................................................................... 6
3. QHSES ........................................................................................................................................ 7
3.1 QHSE considerations ................................................................................................................... 7
3.2 QA / QC considerations ................................................................................................................ 7
3.3 Document Responsibilities ........................................................................................................... 7
4. EQUIPMENT SPREAD ................................................................................................................ 7
5. TECHNICAL INFO ....................................................................................................................... 8
6. SCOPE OF PROCEDURE ........................................................................................................... 8
7. TASK PLAN ................................................................................................................................. 9
APPENDIX A ......................................................................................................................................... 18
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 3 0f 18
1. INTRODUCTION
Oil & Natural Gas Corporation Limited (ONGC), here-in after called as 'Company', is currently involved
with the exploration in several deep-sea fields off the east coast of India. As a part of the overall
development plan, ONGC intends to develop the Vashishta and S1 fields.
The Vashishta field shall comprise two wells (VA-DA and VA-DB) and is located in water depths of 500 to
700 meters. The S1 field shall comprise two wells (S1-A and S-AC) and is located in water depths of
approximately 250 to 420 meters.
ONGC have decided to tie back S2-AB to the existing G1 subsea facilities. Accordingly, S2-AB and all
associated equipment items are not part of this Contract.
The in-line tees located on the pipeline at the S2-AB location will be retained for future tie-ins.
ONGC proposes to produce Vashishta and S1 fields concurrently through in-field flow lines using daisy
chain architecture.
The onshore processing terminal at Odalarevu is located about 90 km to the South- East of Rajahmundry.
This onshore processing terminal at Odalarevu receives hydrocarbons from the GS-15 field and
processing facilities are under construction to receive and process hydrocarbons from the G-1 and GS-15
fields located in the KG basin. The processing facility for gas from Vashishta and S-1 fields will be set up
adjacent to the existing terminal.
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 4 0f 18
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 5 0f 18
The purpose of this document is to describe in detail the re-instatement works on the cofferdam upon
completion of beach pull operations.
The works required will be presented in the format of step by step task plans and drawings which shall be
used by construction personnel to perform the work.
2.2 Definitions
Name Description
COMPANY/ONGC Oil and Natural Gas Corporation Ltd.
CONTRACTOR JRMSA-BMD-LTHE Consortium
SUB-CONTRACTOR Narmada Offshore Constructions Pvt Ltd
“WORK” shall mean all activities all activities
necessary or incidental to be carried out, including
WORK all services to be rendered by the SUB-
CONTRACTOR in accordance with the SUB-
CONTRACT.
2.3 Abbreviation
NAME DESCRIPTION
COMPANY Oil & Natural Gas Corporation Limited (ONGC)
CONTRACTOR McDermott
GP General Purpose
HAT High Astronomical Tide
HSEQS Health, Safety, Environment Quality Surveyor
KP Kilometre Point
LAT Lowest Astronomical Tide
MDR McDermott
MPI Magnetic Particle Inspection
MSL Mean Sea Level
MT Metric Ton
N/A Not Applicable
SWL Safe working Load
TBA To be advised
WT Wall Thickness
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 6 0f 18
2.4 References
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 7 0f 18
3. QHSES
All activities / operations described in this document will be executed in accordance with the
CONTRACTOR’s HSE Plan and SUN-CONTRACTOR’S Emergency Response Plan and in accordance
with the COMPANY’s HSE requirements for CONTRACTORs.
Prior to commencing the works, Task Risk Assessment (TRA) will be performed on individual tasks. The
purpose of the TRA is to identify possible hazards for a specific activity and to identify any mitigating
actions required to perform the task safely. The TRA result will also be presented on worksheets collated
in the Risk Assessment Register. TRA will be performed as part of procedure review or also conducted
prior to commencement of work. A TRA toolbox talk shall be conducted with the workforce prior to
undertaking any work activities.
3.2 QA / QC considerations
All activities and operations shall be performed and completed in accordance with approved procedures,
Drawings, and specifications.
The Field Engineer and the work site supervisors are responsible for monitoring the progress of the work
and recording pertinent information as dictated in the task plan.
Construction manager is responsible for checking this document and ensuring it complies with the overall
project requirements.
4. EQUIPMENT SPREAD
ITEM CAPACITY
Crawler Crane - 1 Nos 100 Ton
Crawler Crane - 1 Nos 75 Ton
Crawler Crane - 2 Nos 50 Ton
Vibro hammer - 1 Nos 415
Excavator - 1 Nos Ex450
Excavator - 1 Nos Ex350
Hydra - 1 Nos 14 Ton
SUBSEA INSTALLATION OF
VASHISHTA & S1 DEVELOPMENT
PROJECT
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 8 0f 18
5. TECHNICAL INFO
The expected Max. lift weight including rigging and contingency is 5 Tons.
6. SCOPE OF PROCEDURE
Initial Status
Pipeline and Beach-Pull Operations are completed.
Ready for Re-instatement
Preparation Works
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 9 0f 18
7. TASK PLAN
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Conduct Tool Box talk and TRA with all the parties in the
1 Site HSE
job.
Position the sand bags and / or carry out the necessary
works near LFP Tie-In point to facilitate Tie-in of Onshore
and Offshore Pipelines.
2 Onshore Contractor
All the necessary works required for maintaining the
trench to facilitate Tie-in shall be performed.
R3137-IN-A-
PRC-
Prior to start of work measure the top of pipe elevation 65255.161_2_
3 FE/SS
and submit to contractor for review Trenching plan
Make sure access on north/south safe to use for both @ cofferdam-
4 Layout 1
excavation and trucks.
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 10 0f 18
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Backfill the cofferdam trench using EX450 on north bund,
8 and have to monitor the filling not to dump stones while Ex450/SS
transferring the sand by excavator.
Trench depth shall be taken continuously to monitor the
9 FE
sea bed depths
Continue backfilling works up to CH 120 till the required
depths are achieved.
EX350 / Ex450 /
10
Refer Attached Table in Appendix A for sea bed depths Trucks / FE
required after backfilling. Top of pipe should be buried
min 2.0M
R3137-IN-A-
Upon completion of backfilling in the trench up to CH 120 PRC-
and acceptance by MDR, the gap between sheet piles 65255.161_2_
rock berm shall be filled with sand based on availability Trenching plan
of sand @ cofferdam-
Layout 1
EX350 / Ex450 /
11
Trucks / SS
Inspect all the Cutting / Lifting gears required for cutting, Site HSE / FE / SS
14
removal and shifting. / WS / RF R3137-IN-A-
PRC-
Position all the cutting gears required for cutting of Weld
15 SS / RF 65255.204_0_
Joints.
cofferdam
Erect barriers in lifting Area / Along Access path till construction
16 SS / RF
designated destination as required. sequence sht-
4-layout 4
Position the 45T crane on north bund and Rig-up the lift
rigging on both sides of the strut. Hook - Up the Tag lines
17 as needed. 45T / RF
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 11 0f 18
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Clear the area for readiness of lifting.
18 45T / Cutter / RF
20 45 T / Cutter / RF
R3137-IN-A-
PRC-
65255.204_0_
cofferdam
construction
sequence sht-
4-layout 4
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 12 0f 18
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
27 45T / Cutter / RF
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 13 0f 18
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Shift the diagonals to stockyard using Hydra.
Repeat the steps 26-27 for removal of all the diagonals.
29 45T / Cutter / RF
Qty to be removed – 4 No’s (2 No’s on each bund.)
Upon completion of removal of diagonals, Position the
100T crane at the end of north bund and Rig-up the lift
30 rigging on both sides of the longitudinal waler. Hook - Up 45T / RF
the Tag lines as needed.
Note: Each sling is rated 10 Ton WLL.
Clear the area for readiness of lifting.
31 45T / Cutter / RF
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 14 0f 18
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Inspection shall take place on all the lifting gears prior to
start of each shift.
Upon completion of Inspection, shift the Power Pack and
Vibro hammer with 45 Ton Crane to the end of cofferdam.
4 SS / 45T / RF
Locate 100ton crane on end of south bund for start of
sheet pile extraction.
Position the guide frame on sheet piles and place
6 walkway on top of guide frame for easy access to the SS / 45T / RF
sheet pile.
Hook-up the vibro hammer to sheet pile and start
7 SS / 100T / RF
extracting for 1 Mtr. from the existing level.
Upon extraction to 1 Mtr., deploy the riggers to connect
the choker sling to sheet pile and hook it to the auxiliary
hook on the crane.
8 SS / 100T / RF
R3137-IN-A-
PRC-
65255.201_0_
Cofferdam
construction
Upon extraction of sheet pile to the seabed level, recover sequence sht-
9 the sheet pile from grove using auxiliary hook on the 100T SS / 100T / RF 1-Layout
crane.
Relocate the guide frame and walk way as needed and
continue extraction of sheet piles till the corner pile is
10 SS / 100T / RF
reached.
11 Shift the sheet piles from access bund to the stock yard. SS / Hydra / RF
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 15 0f 18
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Removal of stones
After the completion of works which are commence
based upon MDR’s instruction i.e. Back filling of CH 120
to CH 150 , removal of struts, walers and diagonals from Info
CH 100 to CH 150 and extraction of sheet piles CH 100
to CH 150 completed, removal of stones should be start.
Conduct Tool Box talk with the excavator operators, shift
supervisors and all the personnel involved in the
operations.
FE / Excavator /
1
Truck
Care shall be taken during the entire operations to
prevent damage to the newly installed pipeline /
umbilical’s.
Position the excavator EX450 at the end of cofferdam
for commencement of rock removal.
R3137-IN-A-
PRC-
65255.201_0_
FE / Excavator / Cofferdam
2
Truck construction
sequence sht-
1-Layout
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 16 0f 18
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Upon completion of rock removals and demobilization of
Narmada’s temporary equipment, the site shall be
restored back to the original condition and handed over
to MDR.
Hold back piles removal at lucker winch location
1 Perform Tool Box Talk and TRA. Project HSE
Perform Visual Inspection of High Pressure hoses,
Elastomers, and other components of the system.
Necessary checks shall be performed on all the safety
features of the system including safety check valve etc.
2 SS / RF
Function test the Vibro Hammer 416 prior to the start of
Operations.
Visual Inspection of all the tools and lifting gears used for
extractor of sheet piles.
3 Site HSE / FE / RF R3137-IN-A-
Inspection shall take place on all the lifting gears prior to PRC-NDT-
start of each shift. 65255.031-
0_Hold back
Upon completion of Inspection, shift the Power Pack and anchor for
Vibro hammer with 45 Ton Crane to the anchor pile beach pull-
location. Layout1
4 SS / 45T / RF
Locate 100ton crane on front of the anchor pile for start
of anchor pile extraction.
Hook-up the vibro hammer to anchor pile and start
5 SS / 100T / RF
extracting for 1 Mtr. from the existing level.
Upon extraction to 1 Mtr., deploy the riggers to connect
the choker sling to anchor pile and hook it to the another
6 SS / 100T / 50T/RF
crane hook(50T)
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 17 0f 18
RESPONSIBLE
REFERENCE
STEP TASK DESCRIPTION PARTY /
DWG
EQUIPMENT
Anchor piles extraction at north bund north side
1 Perform Tool Box Talk and TRA. Project HSE
Perform Visual Inspection of High Pressure hoses,
Elastomers, and other components of the system.
Necessary checks shall be performed on all the safety
2 features of the system including safety check valve etc. SS / FE
Project No. Unit Doc.Type Mat Code Serial No. Rev. Page
W-310 ON CP 0000 818 01 18 0f 18
CH -12 2800
CH -9 2800
CH -6 2800
CH -3 2800
CH 0 2800
CH 3 2800
CH 8 2800
CH 13 2800
CH 18 1700
CH 23 1300
CH 28 1000
CH 33 700
CH 38 100
CH 43 -300
CH 48 -400
CH 53 -500
CH 58 -580
CH 63 -630
CH 69 -750
CH 75 -840
CH 81 -850
CH 87 -870
CH 93 -900
CH 99 -930
CH 105 -1005
CH 110 -1040
CH 115 -1180
CH 120 -1240
CH 125 -1382
CH 130 -1580
CH 135 -1612
CH 140 -1750
CH 145 -1920
CH 150 -2010