WSM-COM-07 Project Construction Completion Pre-Comm and Commissioning Prosedure
WSM-COM-07 Project Construction Completion Pre-Comm and Commissioning Prosedure
WSM-COM-07
Project Construction Completion Rev. 0 10/05/19
Pre-Comm and Commissioning Page 1 of 9
Procedure
WSM-COM-07
Revision Summary
INDEX
2 REFERENCES DOCUMENT
WSM-EI-01 Electrical Installation MC Procedure
WSM-PSFP-01 Piping Spool Fabrication Procedure
4 RESPONSIBILITY
WSM will fully responsible for the Construction Completion including PreCOMM and
give an assistance for the Commissioning activities (if requested).
WSM has defined that the MC and PreComm are in a one part of Project Completion
activities, it means that PreComm and MC are in a single package of completion and the output
from those activities has to be compiled into one integrated filing system prior to
commissioning phase. All of Project Completion relevant dossier will be proper handover
before entering the next step of inspection stage. A Project Construction Completion activities
will be carried out by WSM dedicated Completion team which is responsible with the all
completion.
Project Completion will be proper initiated at the beginning of project execution starts
to develope, all of the mandatory references such as AFC design and drawings, equipment
specification and installation guide have to be received to WSM by the project
company/vendor as soon as the project design is in a ‘Approved for construction’ status then
the completion scenario, methods and computer filing system called Project Completion Filing
centre will start to develop. As the output/report compiled centre, the Project Completion
Filing centre shall always up to date and consist with all relevant information such as status
and progress of the WSM construction work. This documentation activities will be carried out
by the Project Completion Team clerks in accordance to the inspection report of construction
completion activities as follows:
The complete list of all systems/sub-systems and ‘tag items’ will be registered and use
as the inputation of completion items list, together with their relevan technical information
attached so it can be clear initiated in order to prevent a mistake of initiating and tracking for
every single tag items. Mechanical completion inspection will start when the facility defined
in the approval scope, construction works progress approaching at minimum 90%.
There are two type of completion items which will categorized in a punch list
preparation as follows,
1. Type A, for an items to be tested and closed before MC certification (Critical items).
2. Type B, for an items which can be tested and closed after MC certification (Non
Critical items).
WSM has defined that PreComm is a part of Project Completion. The goal is to verify
and validate a mechanical completion through the “check sheet” achieve the correctness and
all necessary testing objectives has been performed. WSM will implement such a relevant test
package and final check of functionality (without energy) for all equipment and loop. It also
ensure that a all system/subsystem is ready to be started up by performing a necessary final
checking through all equipment and system loop such as oiling and lubricant, piping valve
movement, belt transmission alignment, electrical panel, instrument calibration and so on.
Doc. No. WSM-COM-07
Project Construction Completion Rev. 0 10/05/19
Pre-Comm and Commissioning Page 7 of 9
Procedure
As result there will be a PreComm check sheets and test reports complied in a Project
Completion Filing centre as a verification document and MCC attachment to determine that
all checked and tested system/subsystem are in a state of readiness for final commissioning.
There are several activities which need to be performed for the checking and testing :
6 COMMISSIONING (COMM)
WSM has defined that Commissioning activity is the testing activities under the
system/subsystem power has shutted on. This activity will verify the functionality of all
installed equipment and instrumentation (with all completion reports as reference) and
ensuring that all loop of system and subsystem are well closed and installed, proper calibrated
and ready for operation.
Doc. No. WSM-COM-07
Project Construction Completion Rev. 0 10/05/19
Pre-Comm and Commissioning Page 8 of 9
Procedure
7 ATTACHMENT :
7.1 WSM Punch List.
Doc. No. WSM-COM-07
Project Construction Completion Rev. 0 10/05/19
Pre-Comm and Commissioning Page 9 of 9
Procedure