Professional Documents
Culture Documents
Bi Laila
Bi Laila
cgjkbp&JkoLrh o`Rr
tuin&JkoLrh
[k.M dk uke&izkUrh; [k.M
izkjfEHkd vkx.ku
dk;Z dk uke foRrh; o"kZ 2018&19 esa jkT;
lM+d fuf/k&5054 ;kstukUrxZr
xzke fMdjk ls jk;iqj fcysyk rd
lEidZ ekxZ dk fuekZ.k dk;ZA
(Proforma for checking the Preliminary and Detailed Estimate, to be pasted on each estimated)
1. REPORT (A) Proper reference have been quoted and attested copies
attached to the estimate.
(B) In case of revised estimate, the amount of excess has
been given itemwise in the comparative staement with
detailed reasons.
(C) Signatures of A.E., E.E. and S.E. exist.
(D) Details of forest land with name of village & chainage.
(E) Required certificates are mentioned or not.
(F) Name JE/AE who surveyed the work for preparation of estimate
7. BILL OF QUANTITIES Each page bears signatures of J.E., A.E. and by E.E. at
the end of each set.
8. SUMMARY OF This has been signed by A.E., E.E., S.E. and C.E.
ESTIMATED COST
9. PLANS (A) Line diagram on 1" = 4 mile map with making of road in
red colour duly singed by J.E., A.E. and countersinged by
E.E.
(B) Plans have been signed by J.E., A.E. and E.E.
10. GENERAL (A) Names and designation should exist below signatures.
(B) Each page of design, analysis of rates, details of measurements,
bill of quantity and summary of estimated cost should be
certified "Checked and Corrected" by divisional and circle office
J.E.(T) with their signature at the end.
1 Title Page
2 Checklist
3 Index of contents
4 Report
5 Reference
6 Specifications
7 R.M.R.
8 Analysis of rate
9 Details of measurements
10 Bill of quantity
12 Drawing
13 Line Diagram
14 Index Map
izfrosnu
dk;Z dk ukefoRrh; o"kZ 2018&19 esa jkT; lM+d fuf/k&5054
;kstukUrxZr xzke fMdjk ls jk;iqj fcysyk rd lEidZ ekxZ
dk fuekZ.k dk;ZA
dk;Z dk uk foRrh; o"kZ 2018&19 esa jkT; lM+d fuf/k&5054 ;kstukUrxZr xzke fMdjk ls
jk;iqj fcysyk rd lEidZ ekxZ dk fuekZ.k dk;ZA
Distance K P Total
Material - Stone ballast 0 351 351 Km
Km Loading Nominal Net C.P. @ Distance Cost of Norms Amount Total GST Total rate
of for
No. Station size of Rate at 10% on from Cartage waistag waistag 5.0% rounded off
e e Remarks
stone quarry Col. 3 quarry to 10 paise
ballast/grit (Km.) (on Col.4)
1 2 3 4 5 6 7 8 9 11 12 13 14
1 Haldwani 45-90 mm G.S.B. 950.00 351 2549.57 3499.57 3499.60 Details of cartage
1 Haldwani 45-63 mm G.S.B. 1025.00 351 2549.57 3574.57 3574.60 1st Km. To 200Km. Rs. 1823.00
1 Haldwani 22.4-53 mm G.S.B 1050.00 351 2549.57 3599.57 3599.60
1 Haldwani All size grit 1100.00 351 2549.57 3649.57 3649.60 Total 1823.00
1 Haldwani Stone Dust 1100.00 351 2549.57 3649.57 3649.60 201 St To 351 Km @ Rs. 6.50 /Km = Rs. 981.50
1 Haldwani Type "B" Screenin 915.00 351 2549.57 3464.57 3464.60 Total 2804.50
1 Haldwani Boulder 890.00 351 2549.57 3439.57 3439.60 For excluding of CP 10% on Rs. 2804.50 x9.09% 254.93
Total 2549.57
DISTANCE FROM QUARRY
Kachcha Pakka
(1) Quarry to Site 351
Certified that :
(1) The quarry rates given by SE, Barabanki Circle P.W.D., Barabanki Schedule Rate effected From Dt.01.06.2016
(2) The quarry rates are approved by SE, Bareily Circle, P.W.D., Bareily, Letter No. 3198/23M.A.-3/ 2017 dt. 22.04.17.
(3) The cartage rates are approved by S.E. LKO Circle letter No. 4492/2M-L Circle/2018 dt. 26.06.2018
(4) The cartage from the shortest possible route where the overall rates are cheapest hab been adopted.
Distance K P Total
Material - Stone ballast 1 340 341 Km
Km Loading Nominal Net C.P. @ Distance Cost of Norms Amount Total GST Total rate
No. Station size of Rate at 10% on from Cartage of for 5.0% rounded off
waistage waistage Remarks
stone quarry Col. 3 quarry to 10 paise
ballast/grit (Km.) (on Col.4)
1 2 3 4 5 6 7 8 9 11 12 13 14
1 Hamirpur Coarse Sand 875.00 341 2504.93 3379.93 3379.90 Details of cartage
1st Km. to 200th Km. Rs. 1823.00
Total 1823.00
201 St To 341 Km @ Rs. 6.50 /Km = Rs. 916.50
Add. 1/3rd of Ist Km for Kachcha /Km = Rs. 15.90
Total 2755.40
For excluding of CP 10% on Rs. 2755.40 x9.09% 250.47
Total 2504.93
DISTANCE FROM QUARRY
Kachcha Pakka
(1) Quarry to Site 341
Total 341
Unit = cum
Taking output = 300 cum (660 tonees)
Quantity of cemebt assumed as 2
percent of qty by waight for base
course
a) Labour
Mate day 8.4 300.00 2520.00
Mazdoor (Skilled) day 1.67 300.00 501.00
Mazdoor (Unskilled) day 208.33 265.00 55207.45
b) Machinery
dk;Z dk uke %& foRrh; o"kZ 2018&19 esa jkT; lM+d fuf/k&5054
;kstukUrxZr xzke fMdjk ls jk;iqj fcysyk rd lEidZ ekxZ dk
fuekZ.k dk;ZA
Unit- sqm
Taking output = 1750 sqm
a) Labour
Mate day 0.04 300.00
Mazdoor (Unskilled) day 1.00 265.00
b) Machinery
Air compressor 210 cfm hour 1.40 381.10
Bitumen Pressure distributor @ 1750
sqm per hour hour 1.00 1280.20
c) Material
Bitumen (V.G.-10) @ 0.35 kg per sqm t 0.61 28368.00
Amount
(Rs.)
12.00
265.00
533.54
1280.20
17375.40
19466.14
261.34
19727.48
11.27
11.30
Analysis of Rate
dk;Z dk uke %foRrh; o"kZ 2018&19 esa jkT; lM+d fuf/k&5054
;kstukUrxZr xzke fMdjk ls jk;iqj fcysyk rd lEidZ ekxZ dk
fuekZ.k dk;ZA
82463.34
Add cost of CP & overheads @ 12.5% on (a+b+c)
d) excluding cost of Bitumen 7719.34
61480.00
Add cost of CP & overheads @ 12.5% on (a+b+c)
d) 5149.61
excluding cost of Bitumen
Rate of Cement
Rate of cement (PPC) per MT Rs. 6000.00
Total per MT Rs. 6000.00
Says per MT Rs. 6000.00
I. P.C.C grade M 10
(i) Nominal mix 1:3:6
Unit = cum
a) Material
Cement t 0.250 6,000.00 1,500.00
Coarse sand cum 0.48 3,379.90 1,622.35
40 mm aggregate cum 0.576 3,649.60 2,102.17
20 mm aggregate cum 0.288 3,649.60 1,051.08
10 mm aggregate cum 0.096 3,646.70 350.08
b) Labour
Mate day 0.08 300.00 24.00
Mason (1st Class) day 0.10 480.00 48.00
Mazdoor (Unskilled) day 1.63 265.00 431.95
Bhisti day 0.27 300.00 81.00
c) Machinery
Mechnical concrete mixer 0.4/0.28 cum hour 0.40 277.50 111.00
capacity fitted with water measuring device
and preferably also with load cell.
Sub-analysis
Cement mortar 1:3 (1 cement : 3 sand)
Unit = cum
a) Material
Cement t 0.51 6,000.00 3,060.00
Course Sand cum 1.05 3,379.90 3,548.90
b) Labour
Mate day 0.04 300.00 12.00
Mazdoor (Unskilled) day 0.90 265.00 238.50
Bhisti day 0.08 300.00 24.00
Total material and labour = (a+b) 6,883.40
1 1100 Providing and Laying Reinforced
Cement Concrete Pipe NP3 as per
design in Single Row
Providing and laying reinforced cement
concrete pipe NP3 for culverts on first class
bedding of granular material in single row
including fixing collar with cement mortar
1:2 but excluding excavation, protection
works, backfilling, concrete and masonry
works in head walls and parapets Clause
1106.
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
(A) 900 mm dia
a) Labour
Mate day 0.09 300.00 27.00
Mason (1st Class) day 0.25 480.00 120.00
Mazdoor (Unskilled) day 2.00 265.00 530.00
b) Material
Sand at site cum 0.04 1,000.00 40.00
Cement at site t 0.03 6,000.00 180.00
897.00
RCC pipe NP3 concrete pipe including m 7.50 4,429.00 33,217.50
c) collar at site
Add C.P. & Overheads @ 12.50% (a+b) 4,264.31
Cost for 7.5 m = a+b+c 38,378.81
Rate per m = (a+b+c+d)/7.5 5,117.18
Say Rs. 5,117.00
Unit = cum
a) Material
O.B.B. (Brick Bats) cum 1.20 1,200.00 1,440.00
b) Labour
Mate day 0.05 300.00 15.00
Mazdoor (Skilled) day 0.25 260.00 65.00
Mazdoor (Unskilled) day 1.02 265.00 270.30
Total (A+B) 1,790.30
c) C.P. & Overheads @ 12.50% on (a+b) 223.79
Rate per cum = a+b+c+d 2,014.09
Say Rs. 2,014.10
I. Ordinary soil
(i) Depth Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.14 300.00 42.00
Mazdoor (Unskilled) day 3.50 265.00 927.50
b) Overhead & C.P. @ 12.50% on (a) 121.19
Cost for 10 cum = a+b+c 1,090.69
Rate per cum = (a+b+c)/10 109.07
Say Rs. 109.00 /Cum
3.4 301.5 Construction of Embankment with Material
Obtained from Borrow Pits
Construction of embankment with approved
material obtained from borrow pits with a lift
upto 1.5 m, transporting to site, spreading,
grading to required slope and compacting to
meet requirement of Tables 300.1 and 300.2
with a lead upto 50 m as per Technical
Specification Clause 301.5
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 300.00 12.00
Mazdoor (Unskilled) day 1.00 265.00 265.00
Total 277.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket hour 1.67 1,554.00 2,595.18
capacity @ 60 cum per hour
Dozer D-50 for spreading @ 200 cum per ho hour 0.50 4,482.55 2,241.28
Motor grader for grading @ 200 cum per hour hour 0.50 2,858.25 1,429.13
Water tanker 6 kl capacity hour 2.00 370.00 740.00
Three wheel 80-100 kN Static Roller @ 80 hour 1.25 549.45 686.81
cum per hour
Total 7,692.39
J.E. A.E. E.E.
c) Material
Water kl 12.00 50.00 600.00
Compensation for earth taken from private la cum 100.00 0.00 0.00
Total 600.00
G Total 8,569.39
d) d) Overhead Charges& C.P. @ 12.5% on (a+b+c) 1,071.17
Cost for 100 cum = a+b+c+d+e 9,640.57
96.41
Rate per cum = (a+b+c+d+e)/100 96.40
Say Rs 95.00 /cum
3.4 301.5 Construction of Embankment with Material
Obtained from Borrow Pits
Construction of embankment with approved
material obtained from borrow pits with a lift
upto 1.5 m, transporting to site, spreading,
grading to required slope and compacting to
meet requirement of Tables 300.1 and 300.2
with a lead upto 1000 m as per Technical
Specification Clause 301.5
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 300.00 12.00
Mazdoor (Unskilled) day 1.00 265.00 265.00
Total 277.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket hour 1.67 1,554.00 2,595.18
capacity @ 60 cum per hour
Tipper 5.5 cum with 10 t capacity hour 4.50 370.00 1,665.00
Loading of earth as per item 1.1 (ii) cum 100.00 35.00 3,500.00
Unloading of earth as per item 1.1 (iv) cum 100.00 18.00 1,800.00
Dozer D-50 for spreading @ 200 cum per ho hour 0.50 4,482.55 2,241.28
Motor grader for grading @ 200 cum per hour hour 0.50 2,858.25 1,429.13
Water tanker 6 kl capacity hour 2.00 370.00 740.00
Three wheel 80-100 kN Static Roller @ 80 hour 1.25 549.45 686.81
cum per hour
Total 14,657.39
c) Material
Water kl 12.00 50.00 600.00
Compensation for earth taken from private la cum 100.00 0.00 0.00
Total 600.00
G Total 15,534.39
d) d) Overhead Charges& C.P. @ 12.5% on (a+b+c) 1,941.80
Cost for 100 cum = a+b+c+d+e 17,476.19
174.76
Rate per cum = (a+b+c+d+e)/100 174.80
Say Rs 174.00 /cum
J.E. A.E. E.E.
3.14 303.1 Construction of Subgrade and Earthen Shoulders
Construction of subgrade and earthen
shoulders with approved material obtained from
borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and
compacted to meet requirement of Table 300.2
with lead upto 1000 m as per Technical
Specification Clause 303.1.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 300.00 12.00
Mazdoor (Unskilled) day 1.00 265.00 265.00
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity hour 1.67 1,554.00 2,595.18
@ 100 cum per hour
Dozer D-50 for spreading @ 200 cum per ho hour 0.50 4,482.55 2,241.28
Motor grader for grading @ 200 cum per hour hour 0.50 2,858.25 1,429.13
Water tanker with 6 kl capacity hour 2.00 370.00 740.00
Three wheel 80-100 kN Static Roller @ 70 cu hour 1.43 549.45 785.71
c) Material
Water kl 12.00 50.00 600.00
Compensation for earth taken from private la cum 100.00 0.00 0.00
d) Overhead Charges& C.P. @ 12.5% on (a+b+c) 1,083.54
Cost for 100 cum = a+b+c+d+e 9,751.83
Rate per cum = (a+b+c+d+e)/100 97.52
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.08 300.00 24.00
Mazdoor (Unskilled) day 2.00 265.00 530.00
b) Machinery
Dozer D-50 @ 50 cum per hour hour 3.60 4,482.55 16,137.18
(cutting with pushing)
c) Overhead & C.P. @ 12.50% on (a+b) 2,086.40
Cost for 180 cum = a+b+c+d 18,777.58
Rate per cum = (a+b+c+d)/180 104.32
J.E. A.E. E.E.
Analysis of Rate
Providing laying and jointing of NP3 Hume pipe and coller complete with all labour materials and
T&P etc required for placing pipes and coller in position, filling caulking spaces with bitumen
impregnated coir as per direction of Engineer.
J.E. A.E.
P.D., P.W.D. P.D., P.W.D.
Shrawasti Shrawasti
Bill Of Quantity
foRrh; o"kZ 2018&19 esa jkT; lM+d fuf/k&5054 ;kstukUrxZr xzke fMdjk ls jk;iqj
fcysyk rd lEidZ ekxZ dk fuekZ.k dk;ZA
Line Plan
J.E. A.E. E.E.
Analysis of Rate
J.E A.E
2x2 1.20 0.85+1.30 0.40
2.06 cum
2
Toewall 1x1 8 0.47 1.00 3.76 cum
Floor 1x1 7.5 3 0.20 4.50 cum
1x2 3.5 3.00+8.00 0.20
7.70 cum
2
Total 52.80 cum
4 Brick work with 150 class brick in cement mortor 1:3
cement and coarse sand in super structure including
supply of all materials, labour and T&P etc. required
for proper completion of the work
J.E A.E
7 R.C.C. work in slab with the cement and approved
coarse sand and 20mm guage approved stone grit in
the proportion 1:2:4 in floors excluding supply of
reinfocrement and its bending but including its fixing
and binding the same with 24 B.W.G.G,I. binding
wire and including necessary shuttring and centring
etc. and also including supply of all
materials,labour.T&P etc.required for proper
completion of work.
1x1 7.50 4.6 0.40 13.80
(B ) Total 13.80 cum
8 P/L of wearing coat 7.5cm. thick 1:1½:3 cement
concrete in cement and coarse sand approved stone
grit including cost of materials labour T&P etc.
required for proper completion of work.
1x1 7.50 3.00 0.075 1.69
(C ) Total 1.69 cum
9 Mild steel or iron in plain work such as reinforced
cocrete or reinforced brick work wrought to required
shape as necessary including bending for proper
completion of the work and including supply of steel
its wastage bend hooks and authorised overlapping
shall be measured including all materials, labour and
T&P etc.
Bed block 6.00 Cum @ 1.00% x 78.50 4.71 cum
Slab 13.80 Cum @ 1.00% x 78.50 10.83 cum
Wearing coat 1.69 Cum @ 1.00% x 78.50 1.32 cum
Total 16.87 cum
10 Providing, laying and packing brick bats as filter
materials behind abutment and wing walls. including
supply of all materials, labour T&P etc.
1x2 7.50 0.60 2.00 18.00 cum
1x4 5.00 0.60 2.00+1.00
18.00 cum
2
1x4 1.20 0.60 1.00 2.88 cum
1x2 8.00 3.00 0.15 7.20 cum
Total 46.08 cum
S.
Item of work No L B D/H Area
N
o.
1 2 3 4 5 6 7
J.E A.E
11 Stuck cement pointing with 1:2 cement and fine sand
of 1.25 fineness Modules over brick work complete
with all labour, materials ,T&P etc. as per direction of
E/I. as N.S. No. 17.120
Abutment 1x2 7.50 - 1.50 22.50 Sqm.
Wingwall 1x4 5.00 - 2.50+1.00
35.00 Sqm.
2
1x4 1.20 - 1.00 4.80 Sqm.
Top of wingwall 1x4 5.00 0.50 - 10.00 Sqm.
1x4 1.20 0.50 - 2.40 Sqm.
Floor 1x1 7.50 6.00 - 45.00 Sqm.
1x2 3.50 6.00+13.00 -
66.50 Sqm.
2
Parapet 1x2 8.00 - 0.87 13.92 Sqm.
1x2 8.00 0.35 - 5.60 Sqm.
1x2 8.00 - 0.42 6.72 Sqm.
1x4 - 0.47 0.42 0.79 Sqm.
1x4 - 0.37 0.37 0.55 Sqm.
J.E A.E
14 Supply and Laying one layer tarfelt or any other
equipment approved material of junction of wall &
roof as per direction of Engineer-In-Charge including
necessary overlap, giving a coat of approved mastic
paint blow the tarfelt and including supply of all
materials, labour and T&P etc. complete.
J.E A.E
Bill Of Quantity
dk;Z dk uke %& bdkSuk&i;kxiqj ekxZ ds fdeh0&08 esa {kfrxzLr vkpZ iqfy;k
ds LFkku ij 1x3-00eh0 Liku dh vkj0lh0lh0 iqfy;k dk fuekZ.k dk;ZA
C/o R.C.C. culvert 1 x 3 m Span x 2m height.
S.
Item of work Qty. Unit Rate Per Amount
No.
1 Excavation in excavation in foundation
trenches etc not exceeding 1.5M. Depth
including dressing of bottom and side of
trenches, stacking the excavated earth clear
from the edge of excavatioin and subsequent
filling around massonary in 15cm. layers with
compaction including disposal of all surplus
earth as per direction of Engineer-In-Charge
with in a lead of 30M. from the foundation
trenches (SI.No. 251)
191.53 Cum 126.00 Cum 24132.72
2 Cement Concrete with 1:3:6 mix with stone
aggregate 40mm approved 22.4-53mm
Nominal size mechanically Mixed and
vibrated in foundation up to a depth of 1.50
M. below ground level with Hamirpur coarse
sand, and cement including supply of all
materials, labour and T&P etc required for
proper completion of work.
36.61 Cum 8566.30 Cum 313595.11
3 Brick work with 150 class brick in cement
mortor 1:3 cement and coarse sand in
foundation and plinth including supply of all
materials, labour and T&P etc. required for
proper completion of the work
52.80 Cum 6070.00 Cum 320520.28
4 Brick work with 150 class brick in cement
mortor 1:3 cement and coarse sand in super
structure including supply of all materials,
labour and T&P etc. required for proper
completion of the work
53.59 Cum 6322.00 Cum 338820.00
5 P/L C.C. in 1:4:8 with cement fine sand and 40mm
gauge nominal size brick ballast including cost of
materials labour T&P etc required for proper
completion of the work as directed by Engineer-
In-Charge.
9.15 Cum 4045.00 Cum 37011.75
S.
Item of work Qty. Unit Rate Per Amount
No.
J.E A.E
Bill Of Quantity
dk;Z dk uke %& foRrh; o"kZ 2018&19 esa jkT; lM+d fuf/k&5054
;kstukUrxZr xzke fMdjk ls jk;iqj fcysyk rd lEidZ ekxZ dk fuekZ.k dk;ZA
Distt. Shrawasti
bZdkbZ %& izfr fdeh0
ekud ek=k;sa
Quantity Amount
SI No. Description of item Unit Rate
per Km. (Lacs)
1 2 3 4 5 6
1 E/W in excavation in foundation including all labour T&P etc complete.
1x2x1000x0.88x0..58 = 1020.80 cum 1020.80 cum 99.00 1.01
2 C.C. 1:4:8 in foundation.
For Drain - 1x2x1000x0.88x0.10 = 176 cum 176.00
Under C.C. - 1x1x1000x3.00x0.10 = 300.00 cum 300.00
476.00 cum 3850.00 18.33
3 B/W in 1:4 cement and coarse sand including all etc.
1x2x1000x0.76x0.075 = 114.00 cum 114.00
1x2x2x1000x0.23x0.30 = 276.00 cum 276.00
390.00 cum 6142.29 23.95
4 Polythene under C.C. including all etc.
1x1000x3.00 = 3000.00 3000.00 sqm 8.00 0.24
5 C.C. 1:1½:3 cement and C/sand including all etc.
1x1x1000x3.00x0.15 = 450.00 cum 450.00 cum 10596.56 47.68
6 40mm thick C.C. Flooring in 1:2:4 cement coarse sand and 20mm stone ballast
including all etc.
1x2x1000x0.30 = 600 sqm 600.00 sqm 400.00 2.40
7 15mm thick Cement plaster in 1:3 cement and coarse sand mortar including all etc.
dqy ;ksx %& ### #REF! ### #REF! 0.00 0.00 0.00 0.00 #REF! #REF! 0.00 ### ### ### #REF! #REF!
izekf.kr fd;k tkrk gS fd &
1 izLrkfor ekxZ ls tqM+us okyk jktLo xzke@clkoV iwoZ esa fdlh vU; ekxZ ls ugha tqM+k gS rFkk xzke@clkoV dks Single Connectivity gh iznku dh xbZ gSA
2 izLrkfor ekxZksZs ds lajs[k.k dk losZ{k.k dj fy;k x;k gS Shorted Alignment j[krs gq, izkfo/kku U;wure vko';drkuqlkj gh fd;s x;s gSaA
3 mDr izLrkfor lEidZ ekxZ yks0fu0fo0 dh vU; fdlh Hkh ;kstuk ¼ih0,e0th0,l0okbZ0½ vkfn vFkok fdlh vU; foHkkx esa u rks Lohd`r gS ,oa u gh Lohd`fr gsrq yks0fu0fo0 rFkk fdlh
4 mDr izk:i esa dk;Z dh ykxr izeq[k vfHk;Urk }kjk fuxZr v|kof/kd ifji=ksa esa fufgr fn'kkfunsZ'kksa ds vuqlkj xfBr vkx.kuksa dk lkjka'k gSA
5 ekxZ fuekZ.k gsrq Hkwfe miyC/k gSA
6 vkx.ku esa njsa v/kh{k.k vfHk;Urk ckjkcadh o`Rr yks0fu0fo0 ckjkcadh }kjk vuqeksfnr gSA
J.E. A.E.
6 Tack Coat
Providing and applying Tack coat with
bitumen (V.G.-10) using bitumen
distributor at the rate of 0.35 to 0.45
kg per sqm on the prepared granular
surfaces treated with primer &
cleaned with Hydraulic broom as per
Technical Specification Clause 503
(iii)
Km. - 1 1x1 1000.00 3.75 - 3750.00 sqm
J.E. A.E.
9 Earth work in cutting or filling in
making patrie on both side of road
with ordinary soil including all labour
etc complete.
Km. - 1 1x2 900.00 (1.875+2.275)/2 0.200 747.00 cum
1x2 100.00 (1.875+2.075)/2 0.100 39.50 cum
Total 786.50 cum
Km. - 2 (650Mtr.) 1x2 650.00 (1.875+2.275)/2 0.200 539.50 cum
Total 539.50 cum
10 Construction of N.P.-3 Hume Pipe
Culvert including all labour, material
T&P etc complete.
600mm dia 1x2 - - - 2.00 No.
J.E. A.E.
P.D., P.W.D., P.D., P.W.D.,
Shrawasti Shrawasti
BILL OF QUANTITY
dk;Z dk uke %& foRrh; o"kZ 2018&19 esa jkT; lM+d
fuf/k&5054 ;kstukUrxZr xzke fMdjk ls jk;iqj fcysyk rd
lEidZ ekxZ dk fuekZ.k dk;ZA
S.
Item of Work Qty Unit Rate Amount
No.
1 2 3 4 5 6
1 Earth work in cutting or in embankment
in ordinary soil for Excavation to be done
in form of regular pits not exceeding 0.5
M in depth and earth work in
embankment to be in 20 cm layers
including ramming and dressing the
surface to required levels and slopes
and also including 1.5 m lift and 30 m
lead. The earth form cutting to be used
in making embankment or to be
deposited as spoil bank within 30m
distance or as directed by E/I complete
as S.I. No. 253.
Km. - 1 4464.33 cum 112.00 500004.40
Amount
(Rs.)
specific sizes to
thickness, hand
per grade and
stices of coarse
s per (MORD)
3024.00
600.00
66250.00
24725.25
8880.00
1503560.52
271788.48
7200.00
1886028.25
235753.53
2121781.78
5893.84
5893.80
Analysis of Rate
Unit- sqm
Taking output = 1750 sqm
a) Labour
Mate day 0.04 300.00 12.00
Mazdoor (Unskilled) day 1.00 265.00 265.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour 1.40 425.50 595.70
hour
Air compressor 210 cfm hour 1.40 381.10 533.54
Bitumen emulsion pressure
distributor @ 1750 sqm per hour hour 1.00 954.60 954.60
Sr. Description
Rate Amount
No. Unit Quantity
(Rs.) (Rs.)
Cement treated WBM Grade III
Providing ,laying and spreading material on a prepared sub base , cement @ 4% by
waight to the spread material manually mixing in place with rotavator and
compacting with the road rollar at OMC to achive the desired unconfind compressive
strength and to form a layer of Sub base/base.
Unit- Cum
Taking output = 300 cum or 660 t
a) Labour
Mate day 8.4 300.00 2520.00
Mazdoor (Skilled) day 1.67 300.00 501.00
Mazdoor (Unskilled) day 208.33 265.00 55207.45
b) Machinery
Vibratory roller 8-10 tone hour 6.00 994.00 5964.00
Water tanker 6 Kl capacity with 5 km hour 10.00 200.00 2000.00
lead in one hour
Add 85 % Escalation on roller and Water tanker
6769.40
Tractor with Rotavator 25 cum per hour 12.00 518.00 6216.00
hour
Material (Refer Tables
c) 400.7,8,9 and 10) Aggregate
Grading 3 53 mm to 22.4 mm @ 0.91
cum per 10 sqm for compacted cum 363.00 3451.70 1252967.10
thickness of 75mm
Type B Screening Material
cum 72.00 3464.60 249451.20